1
|
IRIDP-2/RMT/DW-10
|
a) Improvement of Durchari Bazar GC-Karallyachari Bazar GC (Shibir Bazar) road from Ch: 3000-3900m.b) Construction of 2x4.00mx5.00m culvert at ch.3420m on the same road.c) Construction of 3x4.00mx5.00m culvert at ch.3590m on the same road.d) Construction
|
0.9000
|
198.550
|
M/S. Nipa Enterprise
|
198.550
|
23/10/2017
|
20/10/2018
|
45
|
23/12/2018
|
|
|
2
|
IRIDP-2/RMT/DW-9
|
a) Improvement of Durchari Bazar-Amtoli road from Ch: 00-1000m.b) Construction of 01 no 1x4.00mx5.00m culvert at ch.175m on the same road.c) Construction of 01 no 2x4.00mx5.00m culvert at ch.400m on the same road.
|
1.0000
|
123.020
|
Suvrankar Chakma
|
123.020
|
27/10/2016
|
14/12/2018
|
80
|
23/12/2018
|
|
|
3
|
IRIDP-2/RMT/DW-8
|
a) Improvement of Belaichari GC-Shilchari GC via Dhupshil road from Ch: 13200-15500m.b) Construction of 01 no 0.900mx1.300m culvert at ch.13912m on the same road.c) Construction of 15 nos 0.900mx1.300m culvert at ch.13300,13375,13423, 13450,13500,13545,13
|
2.3000
|
304.440
|
M/S Milton Traders
|
304.440
|
14/12/2016
|
04/11/2018
|
50
|
23/12/2018
|
|