SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
|
1
|
Baghaichari
|
|
1
|
RANG/BAGHAI/ BRIDGE/W44
|
Construction of 105.00m long PC Girder Bridge on Marishya bazar-Durchari bazar road at ch.10170m
ID No:
|
|
578.829
|
M/S Nipa Enterprise – MNS (JV) R. F Classic Point (1st Floor), 8 Katalgonj Road(Beside Oil kha Mosque), Chawkbazar, Chittagong
|
578.829
|
|
16/10/2019
|
15
|
26/12/2018
|
|
|
2
|
RANG/BAGHAI/UZR/W15
|
Development of Durchari bazar-Karallyachari bazar Road up to Supari Pata Chara
|
1.2600
|
157.090
|
M/S Shaleha Enterprise
|
157.090
|
|
30/11/2018
|
70
|
26/12/2018
|
Box cutting Gi KvR Pj‡Q|
|
|
3
|
RANG/BAGHAI/BRIDGE/W34
|
Construction of 54.06m Long RCC Girder Bridge on Durchari bazar-Karallyachari bazar Road up to Supari Pata Chara Ch.3940m, ID No.
|
|
205.261
|
M/S Nipa Enterprise
|
205.261
|
|
01/10/2019
|
100
|
26/12/2018
|
|
|
4
|
RANG/BAGHAI/UNR/W14
|
Development of Thana H/Q-Doser road
|
0.9100
|
87.443
|
M/S Byagio Enterprise
|
87.443
|
|
14/05/2019
|
100
|
26/12/2018
|
Earth cutting Gi KvR Pj‡Q|
|
|
5
|
RANG/BAGHAI/UNR/W07
|
Thana H/Q-Doser road
|
1.0900
|
89.094
|
Mayadhan Chakma
|
89.094
|
|
28/02/2018
|
100
|
26/12/2018
|
HBB ‡kl gvwU fivU Gi KvR Pj‡Q|
|
|
6
|
RANG/BAGHAI/UZR/W06
|
Development of Durchari bazar-Karallyachari bazar Road up to Supari Pata Chara
|
1.7400
|
191.119
|
Suvanankar Chakma
|
191.119
|
|
30/06/2018
|
70
|
26/12/2018
|
|
|
7
|
RANG/BAGHAI/UZR/W05
|
Development of Marishya bazar-Durchari bazar road
|
1.7200
|
166.455
|
Nishith Baran Talukder, Art Council, Rangamati
|
166.455
|
|
30/06/2018
|
75
|
26/12/2018
|
|
|
|
2
|
Barkal
|
|
1
|
/ RANG/BARKAL/V.Road//W45
|
Development of Barkal Upazila HQ (BGB Mosque) to – Barkal College via Barkal Simanta Vocational Institute road by HBB Pavment; (Barkal H/Q-TO Choto Horina Road (Ch: 1+888-3.388km)=1.5km; ID No: 484212001)
|
1.0780
|
92.231
|
M/S U. M Traders, Majerbasti, Rangamati, Sadar, Rangamati
|
92.231
|
04/01/2018
|
08/04/2019
|
100
|
26/12/2018
|
|
|
|
3
|
Belaichari
|
|
1
|
RANG/BAGHAI/ UZR/W60
|
Rehabilitation of Marishya Bazar-Durchari Bazar Road from Effective Length-2475m
|
2.4750
|
211.779
|
Mr.UT Mong,Maddayum Para Bandarban.
|
211.779
|
|
31/10/2019
|
0
|
26/12/2018
|
|
|
2
|
RANG/BAGHAI/ UZR/W59
|
Rehabilitation of Marishya Bazar-Durchari Bazar Road from & Thana Link Road Ch. 00-62m .; Effective length-2087m
ID No.
|
2.0870
|
230.039
|
Mr.UT Mong,Maddayum Para Bandarban.
|
230.039
|
|
31/10/2019
|
10
|
26/12/2018
|
|
|
3
|
RANG/BELAI/ UZR/W48
|
Development of Belaichari -Farua bazar road Effective Length =1300.00m;
|
1.3000
|
293.070
|
Mr U. T. Mong, Madyam Para, 4 no. Ward, Bandarban Pourosava, Bandarban
|
293.070
|
|
17/03/2019
|
80
|
26/12/2018
|
|
|
|
4
|
Juraichari
|
|
1
|
WD/RIDPCHT-2/ RANG/ JURAI / UNR/W30
|
Periodic Maintenance of Jurachari H/Q-Eraichari Ghat road at
|
0.4200
|
39.390
|
M/S Milton Traders, Roangchari,Bandarban
|
39.390
|
|
31/05/2018
|
100
|
26/12/2018
|
|
|
2
|
RANG/JURAI/ UZR/W47
|
Development of Jurachari H/Q-Shilchari G.C. road Effective Length =1440.00m;
|
1.4400
|
429.913
|
M/S RIP ENTERPRISE, Narankhya, Khagrachari, Sadar, Khagrachari
|
429.913
|
11/01/2018
|
08/11/2019
|
0
|
26/12/2018
|
|
|
3
|
RANG/JURAI/ UZR/W46
|
Development of Jurachari H/Q-Shilchari G.C. road Effective Length =2260.00m;
|
2.2600
|
294.638
|
M/S RIP ENTERPRISE, Narankhya, Khagrachari, Sadar, Khagrachari
|
294.638
|
07/03/2018
|
13/03/2019
|
30
|
26/12/2018
|
|
|
4
|
RANG/JURAI/ BRIDGE/W43
|
Construction of 210.00m long PC Girder Bridge on Jurachari H/Q-Shilchari G.C. road at ch.5970m
ID No: 484472002
|
|
1393.521
|
Quashem Construction & Nahin Enterprise (JV), Millennium Tower (4th Floor) 1558, Agrabad Access Road, Chittagong.
|
1393.521
|
01/04/2018
|
03/10/2019
|
15
|
26/12/2018
|
|
|
5
|
|
Juraichari G.C.-Chalka para Via Lulang Chari road.(Ch: 00-2444m=2.44km) & (Ch: 3944-4944m=1.00km) =3.44km
|
|
0.000
|
|
0.000
|
|
|
0
|
26/12/2018
|
|
|
6
|
RANG/JURAI/ UZR/W01
|
Jurachari H/Q-Shilchari G.C. road
|
1.5000
|
121.536
|
M/S Rip Enterprise
|
121.536
|
03/07/2016
|
12/03/2018
|
80
|
26/12/2018
|
|
|
7
|
RANG/JURAI/ UZR/W10
|
Jurachari H/Q-Shilchari G.C. road
|
1.5300
|
14995914.000
|
M/S Rip Enterprise
|
14995914.000
|
|
29/03/2018
|
1
|
26/12/2018
|
Re-cast
|
|
|
5
|
Kaptai
|
|
1
|
RANG/KAPTAI/UNR/W53
|
Rehabilitation of Baraghonia Market-Debotachari bazar via Tanchangapara road.
|
2.8000
|
241.084
|
M/S RIP ENTERPRISE, Narankhya, Khagrachari, Sadar, Khagrachari
|
241.084
|
|
25/06/2019
|
10
|
26/12/2018
|
|
|
2
|
RANG/KAPTAI/UZR/W20
|
Periodic Maintenance of Raikhali Barakolapara-Bangalhalia R&H ctg. Border via Bongnal road.
|
1.0000
|
33.328
|
M/S Marma Enterprise, Ruma, Bandarban
|
33.328
|
|
30/07/2017
|
100
|
26/12/2018
|
|
|
|
6
|
Kaukhali
|
|
1
|
RANG/KAWK/UNR/W52
|
Periodic Maintenance of Goiatal-Sonaichari road.
|
3.0000
|
100.883
|
S. Ananta Bikash Tripura, Milonpur Khagrachari
|
100.883
|
04/01/2018
|
17/04/2019
|
40
|
26/12/2018
|
|
|
2
|
RANG/KAWK/UZR/W56
|
Periodic Maintenance of Kawkhali HQ- Gagra bazar road.
|
5.0000
|
71.544
|
Mr U. T. Mong, Madyam Para, 4 no. Ward, Bandarban Pourosava, Bandarban
|
71.544
|
|
16/08/2019
|
0
|
26/12/2018
|
|
|
3
|
RANG/KAWK/UZR/W04
|
Periodic Maintenance of Kawkhali HQ- Sugarmil Road ch.
|
1.0000
|
129.155
|
M/S SS Traders
|
129.155
|
|
31/12/2017
|
100
|
26/12/2018
|
WBM Gi KvR Pj‡Q|
|
|
4
|
RANG/KAWKH/ BRIDGE/W41
|
Construction of 20m long RCC Girder Bridge on Kawkhali H/Q-Sugarmill road at ch. 2430m. ID No:
|
|
79.962
|
M/S RIP ENTERPRISE, Narankhya, Khagrachari, Sadar, Khagrachari
|
79.962
|
|
25/06/2019
|
5
|
26/12/2018
|
|
|
5
|
RANG/KAWK/ UZR/W50
|
Development of Ghilachari - Panchari Road ; Effective Length =1912.00m;
|
1.9120
|
264.359
|
Mr U. T. Mong, Madyam Para, 4 no. Ward, Bandarban Pourosava, Bandarban
|
264.359
|
|
03/02/2019
|
20
|
26/12/2018
|
|
|
6
|
RANG/KAWKHALI/ BRIDGE/W27
|
Construction of 42.06m long RCC Bridge on Ghilachari - Panchari Road road at ch. 7519m. ID No:
|
|
131.891
|
Mr U.T Mong, Bandarban sadar,Bandarban, Khagrachari
|
131.891
|
|
30/04/2018
|
90
|
26/12/2018
|
|
|
7
|
RANG/KAWKHALI/ BRIDGE/W33
|
Construction of 50.06m long RCC Girder Bridge on Ghilachari - Panchari Road road at ch. 6510m. ID No:
|
|
208.759
|
Mr U.T Mong, Bandarban sadar,Bandarban, Khagrachari
|
208.759
|
|
20/06/2018
|
5
|
26/12/2018
|
|
|
8
|
RANG/KAWKHALI/ BRIDGE/W24
|
Construction of 20m long RCC Girder Bridge on Kawkhali H/Q to Sugarmil road at ch. 700m
ID No:
|
|
153.517
|
Mr U.T Mong, Bandarban sadar,Bandarban, Khagrachari
|
153.517
|
|
11/12/2017
|
100
|
26/12/2018
|
|
|
9
|
RANG/KAWK/UZR/W02
|
Ghilachari - Panchari Road
|
1.0100
|
136.718
|
Mayadhan Chakma
|
136.718
|
|
15/02/2017
|
100
|
26/12/2018
|
Sand filling & Protection Gi KvR Pj‡Q|
|
|
|
7
|
Langadu
|
|
1
|
RANG/LANGU/ UZR/W36
|
Periodic Maintenance of Longadu-Mainimukh road. BC & HBB road
|
0.5100
|
56.490
|
Jatnashar Tripura, Madhupur, khagrachari
|
56.490
|
|
21/05/2018
|
95
|
26/12/2018
|
|
|
2
|
RANG/LANGU/ UZR/W35
|
Periodic Maintenance of Longadu-Mainimukh road. BC & HBB road
|
0.6000
|
67.442
|
M/S Milton Traders, Rowangchari, Bandarban
|
67.442
|
|
27/05/2018
|
100
|
26/12/2018
|
|
|
3
|
RANG/LANGU/VILL/W61
|
Development of Attrakchara UPC Islamabad R& H Road at the Shop of Jalil PC-Sonai Market via the H/O Barek Chowkider Road
|
0.9000
|
53.673
|
|
53.673
|
|
|
0
|
26/12/2018
|
|
|
4
|
RANG/LANGU/BRIDGE//W60
|
Construction of 84.00m long RCC Girder Bridge Noksobil Canal on Mainimukh -Forest office to Durchari Bazar road Ch.9+054 km, ID No.
|
|
422.699
|
|
422.699
|
|
|
0
|
26/12/2018
|
APP Approved Date: 08/10/18
|
|
5
|
RANG/LANGU/UNR/W57
|
Development of Bagachattar- CO's Tila road
Effective Length-1020m.
ID No.
|
1.0200
|
112.316
|
M/S Shalaha Enterprise
|
112.316
|
|
24/07/2019
|
50
|
26/12/2018
|
|
|
6
|
RANG/LANGU/UNR/W51
|
Development of Kalapakuzza Union (Mahilla)-Mainimukh growth center road
|
1.2840
|
101.543
|
M/S U. M Traders, Majerbasti, Rangamati, Sadar, Rangamati
|
101.543
|
|
17/04/2019
|
55
|
26/12/2018
|
|
|
7
|
RANG/LANGU/ BRIDGE/W42
|
Construction of 105.00m long PC Girder Bridge on Kalapakuzza Union(Mahilla) -Mainimukh growth center Road at ch.2045m.
ID No:
|
|
708.910
|
M/S Nipa Enterprise, & S. Ananta Bikash Tripura (JV)
|
708.910
|
|
16/02/2019
|
0
|
26/12/2018
|
|
|
8
|
RANG/LANGU/ BRIDGE/W40
|
Construction of 90.00m long RCC Girder Bridge on Maini Mukh Forest office to Durchari Bazar road ch.8454m
ID No:
|
|
319.237
|
M/S Rip Enterprise
|
319.237
|
|
19/03/2019
|
80
|
26/12/2018
|
|
|
9
|
RANG/LANGU/ BRIDGE/W39
|
Construction of 140.00m long RCC Girder Bridge on Kalapakuzza Union(Mahilla) -Mainimukh growth center Road at ch. 3520m.
ID No:
|
|
569.801
|
Mr U.T Mong, Bandarban sadar,Bandarban, Khagrachari
|
569.801
|
|
19/03/2019
|
20
|
26/12/2018
|
|
|
10
|
RANG/LANGU/UNR/W19
|
Development of Bagachattar- CO's Tila road
|
0.5850
|
52.963
|
M/S Mita Tripura, Rangamati
|
52.963
|
|
31/05/2018
|
85
|
26/12/2018
|
Re-cast
|
|
11
|
RANG/LANGU/UNR/W18
|
Development of Bagachattar- CO's Tila road
|
0.3900
|
67.174
|
M/S Mita Tripura, Rangamati
|
67.174
|
18/07/2016
|
31/05/2018
|
85
|
26/12/2018
|
Re-cast
|
|
12
|
RANG/LANGU/UZR/W12
|
Development of Mainimukh -Forest office to Durchari Bazar road
|
1.8230
|
187.546
|
M/S Milton Traders, Rowangchari, Bandarban
|
187.546
|
|
19/11/2017
|
60
|
26/12/2018
|
|
|
13
|
RANG/LANGU/UZR/W11
|
Development of Mainimukh -Forest office to Durchari Bazar road
|
2.0210
|
241.298
|
Nishith Baran Talukder, Art Council, Rangamati
|
241.298
|
|
01/10/2018
|
100
|
26/12/2018
|
Re-cast
|
|
14
|
RANG/LANGU/UNR/W09
|
Development of Kalapakuzza Union (Mahilla)-Mainimukh growth center road
|
0.9950
|
130.260
|
M/S Shaleha Enterprise
|
130.260
|
|
30/11/2018
|
95
|
26/12/2018
|
Re-cast
|
|
15
|
RANG/LANGU/UZR/W08
|
(Part-A) Mainimukh -Forest office to Durchari Bazar road (Part -B) Mainimukh -Forest office to Durchari Bazar road.
|
2.1100
|
172.420
|
M/S Salim & Brothers
|
172.420
|
|
30/11/2017
|
100
|
26/12/2018
|
|
|
16
|
RANG/LANGU/UNR/W13
|
Development of Kalapakuzza Union (Mahilla)-Mainimukh growth center road
|
1.8760
|
18620265.000
|
M/S Shaleha Enterprise
|
18620265.000
|
|
25/05/2018
|
1
|
26/12/2018
|
Re-cast
|
|
|
8
|
Nanniarchar
|
|
1
|
RANG/NANIA/UZR/W03
|
Development of R & H road - Karatchari via Golachari road
|
1.0000
|
116.319
|
M/S Dewan Enterprise
|
116.319
|
|
11/08/2016
|
100
|
26/12/2018
|
WBM ‡kl Ges Protection Gi KvR Pj‡Q|
|
|
|
9
|
Rajosthali
|
|
1
|
RANG/RAJOS/UZR/W55
|
Periodic Maintenance of Rajosthali H/Q-Khansama para road
|
2.0000
|
30.630
|
Mr. U T Mong, Maddampara, Bandarban
|
30.630
|
|
25/04/2019
|
100
|
26/12/2018
|
|
|
2
|
RANG/RAJOS/UNR/W54
|
Periodic Maintenance of Bangalhalia-Raikhali Barakhola para via Dongnala road.
|
2.0000
|
22.989
|
Nishith Baran Talukder, Tobolchari, Rangamati
|
22.989
|
|
25/04/2019
|
0
|
26/12/2018
|
|
|
3
|
RANG/RAJOS/ UZR/W58
|
Development of Rajasthali H/Q-Khansama para road (To words Bagmara GC)
Effective Length-3000m.
|
3.0000
|
299.506
|
M/S RIP ENTERPRISE, Narankhya, Khagrachari, Sadar, Khagrachari
|
299.506
|
|
27/06/2019
|
0
|
26/12/2018
|
|
|
4
|
RANG/RAJOS/ UZR/W17
|
Development of Rajasthali H/Q-Khansama para road (To words Bagmara GC)
|
0.6500
|
165.618
|
Mr. UT Mong, Madham para, Sadar, Bandarban
|
165.618
|
|
28/05/2018
|
100
|
26/12/2018
|
Re-cast
|
|
5
|
RANG/RAJOS/ UZR/W16
|
Development of Rajasthali H/Q-Khansama para road (To words Bagmara GC)
|
0.6600
|
151.604
|
Mr. UT Mong, Madham para, Sadar, Bandarban
|
151.604
|
|
30/05/2018
|
100
|
26/12/2018
|
Re-cast
|
|
|
10
|
Rangamati-s
|
|
1
|
RANG/SADAR/UZR/W23
|
Periodic Maintenance of Jhagrabil (R&H) - Kaptai (R&H) via Baradam Road . Effectiove length 2500m,
|
2.5000
|
103.125
|
Mayadhan Chakma
|
103.125
|
|
22/11/2017
|
100
|
26/12/2018
|
|
|
|
Total :
|
62.4560 (Km)
|
33626465.17 (Lac)
|
33626465.17 (Lac)
|
|
|
|
|
|
|
|