1
|
CuCC-RB-1
|
New Construction of Bus Terminal at Alekharchar
|
|
0.000
|
|
0.000
|
|
|
0
|
23/07/2026
|
After submission of the acquisition proposal on 06-02-2025. Ministry Team inspected the site on 02-04-2025, and final approval from the LGRD Ministry was received on 21-09-2025. PMU issued a letter to PE to expedite the process on 09-11-2025. Now, Land Acquisition Proposal (LAP) is being prepared by CuCC and will be submitted to DC office shortly.
On the other hand, the Topo & Geo survey has been done.
|
|
2
|
CuCC-D-4
|
Re-habilitation of Racecourse and Gungaijuri Drainage System
|
|
3460.913
|
|
3460.913
|
|
|
0
|
23/07/2026
|
Tender opened on 12-01-2026, and evaluation has been carried out & received by PMU. Then, PMU sent to the Ministry for approval in May 2026.
|
|
3
|
CuCC-OI-2
|
Improvement of Dharmosagor City Park
|
|
4854.281
|
|
4854.281
|
|
|
0
|
23/07/2026
|
Tender opened on 16-04-2026 and evaluation is in progress
|
|
4
|
CuCC-D-5
|
RCC drains in northern part of Sawpara area and East side of railway
|
|
4415.109
|
|
4415.109
|
|
|
0
|
23/07/2026
|
Tender opened on 29-12-2025, and evaluation has been carried out & received by PMU. Then, PMU sent to the Ministry for approval in May 2026.
|
|
5
|
CuCC-SWM-1
|
Improvement of collection, transportation system and Improvement of landfill site at Jhakunipara.
|
|
0.000
|
|
0.000
|
|
|
0
|
23/07/2026
|
Design, Drawing, Cnd ost Estimate submitted to PMU on 9 June 2026.
Land Acquisition revised proposal for 15 acres sent to the Ministry on 06-02-2025 for administrative approval for the UDCGP Subproject. PE is asking for an approval letter from PMU for 15 acres of land acquisition. After submission of the acquisition proposal on 06-02-2025. Ministry Team inspected the site on 02-04-2025, and final approval from the LGRD Ministry was received on 21-09-2025. PMU issued a letter to PE to expedite the process on 09-11-2025. Land Acquisition Proposal (LAP) submitted to the DC office on 01-12-2025. Now, the DC Office is in the process of verifying the LAP.
|
|
6
|
CuCC-RB-2
|
Expansion of Cumilla Bus Terminal at Ashrafpur (Jangalia bus stand)
|
|
0.000
|
|
0.000
|
|
|
0
|
23/07/2026
|
After submission of the acquisition proposal on 06-02-2025. Ministry Team inspected the site on 02-04-2025, and final approval from the LGRD Ministry was received on 21-09-2025. PMU issued a letter to PE to expedite the process on 09-11-2025. Lastly, the Ministry of LGRD formed a committee on 22-10-2025 for the submission of reports after visiting the disputed location/spots. Again, the LGRD Ministry reformed the previous committee on 24-03-2026. But the committee has not yet commenced their works.
In DED, the master plan preparation is ongoing.
|
|
7
|
CuCC-D-3
|
RCC drains besides Cumilla Chittagong Bypass Roads and Medical College Hospital Road.
i) Dhaneswar Road from Ch.0+000 to 0+180 km & from Ch. 0+000km to 0+300km. ii) Nagar Health Center Road from Ch. 0+000Km to 400Km. iii) Ballavpur Road from Ch. 0+000Km to 580Km. iv) Cumilla Chittagong Bypass Road from Ch. 0+000Km to Ch. 1+480Km. v) Goal Mathon Road from Ch. 0+000Km to Ch.0+680Km.
|
|
1772.372
|
Affan Builders Ltd.
|
1772.372
|
07/05/2025
|
06/07/2026
|
81
|
23/07/2026
|
The work started on 07-05-2025. The drain base, Vertical wall, and Top Slab 3245 m completed.
|
|
8
|
CuCC-OI-1
|
Supplying and installation of LED street light
|
|
1749.435
|
M/S RP Construction-Affan Builders Limited-Bothi Enterprise JV
|
1749.435
|
15/06/2025
|
13/10/2026
|
42
|
23/07/2026
|
1186 no. poles have been installed out of total 2437. Installation of Wire Rack, Insulator & Cables are done for 986 no. poles.
|
|
9
|
CuCC-D-2
|
RCC drain from Cumilla Chittagong Bypass Road to west side along the main road
|
|
824.025
|
MCS.MHE (JV)
|
824.025
|
21/02/2024
|
07/02/2025
|
21
|
23/07/2026
|
Work has been cancelled. Bill prepared as per joint measurement and Contractor signed a few days ago. Now preparation for sending PD office is in progress. Estimate of remaining works has been also sent to PD office/PMU.
|
|
10
|
CuCC-D-1
|
Construction of RCC drain in Chowara area.
Part : A i) Ch.1+390 km to Ch.0+170 km (Ulurchar Road) ii) Ch.0+700 km to Ch. 0+460 km (Pathankoat Road) iii) Ch.0+000 km to Ch. 0+277 km (Ulurchar Link Road) iv) Ch.0+387 km to 0+010 km (Milestone College Road & Old Dhaka Chattagram Road).
Part: B i) Ch.0+787 km to Ch.1+600 km (Old Dhaka Chattagram Road) ii) Ch.0+000 km to Ch.0+077km (Chowara Kitchen Market Road) iii) Ch.0+000 km to Ch.0+160 km (Chowara Kitchen Market Road) iv) Ch.1+020 km to Ch.1+140 km (Chowara Bazar Road).
Part: C i) Ch.0+972 km to 0+570 km (Chowara Bazar Road) ii) Ch.570 km to Ch. 0+(-20) km (Raipur Road) iii) Ch.0+067 km to Ch.0+000 km (Councillor Bari Raipur Road )
|
|
2251.696
|
Mostufa Zaman Traders(Pvt) Ltd.
|
2251.696
|
05/05/2025
|
06/07/2026
|
78
|
23/07/2026
|
The work started on 05-05-2025. The drain base, wall and Top Slab 3675m completed.
|