Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Basail
1 PEDP-III/TNG/BAS/2011-12/W3.0075 DUMNIBARI School Major Maintenance 194894.000 M/s Ratan Traders 194894.000 17/07/2012 22/01/2013 100 22/09/2014  
2 PEDP-III/TNG/BAS/2011-12/W2.0212 kamotia School Additional Room 3388000.000 M/S Tarafder Builders 3388000.000 17/02/2013 16/02/2014 100 22/09/2014  
3 PEDP-III/TNG/BAS/2013-14/W2.3366 KASHIL GOVT. PRIMARY SCHOOL. School Additional Room 6279000.000 M/S Alif Enterprise 6279000.000 20/02/2014 19/11/2014 0 22/09/2014  
4 PEDP-III/TNG/BAS/2011-12/W2.1016 balina School Additional Room 5186000.000 M/s Torofder Builders 5186000.000 16/07/2012 15/07/2013 100 22/09/2014  
5 PEDP-III/TNG/BAS/2011-12/W2.1419 KANCHON PUR DIKKHIN School Additional Room 2385000.000 M/s Torofder Builders 2385000.000 23/10/2012 31/12/2013 100 22/09/2014  
6 PEDP-III/TNG/BAS/2013-14/W2.3365 shehrail Communits Primary School School Additional Room 4896000.000 M/S Torofder builders 4896000.000 20/02/2014 19/11/2014 55 22/09/2014  
7 PEDP-III/TNG/BAS/2011-12/W1.0149 TENGURIA PARA School Reconstruction 5140000.000 M/S Tarafder Builders 5140000.000 28/03/2013 27/06/2014 95 22/09/2014  
2 Bhuapur
1 PEDP-III/TNG/BHU/2011-12/W3.0076 CHAR OLOWA School Major Maintenance 159792.000 M/s Chokder Enter prise 159792.000 22/08/2012 02/10/2012 100 22/09/2014  
2 PEDP-III/TNG/BHU/2012-13/W2.1934 CHAR TAL TOLA School Additional Room 1643000.000 M/S, Parvin Enterprise 1643000.000 30/09/2013 02/07/2014 60 22/09/2014  
3 PEDP-III/TNG/BHU/2013-14/W2.2793 Dovaya Raje Primary school School Additional Room 3955000.000 M/S. Trade Billow 3955000.000 19/06/2014 20/06/2015 17 22/09/2014  
4 PEDP-III/TNG/BHU/2013-14/W2.2792 CHAR CHONDONI School Additional Room 6279000.000 M/S. Dhaka Steel 6279000.000 19/06/2014 20/06/2015 0 22/09/2014  
5 PEDP-III/TNG/BHU/2011-12/W2.1017 GOBINDOPUR School Additional Room 1643000.000 M/s Apu Enterprise 1643000.000 11/09/2012 22/06/2013 100 22/09/2014  
6 PEDP-III/TNG/BHU/2011-12/W1.0418 PASANY RAMAIL School Reconstruction 1643000.000 M/s Jamil Enterprise 1643000.000 11/09/2012 22/06/2013 100 22/09/2014  
3 Delduar
1 PEDP-III/TNG/DEL/2011-12/W3.0077 ALSHA-KANDAPARA School Major Maintenance 241657.000 M/s Taposh Traders 241657.000 10/09/2012 26/03/2013 100 22/09/2014  
2 PEDP-III/TNG/DEL/2011-12/W2.0213 DUBAIL School Additional Room 3388000.000 M/s Asraf bin-Asad 3388000.000 11/09/2013 25/09/2013 100 22/09/2014  
3 PEDP-III/TNG/DEL/2011-12/W2.1018 SHAIL KURIA School Additional Room 5186000.000 M/s Hrydoya Construction 5186000.000 12/08/2012 25/09/2013 100 22/09/2014  
4 PEDP-III/TNG/DEL/2013-14/W2.2193 KATULI School Additional Room 4896000.000 M/S, Nahid Traders 4896000.000 22/10/2013 31/08/2014 45 22/09/2014  
5 PEDP-III/TNG/DEL/2013-14/W2.2795 SHINGHAORAGI NORTH School Additional Room 4896000.000 M/S, Milon Traders 4896000.000 24/02/2014 14/11/1931 15 22/09/2014  
6 PEDP-III/TNG/DEL/2011-12/W1.0150 MIR KUMULLI School Reconstruction 5140000.000 M/s Sajedul Enterprise 5140000.000 10/09/2012 24/09/2013 100 22/09/2014  
4 Dhanbari
1 PEDP-III/TNG/DHA/2013-14/W2.2796 SATAR KANDI School Additional Room 2995000.000 M/S Nabila Con. 2995000.000 05/03/2014 11/12/2014 70 22/09/2014  
5 Ghatail
1 PEDP-III/TNG/GHA/2011-12/W3.0078 DULALIA School Major Maintenance 199951.000 M/s Al-Modina Traders 199951.000 04/10/2012 03/05/2013 100 22/09/2014  
2 PEDP-III/TNG/GHA/2012-13/W7.029 Ext. & Renovation of Ghatail UEO School Upazila Education Office 242585.000 M/S Asha Traders 242585.000 02/05/2013 01/11/2013 100 22/09/2014  
3 PEDP-III/TNG/GHA/2011-12/W2.0582 DHOLA PARA School Additional Room 2993000.000 M/s Asha traders 2993000.000 02/07/2012 05/08/2013 100 22/09/2014  
4 PEDP-III/TNG/GHA/2011-12/W2.1019 MURAID School Additional Room 5186000.000 M/s Mirja Enterprise 5186000.000 17/06/2012 11/07/2013 100 22/09/2014  
5 PEDP-III/TNG/GHA/2011-12/W2.0581 SORABARI School Additional Room 4069000.000 Md. Abdus Salam Khan 4069000.000 16/07/2012 06/08/2013 100 22/09/2014  
6 PEDP-III/TNG/GHA/2011-12/W2.1420 CHUNGLI PARA School Additional Room 2385000.000 Md. Abu Sayed Khan 2385000.000 12/05/2013 28/05/2014 95 22/09/2014  
7 PEDP-III/TNG/GHA/2011-12/W1.0151 BAILTAIL School Reconstruction 5140000.000 M/s Novera Construction 5140000.000 05/07/2012 11/07/2013 95 22/09/2014  
8 PEDP-III/TNG/2011-12/W1.0627 GHATAIL DOKKHIN School Reconstruction 6072000.000 M/S Asha Traders 6072000.000 03/07/2012 30/06/2014 90 22/09/2014  
6 Gopalpur
1 PEDP-III/TNG/GOP/2011-12/W3.0338 BELUA School Major Maintenance 370511.000 M/S Sadaron Enterprise 370511.000 23/10/2012 13/02/2029 100 22/09/2014  
2 PEDP-III/TNG/GOP/2011-12/W2.0583 SATERKANDI School Additional Room 3388000.000 M/S. Sohel Enterprise 3388000.000 31/07/2012 01/08/2013 100 22/09/2014  
3 PEDP-III/TNG/GOP/2013-14/W2.2798 JOYNAGAR School Additional Room 2940000.000 M/S. Mir Brothers 2940000.000 05/06/2014 04/06/2015 40 22/09/2014  
4 PEDP-III/TNG/GOP/2013-14/W2.2799 Dhopakandi School Additional Room 4896000.000 M/S. Sohel Enterprise 4896000.000 05/06/2014 04/06/2015 15 22/09/2014  
5 PEDP-III/TNG/GOP/2011-12/W1.0419 PORABARI School Reconstruction 5140000.000 M/S. Kundu Traders 5140000.000 31/07/2012 01/08/2013 100 22/09/2014  
7 Kalihati
1 PEDP-III/TNG/KAL/2013-14/W2.2804 VANDESHAR School Additional Room 2995000.000 M/S, Dhaka Steel 2995000.000 29/10/2013 02/05/2014 95 22/09/2014  
2 PEDP-III/TNG/KAL/2013-14/W2.2803 Josir School Additional Room 6279000.000 M/S Dhaka Steel 6279000.000 29/10/2013 02/05/2014 95 22/09/2014  
3 PEDP-III/TNG/KAL/2011-12/W2.0214 BORTIA BARI School Additional Room 3388000.000 M/s Tusar Enterprise 3388000.000 08/04/2013 08/04/2014 90 22/09/2014  
4 PEDP-III/TNG/KAL/2012-13/W2.1935 BHUKTA School Additional Room 3388000.000 M/s Tusar Enterprise 3388000.000 08/04/2013 14/01/2014 95 22/09/2014  
5 PEDP-III/TNG/KAL/2011-12/W2.0584 DIMUKHA School Additional Room 2993000.000 M/s Dhaka Steel 2993000.000 07/08/2012 07/08/2013 95 22/09/2014  
6 PEDP-III/TNG/KAL/2013-14/W2.2802 HARIPUR School Additional Room 3546000.000 M/S, Abu Sayed Khan 3546000.000 29/10/2013 02/11/2014 95 22/09/2014  
7 PEDP-III/TNG/KAL/2011-12/W2.1021 BILBORNI School Additional Room 5186000.000 M/s Sumon Enterprise 5186000.000 07/08/2012 05/08/2013 100 22/09/2014  
8 PEDP-III/TNG/KAL/2013-14/W2.2801 Dholkan School Additional Room 3955000.000 M/S, Dhaka Steel 3955000.000 29/10/2013 02/11/2014 40 22/09/2014  
9 PEDP-III/TNG/KAL/2011-12/W2.1421 Bilsaya School Additional Room 2191000.000 M/s Dhaka Steel 2191000.000 08/04/2013 08/04/2014 95 22/09/2014  
10 PEDP-III/TNG/KAL/2011-12/W2.1422 DOSHAKIA School Additional Room 2385000.000 M/s Dhaka Steel 2385000.000 08/04/2013 14/04/2014 100 22/09/2014  
11 PEDP-III/TNG/KAL/2011-12/W2.1020 GOHALIA BARI School Additional Room 5186000.000 M/s Tusar Enterprise 5186000.000 07/08/2012 07/08/2013 100 22/09/2014  
12 PEDP-III/TNG/KAL/2013-14/W2.2800 JIDAHAKHAS School Additional Room 6279000.000 Md Abu Sayed 6279000.000 29/10/2013 02/11/2014 70 22/09/2014  
13 PEDP-III/TNG/KAL/2011-12/W1.0421 JHAGORMAN School Reconstruction 5140000.000 M/s Tusar Enterprise 5140000.000 05/08/2012 13/11/2013 100 22/09/2014  
14 PEDP-III/TNG/KAL/2011-12/W1.0420 PALIMA GOLPARA School Reconstruction 5140000.000 M/s Tusar Enterprise 5140000.000 07/08/2012 13/11/2013 100 22/09/2014  
8 Madhupur
1 PEDP-III/TNG/MAD/2011-12/W3.0081 Lukdew School Major Maintenance 187021.000 M/s Adarsha Songosta 187021.000 20/09/2012 19/03/2013 100 22/09/2014  
2 PEDP-III/TNG/MAD/2011-12/W1.0152 BHOBANITAKI School Reconstruction 5140000.000 M/s Shahana Steel Enterprise 5140000.000 12/07/2012 11/07/2013 100 22/09/2014  
9 Mirzapur
1 PEDP-III/TNG/MIR/2011-12/W3.0080 AGDHOLLA School Major Maintenance 282229.000 M/s Milon Traders 282229.000 18/07/2012 13/02/2013 100 22/09/2014  
2 PEDP-III/TNG/MIR/2011-12/W2.1026 BONGKHURI School Additional Room 5186000.000 M/s Mrida Enterprise 5186000.000 22/08/2012 21/08/2013 100 22/09/2014  
3 PEDP-III/TNG/MIR/2011-12/W2.0216 KOHELA School Additional Room 3388000.000 M/s Mridha Enterprise 3388000.000 04/07/2012 10/07/2013 100 22/09/2014  
4 PEDP-III/TNG/MIR/2011-12/W2.1025 BAGJAN School Additional Room 5186000.000 M/s G.S Enterprise 5186000.000 22/08/2012 21/08/2013 100 22/09/2014  
5 PEDP-III/TNG/MIR/2011-12/W2.0588 GHUGI School Additional Room 2993000.000 M/s Milon Traders 2993000.000 23/07/2012 22/07/2013 100 22/09/2014  
6 PEDP-III/TNG/MIR/2011-12/W2.1423 CHANDULIA School Additional Room 2385000.000 M/s Mridha Enterprise 2385000.000 18/09/2012 15/10/2013 100 22/09/2014  
7 PEDP-III/TNG/MIR/2012-13/W2.1936 DEOHATA School Additional Room 4069000.000 M/s Mrida Enterprise 4069000.000 30/12/2012 16/10/2013 100 22/09/2014  
8 PEDP-III/TNG/MIR/2011-12/W2.0587 GORAI School Additional Room 4069000.000 M/s Tapos traders 4069000.000 20/09/2012 19/09/2013 100 22/09/2014  
9 PEDP-III/TNG/MIR/2011-12/W2.0586 HALIDRA CHALA School Additional Room 2993000.000 M/s G.S Enterprise 2993000.000 23/07/2012 22/07/2013 100 22/09/2014  
10 PEDP-III/TNG/MIR/2011-12/W2.1024 BANIARA School Additional Room 5186000.000 M/s G.S Enterprise 5186000.000 22/08/2012 21/08/2013 100 22/09/2014  
11 PEDP-III/TNG/MIR/2011-12/W2.0215 UFULKI School Additional Room 3388000.000 M/s BB-ZC-HT (JV) 3388000.000 04/07/2012 10/07/2013 100 22/09/2014  
12 PEDP-III/TNG/MIR/2011-12/W2.0585 MAHERA School Additional Room 2993000.000 M/s G.S Enterprise 2993000.000 23/07/2012 22/07/2013 100 22/09/2014  
13 PEDP-III/TNG/MIR/2011-12/W2.1023 PANCH GAON School Additional Room 5186000.000 M/s BB-ZC-HT (JV) 5186000.000 22/08/2012 21/08/2013 100 22/09/2014  
14 PEDP-III/TNG/MIR/2011-12/W2.1424 PEKUA School Additional Room 2385000.000 M/S G S Enterprise 2385000.000 18/09/2012 15/10/2013 100 22/09/2014  
15 PEDP-III/TNG/MIR/2011-12/W2.1425 JHOP BARI School Additional Room 2191000.000 M/s BB-ZC-HT (JV) 2191000.000 18/09/2012 15/10/2013 100 22/09/2014  
16 PEDP-III/TNG/2012-13/W2.1668 KANTALIA School Additional Room 2385000.000 Alife Traders 2385000.000 30/10/2013 09/08/2014 100 22/09/2014  
17 PEDP-III/TNG/MIR/2011-12/W2.1022 POLLOBY NUMDAR PUR School Additional Room 5186000.000 M/s Reu International 5186000.000 22/08/2012 21/08/2013 100 22/09/2014  
18 PEDP-III/TNG/MIR/2011-12/W1.0428 WARSHI UTTOR School Reconstruction 5140000.000 M/s G.S Enterprise 5140000.000 04/07/2012 10/10/2013 100 22/09/2014  
19 PEDP-III/TNG/MIR/2011-12/W1.0427 KURIPARA UTTAR School Reconstruction 5140000.000 M/s Ridoy & Mridha (JV) 5140000.000 04/07/2012 10/10/2013 100 22/09/2014  
20 PEDP-III/TNG/MIR/2011-12/W1.0426 SINGJURI School Reconstruction 5140000.000 M/S BB-ZC-HT (JV) 5140000.000 04/07/2012 10/10/2013 100 22/09/2014  
21 PEDP-III/TNG/MIR/2011-12/W1.0425 RAJABARI BONGKURTOLA School Reconstruction 5140000.000 M/s HoRidoy & Mridha (JV) 5140000.000 04/07/2012 10/10/2013 100 22/09/2014  
22 PEDP-III/TNG/MIR/2011-12/W1.0424 PATHALIA PARA School Reconstruction 5140000.000 M/s Tapos Traders 5140000.000 04/07/2012 10/10/2013 100 22/09/2014  
23 PEDP-III/TNG/MIR/2011-12/W1.0423 GORAKKI School Reconstruction 5140000.000 M/s Tarofder Builders 5140000.000 04/07/2012 10/10/2013 100 22/09/2014  
24 PEDP-III/TNG/MIR/2011-12/W1.0422 GUNTIA School Reconstruction 5140000.000 M/s G.S Enterprise 5140000.000 04/07/2012 10/10/2013 100 22/09/2014  
10 Nagarpur
1 PEDP-III/TNG/NAG/2011-12/W3.0082 PAKUTIA DHUPUTIA School Major Maintenance 289449.000 M/S Bhai Bhai Construction 289449.000 04/10/2012 06/04/2013 100 22/09/2014  
2 PEDP-III/TNG/NAG/2013-14/W7.045 Ext. & Renovation of NagarpurUEO School Upazila Education Office 1107300.000 M/s Sthapoty Construction 1107300.000 04/05/2014 11/11/2014 50 22/09/2014  
3 PEDP-III/TNG/NAG/2013-14/W2.2808 JANGALIA School Additional Room 2765000.000 M/S. Kalachand & Dilip (JV) 2765000.000 0 22/09/2014  
4 PEDP-III/TNG/NAG/2012-13/W2.1937 BETUAJANI School Additional Room 2993000.000 M/S Parvez Enterprise 2993000.000 09/07/2013 08/01/2014 90 22/09/2014  
5 PEDP-III/TNG/NAG/2011-12/W2.1426 SRIBOROTIA School Additional Room 2385000.000 M/S Taposh traders 2385000.000 16/12/2012 25/12/2013 90 22/09/2014  
6 PEDP-III/TNG/NAG/2011-12/W2.0589 DOPTIOR School Additional Room 2993000.000 Kalachand Podder 2993000.000 29/09/2012 29/09/2013 100 22/09/2014  
7 PEDP-III/TNG/NAG/2013-14/W2.2807 NISHCHINTO PUR School Additional Room 3955000.000 M/S. Kalachand & Dilip (JV) 3955000.000 0 22/09/2014  
8 PEDP-III/TNG/NAG/2011-12/W2.0217 DHUNAIL School Additional Room 3388000.000 M/s Dhaka Steel 3388000.000 15/07/2012 14/07/2013 100 22/09/2014  
9 PEDP-III/TNG/NAG/2011-12/W2.1427 PAKUTIA School Additional Room 3388000.000 Kalachand Podder 3388000.000 19/01/2013 25/01/2014 100 22/09/2014  
10 PEDP-III/TNG/NAG/2011-12/W2.1027 MUSHURIA School Additional Room 5186000.000 M/s Sthapoty Construction 5186000.000 15/07/2012 14/07/2013 100 22/09/2014  
11 PEDP-III/TNG/NAG/2013-14/W2.2806 SOLIMABAD School Additional Room 2995000.000 M/S. S. Hossain 2995000.000 50 22/09/2014  
12 PEDP-III/TNG/NAG/2011-12/W1.0429 PAISHANA School Reconstruction 5140000.000 M/s Sthapoty & MR Construction 5140000.000 10/03/2013 10/05/2014 100 22/09/2014  
13 PEDP-III/TNG/NAG/2011-12/W1.0655 Agdhegulia North School Reconstruction 1643000.000 Asha Traders 1643000.000 20/09/2012 09/06/2013 100 22/09/2014  
11 Shakhipur
1 PEDP-III/TNG/SHA/2011-12/W3.0083 DHALIPARA School Major Maintenance 107500.000 M/s Sermin Enterprise 107500.000 26/09/2012 19/04/2013 100 22/09/2014  
2 PEDP-III/TNG/SHA/2013-14/W2.2814 B.B.C.BORDER School Additional Room 2995000.000 M/S, Sheik Traders 2995000.000 05/01/2014 04/10/2014 100 22/09/2014  
3 PEDP-III/TNG/SHA/2011-12/W2.1428 BERBARI KHONDOKAR PARA School Additional Room 2385000.000 M/s Salma & Chow.(JV) 2385000.000 26/08/2012 03/12/2013 100 22/09/2014  
4 PEDP-III/TNG/SHA/2013-14/W2.2813 PROTIMA BONKI PURBO School Additional Room 4896000.000 M/S.Fore Brothers Enterprise 4896000.000 19/12/2013 04/01/2015 92 22/09/2014  
5 PEDP-III/TNG/SHA/2011-12/W2.0219 DARIAPUR NORTH School Additional Room 3388000.000 M/s Salma & Chowdury(JV) 3388000.000 26/08/2012 29/09/2013 100 22/09/2014  
6 PEDP-III/TNG/SHA/2013-14/W2.2811 KOCHUA School Additional Room 6279000.000 Mohon & Hridoy (JV) 6279000.000 05/01/2014 04/01/2015 92 22/09/2014  
7 PEDP-III/TNG/SHA/2013-14/W2.2810 JOGIRKOFA (BAGPARA) School Additional Room 6279000.000 M/S. Milon Traders 6279000.000 30/03/2014 23/04/2015 60 22/09/2014  
8 PEDP-III/TNG/SHA/2011-12/W2.0218 AMTOIL School Additional Room 3388000.000 M/s Salma & Chowdury(JV) 3388000.000 26/08/2012 29/09/2013 100 22/09/2014  
9 PEDP-III/TNG/SHA/2013-14/W2.2809 MOHANONDO PUR School Additional Room 3546000.000 M/S. Mohona & Hridoy (JV) 3546000.000 23/12/2014 04/01/2015 90 22/09/2014  
10 PEDP-III/TNG/SHA/2011-12/W1.0430 BARBARI KASRAPARA School Reconstruction 5140000.000 Md. Abdul Jalil Sarkar 5140000.000 26/08/2012 29/12/2013 100 22/09/2014  
12 Tangail-s
1 PEDP-III/TNG/SAD/2011-12/W3.0084 SHAROTIYA School Major Maintenance 236329.000 M/s SB Traders 236329.000 10/09/2012 06/03/2013 100 22/09/2014  
2 e-Tender/PEDP-III/TNG/SAD/2013-14/W7.087 Ext. & Renovation of Tangail-SUEO School Upazila Education Office 681357.000 M/S, Nazrul Islam 681357.000 12/03/2014 23/09/2014 100 22/09/2014  
3 PEDP-III/TNG/SAD/2011-12/W2.0221 JAHANGIR SMRITY SAVASMROM School Additional Room 3388000.000 Md. Abdul Jalil Sarker 3388000.000 02/11/2012 01/11/2013 100 22/09/2014  
4 e-Tender/PEDP-III/TNG/SAD/2013-14/W2.2816 ALUK DIA School Additional Room 2995000.000 M/S. Friends Const. & M/S. Alif Ent. JV 2995000.000 0 22/09/2014  
5 e-Tender/PEDP-III/TNG/SAD/2013-14/W2.2818 RANGACHIRA School Additional Room 6279000.000 M/S. Friends Construction 6279000.000 20/05/2014 25/05/2015 0 22/09/2014  
6 e-Tender/PEDP-III/TNG/SAD/2013-14/W2.2817 GOILA HOSSAIN School Additional Room 2000000.000 M/S. Neloy Enterprise 2000000.000 20/05/2014 20/02/2015 15 22/09/2014  
7 PEDP-III/TNG/SAD/2011-12/W2.1429 DELDHA School Additional Room 2385000.000 M/s Rahaman Construction 2385000.000 16/11/2012 15/11/2013 100 22/09/2014  
8 PEDP-III/TNG/SAD/2011-12/W2.0591 KAKUA School Additional Room 2993000.000 M/s Friends Construction 2993000.000 15/10/2012 01/11/2013 100 22/09/2014  
9 PEDP-III/TNG/SAD/2011-12/W2.0590 DHORER BARI School Additional Room 2993000.000 M/s Tapos Traders 2993000.000 15/10/2012 01/11/2013 100 22/09/2014  
10 e-Tender/PEDP-III/TNG/SAD/2013-14/W2.2815 CHAKLADER PARA School Additional Room 4896000.000 M/S. Sanvee Traders 4896000.000 18/05/2014 24/05/2015 30 22/09/2014  
11 PEDP-III/TNG/SAD/2012-13/W2.1938 PORA BARI School Additional Room 2793000.000 M/S, Sadek Traders 2793000.000 20/02/2013 21/03/2014 100 22/09/2014  
12 PEDP-III/TNG/SAD/2011-12/W2.1028 GOSSAI JOWAIR School Additional Room 5186000.000 M/s Sunvee Traders 5186000.000 15/10/2012 01/11/2013 100 22/09/2014  
13 PEDP-III/TNG/SAD/2011-12/W2.0220 BARTHA School Additional Room 3388000.000 M/s Friends Construction 3388000.000 15/10/2012 01/11/2013 100 22/09/2014  
14 PEDP-III/TNG/SAD/2013-14/W2.2194 CHOWDHURY MALONCHO School Additional Room 8417000.000 M/S Nice Traders 8417000.000 21/10/2013 04/11/2014 30 22/09/2014  
15 e-Tender/PEDP-III/TNG/2013-14/W2.2819 BERABUCHNA School Additional Room 2995000.000 M/S, Shithi Enterprise 2995000.000 10/03/2014 08/12/2014 25 22/09/2014  
16 PEDP-III/TNG/SAD/2011-12/W2.1430 ENAYET PUR School Additional Room 2385000.000 RAhman Constraction 2385000.000 20/02/2013 21/03/2014 100 22/09/2014  
17 PEDP-III/TNG/SAD/2011-12/W1.0435 CHARPOULI School Reconstruction 1643000.000 M/S Nice Traders 1643000.000 22/03/2013 21/12/2013 100 22/09/2014  
18 PEDP-III/TNG/2011-12/W1.0628 BASHA School Reconstruction 6072000.000 M/S Rahman Construction 6072000.000 10/07/2012 25/07/2013 100 22/09/2014  
19 PEDP-III/TNG/SAD/2011-12/W1.0434 RAMDEB PUR School Reconstruction 5140000.000 M/s Friends Construction 5140000.000 02/11/2012 01/02/2014 100 22/09/2014  
20 PEDP-III/TNG/SAD/2011-12/W1.0433 VAT CHANDA School Reconstruction 5140000.000 M/s Nice Traders 5140000.000 22/07/2012 22/10/2013 100 22/09/2014  
21 PEDP-III/TNG/SAD/2011-12/W1.0432 RAGHOB KORBA School Reconstruction 5140000.000 M/s Boloram Bonik 5140000.000 22/07/2012 22/10/2013 100 22/09/2014  
22 PEDP-III/TNG/SAD/2011-12/W1.0431 KANDILA School Reconstruction 5140000.000 M/s Dhaka Steel 5140000.000 22/07/2012 22/10/2013 100 22/09/2014  
Total : 0.0000 (Km) 430282575.00 (Lac) 430282575.00 (Lac)