Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Alikadam
1 IRIDP-2/BAN/DW-15 Improvement of Rafer Bazar. 30.350 M/S. U T Mong 30.350 19/10/2017 30/08/2018 90 23/12/2018  
2 IRIDP-2/BAN/DW-10 Development of Puamuhuri Bazar. 24.270 UC Manue Marma 24.270 10/04/2017 28/02/2018 100 23/12/2018  
3 IRIDP-2/BAN/DW-9 Development of Karuk pata Bazar. 24.270 UC Manue Marma 24.270 10/04/2017 28/02/2018 100 23/12/2018  
2 Lama
1 IRIDP-2/BAN/DW-7 Development of Sarai(Daluchari) Bazar. 30.110 Ms. Azizur Rahaman & Con. 30.110 28/10/2017 20/06/2018 100 23/12/2018  
2 IRIDP-2/BAN/DW-6 Development of Kumari Bazar. 35.940 Ratan Sen Tanchangaya 35.940 10/04/2017 03/10/2017 100 23/12/2018  
3 IRIDP-2/BAN/DW-5 a) Improvement of Malumghat Tea state-Boro Chonkhola road from Ch: 00-2100m.b) Construction of 0.60mx1.125m culvert at 565 & 700m on the same road. 2.1000 112.870 M/S Milton Traders 112.870 10/04/2017 30/04/2018 100 23/12/2018  
4 IRIDP-2/BAN/DW-1 a) Improvement of Fitong-Chiubtoli road from Ch: 00-2000m. b) Construction of 05 nos 0.600mx1.125m culvert at ch.590,1140,1290,1770 & 1920m on the same road. c) Construction of 01 no 1x3.00x2.50m culvert at ch.740m on the same road. d) Construction of 01 2.0000 99.470 M/S Absar Construction 99.470 30/03/2016 30/09/2017 100 23/12/2018  
3 Naikhyongchari
1 IRIDP-2/BAN/DW-8 a) Improvement of Sonaichari UP Office-Kawerkhope Bazar road from Ch: 1000-1522m.b) Construction of 1.60mx1.60m culvert at 1060m on the same road. 52.980 MS. Prasanna Kanti Amu 52.980 10/04/2017 30/01/2019 85 23/12/2018  
2 IRIDP-2/BAN/DW-2 a) Improvement of Sonaichari UP Office-Kawerkhope Bazar road from Ch: 00-1000m. b) Construction of 02 nos 1.60mx1.60m culvert at ch.261 & 947m on the same road. c) Construction of 01 no 4.00mx3.00m culvert at ch.855m on the same road. 1.0000 101.340 M/S Milton Traders 101.340 14/03/2016 07/03/2017 100 23/12/2018  
4 Rowangchari
1 IRIDP-2/BAN/MW-14 Maintenance of Rowangchari Bazar GC Road from Ch: 570-2113m. 1.5600 46.640 M/S. U T Mong 46.640 03/10/2017 03/03/2018 100 23/12/2018  
2 IRIDP-2/BAN/DW-13 Improvement of Moorong Bazar. 29.930 M/S. U T Mong 29.930 0 23/12/2018  
3 IRIDP-2/BAN/DW-4 a) Improvement of Ruma BC-Mawofa para via Tarasa UP Office road from Ch: 00-1000m.b) Construction of 03 nos 1x2.00mx2.00m culvert at ch.1000,1160 & 1455m on the sam6e road.c) Construction of 01 no 1.60mx1.60m culvert at ch.1335m on the same road. 1.0000 99.000 Shah Jabbaria Enterprise 99.000 27/10/2017 16/07/2018 100 23/12/2018  
5 Ruma
1 IRIDP-2/BAN/DW-3 a) Improvement of Bagalake- Chinglok Para road from Ch: 2535-3553m.b) Construction of 02 nos 1.60mx1.60m culvert at ch.2582 & 2332m on the same road.c) Construction of 01 no 2x4.50x4.50m culvert at ch.1880m on the same road.d) Construction of 02 nos 1x2.0 1.0000 98.960 M/s Emmu Construction. 98.960 30/05/2016 30/06/2018 100 23/12/2018  
6 Thanchi
1 IRIDP-2/BAN/DW-12 Improvement of Blipara Bazar. 70.500 M/S. U T Mong 70.500 18/10/2017 21/07/2018 100 23/12/2018  
2 IRIDP-2/BAN/DW-11 Improvement of Thanchi Bazar. 37.310 M/S. U T Mong 37.310 24/08/2017 27/08/2017 100 23/12/2018  
Total : 8.6600 (Km) 893.94 (Lac) 893.94 (Lac)