Construction of 668.00 m Long pre-stressed Girder Bridge over Baro Baliatoli Andermanik River at Kalapara Upazila under Patuakhali District. (Andermanik)

Menu
Project Office LGED
Construction of 668.00 m Long pre-stressed Girder Bridge over Baro Baliatoli Andermanik River at Kalapara Upazila under Patuakhali District.
Local Government Engineering Department (LGED)
RDEC Bhaban, Level-9, Agargaon, Sher-e-Bangla Nagar, Dhaka, BANGLADESH.

Andermanik, Progress Status

Sl. Title Publish Date Download
1 ADP Progress January 2019 04/02/2019
2 ADP Progress Dec 2018 15/01/2019
3 ADP Progress Report for the month of December 2018 10/01/2019
At a Glance
Short Title: Andermanik
Ministry: LGRD
Executing Agency: LGED
Approval Ref: 20.00.0000.412.06. 009.13-328 dte; 11-11-2013
Project Code: 224047200
Sector: Rural
Status: Ongoing Investment Project
Funded By: GOB.
Budget: 167.12 Crore
Start Date: Jul-2013
Completion Date: Jun-2021
Name of PD: Md. Ruhul Amin Khan