Project Scheme Detail List
SL No.
Package No.
Name
Length (Km)
Allotment (Lac)
Name of Contractor
Contract Amount (Lac)
Date of Commencement
Date of Completion
Physical Progress (%)
Date of Progress Update
Remarks
1
B.baria-s
1
W.611
Construction of NATAY (UTTAR) UP Complex
101.500
101.500
30/05/2019
70
16/08/2020
FINAL
2
w.399
Construction of shuhilpur (s) UP Complex
89.540
89.540
24/05/2017
100
16/08/2020
FINAL
2
Bancharampur
1
W.295
Construction of SALIMABAD UP Complex
82.410
82.410
04/10/2016
100
13/08/2020
FINAL
2
W.017
Construction of SAIFULLAKANDI UP Complex
69.820
69.820
05/03/2014
100
13/08/2020
FINAL
3
w.222
Construction of PAHARIAKANDI UP Complex
81.060
81.060
29/08/2015
100
13/08/2020
FINAL
3
BijoyNagar
1
w.545
Construction of Singrabil UP Complex
115.480
115.480
20/06/2019
100
16/08/2020
final
2
w.413
Construction of Paharpur UP Complex
88.390
88.390
17/09/2016
100
16/08/2020
final
3
W.479
Construction of CHAR-ISLAMPUR UP Complex
104.570
104.570
12/11/2018
100
13/08/2020
FINAL
4
Nabinagar
1
129/176
Construction of kaitala (s) UP Complex
87.940
87.940
30/06/2015
100
31/08/2020
final
2
w.579
Construction of bitghor UP Complex
116.870
116.870
14/04/2019
100
16/08/2020
ongoing
3
w.072
Construction of shymogram UP Complex
84.080
84.080
30/03/2015
100
16/08/2020
final
4
w.089
Construction of dabhallusar UP Complex
84.080
84.080
100
16/08/2020
final
5
197/246
Cons. of Sreerampur up
59.000
59.000
30/06/2011
100
11/07/2020
revised & final
5
Sarail
1
W.134
Construction of CHUNTA UP Complex
83.760
83.760
30/01/2016
100
16/08/2020
FINAL
Total :
0.0000 (Km)
1248.50 (Lac)
1248.50 (Lac)