Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Gazipur-s
1 GCC-WS-1 Installation of Production Tube well and water distribution system in Zone 3. 772.696   772.696 0 23/07/2026 Tender Evaluation validity period expired. There is a probability of being retendered.
2 GCC-SWM-2 Improvement of collection, transportation and disposal site at Gazipur area of Gazipur City Corporation (GCC) 0.000   0.000 0 23/07/2026 Drawing, Design, and Cost Estimate submitted to PMU on 23 May 2026
3 GCC-D-4 RCC drains from Dhaka-Mymensingh road Chandana Chowrasta to Turag River 2153.895   2153.895 0 23/07/2026 Tender in Live!
4 GCC-WS-2 Installation of Production Tube well and water distribution system in Zone 7, Zone 8 3388.461 FSL-SJC-JV 3388.461 07/07/2025 11/11/2026 14 23/07/2026 Test boring was ongoing. Previously, a case was filed. Later on 25/01/2026, it was dismissed from the High Court Division. Now, as soon as possible, the work will restart.
5 GCC-SWM-1 Improvement of collection, transportation and disposal site at Tongi area of Gazipur City Corporation (GCC). 220.269   220.269 0 23/07/2026 Under Tendering process.
6 GCC-RB-3 Construction of Kashimpur - Naojor Road 0.9080 2284.528   2284.528 0 23/07/2026 DED Ongoing, Drawing and cost estimate are anticipated to be submitted to PMU in 1st week of June 2026.
7 GCC-RB-2 Construction of Kashimpur - Naojor Connecting Bridge over Turag River 10980.547   10980.547 0 23/07/2026 Regarding Land Acquisition, the ULB obtained NOCs from the Gazipur Development Authority, the DOE, and the Department of Urban Development. Already sent the letter. Tender Evaluation ongoing.
8 GCC-RB-1 Construction of Overpass near Joydebpur Railway Station 23699.282   23699.282 0 23/07/2026 Drawing, Design, and Cost estimate submitted to PMU on 30 Sep 2025. JICA review is completed, and A revised cost estimate is also completed. There was a technical meeting on non-scheduled items on 12 May, 2026. Land Acquisition Status (The land acquisition file is now in the DC office, awaiting a joint visit. NOC from the Roads & Highway Department, BRRI, and Bangladesh Railway is due.
9 GCC-D-3 Construction of RCC Drains 1) Inner Bari Road & Jhajhor Road to Bottola Road & Basura Road (North); i)Basura by-pass (Inner bari mor) to Pucca bridge of Inner Bari Road. (Ch.0+000 to 0+768 m). ii)Jhajhor by-pass (Jhajhor mor) to Pucca Bridge of Jhajhor Road. (Ch. 0+000 to 1+200 m). 2) From Jhajhor Bypass to Jhajhor Bypass (South); i)Morian by-pass to Morian Purbapara bridge (Ch.0+000 to 0+398 m) ii)Morian mor to Morian bridge (0+000 to 0+690 m). 1612.123 Al-ME JV 1612.123 12/09/2024 15/01/2026 83 23/07/2026 PCC Casting=2950m, Base Casting =2950m, wall casting=2950m, Top slab casting=2925m sub base=1500m
10 GCC-D-2 RCC drains from Mirrer Bazar to Nondibari Road (Across a railway) i) Construction of Drain of Shikder Bari Road From Ch.0+000 km ~ 0+440 km ii) Construction of Drain of Kosaybari Road From Ch 0+000 km~ 0+320 km iii) Construction of Drain of Connecting road between Kosaybari road to Mirrer Bazar-Nondibari Road From Ch. 0+000 km ~ Ch. 0+380 km iv)Construction of Drain of Mirrer Bazar to Nondibari Road from Ch.0+340 km~ Ch.1+780 km 1551.093 M.N Enterprise 1551.093 05/12/2024 22/02/2026 81 23/07/2026 PCC Casting=2200m, Base Casting =2180m, wall casting=2150m, Top slab casting=2150m
11 GCC-D-1 Construction of RCC drain from Dhaka Mymensingh Highway to Turag River i) Squibe road start from Dhaka Mymensingh Highway to Turag river from Ch.0+100 km to 1+882 km. ii)Link Connecting Safiuddin Road and College Road-College Road from Ch.0+000 km to 0+340 km. iii) Sultana Razia road start from Dhaka Mymensingh Highway to College Road Ch. 0+000 km to 0+316 km. iv) Link connecting Moktarbari road and Safiuddin Road-Safiuddin Road-Link connecting Safiuddin Road College Road-Link connecting College Road to Surtaranga road from Ch.0+000 km to 0+734 km. v) Surtaranga Road-Link connecting Surtaranga Road and Squibe road from Ch.0+000 km to 0+502 km. 4025.662 SEPL-SBL JV 4025.662 24/11/2025 09/02/2027 14 23/07/2026 PCC Casting=200m, Base Casting =150m, wall casting=150m, Top slab casting=140m
Total : 0.9080 (Km) 50688.56 (Lac) 50688.56 (Lac)