SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 B.baria-s
1 PD CLBUURP, W-196 Const.of RCC Bridge on Panchaboti R&H - Akhaura Borobazar road at Ch.7360m over Louho river 230.990 M/S Mostafa Kamal 230.990 27/10/2011 16/05/2014 100 01/04/2019
2 Bancharampur
1 PD CLBUURP, W-366 Const. of Bridge on Nogorirchar Khal at Baherchar-Dhariarchar road via Nogorirchar road at Ch.600m. 1.000 1.000 0 25/01/2021 Switched for FS to IBRR
2 PD CLBUURP, W-194A b) Remaining Work (Approach road) for Const. of RCC Y-shape Bridge on Charlohalia & Burburia Village of Bancharampur - Ramkrishnapur village of Homna road. 2782.000 Navana Construction Ltd. 2782.000 13/12/2015 19/06/2016 100 21/05/2019
3 PD CLBUURP, W-194 a) Const. of RCC Y-shape Bridge on Charlohalia & Burburia Village of Bancharampur - Ramkrishnapur village of Homna road. 6809.620 WMCG -Navana 6809.620 09/06/2011 10/09/2014 100 21/05/2019
3 BijoyNagar
1 PD CLBUURP, W-197 Const.of RCC Bridge on Amtali NHW-Madabpur GC Via Satborga Bazar road over Sonai river 291.580 MMK & MRC 291.580 14/06/2011 20/12/2012 100 18/02/2020
4 Kasba
1 PD CLBUURP, W-195 Const.of RCC Bridge on Kharara R&H - Shimrail GC via Kheora Bazar road at Ch. 7550m. 146.470 M/S Tushi Enterprise 146.470 24/10/2011 01/05/2013 100 21/05/2019
5 Nabinagar
1 PD CLBUURP, W-366A Const.of Bridge on Ibrahimpur to Jamuna Khal road via Palpara bazar at Ch. 3564m. 1.000 1.000 0 25/01/2021 Switched for FS to IBRR
2 PD CLBUURP, W-194B d) Const.of RCC Bridge on shahagoda-shahapur Agrani Bank road over Nabinagar-Muradnagar inter upazila khal. 0.000 0.000 0 07/07/2019 Not required
Total : 0.0000 (Km) 10262.66 (Lac) 10262.66 (Lac)