Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Cox's bazar-s
1 CBP-RB-1 Construction of Road from Kasturaghat LGED bridge to Boat ghat. 2599.975 Dockyard & Engineering Works Limited (Address: Dockyard & Engineering Works Limited, Bangladesh Navy, Sonakanda, Bandar, Narayanganj-1413, Bangladesh) 2599.975 08/11/2027 0 23/07/2026 Contract Signed on 17 May 2026
2 CBP-WS-2 Installation of water distribution system in Ward 7 0.000   0.000 0 23/07/2026 Test tube well work is completed. ULB verbally informed of the cancellation of this subproject.
3 CBP-D-1 a) Construction of RCC Drain with footpath from Gonarpara, Krishnanondodham and Boddho Ghona to Bakkhali River via Bazarghata Chauln Bazar and Bora Bazar. b) Construction of RCC Drain with footpath from Kalur Dokan to Bakkhali River via Tekpara Primary School and Janata Sarak Sluice gate at 4 No. Ward 3575.799   3575.799 0 23/07/2026 Tender opened on 23-02-2026, now under evaluation by the ministry.
4 CBP-SWM-2 Development of sanitary landfill site in SM Para. 5334.481   5334.481 0 23/07/2026 The LA branch is preparing the joint investigation report. With CBP, Under the Tendering Process.
5 CBP-SWM-1 Improvement open dump site to Sanitary Land Fill at Pana Market 880.254 M/S Sampan Construction 880.254 10/04/2025 25/09/2026 12 23/07/2026 Waste shaping & Reservoir work is going on. One local person claims about 40% land in this SP as his own. ULB knows the issue. Pourashava Assistant Engineer advised the contractor to continue the work. If there is any problem, pourashava will solve it. Pourashava wants to solve the problem mutually.
6 CBP-RB-4 Construction of Coastal Road from Hotel Sayman to Marine Drive road. 1.2250 19557.619   19557.619 0 23/07/2026 Drawing, Design, and Cost Estimate submitted to PMU on 25 Sep 2025. Detailed design and drawing signed by CBP and sent to LGED HQ. A letter issued by CBP for partial NoC to the relevant authorities, NoC from RHD has been received already. A revised cost estimate is underway. The design report was submitted to RHD on 9 Feb 2026. Now waiting for their approval. NOCs received from the relevant authorities.
7 CBP-RB-3 Improvement of Central Bus Terminal 0.000   0.000 0 23/07/2026 Detailed design and drawing completed in January 2026. The Cost Estimate is ongoing.
8 CBP-RB-2 Construction of Coastal Road from Shugondha Point to Hotel Sayman. 1.2800 6517.238 National Development Engineers Ltd. 6517.238 10/05/2026 27/05/2028 0 23/07/2026 Contract Agreement was signed on 27 April 2026
9 CBP-OI-1 Update of existing street light to smart light system. 2988.620 HTMS Limited 2988.620 05/12/2025 25/05/2026 44 23/07/2026 Road restoration work and underground pipe laying work are going on. Revise estimate is approved on 16 March 2026.
10 CBP-WS-1 Installation of water distribution system in Ward 6, Ward 8 3278.981 FSL-SJC (JV) 3278.981 13/06/2024 01/12/2025 54 23/07/2026 HDPE pipe laying is ongoing. Extended time upto 13 May 2026. For work progress, the cost estimate needs to be revised for approval.
Total : 2.5050 (Km) 44732.97 (Lac) 44732.97 (Lac)