Government of the People’s Republic of Bangladesh

Local Government Engineering Department

Office of the Executive Engineer

District: Satkhira.

 

Memo No : LGED/XEN/Sat/11/ 295                                                                                                     Dated  :  15 / 02 / 2011

 

Invitation for Tender (Works)

Tender Notice Number: 10/2010 - 2011

 

Sealed tenders are hereby invited from the tenders enlisted  under Clause No. 52 (I) & (2)  of  PPR - 2008 for limited tender Method up to Taka 2.00  Crore and as defined in the tender documents for the under mentioned works as per terms and conditions stated below:

Package

 No.

Gr

No

Name of Works

Tender

security

(Tk.)

Time for

completion

( days )

Price of tender document

(Tk.)

 

GOB Maintenance

 

 

GOBM/10/ SAT/W  52

1.

Periodic Maintenance of Tala GC-Subasini Bazar (R&H) via Jhatpur GC road at Ch:00-805m under Tala Upazila, Satkhira.

45,000/-

60 days

750/-

GOBM/10/SAT/W  53

2

Periodic Maintenance of Tala GC-Subasini Bazar (R&H) via Jhatpur GC road at Ch:805-3550m under Tala Upazila, Satkhira.

46,000/-

60 days

750/-

 

Union Infrastructure development (Khulna, Bagarhat & Satkhira) Project.

 

 

LGED/XEN/Sat/T-10/68

3

Improvement of Ramjibanpur more -Sirajpur hat road by WBM + 25mm BC + 7mm Seal Coat at Ch: 00-1115m with 1 Nos RCC Box culvert + 2 Nos U-drain  under Shyamnagar Upazila, Satkhira (Package No: UIDP (KBS)/VR-24/Sat/11).

1,00,000/-

365 days

2,000/-

LGED/XEN/Sat/T-10/69

4

Improvement of Ramjibanpur more -Harinagati road by WBM + 25mm BC + 7mm Seal Coat at Ch: 00-1000m under Shyamnagar Upazila, Satkhira (Package No: UIDP (KBS)/VR-25/Sat/11).

80,000/-

365 days

1,000/-

LGED/XEN/Sat/T-10/70

5

Improvement of Baladanga Sanapara Pacca Road (Baladanga R&H) - Akhrakhola road at Ch: 185 - 610m under Sadar Upazila, Satkhira (Package No: UIDP (KBS) /VR-26/Sat/11).

30,000/-

365 days

750/-

LGED/XEN/Sat/T-10/71

6

Improvement of Vatpara-Gharchala P/School road by HBB at Ch:2750 - 3100m & Construction of 1 Nos 375mm x 450mm size U-type drain culvert at Ch:2995m under Sadar Upazila, Satkhira (Package No: UIDP (KBS) /VR-09 /Sat/11).

20,000/-

365 days

750/-

LGED/XEN/Sat/T-10/72

7

Improvement of Tailkupi-Moshadanga road by 25mm BC+7mm seal coat at Ch:2450-3450m under Tala Upazila, Satkhira. (Package No: UIDP (KBS) /VR-27/ Sat/11).

58,000/-

365 days

1,000/-

LGED/XEN/Sat/T-10/73

8

Improvement of Mohandi Rishipara-Ganali Bazar  road by 25mm BC+7mm seal coat at Ch:00-1000m with 1 No U-drain at Ch:800m & Palasiding work under Tala Upazila, Satkhira. (Package No: UIDP (KBS) /VR-28/ Sat/11).

66,000/-

365 days

1,000/-

LGED/XEN/Sat/T-10/74

9

Improvement of Masiara Ghora Battola-Uttor Masiara Kha Mosque road by 25mm BC+7mm seal coat at Ch:1600-2600m with 3 Nos U-drain at Ch:1800m, Ch:2250m, Ch:2600m & Palasiding work under Tala Upazila, Satkhira. (Package No: UIDP (KBS) /VR-29/ Sat/11).

68,000/-

365 days

1,000/-

LGED/XEN/Sat/T-10/75

10

Improvement of Tala UP office (Hospital)-Jatpur GC road by 25mm BC+7mm seal coat at Ch:700-1700m with 1 No U-drain at Ch:1000m under Tala Upazila, Satkhira. (Package No: UIDP (KBS) /UNR-11/ Sat/11).

78,000/-

365 days

1,000/-

LGED/XEN/Sat/T-10/76

11

Improvement of Kheshra UP-Dakhin Shajatpur Bazar road by 25mm BC+7mm seal coat at Ch:950-2300m with 7 Nos U-drain at Ch:1000m, 1200m, 1400m, 1800m, 1850m, 2200m & 2250m under Tala Upazila, Satkhira. (Package No: UIDP (KBS) /UNR-12/ Sat/11).

1,10,000/-

365 days

2 ,000/-

 

Rural Infrastructure development ( Khulna, Bagarhat & Satkhira ) Project.

 

 

LGED/XEN/Sat/T-10/77

12

Improvement of  Iswaripur U.P Office - Harinagar hat (G.C)  road via Dhumkali with H.B.B at Ch: 3760m under Shyamnagar Upazila, Satkhira (Package No: RIDP (KBS) /UNR-01/Sat/11)

18,000/-

365 days

500/-

LGED/XEN/Sat/T-10/78

13

Improvement of  Islamkati R&H - Budhata GC via Jetua GC road by 25mm BC+7mm Seal Coat at Ch: 8187-9252m with 2 Nos U-drain at Ch:8600m & Ch:9150m and Palisiding work  under Tala Upazila, Satkhira (Package No: RIDP (KBS) /UZR-02/Sat/11)

1,20,000/-

365 days

2,000/-

 

 

 

Contd.....P/2

 

 

 

 

 

 

 

Contd.....P/2

 

 

 

 

 

 

 

1.

Source of Funds

:

GOB

2.

Date, time and place of pre-tender meeting

:

Date: 3rd March 2011, Time: 11.00am and

Place: Office of the undersigned

3.

Last date, time and places of selling tender documents

 

:

Date:  14th March  2011, Time: During Office hours

Places: Office of the undersigned / The concern Upazila Engineer, Upazila: Sadar,Tala & Shyamnagar District: Satkhira./ The Executive Engineer, LGED Jessore/The Deputy Commissioner, Satkhira./ The Superintendent of Police, Satkhira. / The Superintending Engineer (Maint), LGED Bhaban, Agargaon Sher-E-Bangla Nagar,Dhaka-1207/The Project Director, Union Infrastructure development ( Khulna, Bagarhat & Satkhira ) Project/ Rural Infrastructure development ( Khulna, Bagarhat & Satkhira ) Project, LGED Bhaban, Agargaon Sher-E-Bangla Nagar, Dhaka-1207

4.

Last date, time and places of receiving tender

:

Date:  15th March  2011, Time: 12.00 noon and                           

Places: Office of the undersigned / The concern Upazila Engineer, Upazila: Sadar,Tala & Shyamnagar District: Satkhira./ The Deputy Commissioner, Satkhira./The Superintendent of Police, Satkhira/The Executive Engineer, LGED  Jessore.

5.

Date, time and place of opening of tender

:

Date:  15th   March  2011, Time: 03.00 pm and

Place: Office of the undersigned

 

 

6.

Tender shall be valid for a period of 120 days after tender opening and must be accompanied by the tender security specified above. Interested Tenderer may obtain further information from the office of the undersigned and purchase the tender documents in cash/treasury chalan/ bank draft from the places mentioned above. The Tenderer or their authorized representatives are allowed to attend the opening of tenders. The authority reserves the right to accept or reject any or all the tenders without assigning any reasons whatsoever.

7.

The provisions laid down in the public Procurement Regulation (PRP) 2008, PRP(2nd revision)-2009 & PW-2,PW-3 for procurement of work will be binding upon the contractors

 

8.

In case of official estimate up to take 2.00(Two) crore, the total Quoted amount by the contractor Must not be less or above than 5% of the official estimate, otherwise the tender shall be rejected .

 

This invitation for tender is available on the website http/www.lged.gov.bd

 

 

 

(Md. Anwarul Islam)

Executive Engineer.

Ph:0471-63413

 

Memo No : LGED/XEN/Sat/ 11/ 295                                                                                                                    Dated  : 15/02/2011 

 

                Copy forwarded for kind information & necessary action to :

 

1.             The Superintending Engineer (Maint.) , LGED Bhaban, Agargaon Sher-E-Bangla Nagar, Dhaka-1207

2.             The Superintending Engineer, LGED, Khulna Region, District: Jessore.

3.             The Project Director, Union Infrastructure development ( Khulna, Bagarhat & Satkhira )Project/ Rural Infrastructure

development ( Khulna, Bagarhat & Satkhira ) Project, LGED Bhaban, Agargaon Sher-E-Bangla Nagar, Dhaka-1207

4.             The Deputy Commissioner, District: Satkhira.

5.             The Chief Executive Officer, Zilla Parishad, Satkhira.

6.             The Superintendent of Police, District: Satkhira.

7.             The Executive Engineer, LGED, District:_____________________.

8.             The Executive Engineer, RHD/PHE/BWDB, Satkhira.

9.             The Mayor, Pourashava, Satkhira.

10.           The Upazila Engineer, LGED, Upazila : _________________, Satkhira.

11.           Assistant Engineer, LGED, GIS Unit, Level - 4, LGED Bhaban, Agargaon, Dhaka-1207.

                He is requested to publish  the IFT at the LGED web site.

12.           The Editor .......................................................................  He is requested to publish the tender notice.

12.           Notice Board (All).

 

 

 

 

( G. M. Mujibor Rahman )

Senior Assistant Engineer.

LGED, Satkhira.