Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Chakoria
1 IRIDP-2/COX/DW-7 a) Improvement of Hajian Madha Para- Hajian GPS Road (Shikolghat RHD-Hajian-Kakara UP Connecting) Road from Ch:00-850m.b) Construction of 01 no 0.625mx0.600m culvert at ch. 35m on the same road. 0.8500 49.800 M/S. Nazrul Construction 49.800 05/09/2016 28/02/2017 100 23/12/2018  
2 IRIDP-2/COX/DW-6 Improvement of Upazila Head Quarter-Mog Bazar-Chiringa Up via Rubber dam vai jalasha vai Rampura Bazar RHD Road (Rampur Jalasha) Road from Ch:871-2121m. 1.2490 68.250 M/S. Hakim & Brothers 68.250 02/02/2016 25/12/2017 72 23/12/2018  
3 IRIDP-2/COX/DW-5 Improvement of Badarkhali 2No. Block RHD West side UZR Connecting Road from Ch:00-496m. 0.4960 37.540 M/S.Ruma Construction 37.540 11/02/2016 25/06/2018 100 23/12/2018  
4 IRIDP-2/COX/DW-4 a) Improvement of Malumghat Bazar RHD- Cha Bagan-Lama Connecting Road from Ch:00-1000m.b) Construction of 02 nos 0.625mx0.600m culvert at ch. 510 & 980m on the same road. 1.0000 58.590 M/S. Suchana Enterprise 58.590 03/02/2016 02/08/2016 100 23/12/2018  
2 Cox's bazar-s
1 IRIDP-2/COX/DW-10 a) Improvement of Bou Bazar-Chaberpara Jame Mosco via Shikderpara Primary School Road from Ch:00-470m.b) Construction of 03 nos 0.625mx0.600m culvert at ch. 232, 271 & 400m on the same road. 0.4700 30.050 M/S. Bushra Enterprise 30.050 16/03/2016 20/06/2017 100 23/12/2018  
2 IRIDP-2/COX/DW-9 Improvement of Khurulia Nayapara Road from Ch:00-514m. 0.5140 30.000 M/S.Ruma Construction 30.000 11/02/2016 25/01/2018 100 23/12/2018  
3 IRIDP-2/COX/DW-8 a) Improvement of Asfaker Shop to babul Co.House From Side Via Haidarpara to battatali (West Chowfaldandi) Road from Ch:00-1037m.b) Construction of 01 no 0.900mx0.900m culvert at ch. 404m on the same road. 1.0300 60.030 M/S.Ruma Construction 60.030 11/02/2016 30/04/2018 100 23/12/2018  
3 Pekua
1 IRIDP-2/COX/DW-3 a) Improvement of Sonali Bazar to Uzantia Koloni Cyclone Shelter Connecting road from Ch:00-387m.b) Construction of 01 no 0.625mx0.600m culvert at ch. 93m on the same road. 0.3870 24.820 Md. Didarul Islam 24.820 30/03/2016 15/06/2017 100 23/12/2018  
2 IRIDP-2/COX/DW-2 Improvement of Kazir Bazar to Katafari Road from Ch:11-223m. 0.1100 27.070 M/S. Hossain & Brothers 27.070 27/03/2016 15/02/2017 100 23/12/2018  
3 IRIDP-2/COX/DW-1 a) Improvement of Taitong Napitkhali Razakhali Mognama Upkulia from Ch:6000-6384m.b) Construction of 01 no 0.625mx0.600m culvert at ch. 6425m on the same road. 0.3800 24.480 M/S. K.R. Builders 24.480 07/03/2016 30/04/2017 100 23/12/2018  
4 Ramu
1 IRIDP-2/COX/DW-15 Improvement Ramu Ukhiarghona -Gorjania Road from Ch.00-689m. 0.6890 44.590 M/S. Bazal & Brothers 44.590 07/03/2016 31/12/2017 100 23/12/2018  
2 IRIDP-2/COX/DW-14 Kaccapia UP-Rubber Dam Connecting Road from Ch: 1300-2104m. 0.8000 45.000 M/S. Bazal & Brothers 45.000 25/02/2016 28/02/2018 100 23/12/2018  
3 IRIDP-2/COX/DW-13 a) Improvement of Rajarkul UP Office-Shikalghat Kawarkhope UP Road from Ch:1292-2200m.b) Construction of 01 no 1x1.00x1.00m culvert at ch. 2170m on the same road.c) Construction of 01 nos 0.625mx0.600m culvert at ch. 2050m on the same road. 0.9100 57.770 M/S. Bazal & Brothers 57.770 07/03/2016 31/12/2017 100 23/12/2018  
4 IRIDP-2/COX/DW-12 Improvement of Joarianala -Shoudagor para Road from Ch:000-522m. 0.5220 30.000 M/S. Bazal & Brothers 30.000 25/02/2016 28/02/2018 100 23/12/2018  
5 IRIDP-2/COX/DW-11 a) Improvement of Ramu Central Jame Mosque -Mondol Para Road from Ch:00-385m.b) Construction of 02 nos 0.625mx0.600m culvert at ch. 140 & 225m on the same road. 0.3850 29.990 M/S. M. Haque & Co. 29.990 08/02/2016 30/10/2016 100 23/12/2018  
Total : 9.7920 (Km) 617.98 (Lac) 617.98 (Lac)