SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
|
1
|
Austagram
|
|
1
|
IRIDP-2/KISH/DW-08
|
a)Improvement of Savianagar GC- Humayunpur UP via Alinagar road. (Ch. 00-2656m). b) Construction of 3.00mx3.00m RCC Box culvert at ch.1260m on the same road. c) Construction of 03 nos 0.625mx0.600m culvert at ch.171m, 267m, 2370m on the same road.
|
2.6600
|
609.619
|
M/S Mahabub Alam
|
609.619
|
06/03/2016
|
22/08/2016
|
85
|
23/12/2018
|
|
|
|
2
|
Bajitpur
|
|
1
|
IRIDP-2/KISH/DW-11
|
Construction of Ghatla on Alhaz Afzal Hossain road at Humaipur Village road .at Ch.00.
|
|
4.479
|
M/S J.N Enterprise,prop: Md. Tajul islam
|
4.479
|
07/04/2016
|
20/02/2017
|
100
|
23/12/2018
|
|
|
2
|
IRIDP-2/KISH/DW-10
|
Improvement of Alhaz Afzal Hossain road at Humaipur Village road . (Ch. 00-1302m).
|
1.3000
|
121.015
|
M/S J.N Enterprise,prop: Md. Tajul islam
|
121.015
|
03/03/2016
|
22/08/2016
|
100
|
23/12/2018
|
|
|
3
|
IRIDP-2/KISH/DW-9
|
a)Improvement of Shuvarampur pucca road – Purahaty road . (Ch. 205-805m). b) Construction of 02 nos 0.600mx0.600m culvert at ch.577m, 700m on the same road.
|
0.6000
|
75.807
|
M/S Momo Construction, Prop: Md.Asaduzzaman Bhuiyan Jibon
|
75.807
|
03/03/2016
|
22/08/2016
|
70
|
23/12/2018
|
|
|
|
3
|
Bhairab
|
|
1
|
IRIDP-2/KISH/DW-15
|
Sreenagar Nuton Bazar – Munsi Bari road ( Ch.00-360m ) .
|
0.3600
|
42.188
|
M/S Mayer Doa Traders, Prop: Md Arman ullh
|
42.188
|
29/02/2016
|
19/10/2016
|
100
|
23/12/2018
|
|
|
2
|
IRIDP-2/KISH/DW-14
|
Improvement of Banshgari Circular road (East para ) . (Ch. 3150-3415m).
|
0.2700
|
20.634
|
M/S. Shiplu Traders
|
20.634
|
07/03/2016
|
28/08/2016
|
100
|
23/12/2018
|
|
|
3
|
IRIDP-2/KISH/DW-13
|
Improvement of Sreenagar UP office – Gochamara Bazar upto Darichandiber road (Ch. 2685-3015m).
|
0.3300
|
52.265
|
M/S Anwera Enterprise,Prop: Md. Mynuddin
|
52.265
|
06/03/2016
|
29/12/2016
|
100
|
23/12/2018
|
|
|
|
4
|
Katiadi
|
|
1
|
IRIDP-2/KISH/DW-7
|
a)Improvement of Kaiosto Polli – Jamsait (Kishoregonj Boirab R&H road – Kaiosto Polli road ) road . (Ch. 00-1050m). b) Construction of 04 nos 0.625mx0.600m culvert at ch.255m, 452m, 640m, 850m on the same road.
|
1.0500
|
59.029
|
M/S Ibrahim Construction,Prop: Kazi Monirul hasan
|
59.029
|
01/03/2016
|
30/06/2017
|
100
|
23/12/2018
|
|
|
2
|
IRIDP-2/KISH/DW-6
|
a)Improvement of Shimoha Nahardia Nadna road(Pulerghat Kargaon pucca road – Vitipara road ) . (Ch. 00-1620m). b) Construction of 04 nos 0.625mx0.600m culvert at ch.150m, 250m, 630m, 900m on the same road.
|
1.6200
|
89.524
|
M/S Rafi Construction,Prop: Jahirul Islam Ujjal
|
89.524
|
23/02/2016
|
27/04/2017
|
100
|
23/12/2018
|
|
|
|
5
|
Kuliarchar
|
|
1
|
IRIDP-2/KISH/DW-5
|
Improvement of Big Chhaysuti – Alalpur village road (Ch. 1600-3100m).
|
1.5000
|
82.835
|
M/S Mahabub Alam
|
82.835
|
29/02/2016
|
22/08/2016
|
100
|
23/12/2018
|
|
|
2
|
IRIDP-2/KISH/DW-4
|
Improvement of Salua UP Office - Vitigoan village road (Ch:00-2410).
|
2.4100
|
146.615
|
M/S. Momo Construction, Prop: Md. Asaduzzaman Bhuiyan Jibon
|
146.615
|
03/03/2016
|
|
70
|
23/12/2018
|
|
|
|
6
|
Nikli
|
|
1
|
IRIDP-2/KISH/DW-12
|
a)Improvement of Kursha Mor RHD – Gurauttra River road . (Ch.00-2900m). b) Construction of 05 nos 0.600mx0.600m culvert at ch.950m,1250m,1525m, 2350m, 2610m, on the same road.
|
2.9000
|
244.360
|
M/S. Osman Gani
|
244.360
|
03/03/2016
|
06/03/2017
|
100
|
23/12/2018
|
|
|
|
7
|
Pakundia
|
|
1
|
IRIDP-2/KISH/DW-3
|
a)Improvement of Chalkdigha - Adarshapara Bazar road (Ch. 1000-2570m). b) Construction of 06 nos 0.600mx0.600m culvert at ch.1306m, 1483m, 1922m, 2132m, 2289m, 2412m, on the same road.
|
1.5700
|
91.554
|
M/S A.K.M Shafiqul Islam, Prop: AKM Shafikul Islam
|
91.554
|
07/03/2016
|
21/08/2016
|
70
|
23/12/2018
|
|
|
2
|
IRIDP-2/KISH/DW-2
|
a)Improvement of Patuabhanga UP – Amtolihat road (Ch. 00-1850m). b) Construction of 08 no 0.600mx0.600m culvert at ch.85m, 190m, 812m, 1019m, 1076m, 1342m, 1441m, 1763m on the same road.
|
1.8500
|
114.028
|
M/S A.K.M Shafiqul Islam, Prop: AKM Shafikul Islam
|
114.028
|
07/03/2016
|
21/08/2016
|
100
|
23/12/2018
|
|
|
3
|
IRIDP-2/KISH/DW-1
|
a)Improvement of Dargabazar – Adarshapara Bazar road (Ch. 441-2171m). b) Construction of 03 no 0.600mx0.600m culvert at ch.650m,726m, 863m on the same road.
|
1.7300
|
94.901
|
M/S kazi Traders,Prop: Kazi Mohammod hossain
|
94.901
|
18/02/2016
|
21/08/2016
|
100
|
23/12/2018
|
|
|
|
Total :
|
20.1500 (Km)
|
1848.85 (Lac)
|
1848.85 (Lac)
|
|
|
|
|
|
|
|