1
|
CoCC2-07
|
Installation of street lighting system in different areas of CoCC (2550 Nos. GI Pole with 2550 Nos. LED Street light Including all accessories)
|
|
2068.607
|
PDL-IEL-MDHV(JV)
|
2068.607
|
22/01/2018
|
21/01/2019
|
0
|
07/02/2019
|
|
|
2
|
CoCC2-06
|
Installation of 9 nos production Tube-wells including pump house with all other accessories in ward no 01 to 27
|
|
568.086
|
MSST-MCS JV
|
568.086
|
27/11/2018
|
26/11/2019
|
0
|
07/02/2019
|
|
|
3
|
CoCC2-08
|
b) Construction of Drain, Footpath & Road at Fazlul Hoque Road (From Kandirpar to Rajgonj) (Ch. 0+00 to 0+729) and Construction of Drain & Footpath from Post Office or Circuit House to Rajgonj (Ch. 0+000 to 0+626).
c) Re-construction of Drain Judge Court-Eidgah-Stadium Market-New Market-Kandirpar to Circit House road side Khal at Hotel Salauddin (Ch. 0+000 to 1+900).
|
5.0200
|
1506.450
|
Rana builders
|
1506.450
|
22/01/2018
|
21/01/2019
|
0
|
07/02/2019
|
|
|
4
|
CoCC2-05
|
(a) Excavation of Khal from Medical Hospital to EPZ road with beautification. ( Ch. 00 + 00 to 00 + 800 m.)
(b) Excavation of Airport khal (EPZ poket gate to Gopenathpur khal/Canal) . ( Ch. 00 + 00 to 05 + 000 m.)
(c) Excavation of Unaishar khal (South- Westen side of EPZ wall to Gopenathpur khal/Canal via Kazipara-Hirapur) with beautification ( Ch. 00 + 00 to 7 + 000 m.)
(d) Excavation of Kuchaitoly khal (Kuchaitoly to Gopenathpur khal/Canal via Donessor-Rajapara-Tarapaia) . ( Ch. 00 + 00 to 15 + 000 m.)
(e) Excavation of Sonaichori khal/Canal (from Pathankot to Gopenathpur khal/Canal via Chowara Bazar Matiara) . ( Ch. 00 + 00 to 06 + 000 m.)
|
28.4740
|
1665.060
|
HASAN TECHNO BUILDERS,TAHER BROTHERS LTD (JV)
|
1665.060
|
09/07/2018
|
03/09/2019
|
0
|
07/02/2019
|
|
|
5
|
ICGP B2 CoCC09
|
b) (i) Reconstruction of drain from Akther Hamid Khan road to Morden Hospital and Nowgaon chowmohoni (Laksam road) via RAB office, Ch.0+000-1+063.
b) (ii) Reconstruction of drain from Akther Hamid Khan road to Morden Hospital and Nowgaon chowmohoni (Laksam road) via RAB office, Link, Ch.0+000-0+341.
c) (i) Reconstruction of Rampur road from Kourt bari road (Cantonment gate and opposite side of land office) to Kourt bari road (Moynamoty Housing) via Rampur area, Ch.0+000-1+690. 1 x 1 m x 1 m Size Box Culvert at Ch.0+603, 0+825, 0+928, 1+207, 1+351, 1+385. & 1 x 3 m x 1.5 m Size Box Culvert at Ch.1+325,& 1x1.5mx1.5m box culvert at Ch.1+588.
c) (ii) Reconstruction of Rampur road from Kourt bari road (Cantonment gate and opposite side of land office) to Kourt bari road (Moynamoty Housing) via Rampur area, Link, Ch.0+000-0+593. 1 x 1.5 m x 1.5 m Size Box Culvert at Ch.0+476.
f) (ii) Reconstruction of drain from Laksam road to Easin market via Mirpukurpar, Ch.0+000-0+402.
g) Reconstruction of drain from Thomson bridge - EPZ (North side) - Housing Estate - Medical College near Bakhrabad Gas office.Ch.0+000-2+450. & Link drain At Ch.1+755(R/S), Ch.0+000-0+250.
|
6.7890
|
1466.377
|
Hasan builders
|
1466.377
|
17/12/2017
|
16/12/2018
|
0
|
07/02/2019
|
|
|
6
|
ICGP B2 CoCC04
|
(c) Re-construction of 8m span R.C.C. Bridge at Kazipara.
(d) Re-construction of 8m span R.C.C. Bridge at Near Noagah Chowmohony over katakhali khal.
(h) Construction of 3X5.0mX4.0m RCC Box Culvert at Rececourse Khalpar
|
0.0400
|
528.051
|
HASAN BUILDERS
|
528.051
|
17/12/2017
|
16/12/2018
|
0
|
07/02/2019
|
|
|
7
|
ICGP B2 CoCC-03
|
Part: 1, Road Improvement
a) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road to Airport Road (Laxmipur Chownohony) Via Gram Chowara And Laxmipur By B.C From I.SG.( Ch. 0+000 to 02+ 855 m). b) Reconstruction of Road Start From Old Dhaka-Chittagong Highway road (Near City Corporation Office) Via Raypur, Dayapur. Link From Doyapur Madrasa to Dhaka-Chittagong Highway Road By B.C From I.SG. (Ch. 0+000 to 02+ 772 m). c) Contraction of Road Start From Dhaka-Chittagong Highway Road to Airport Road, Domoria Road & Tarapaia Road Via Laxminagar, Laxmipur Katcha Road By B.C (Ch. 00+00 to 02+ 284 m) Link -1(Ch. 0+ 000 To 0+ 278) Link -2(Ch. 0+000 To 0+ 625) d) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road (Old Chowara) to Rajapara (Near Post Office) Via Domoria, Tarapaia & Noapara By B.C From I.S.G (Ch. 0+000 to 03+302m) e) Reconstruction of Dhaneshor Road (From Old Dhaka - Chittagong Highway Road to Airport Road) By B.C From I.S.G. (Ch.0+000 to 02+368m). f) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road to Airport Road Via Goalmothon & Rajapara By B.C From I.S.G (Ch.0+000 to 02+812m). Link -1 (Ch.0+000 to 0+700) g) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road (Chowara Madrasha & Chira Mill) to Dhaka-Chittagong Highway Road (Matiara & Chashapara) By B.C From I.S.G.(Ch.0+000 to 1+148m). Link -1 (Ch.0+000 to 0+657) Link-2 (Ch.0+000 to 0+539)
Part: 2, Drainage
a) Contruction of Drain (RCC) From Laxmipur Khal to Dhaka- Chittagong Highway Besides Airport Road & From Doyapur Madrasa (Ch. 0+000-0+712)Link -1 (Ch.0+000-1+372) b) Contruction of Drain (RCC) From Sonaichori Khal to Funka Industries Besides Old Dhaka-Chittagong Highway Road.(Ch.0+000-2+449)
|
24.8700
|
4260.584
|
HASAN TECHNO BUILDERS,TAHER BROTHERS LTD (JV)
|
4260.584
|
20/06/2018
|
26/10/2019
|
0
|
07/02/2019
|
|
|
8
|
CoCC2-02
|
(a) Reconstruction of road Start from Dhaka-Chittogong Highway road (Joypur) to Kotbari road (Singapur Market) area by B.C. from I.S.G.
(b) Reconstruction of road Start from Kotbari road (Beltoly school gate) to Batabaria moszid by B.C. from I.S.G.
(c) Development of Monipur road (from Batabaria to City Boundary) by B.C. from I.S.G.
(d) Reconstruction of road Start from Kotbari road (Gondmoty moszid) to Museum road (Shalbon High school & opposite side of BARD Boundary) & Gabtoly Beby Stand via Bagmara & Lalmai area. Link : Morapara road & Mannan Darbesh house road by B.C. from I.S.G.
(e) Repairing of Museum road (Kotbari road to University) by Base Course and B.C.
|
21.8170
|
3816.062
|
RAB-RC(PVT)LTD,M/S HOQUE ENTERPRISE (JV)
|
3816.062
|
20/06/2018
|
26/10/2019
|
0
|
07/02/2019
|
|
|
9
|
CoCC2-01
|
(a) Reconstruction of road Start from Kazipara road (Pry. School) to Kazipara road (Graveyard) via Kazipara area by B.C. from I.S.G. (b) Development of road from Old Ctg road (Chowara cattle market) to Dhaka – Chittagong Highway(matiara) via hindu para+ 1 bridge (30m)
(c) Reconstruction of road from Lacsam road to Airport road, and Kazipara road via herapur ,Mostapur, Laxminagar, Disabond and Kazipara
(d) Construction of Drain (RCC/Briek/ Pipe) from EPZ khal to Laxminagar Chowmohony, Asrayon, Airport road.by RCC
|
3.2000
|
1041.120
|
MAMCL-PC-SAS(JV)
|
1041.120
|
17/12/2017
|
16/12/2018
|
0
|
07/02/2019
|
|