Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Gopalganj-s
1 CCRIP/ADB/GOPAL/UZR/2015/W-17 Improvement of Kathi-Teligati-Raghunathpur Road (GC-FRB) 3.8130 405.820 M/S ST & SE (JV) Chandmari road,Gopalgonj 405.820 07/02/2016 27/06/2017 100 19/01/2019  
2 Kotwalipara
1 CCRIP/ADB/GOPAL/UZR/2014/W-05 Improvement of Radhagonj UPC-Doglas High School-Bhangergat GC Rd 2.9970 759.110 M/S ASCL & RRPL JV. Panthapath,Dhaka-1207 759.110 08/01/2015 28/07/2016 95 19/01/2019 Work on going
2 CCRIP/IFAD/GOPAL/BR/2015/W-20 Improvement of Construction of 16.00 m Long Bridge on Suagram UPC-Kandi bazar road. 111.920 Nihar,Cell # 01774965666 111.920 24/02/2016 10/01/2017 95 19/01/2019  
3 CCRIP/ADB/GOPAL/UZR/2015/W-19 Improvement of Constrction of 39.00 m Long Bridge on Radhagonj UPC-Doglas High School-Bhangergat GC Rd Improvement of Constrction of 90.00 m Long Bridge on Majbari R & H-Radhagonj Bazar Road 854.380 M/s Rizvi Construction &M/s.Anamica Traders(JV)107/A,DB Road Mymensingh. 854.380 21/12/2016 20/06/2018 60 19/01/2019 Work on going
4 CCRIP/IFAD/GOPAL/VR/2014/W-09 Improvement of WAPDA hat R&H - Bandabari Bazar Road _Palasiding 15.390 Champa Begum,Chairman and Kohinur Begum,Secretary. 15.390 29/11/2014 31/12/2016 100 19/01/2019  
5 CCRIP/IFAD/GOPAL/VR/2014/W-13 Improvement of Bujurgikona Bazar-Baro Dakhinpar via Wapda hat Road 2.0000 292.180 Asik,Cell # 01713571133 292.180 21/06/2015 28/06/2015 95 19/01/2019 Revised
6 CCRIP/IFAD/GOPAL/VR/2014/W-12 Improvement of Suagram UPC-Kandi bazar road. 0.2160 9.660 Bithika Roy,Chairman and Kusum Halder,Secretary. 9.660 29/11/2014 30/06/2016 100 19/01/2019  
7 CCRIP/IFAD/GOPAL/VR/2014/W-11 Improvement of Suagram UPC-Kandi bazar road. 0.3840 8.890 Konoklata Mozumdar,Chairman and Rina Bala,Secretary. 8.890 29/11/2014 30/06/2016 100 19/01/2019  
8 CCRIP/IFAD/GOPAL/VR/2014/W-10 Improvement of Suagram UPC-Kandi bazar road. 0.4000 10.020 Suity Baroi,Chairman and Tunu Rani Baroi,Secretary. 10.020 29/11/2014 30/06/2016 100 19/01/2019  
9 CCRIP/IFAD/GOPAL/VR/2016/W-23 Improvement of Pirarbari hat-Nabagram UP Road 3.0000 292.180 M/S Safa Bricks,213,Udayon Road, Gopalgonj. 292.180 09/05/2016 11/11/2017 70 19/01/2019  
10 CCRIP/IFAD/GOPAL/VR/2017/W-27 Improvement of WAPDA hat R & H - Bandhabari Bazar Road 2.0000 128.540 MME & HJAS (JV), Sheikh Abdus Samad, Gagor Bazar, Kotalipara. 128.540 29/08/2017 08/04/2018 95 19/01/2019 Work on going
11 CCRIP/IFAD/GOPAL/UNR/2016/W-26 Improvement of Suagram UPC-Kandi bazar road. 2.0000 185.180 M/S Lutful Kabir,Dillbag,Bagura,Alekanda Road, Barisal. 185.180 12/01/2017 07/12/2017 45 19/01/2019  
12 CCRIP//GOPAL/UNR/2014/W-02 Improvement of Pubra WAPDA hat-Suagram UPC Road 2.5000 221.090 ASCL & RCC (JV) Panthopath, Dhaka. 221.090 14/01/2015 20/01/2016 100 19/01/2019 Final Bill
3 Muksudpur
1 CCRIP/ADB/GOPAL/UZR/2015/W-16 Improvement of Muksudpur R&H to Kalinagar GC via Kishnadia Bahirbag Road 2.7910 423.000 ASCL & RCC (JV) 17/C Panthopath, Dhaka. 423.000 07/02/2016 22/11/2017 100 19/01/2019 Final Bill
2 CCRIP/IFAD/GOPAL/VR/2014/W-08 Improvement of WAPDA hat R&H - Bandabari Bazar Road (1600-2000m) 15.050 Kulsum Begum,Chairman and Morjina Begum,Secretary. 15.050 29/11/2014 31/12/2016 100 19/01/2019  
3 CCRIP/IFAD/GOPAL/VR/2014/W-07 Improvement of WAPDA hat R&H - Bandabari Bazar Road (1000-1600m) 15.040 Shirin Kazi,Chairman and Rahima Begum,Secretary. 15.040 29/11/2014 31/12/2016 100 19/01/2019  
4 CCRIP/IFAD/GOPAL/VR/2014/W-06 Improvement of WAPDA hat R&H - Bandabari Bazar Road (0-1000m) 15.520 Mina Vokto,Chairman and Nasima Begum, Secretary. 15.520 29/11/2014 31/12/2016 100 19/01/2019  
4 Tungipara
1 CCRIP//GOPAL/UNR/2014/W-01 Improvement of Gopalpur UP-Borauhati Road 1.5400 170.960 Md. Babul Sheik, Tungipara, Gopalgonj. 170.960 14/01/2015 20/01/2016 100 19/01/2019 Final Bill
2 CCRIP/IFAD/GOPAL/BR/2015/W-21 Improvement of Construction of 26.00 m Long Bridge on Pakurtia Bazar-Karfa Bazar Road 250.860 Narayon chandro dham-01740948994 & Sanjoy-01973545488 250.860 06/03/2016 12/09/2017 85 19/01/2019 Revised
Total : 23.6410 (Km) 4184.79 (Lac) 4184.79 (Lac)