1
|
CBP-RB-1
|
Construction of Road from Kasturaghat LGED bridge to Boat ghat.
|
|
2599.975
|
Dockyard & Engineering Works Limited
(Address: Dockyard & Engineering Works Limited,
Bangladesh Navy, Sonakanda, Bandar,
Narayanganj-1413, Bangladesh)
|
2599.975
|
|
08/11/2027
|
0
|
23/07/2026
|
Contract Signed on 17 May 2026
|
|
2
|
CBP-WS-2
|
Installation of water distribution system in Ward 7
|
|
0.000
|
|
0.000
|
|
|
0
|
23/07/2026
|
Test tube well work is completed.
ULB verbally informed of the cancellation of this subproject.
|
|
3
|
CBP-D-1
|
a) Construction of RCC Drain with footpath from Gonarpara, Krishnanondodham and Boddho Ghona to Bakkhali River via Bazarghata Chauln Bazar and Bora Bazar.
b) Construction of RCC Drain with footpath from Kalur Dokan to Bakkhali River via Tekpara Primary School and Janata Sarak Sluice gate at 4 No. Ward
|
|
3575.799
|
|
3575.799
|
|
|
0
|
23/07/2026
|
Tender opened on 23-02-2026, now under evaluation by the ministry.
|
|
4
|
CBP-SWM-2
|
Development of sanitary landfill site in SM Para.
|
|
5334.481
|
|
5334.481
|
|
|
0
|
23/07/2026
|
The LA branch is preparing the joint investigation report.
With CBP, Under the Tendering Process.
|
|
5
|
CBP-SWM-1
|
Improvement open dump site to Sanitary Land Fill at Pana Market
|
|
880.254
|
M/S Sampan Construction
|
880.254
|
10/04/2025
|
25/09/2026
|
12
|
23/07/2026
|
Waste shaping & Reservoir work is going on.
One local person claims about 40% land in this SP as his own. ULB knows the issue. Pourashava Assistant Engineer advised the contractor to continue the work. If there is any problem, pourashava will solve it. Pourashava wants to solve the problem mutually.
|
|
6
|
CBP-RB-4
|
Construction of Coastal Road from Hotel Sayman to Marine Drive road.
|
1.2250
|
19557.619
|
|
19557.619
|
|
|
0
|
23/07/2026
|
Drawing, Design, and Cost Estimate submitted to PMU on 25 Sep 2025. Detailed design and drawing signed by CBP and sent to LGED HQ. A letter issued by CBP for partial NoC to the relevant authorities, NoC from RHD has been received already. A revised cost estimate is underway.
The design report was submitted to RHD on 9 Feb 2026. Now waiting for their approval.
NOCs received from the relevant authorities.
|
|
7
|
CBP-RB-3
|
Improvement of Central Bus Terminal
|
|
0.000
|
|
0.000
|
|
|
0
|
23/07/2026
|
Detailed design and drawing completed in January 2026.
The Cost Estimate is ongoing.
|
|
8
|
CBP-RB-2
|
Construction of Coastal Road from Shugondha Point to Hotel Sayman.
|
1.2800
|
6517.238
|
National Development Engineers Ltd.
|
6517.238
|
10/05/2026
|
27/05/2028
|
0
|
23/07/2026
|
Contract Agreement was signed on 27 April 2026
|
|
9
|
CBP-OI-1
|
Update of existing street light to smart light system.
|
|
2988.620
|
HTMS Limited
|
2988.620
|
05/12/2025
|
25/05/2026
|
44
|
23/07/2026
|
Road restoration work and underground pipe laying work are going on.
Revise estimate is approved on 16 March 2026.
|
|
10
|
CBP-WS-1
|
Installation of water distribution system in Ward 6, Ward 8
|
|
3278.981
|
FSL-SJC (JV)
|
3278.981
|
13/06/2024
|
01/12/2025
|
54
|
23/07/2026
|
HDPE pipe laying is ongoing.
Extended time upto 13 May 2026. For work progress, the cost estimate needs to be revised for approval.
|