SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
|
1
|
Gopalganj-s
|
|
1
|
OTM/16-17/Office Building-01
|
Extenton of XEN's Office Building (Motor Garage room for Mechanic & Electric wire connection) under CRRIP, FSU, Gopalgonj.
|
|
3.156
|
|
3.156
|
|
|
1
|
11/10/2020
|
FB Paid
|
|
2
|
LCS/TP/20-21/Gop-S/03
|
Tree Plantation & One year Caretaking of Nizra Duanipara via Kathabari Road from ch. 00m-1000m under Sadar Upazila, Dist: Gopalgonj.
|
1.0000
|
2.503
|
|
2.503
|
|
|
0
|
11/10/2020
|
|
|
3
|
LCS/TP/20-21/Gop-S/02
|
Tree Plantation & One year Caretaking of Kalpur UZR-Judupur (Sadar Portion) Road from ch. 00m-1500m under Sadar Upazila, Dist: Gopalgonj.
|
1.5000
|
3.744
|
|
3.744
|
|
|
0
|
11/10/2020
|
|
|
4
|
LCS/TP/20-21/Gop-S/01
|
Tree Plantation & One year Caretaking of Ghoradair-Shashabari Road from ch. 00m-2500m under Sadar Upazila, Dist: Gopalgonj.
|
2.5000
|
6.227
|
|
6.227
|
|
|
0
|
11/10/2020
|
|
|
5
|
LCS/Market/16-17/Gop-S/03
|
Development of Boultali Hat (Twin Toilet, Deep Tube-well & CC internal road) under Sadar Upazila, Dist: Gopalganj
|
|
27.441
|
Kajoli/Bina
|
27.441
|
19/03/2018
|
30/01/2020
|
1
|
11/10/2020
|
FB Paid
|
|
6
|
LCS/Market/16-17/Gop-S/02
|
Development of Pukuria Bazar (Twin Toilet, Fish shed, Deep Tube-well & Internal road) under Sadar Upazila, Dist: Gopalganj
|
|
23.427
|
Farjana/Kajoli
|
23.427
|
05/03/2018
|
17/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
7
|
LCS/Market/16-17/Gop-S/01
|
Development of Bherarhat (Construction of Twin Toilet, 1 No Fish Shed & 1 No Deep Tube Well) under Horidhashpur UP of Gopalganj Sadar Upazila, Dist: Gopalganj.
|
|
11.963
|
Nazma/ Monowara
|
11.963
|
12/06/2017
|
31/12/2017
|
1
|
11/10/2020
|
FB Paid
|
|
8
|
LCS/SP/17-18/Gop-S/01
|
Slope Protection work on Khalia H/O Kuddus Mollah to H/O Moshar Ali Road at ch 250m-276m(RS) & 400m-416m (RS) under Jalalabad UP of Sadar Upazila, Dist: Gopalganj. ID No. 33532-5394
|
|
2.166
|
Shutarita/ Juthika
|
2.166
|
22/06/2018
|
30/06/2018
|
0
|
11/10/2020
|
Work start soon
|
|
9
|
LCS/Khal/17-18/Gop-S/03
|
Re-excavation of Khal on Shanpukuria Nitai Khal (House of Somir to Basir khal ) at ch. 715m-1650m under Satpar UP of Sadar Upazila, Dist: Gopalganj. Group-02
|
0.9350
|
15.719
|
Bithika/Suchittra
|
15.719
|
17/03/2018
|
30/06/2020
|
1
|
11/10/2020
|
FB Paid
|
|
10
|
LCS/Khal/17-18/Gop-S/02
|
Re-excavation of Khal on Shanpukuria Nitai Khal (House of Somir to Basir khal ) at ch. 0.0m-715m under Satpar UP of Sadar Upazila, Dist: Gopalganj. Group-01
|
0.7150
|
15.485
|
Namita/Urmila
|
15.485
|
17/03/2018
|
30/06/2020
|
1
|
11/10/2020
|
FB Paid
|
|
11
|
LCS/Khal/17-18/Gop-S/01
|
Re-excavation of Khal on Baroivita khal (Baroivita Asrayan Kendra to Baroivita Beel khal) at ch. 0.0m-1000m under Satpar UP of Sadar Upazila, Dist: Gopalganj.
|
1.0000
|
13.492
|
Rina/Tara
|
13.492
|
14/03/2018
|
10/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
12
|
LCS/DS/19-20/Gop-S/04
|
Construction of 2 Nos. U-drain (0.900m×0.900m) on Suktail UP Office to Char Suktail Pucca at ch.250m & 550m under Suktail UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325397
|
|
3.311
|
|
3.311
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
13
|
LCS/DS/19-20/Gop-S/03
|
Construction of 1 No. U-drain (0.900m×0.900m) on Kekania H/O Jakaria Sheikh to H/O Emdad Sheikh road at ch.130 m under Suktail UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325400
|
|
1.655
|
|
1.655
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
14
|
LCS/DS/19-20/Gop-S/02
|
Construction of 1 No. U-drain (0.900m×0.900m) on Bijoypasa-Joynagar RHD to H/O Saif Chowdhury road at ch.130m under Suktail UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325399
|
|
1.655
|
|
1.655
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
15
|
LCS/DS/19-20/Gop-S/01
|
Construction of 3 Nos. U-drain (0.900m×0.900m) on Boultali-Gonapara road to H/O Arinda Khals road at ch 250m, 600m & 1000m under Boultali UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325398
|
|
4.967
|
|
4.967
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
16
|
LCS/DS/17-18/Gop-S/03
|
Detail estimate for Construction of 1 No Box culvert (4.00m×4.00m) on Ichakhali H/O Ramjan Ali to H/O Toslu Mollah via Shadhur Khal at ch. 690m under via under Jalalabad UP of Sadar Upazila, Dist: Gopalganj. ID No. 33532-5392
|
|
13.659
|
Kamona/ Lovly
|
13.659
|
03/04/2018
|
30/06/2018
|
0
|
11/10/2020
|
Work shall start soon.
|
|
17
|
LCS/DS/17-18/Gop-S/02
|
Construction of 2 Nos. single vent U-drain (0.900m×0.900m) on Khalia H/O Kuddus Mollah to H/O Moshar Ali Road at ch 175m & 450m under Jalalabad UP of Sadar Upazila, Dist: Gopalganj. ID No. 33532-5394
|
|
2.273
|
Suchitra/ Zaheka
|
2.273
|
03/04/2008
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
18
|
LCS/DS/17-18/Gop-S/01
|
Construction of 2 Nos. single vent U-drain (0.900m×0.900m) on Khalia Rishibari to H/O Khudiram road via H/O Nazrul Member at ch 220m & 560m under Jalalabad UP of Sadar Upazila, Dist: Gopalganj. ID No. 33532-5393
|
|
2.574
|
Shamoly/Parul
|
2.574
|
14/02/2018
|
13/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
19
|
LCS/HBB/19-20/Gop-S/02
|
Improvement of Uttar Para Falsi Road to H/o Sabu Kazi road by HBB from ch: 00-490m under Sadar Upazila, Dist: Gopalganj. ID No. 33532-5396
|
0.4900
|
25.205
|
Aleya/Sarothi
|
25.205
|
10/01/2020
|
30/06/2020
|
1
|
11/10/2020
|
FB Paid
|
|
20
|
LCS/HBB/19-20/Gop-S/01
|
Improvement of Sotiarkul Sluice gate to Kader Khal road by HBB from ch: 00-710m under Sadar Upazila, Dist: Gopalganj. ID No. 33532-5395
|
0.7100
|
31.645
|
Nurnahar/ Lima
|
31.645
|
10/01/2020
|
30/03/2020
|
0
|
11/10/2020
|
On going
|
|
21
|
LCS/HBB/17-18/Gop-S/03
|
Improvement of road by HBB on Khalia H/O Kuddus Mollah to H/O Moshar Ali Road at ch 0.0m-574m under Jalalabad UP of Sadar Upazila, Dist: Gopalganj.
|
0.5740
|
18.406
|
Rexona/Morzina
|
18.406
|
30/03/2018
|
10/06/2018
|
0
|
11/10/2020
|
Land Provlem solved shall finalized soon
|
|
22
|
LCS/HBB/17-18/Gop-S/02
|
Improvement of road by HBB on Khalia Rishibari to H/O Khudiram road via H/O Nazrul Member at ch 0.0m-657m under Jalalabad UP of Sadar Upazila, Dist: Gopalganj.
|
0.6570
|
22.230
|
Nargis/Hasna
|
22.230
|
10/03/2018
|
10/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
23
|
LCS/HBB/17-18/Gop-S/01
|
Improvement of Road by HBB on Barfa Pacca Road to Asrayan Kendro via Rahmotpara at ch.0m-1000m under Jalalabad UP of Sadar Upazila, Dist: Gopalganj.
|
1.0000
|
30.057
|
Hasna/ Nargis
|
30.057
|
26/12/2017
|
25/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
24
|
LCS/EW/19-20/Gop-S/04
|
Detailed Estimate for Earthen Road Embankment of Suktail UP Office to Char Suktail Pucca from ch. 00m-700m under Suktail UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325397
|
0.7000
|
8.729
|
|
8.729
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
25
|
LCS/EW/19-20/Gop-S/03
|
Detailed Estimate for Earthen Road Embankment of Kekania H/O Jakaria Sheikh to H/O Emdad Sheikh road from ch. 00m-510m under Suktail UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325400
|
0.6000
|
6.401
|
|
6.401
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
26
|
LCS/EW/19-20/Gop-S/02
|
Detailed Estimate for Earthen Road Embankment of Bijoypasa-Joynagar RHD to H/O Saif Chowdhury road from ch. 00m-600m under Suktail UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325399
|
0.6000
|
7.863
|
|
7.863
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
27
|
LCS/EW/19-20/Gop-S/01
|
Detailed Estimate for Earthen Road Embankment of Boultali-Gonapara road to H/O Arinda Khals road from ch. 00m-1150m under Boultali UP of Gopalgonj Sadar Upazila, Dist: Gopalganj. ID No. 335325398
|
1.1500
|
20.238
|
|
20.238
|
|
|
0
|
11/10/2020
|
Not yet started
|
|
28
|
LCS/DS/17-18/GOPAS-17
|
Construction of 2 nos. U-Drains at ch. 600m & 1000m on Nizra UPHQ to Nizra Duania via Katahlbari Road , Ch. 0.00m – 1450.00m under Nizra UP, Gopalganj Sadar Upazila, Gopalganj.
|
|
4.261
|
Unnati/Archana
|
4.261
|
23/05/2017
|
22/12/2017
|
100
|
19/01/2019
|
|
|
29
|
LCS/EW/17-18/GOPAS-16
|
Group-3: 870m-1450m
|
0.5800
|
11.252
|
Sukumar/Rasel
|
11.252
|
17/02/2018
|
13/06/2018
|
60
|
19/01/2019
|
|
|
30
|
LCS/EW/17-18/GOPAS-15
|
Group-2: 560m-870m
|
0.3100
|
11.151
|
|
11.151
|
|
|
0
|
19/01/2019
|
|
|
31
|
LCS/EW/17-18/GOPAS-14
|
Group-1: 0m -560m
|
0.5600
|
11.467
|
Dulali/Shuli
|
11.467
|
15/04/2017
|
13/12/2017
|
5
|
19/01/2019
|
|
|
32
|
LCS/Khal/17-18/GOPAS-12
|
G1: 0-715mG2: 715-1650mDetail estimate for Raising / Re-Shaping of Earthen Road Embankment of Nizra UPHQ to Nizra Duania via Katahlbari Road , Ch. 0.00m – 1450.00m under Nizra UP, Gopalganj Sadar Upazila, Gopalganj.
|
1.6500
|
31.205
|
Nomita/Urmila,Bithika/Suchittra
|
31.205
|
13/03/2018
|
16/06/2018
|
50
|
19/01/2019
|
|
|
33
|
LCS/Khal/17-18/GOPAS-11
|
Re-excavation of Khal on Baroivita Khal (Baroivita Asrayan kendra to Baroivita Beel Khal) at ch. 0m-1000m under Satpar UP of Sadar Upazila, Gopalganj Re-excavation of Khal on Shanpukuria Nitai Khal (House of Somir to Basir Khal) at ch. 0m-1650m under Satp
|
1.0000
|
13.492
|
Rina/Tara
|
13.492
|
08/03/2018
|
10/06/2018
|
100
|
19/01/2019
|
|
|
34
|
LCS/Ghat/17-18/GOPAS-10
|
Construction of Boat Landing Station at Pukuria Bazar Ghat (Modhumoti River) under Paikkandi UP, Sadar Upazila, Gopalganj.
|
|
22.858
|
|
22.858
|
|
|
0
|
19/01/2019
|
|
|
35
|
LCS/MD/17-18/GOPAS-09
|
Development of Boultali Hat (Twin Toilet, Deep Tube-well & Internel CC road) under Sadar Upazilla, Dist: Gopalganj. Salvage-2,76,834.00
|
|
27.441
|
Kazoli/Bina
|
27.441
|
20/03/2018
|
21/06/2018
|
25
|
19/01/2019
|
|
|
36
|
LCS/MD/17-18/GOPAS-08
|
Development of Pakurria Bazar (Twin Toilet, Fish shed, Deep Tube-well & Internel road) under Sadar Upazilla, Dist: Gopalganj
|
|
23.427
|
Doli/Kojoli
|
23.427
|
|
17/05/2018
|
60
|
19/01/2019
|
|
|
37
|
LCS/SP/17-18/GOPAS-07
|
Slope Protection at ch. 250-276m(RS) & 400-416m(RS)=42m on Khalia H/O Kuddus Mollah to H/O Moshar Ali Road at Ch. 0 to 574m , under Jalalabad UP, Sadar Upazila, Gopalganj.
|
42.0000
|
1.887
|
Shamoli/Parul
|
1.887
|
|
|
0
|
19/01/2019
|
|
|
38
|
LCS/DS/17-18/GOPAS-06
|
Detail estimate for Construction of 1 No Box Culvert (4.00m×4.00m) on Ichkhali H/O Ramjan Ali to H/O Toslu Mollah via Shadhur khal at ch. 690m under via under Jalalabad UP of Sadar Upazila, Dist: Gopalganj.
|
|
11.879
|
Kamona/lovli
|
11.879
|
|
|
0
|
19/01/2019
|
|
|
39
|
LCS/DS/17-18/GOPAS-05
|
Construction of 2 Nos. U-Drain (0.900mx0.90m) Single Vent at Ch.175m & 450m on Khalia H/O Kuddus Mollah to H/O Moshar Ali Road at Ch. 0 to 574m , under Jalalabad UP, Sadar Upazila, Gopalganj.
|
|
2.273
|
Suchitra/Jthika
|
2.273
|
01/04/2018
|
30/06/2018
|
100
|
19/01/2019
|
|
|
40
|
LCS/DS/17-18/GOPAS-04
|
Construction of 2 nos. U-Drain (0.900mmx0.900mm) Single Vent at 220m & 560m on Khalia Rishibari to H/O Khudiram Road via H/O Nazrul Member at Ch. 0 to 657m , under Jalalabad UP, Sadar Upazila, Gopalganj.
|
|
2.574
|
Shamoli/Parul
|
2.574
|
14/02/2018
|
13/06/2018
|
100
|
19/01/2019
|
|
|
41
|
LCS/HBB/17-18/GOPAS-03
|
Improvement of Road by HBB on Khalia H/O Kuddus Mollah to H/O Moshar Ali Road at Ch. 0 to 574m , under Jalalabad UP, Sadar Upazila, Gopalganj
|
0.5740
|
18.406
|
Rexona/Morzina
|
18.406
|
10/03/2018
|
10/06/2018
|
80
|
19/01/2019
|
|
|
42
|
LCS/HBB/17-18/GOPAS-02
|
Improvement of Road by HBB on Khalia Rishibari to H/O Khudiram Road via H/O Nazrul Member at Ch. 0 to 657m , under Jalalabad UP, Sadar Upazila, Gopalganj.
|
0.6570
|
22.230
|
Nargis/Hasna
|
22.230
|
10/03/2018
|
10/06/2018
|
80
|
19/01/2019
|
|
|
43
|
LCS/HBB/17-18/GOPAS-01
|
Improvement of Road by HBB on Barfa Pacca Road to Asrsyan Kendro via Rahmotpara at Ch. 0.00m – 1000.00m under Jalalabad UP, Sadar Upazila, Gopalganj.
|
1.0000
|
30.057
|
Hasna/Nargis
|
30.057
|
26/12/2018
|
25/05/2018
|
100
|
19/01/2019
|
17-18
|
|
|
2
|
Kasiani
|
|
1
|
LCS/TP/20-21/Kasiani/03
|
Tree Plantation & One year Caretaking of Zikabari Dhalibari Carpeting road- Solier Kull Primary School Road from ch. 00m-1600m under Kasiani Upazila, Dist: Gopalgonj.
|
1.6000
|
3.810
|
|
3.810
|
|
|
0
|
11/10/2020
|
|
|
2
|
LCS/TP/20-21/Kasiani/02
|
Tree Plantation & One year Caretaking of Puisur-Jodupur Road from ch. 00m-2400m under Kasiani Upazila, Dist: Gopalgonj.
|
2.4000
|
6.181
|
|
6.181
|
|
|
0
|
11/10/2020
|
|
|
3
|
LCS/TP/20-21/Kasiani/01
|
Tree Plantation & One year Caretaking of Singa Anderkota Khakie Mata Mondir –Singa Malaker bari Road from ch. 00m-1000m under Kasiani Upazila, Dist: Gopalgonj.
|
1.0000
|
2.503
|
|
2.503
|
|
|
0
|
11/10/2020
|
|
|
4
|
LCS/Ghat/19-20/Kasiani/01
|
Construction of .Public Ghatla at Khakhe Mata Mondir Pond Under Singa UP of Kasiani Upazila, Dist: Gopalganj.
|
|
9.125
|
Anita/Shutrita
|
9.125
|
28/02/2020
|
20/05/2020
|
1
|
11/10/2020
|
FB paid
|
|
5
|
LCS/SP/17-18/Kasiani/03
|
Construction of Slope protection work on Majra High School to Bishwa road at ch. 980m-1000m (LS) &1075m-1105m (LS) under Sajail UP of Kasiani Upazila, Dist: Gopalganj.
|
|
2.360
|
Hasi/ Jorna
|
2.360
|
28/02/2018
|
20/04/2018
|
1
|
11/10/2020
|
Final Bill Paid
|
|
6
|
LCS/SP/17-18/Kasiani/02
|
Construction of Slope protection work on Bagjhapa Pucca Rasta to Rail Line road at ch. 395m-405m (LS) under Sajail UP of Kasiani Upazila, Dist: Gopalganj.
|
|
0.499
|
Hasi/ Jorna
|
0.499
|
28/02/2018
|
17/04/2018
|
1
|
11/10/2020
|
Final Bill Paid
|
|
7
|
LCS/SP/17-18/Kasiani/01
|
Construction of protection work on Road of Talbari GPS at ch. 85m-110m (RS), 255m-275m (LS) & 385m-410m (RS) under 14 No. Nijamkandi UP of Kasiani Upazila, Dist: Gopalganj.
|
|
3.146
|
Rekha/Shirin
|
3.146
|
28/12/2017
|
08/03/2018
|
0
|
11/10/2020
|
work stopped due to rain
|
|
8
|
LCS/SP/16-17/Kasiani/02
|
Slope protection work on Fakira Vita Boro bahirbag School-Baroihat Community Clinic road at ch. 250m-290m, 350m-400m, 550m-565m, 1100m-1130m & 1700m-1740m under Rajpat UP of Kasiani Upazila, Dist: Gopalganj.
|
|
8.054
|
Morjina/Sonia
|
8.054
|
20/04/2018
|
30/06/2019
|
1
|
11/10/2020
|
FB Paid
|
|
9
|
LCS/SP/16-17/Kasiani/01
|
Slope protection work on Zikabari carpeting road-Solier kull Primary School road at ch. 00.0-25m, 300m-340m & 730m-780m under Mahamudpur UP of Kasiani Upazila, Dist: Gopalganj.
|
|
5.292
|
Lotika/Parboti
|
5.292
|
09/05/2017
|
15/01/2018
|
1
|
11/10/2020
|
FB Paid
|
|
10
|
LCS/DS/19-20/Kasiani/01
|
Construction of 1 No. Box culvert (2.00m×2.00×3.66m) Singel Vent on Korigram Sarbojonin Durga Mondir-Barkhadia Road near the H/O Sobuj Sarker at Ch. 350m Under Puisur UP of Kasiani Upazila, Dist: Gopalgonj. ID No. 335435878
|
|
7.196
|
Monju/ Champa
|
7.196
|
28/02/2020
|
25/05/2020
|
1
|
11/10/2020
|
FB paid
|
|
11
|
LCS/DS/17-18/Kasiani/04
|
Construction of 3 Nos. U-drain (0.900m×0.900m) on Majra High School to Bishwa road at ch. 10m, 920m &1115m under Sajail UP of Kasiani Upazila, Dist: Gopalganj. ID No. 33543-4252
|
|
5.200
|
Hasi/Juma
|
5.200
|
13/04/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
12
|
LCS/DS/17-18/Kasiani/03
|
Construction of 1 No. U-drain (0.900m×0.900m on Jakir Mollah Shop to Raja Miyar House road at ch. 550m under Sajail UP of Kasiani Upazila, Dist: Gopalgonj. ID No. 33543-4103
|
|
1.462
|
Hasi/Juma
|
1.462
|
13/04/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
13
|
LCS/DS/17-18/Kasiani/02
|
Construction of 1 No. single vent U-drain (0.900m×0.900m) on Bagjhapa Pucca Rasta to Rail Line road at ch. 650m under Sajail UP of Kasiani Upazila, Dist: Gopalganj. ID No. 335435467
|
|
1.851
|
Hasi/Juma
|
1.851
|
13/04/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
14
|
LCS/DS/17-18/Kasiani/01
|
Construction of 1 No. U-drain (0.900m×0.900m) single vent on Road of Talbari GPS at ch. 175m under 14 No. Nijamkandi UP of Kasiani Upazila, Dist: Gopalganj.
|
|
1.718
|
Rekha/Serin
|
1.718
|
03/01/2018
|
30/05/2018
|
0
|
11/10/2020
|
Work stop due to rain
|
|
15
|
LCS/DS/16-17/Kasiani/02
|
Construction of 4nos U-drain (0.900m´0.900m) on Fakira Vita Boro bahirbag School-Baroihat Community Clinic road at ch. 350m, 547m, 800m & 1600m under Rajpat UP of Kasiani Upazila, Dist: Gopalganj.
|
|
7.025
|
Morjina/Sonia
|
7.025
|
20/04/2018
|
30/06/2019
|
0
|
11/10/2020
|
Work stope due to water loging
|
|
16
|
LCS/DS/16-17/Kasiani/01
|
Construction of 3nos U-drains (0.900m´0.900m) on Zikabari carpeting road-Solier kull Primary School road at ch. 100m, 1100m & 1250m under Mahamudpur UP of Kasiani Upazila, Dist: Gopalganj.
|
|
5.247
|
Latia/Parboti
|
5.247
|
29/05/2017
|
15/01/2018
|
1
|
11/10/2020
|
FB paid
|
|
17
|
LCS/HBB/17-18/Kasiani/03
|
Detail estimate for Improvement of road by HBB on Majra High School to Bishwa road at ch. 0m-1280m under Sajail UP of Kasiani Upazila, Dist: Gopalganj.
|
1.2800
|
41.843
|
Forida/Janu
|
41.843
|
26/02/2018
|
15/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
18
|
LCS/HBB/17-18/Kasiani/02
|
Detail estimate for Improvement of road by HBB on Bagjhapa Pucca Rasta to Rail Line road at ch. 0m-675m under Sajail UP of Kasiani Upazila, Dist: Gopalganj.
|
0.6750
|
22.699
|
Dina/Shefali
|
22.699
|
16/01/2018
|
12/06/2018
|
1
|
11/10/2020
|
FB paid
|
|
19
|
LCS/HBB/17-18/Kasiani/01
|
Improvement of road by HBB on Road of Talbari GPS at ch. 0m-475m under 14 No. Nijamkandi UP of Kasiani Upazila, Dist: Gopalganj.
|
0.4750
|
16.193
|
Rabeya/Shahinur
|
16.193
|
03/01/2018
|
12/06/2018
|
1
|
11/10/2020
|
FB paid as per work done
|
|
20
|
LCS/EW/19-20/Kasiani/03
|
Raising/Re-Shaping of Earthen Road Embankment of Singa Anderkota Khakie Mata Mondir-Singa Malaker Bari Road from ch. 00m-1000m Singa UP under Kasiani Upazila, Dist: Gopalganj. ID No. 335435877
|
1.0000
|
20.156
|
Nomita/ Laboni
|
20.156
|
01/03/2020
|
30/05/2020
|
1
|
11/10/2020
|
FB paid
|
|
21
|
LCS/EW/19-20/Kasiani/02
|
Raising/Re-Shaping of Earthen Road Embankment of Korigram Sarbojoin Durga Mondir-Barkhadia Road from ch. 00m-700m under Pusiur UP Kasiani Upazila, Dist: Gopalganj. ID No. 335435878
|
0.7000
|
13.832
|
Lilu/Tustu
|
13.832
|
20/02/2020
|
19/05/2020
|
1
|
11/10/2020
|
FB paid
|
|
22
|
LCS/EW/19-20/Kasiani/01
|
Raising/Resectioning of Earthen road Embankment of Zikabari Dhalibari Carpeting road-Solier Kull Praimary School road from ch: 00m-1000m under Kasiani Upazila, Dist: Gopalganj. ID No. 33543-5870
|
1.0000
|
31.262
|
Lotika/Kuntola
|
31.262
|
25/12/2019
|
30/05/2018
|
1
|
11/10/2020
|
FB paid
|
|
23
|
LCS/EW/17-18/Kasiani/04
|
Raising/Re-Shaping of Earthen Road Embankment on Ramdia College Road to Ramdia West Simana road at ch. 0.0m-500m under Bethuri UP of Kasiani Upazila, Dist: Gopalganj. ID No. 33543-5882
|
0.5000
|
4.532
|
Gouri/China
|
4.532
|
21/03/2018
|
20/06/2018
|
0
|
11/10/2020
|
Work stop due to rain
|
|
24
|
LCS/EW/17-18/Kasiani/03
|
Raising/Re-Shaping of Earthen Road Embankment on Falsi Syed Mollah House to Miraj Fakir House road at ch. 0.0m-1000m under Nijamkandi UP of Kasiani Upazila, Dist: Gopalganj. ID No. 33543-5878
|
1.0000
|
9.158
|
Madina/Taku
|
9.158
|
08/03/2018
|
28/06/2018
|
0
|
11/10/2020
|
Work stoped due to local objection
|
|
25
|
LCS/EW/17-18/Kasiani/02
|
Raising/Re-Shaping of Earthen Road Embankment on Mustafijur House to Falsi Moddho Danga road at ch. 0m-600m under Nijamkandi UP of Kasiani Upazila, Dist: Gopalganj. ID No. 33543-5879
|
0.6000
|
10.577
|
Nasima/ Adu
|
10.577
|
06/03/2018
|
20/05/2020
|
1
|
11/10/2020
|
FB paid
|
|
26
|
LCS/EW/17-18/Kasiani/01
|
Detail estimate for Palisading work with earth filling on Gopinathpur Kazipara Falshi to Taltola Road at ch. 0-15m(RS), 60m-90m (RS), 110m-120m (RS), 150m-195m (RS) & 3300m-3327m (LS) Total=127m under 14 No. Nijamkandi UP of Kasiani Upazila, Dist: Gopalga
|
0.1270
|
7.636
|
Shorifa/Hira
|
7.636
|
28/01/2018
|
12/06/2018
|
1
|
11/10/2020
|
FB Paid (EW Vol: less)
|
|
27
|
LCS/EW/16-17/Kasiani/01
|
Improvement of Earth work Zikabari Dhalibari carpeting road-Solier kull Primary School Road at ch. 950m-1525m under Mahamudpur UP of Kasiani Upazila, Dist: Gopalganj.
|
0.5750
|
10.445
|
Kuntali/Rekha
|
10.445
|
08/05/2017
|
04/01/2018
|
1
|
11/10/2020
|
FB paid
|
|
28
|
LCS/MD/17-18/KASI-31
|
Development of Parulia Hat (MSP, Twin Toilet, Deep Tube-well & Internel CC road) under Kasiani Upazilla, Dist: Gopalganj
|
|
25.194
|
|
25.194
|
|
|
0
|
19/01/2019
|
|
|
29
|
LCS/SP/17-18/KASI-30
|
Construction of slope protection work at Ch. 3-25m (RS) & 200-230m (RS) on Ramdia Satper BC Road to DIG Road House, Ch. 0 to 285m, under Puisur UP, Kasinai Upazila, Gopalganj.
|
0.0520
|
2.390
|
|
2.390
|
|
|
0
|
19/01/2019
|
|
|
30
|
LCS/SP/17-18/KASI-29
|
Construction of slope protection work on Majra High School to Bishwa road at ch. 980m-100m(LS) & 1075m-1105m(LS) under Sajail UP, Kasiani Upazila, Gopalganj.
|
0.0500
|
2.360
|
Hasi/ Jorna
|
2.360
|
13/04/2018
|
30/06/2018
|
70
|
19/01/2019
|
|
|
31
|
LCS/SP/17-18/KASI-28
|
Construction of slope protection work on Nichu Majra West Para Bishwa road to Badol Mistrir House at ch. 5m-35m under Sajail UP, Kasiani Upazila, Gopalganj.
|
0.0300
|
1.406
|
|
1.406
|
|
|
0
|
19/01/2019
|
|
|
32
|
LCS/SP/17-18/KASI-27
|
Construction of slope protection work on Falsi Syed Mollah House to Miraj Fakir House road at Ch.0m-30m Under Nijamkandi UP, Kasiani Upazila, Gopalganj.
|
0.0300
|
1.406
|
Rekha/Shirin
|
1.406
|
|
|
0
|
19/01/2019
|
|
|
33
|
LCS/SP/17-18/KASI-26
|
Construction of slope protection work at at Ch.0-15m(RS), 60-90m(RS), 110-120m (RS), 150-195m(RS) & 3300-3327m(LS) Total=127m on Gopinathpur Kazipara Falshi to Taltola Road, ch.0 to 4870m under 14 no. Nijamkandi UP, Kasiani Upazila, Gopalganj.
|
0.1270
|
7.636
|
Shorifa/Hira
|
7.636
|
28/01/2018
|
12/06/2018
|
100
|
19/01/2019
|
|
|
34
|
LCS/SP/17-18/KASI-25
|
Construction of slope protection work at Ch. 85-110 (RS), 255-275m(LS) & 385-410m(RS)m on Talbari GPS at Ch. 0 to 475m Road , under 14 no. Nijamkandi UP, Kasiani Upazila, Gopalganj.
|
0.0700
|
3.146
|
Rekha/Shirin
|
3.146
|
08/03/2018
|
30/05/2018
|
70
|
19/01/2019
|
|
|
35
|
LCS/SP/17-18/KASI-24
|
Construction of slope protection work at Ch. 395-405m on Bagjhapa Pucca Rasta to Rail Line Road at Ch. 0 to 675m Road, under Sajail UP, Kasiani Upazila, Gopalganj.
|
0.0100
|
0.499
|
Hasi/ Jorna
|
0.499
|
13/04/2018
|
30/06/2018
|
70
|
19/01/2019
|
|
|
36
|
LCS/DS/17-18/KASI-23
|
Construction of 1x2.0mx2.0 Box Culvert at 12m on Hashmoth Shikder House Road, ch. 0-600m under Maheshpur UP, Kasinai Upazila, Gopalganj.
|
|
4.834
|
|
4.834
|
|
|
0
|
19/01/2019
|
|
|
37
|
LCS/DS/17-18/KASI-22
|
Construction of 1x2.6mx2.6 Box Culvert at 1350m on Jikabar Dhalibari Carpeting Road to Solierkull Primary School Road, ch. 0-1525m under Mahmudpur UP, Kasinai Upazila, Gopalganj.
|
|
8.873
|
|
8.873
|
|
|
0
|
19/01/2019
|
|
|
38
|
LCS/DS/17-18/KASI-21
|
Construction of 1 no U-drains (0.900mmx0.900mm) on Jakir Mollah Shop to Raja Miyar House road at ch. 550m under Sajail UP, Kasinai Upazila, Gopalganj.
|
|
1.462
|
Hasi/ Jorna
|
1.462
|
13/04/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
39
|
LCS/DS/17-18/KASI-20
|
Construction of 1 no U-drains (0.900mmx0.900mm) single vent on Nichu Majra West Para Bishwa road to Badol Mistrir House at ch. 220m under Sajail UP, Kasiani Upazila, Gopalganj.
|
|
1.462
|
|
1.462
|
|
|
0
|
19/01/2019
|
|
|
40
|
LCS/DS/17-18/KASI-19
|
Construction of 3 no U-drains (0.900mmx0.900mm) on Majra High School to Bishwa road at ch. 10m, 920m & 1115m under Sajail UP, Kasiani Upazila, Gopalganj.
|
|
5.200
|
Hasi/Jorna
|
5.200
|
13/04/2018
|
30/06/2018
|
75
|
19/01/2019
|
|
|
41
|
LCS/DS/17-18/KASI-18
|
Construction of 2 no U-drains (0.900mmx0.900mm) on Ramdia College Road to Ramdia West Simana road at ch. 240m & 350m under Bethuri UP, Kasinai Upazila, Gopalganj.
|
|
2.899
|
|
2.899
|
|
|
0
|
19/01/2019
|
|
|
42
|
LCS/DS/17-18/KASI-17
|
Construction of 2 no U-drains (0.900mmx0.900mm) on Satpar Ramdia Pucca Road to WAPDA Khal at ch. 100m & 250m under Hatiara UP, Kasinai Upazila, Gopalganj.
|
|
3.198
|
|
3.198
|
|
|
0
|
19/01/2019
|
|
|
43
|
LCS/DS/17-18/KASI-16
|
Construction of 2 no U-drains (0.900mmx0.900mm) on Mustafijur House to Falsi Moddho Danga road at ch. 250m & 440m under Nijamkandi UP, Kasinai Upazila, Gopalganj.
|
|
3.524
|
Shorifa/Hira
|
3.524
|
|
|
0
|
19/01/2019
|
|
|
44
|
LCS/DS/17-18/KASI-15
|
Construction of 2 no U-drains (0.900mmx0.900mm) on Falsi Syed Mollah House to Miraj Fakir House road at ch. 525m & 800m under Nijamkandi UP, Kasinai Upazila, Gopalganj.
|
|
3.198
|
Shorifa/Hira
|
3.198
|
|
|
0
|
19/01/2019
|
|
|
45
|
LCS/DS/17-18/KASI-14
|
Construction of 1 no U-drains (0.900mmx0.900mm) single vent at ch. 175m on Talbari GPS at Ch. 0 to 475m Road , under 14 no. Nijamkandi UP, Kasiani Upazila, Gopalganj.
|
|
1.718
|
Rekha/Shirin
|
1.718
|
03/01/2018
|
30/05/2018
|
70
|
19/01/2019
|
|
|
46
|
LCS/DS/17-18/KASI-13
|
Construction of 1 no U-drains (0.900mmx0.900mm) single vent at ch. 650m on Bagjhapa Pucca Rasta to Rail Line Road at Ch. 0 to 675m Road, under Sajail UP, Kasiani Upazila, Gopalganj.
|
|
1.851
|
Hasi/ Jorna
|
1.851
|
13/04/2018
|
30/06/2018
|
80
|
19/01/2019
|
|
|
47
|
LCS/HBB/17-18/KASI-12
|
Improvement of Road by HBB on Jakir Mollah Shop to Raja Miyar House road at ch. 0m/680m under Sajail UP, Kasinai Upazila, Dist: Gopalganj.
|
0.6800
|
21.867
|
|
21.867
|
|
|
0
|
19/01/2019
|
|
|
48
|
LCS/HBB/17-18/KASI-11
|
Detail estimate for Improvement of Road by HBB on Nichu Majra West Para Bishwa road to Badol Mistrir House at ch. 0m-700m under Sajail UP, Kasiani Upazila, Gopalganj.
|
0.7000
|
23.005
|
|
23.005
|
|
|
0
|
19/01/2019
|
|
|
49
|
LCS/HBB/17-18/KASI-10
|
Detail estimate for Improvement of Road by HBB on Majra High School to Bishwa road at ch 0m-1280m under Sajail UP, Kasiani Upazila, Gopalganj.
|
1.2800
|
41.843
|
Farida/Janu
|
41.843
|
26/02/2018
|
15/06/2018
|
50
|
19/01/2019
|
|
|
50
|
LCS/HBB/17-18/KASI-09
|
Improvement of Road by HBB on Talbari GPS at Ch. 0 to 475m Road , under 14 no. Nijamkandi UP, Kasinai Upazila, Gopalganj.
|
0.4750
|
16.193
|
Rabeya/Shahinur
|
16.193
|
03/01/2018
|
12/06/2018
|
100
|
19/01/2019
|
|
|
51
|
LCS/HBB/17-18/KASI-08
|
Improvement of Road by HBB on Bagjhapa Pucca Rasta to Rail Line Road at Ch. 0 to 675m Road, under Sajail UP, KasianiUpazila, Gopalganj.
|
0.6750
|
22.699
|
Dina/Shefali
|
22.699
|
16/01/2018
|
12/06/2018
|
100
|
19/01/2019
|
|
|
52
|
LCS/EW/17-18/KASI-07
|
Approach road filling by earth on Hashmoth Shikder House Road, ch. 0-600m under Maheshpur UP, Kasinai Upazila, Gopalganj.
|
0.0800
|
1.165
|
|
1.165
|
|
|
0
|
19/01/2019
|
|
|
53
|
LCS/EW/17-18/KASI-06
|
Raising/Re-shaping of Earthen Road Embankment on Ramdia Satper BC Road to DIG Road House, Ch. 0 to 285m, under Puisur UP, Kasinai Upazila, Gopalganj
|
0.2850
|
4.280
|
|
4.280
|
|
|
0
|
19/01/2019
|
|
|
54
|
LCS/EW/17-18/KASI-05
|
Raising/Re-shaping of Earthen Road Embankment on Ramdia College Road to Ramdia West Simana Road at ch. 0m-50m under Bethuri Up of Kasiani Upazila, Dist: Gopalganj.
|
0.5000
|
4.532
|
Gouri/China
|
4.532
|
21/03/2018
|
20/06/2018
|
72
|
19/01/2019
|
|
|
55
|
LCS/EW/17-18/KASI-04
|
Raising/Re-shaping of Earthen Road Embankment on East Para GPS BC Road to South Para House road at ch. 0m-470m under Bethuri Up of Kasiani Upazila, Dist: Gopalganj.
|
0.4700
|
7.874
|
|
7.874
|
23/03/2018
|
|
0
|
19/01/2019
|
|
|
56
|
LCS/EW/17-18/KASI-03
|
Raising/Re-shaping of Earthen Road Embankment on Satpar Ramdia Pucca Road to WAPDA Khal at ch. 0m-700m under Hatiara Up of Kasiani Upazila, Dist: Gopalganj.
|
0.7000
|
8.565
|
|
8.565
|
|
|
0
|
19/01/2019
|
|
|
57
|
LCS/EW/17-18/KASI-02
|
Raising/Re-shaping of Earthen Road Embankment on Mustafijur House to Falsi Moddho Danga road at ch. 0m-600m under Nijamkandi Up of Kasiani Upazila, Dist: Gopalganj.
|
0.6000
|
10.577
|
Nasima/Adu
|
10.577
|
06/03/2018
|
28/06/2018
|
70
|
19/01/2019
|
|
|
58
|
LCS/EW/17-18/KASI-01
|
Raising/Re-shaping of Earthen Road Embankment on Falsi Syed Mollah House to Miraj Fakir House road at ch. 0m-1000m under Nijamkandi Up of Kasiani Upazila, Dist: Gopalganj.
|
1.0000
|
9.158
|
Madina/Tuku
|
9.158
|
08/03/2018
|
28/06/2018
|
20
|
19/01/2019
|
17-18
|
|
|
3
|
Kotwalipara
|
|
1
|
LCS/TP/20-21/Kotali/03
|
Tree Plantation & One year Caretaking of Lebubari GPS-Kakhanda via Paikerbari, Tulshibari & Raybari Road from ch. 00m-1000m under Kotalipara Upazila, Dist: Gopalgonj.
|
1.0000
|
2.503
|
|
2.503
|
|
|
0
|
11/10/2020
|
|
|
2
|
LCS/TP/20-21/Kotali/02
|
Tree Plantation & One year Caretaking of Shouldoho Embankment to Bhorot Sarker house via 107 No. Shouldoho Govt. Primary School Road from ch. 00m-1000m under Kotalipara Upazila, Dist: Gopalgonj.
|
1.0000
|
2.503
|
|
2.503
|
|
|
0
|
11/10/2020
|
|
|
3
|
LCS/TP/20-21/Kotali/01
|
Tree Plantation & One year Caretaking of Bhi Bazar Road to Botbari Mondir via Belerbari Road from ch. 00m-1000m under Kotalipara Upazila, Dist: Gopalgonj.
|
1.0000
|
2.503
|
|
2.503
|
|
|
0
|
11/10/2020
|
|
|
4
|
LCS/Market/16-17/Kotali/01
|
Development of Chwdhury Hat (Construction of Twin Toilet, 1no fish shed, 2nos Muli Purpose shed & 1 no Deep Tube Well) under Pinjuri UP of Kotalipara Upazila, Dist: Gopalganj.
|
|
23.913
|
Rita/Anjali
|
23.913
|
14/05/2017
|
30/06/2018
|
0
|
11/10/2020
|
Work stop due to higher rate of Mat
|
|
5
|
LCS/SP/17-18/Kotali/03
|
Slope Protection work on Bot Bari Ashok Babur Bari to Assaram road ch.8m-43m(RS), 150m-175m(RS) 180m-220m(RS) & 150m-200m (LS) under Radhaganj UP of Kotalipara Upazila, Gopalganj. ID : 33551-5489
|
|
6.905
|
Archona/Purnima
|
6.905
|
15/02/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
6
|
LCS/SP/17-18/Kotali/02
|
Slope Protection work on Horinahati BD road to Pochim Horinahati GPS BC road at ch.72m-100m(RS), 220m-230m (RS), 305m-337m (RS), 435m-465m (LS) 495m-520m(RS) 520m-565m(LS) & 613m-643m (LS) under Sadullahpur UP of Kotalipara Upzila, Dist: Gopalgonj. ID No
|
|
9.390
|
Khodeza/Mukta
|
9.390
|
11/02/2018
|
30/06/2018
|
0
|
11/10/2020
|
Not stated due to higher rate of mat.
|
|
7
|
LCS/SP/17-18/Kotali/01
|
Part-2: Construction of 100m slope protection at ch 374m-391m =17m Rt/side ch. 416m-442m =26m ×2=54m Both side & ch. 460m-491m=31m Lt/side under Sadullahpur UP of Kotalipara Upazila, Dist: Gopalganj.
|
|
4.680
|
Ashima/Sima
|
4.680
|
14/02/2018
|
30/04/2018
|
0
|
11/10/2020
|
Not stated due to higher rate of mat.
|
|
8
|
LCS/Khal/17-18/Kotali/03
|
Re-excavation of khal from Nitai Bazar to Trimohini khal at ch. 900-2200m under Sadullahpur UP Kotalipara Upazila, Dist: Gopalganj.Group-3:
|
1.3000
|
13.002
|
Monica/Kusum
|
13.002
|
17/03/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid (Less vol)
|
|
9
|
LCS/Khal/17-18/Kotali/02
|
Re-excavation of khal from Nitai Bazar to Trimohini khal at ch. 450m-900m under Sadullahpur UP Kotalipara Upazila, Dist: Gopalganj.Group-2:
|
0.4500
|
9.857
|
Sreeti/Rita
|
9.857
|
17/03/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid (Less vol)
|
|
10
|
LCS/Khal/17-18/Kotali/01
|
Re-excavation of khal from Nitai Bazar to Trimohini khal at ch. 0-450m under Sadullahpur UP Kotalipara Upazila, Dist: Gopalganj.Group-1:
|
0.4500
|
11.550
|
Maiabaroi/ Kajuli
|
11.550
|
17/03/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid (Less vol)
|
|
11
|
LCS/DS/19-20/Kotali/01
|
Construction of 2 Nos U-drain (0.900m×0.900m) on Uttar Nayerbari GPS to West-North Nayer Bari Rashid Boyati Bari at ch. 0m & 925m under Kotalipara Upazila, Dist: Gopalganj.
|
|
3.584
|
|
3.584
|
|
|
0
|
11/10/2020
|
Not yet contracted
|
|
12
|
LCS/DS/16-17/Kotali/03
|
Construction of 2 Nos. U-drain (0.900m×0.900m) on Bot Bari Ashok Babur Bari to Assaram road ch.294m &620m under Radhaganj UP of Kotalipara Upazila, Gopalganj.ID : 33551-5489
|
|
4.446
|
Dalia/Namita
|
4.446
|
15/02/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
13
|
LCS/DS/16-17/Kotali/02
|
Construction of 5 Nos. Single Vent U-drain (0.900m×0.900m) on Kusla UP to Tupuria R&H road at ch 400m, 1000m, 1500m, 1750m & 2180m under Kusla UP of Kotalipara Upzila, Dist: Gopalgonj. ID No. 33551-4024
|
|
9.249
|
Tajrin/Rahimon
|
9.249
|
25/01/2018
|
30/06/2018
|
1
|
11/10/2020
|
1 no U-drain not complete due to land problem
|
|
14
|
LCS/DS/16-17/Kotali/01
|
Construction of 4 Nos. single vent U-drain (0.900m×0.900m) on Uttar Nayerbari GPS to West-North Nayer Bari Rashid Boyati Bari at ch. 0m-1085m under Sadullahpur UP of Kotalipara Upazila, Dist: Gopalganj.
|
|
7.046
|
Soniti/Sabita
|
7.046
|
11/02/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
15
|
LCS/HBB/19-20/Kotali/02
|
Improvement of road by HBB Kafula bari Community Clinic-Gobindo Halder Bari Road at ch. 00m-501m under Kotalipara Upazila, Dist: Gopalganj.
|
0.5000
|
16.304
|
Sharasoti/Shapna
|
16.304
|
01/06/2020
|
25/12/2020
|
0
|
11/10/2020
|
Work will start soon
|
|
16
|
LCS/HBB/19-20/Kotali/01
|
Improvement of road by HBB Uttar Nayerbari GPS to West-North Nayerbari Rashid bari at ch. 00m-1085m under Kotalipara Upazila, Dist: Gopalganj.
|
1.0850
|
44.475
|
|
44.475
|
|
|
0
|
11/10/2020
|
Not yet contracted
|
|
17
|
LCS/HBB/17-18/Kotali/03
|
Improvement of eroded road by HBB from Chitoshi GPS to Kandirpar WAPDA Beribandth at ch. 1650m-2575m under Pinjuri UP of Kotalipara Upazila, Dist: Gopalganj. Group: 2
|
0.9250
|
37.801
|
Uzzali/Minoti
|
37.801
|
07/01/2018
|
30/04/2018
|
0
|
11/10/2020
|
Stop due to high rate of matarials
|
|
18
|
LCS/HBB/17-18/Kotali/02
|
Improvement of eroded road by HBB from Chitoshi GPS to Kandirpar WAPDA Beribandth at ch. 1000m-1650m under Pinjuri UP of Kotalipara Upazila, Dist: Gopalganj. Group: 1
|
0.6500
|
35.997
|
Rabeya/Tahera
|
35.997
|
07/01/2018
|
30/04/2018
|
0
|
11/10/2020
|
Stop due to high rate of matarials
|
|
19
|
LCS/HBB/17-18/Kotali/01
|
Improvement of eroded Road by HBB from Pakhorpar LGED Bridge to Paikerbari Community Clinic at ch.0m-660m under Sadullahpar UP of Kotalipara Upazila, Dist: Gopalganj.
|
0.6600
|
28.182
|
Susoma/Banai
|
28.182
|
01/01/2018
|
30/04/2018
|
1
|
11/10/2020
|
FB Paid
|
|
20
|
LCS/HBB/16-17/Kotali/01
|
Improvement of road by HBB on Kurpala Sultan Fakir House to Kagdanga Kheya ghat road via Kurpala Madrasha & Gucchogram at ch. 125m-885m under Pinjuri UP of Kotalipara Upazila, Dist: Gopalganj.
|
0.7600
|
31.641
|
Sarola/Shiuli
|
31.641
|
19/05/2017
|
30/04/2018
|
1
|
11/10/2020
|
FB Paid
|
|
21
|
LCS/EW/17-18/Kotali/03
|
Raising/Re- shaping of Earthen road Embankment on Bot Bari Ashok Babur Bari to Assaram road ch.0m-700m under Radhaganj UP of Kotalipara Upazila, Gopalganj.
|
0.7000
|
12.443
|
Bina/Taslima
|
12.443
|
15/02/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid (Less vol)
|
|
22
|
LCS/EW/17-18/Kotali/02
|
Improvement of Earthen Shoulders on Horinahati BD road to Pochim Horinahati GPS BC road at ch.0m-645m under Sadullahpur UP of Kotalipara Upzila, Dist: Gopalgonj. ID No. 33551-5083
|
0.6450
|
3.640
|
Rahima/Kabita
|
3.640
|
13/03/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid (Less vol)
|
|
23
|
LCS/EW/17-18/Kotali/01
|
Detail estimate for Raising & Re-sectioning of Rural earth road from Uttar Nayerbari GPS to West-North Nayer Bari Rashid Boyati Bari at ch. 0m-1085m under Sadullahpur UP of Kotalipara Upazila, Dist: Gopalganj.
|
1.0850
|
14.214
|
Minu/Dipu
|
14.214
|
11/02/2018
|
30/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
24
|
LCS/EW/16-17/Kotali/01
|
Improvement of road by earth work on Kafula bari Community Clinic-Gobindo Halder Bari Road at ch. 0.0m-510m. under Ramsil UP of Kotalipara Upazila, Dist: Gopalganj.
|
0.5100
|
6.250
|
Sapna/Sorohoti
|
6.250
|
13/04/2017
|
30/04/2018
|
1
|
11/10/2020
|
FB Paid
|
|
25
|
LCS/Khal/17-18/KOTA-20
|
G2: 900 - 2200m
|
1.3000
|
13.002
|
Monica & Kusum
|
13.002
|
15/03/2018
|
30/06/2018
|
100
|
19/01/2019
|
|
|
26
|
LCS/Khal/17-18/KOTA-19
|
G2: 450 - 900m
|
0.4500
|
9.857
|
Sreeti & Rita
|
9.857
|
15/03/2018
|
30/06/2018
|
100
|
19/01/2019
|
|
|
27
|
LCS/Khal/17-18/KOTA-18
|
G1: 0 - 450m
|
0.4500
|
11.550
|
Maiabaroi & Kajuli
|
11.550
|
15/03/2018
|
30/06/2018
|
100
|
19/01/2019
|
|
|
28
|
|
Re-excavation of Khal from Nitai Bazar to Trimohini Khal at ch. 0-2200m under Sadullahpur UP, Kotalipara Upazila, Gopalganj.
|
|
0.000
|
|
0.000
|
|
|
0
|
19/01/2019
|
|
|
29
|
LCS/Ghat/17-18/KOTA-17
|
Construction of Boat Landing Station at Tupuria Hat Khal Bank adjacent to Tupuria Hat under Kushla UP, of Kotalipara Upazila, Gopalganj.
|
|
22.628
|
|
22.628
|
|
|
0
|
19/01/2019
|
|
|
30
|
LCS/SP/17-18/KOTA-16
|
Slope Protection work on Sadullahpur UPC-Noyerbari Bazar-Pirerbari Bazar Road at ch. 250-320m(RS), 325-365(LS), 355-370(RS), 388-438m(LS), 485-510m(LS),1140-1190m(LS), 1907-1942m(RS), 1935-2000m(LS),2365-2385m(RS) & 2385-2585m(LS)=570m under SadullahpurU
|
0.5700
|
26.374
|
|
26.374
|
|
|
0
|
19/01/2019
|
|
|
31
|
LCS/SP/17-18/KOTA-15
|
Slope Protection work on Bot Bari Ashok Babur Bari to Assaram road ch. 8m-43m(RS), 150m-175m(RS), 180m-220m(RS) & 150m-200m(LS) under Radhaganj UP of Kotalipara Upazila, Gopalganj.
|
0.1500
|
6.905
|
Archana/Purnima
|
6.905
|
|
|
0
|
19/01/2019
|
|
|
32
|
LCS/SP/17-18/KOTA-14
|
Slope Protection work on Horinahati BD road to Pochim Horinahati GPS BC road at ch. 72m-100m(RS), 220m/230m(RS), 305m-337m(RS), 435m-465m(LS), 495m-520m(RS), 520m-565m(LS) & 613m-643m(LS) under Sadullahpur UP of Kotalipara Upazila, Gopalganj.
|
0.2000
|
9.390
|
Khodeja/Mukta
|
9.390
|
07/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
33
|
LCS/SP/17-18/KOTA-13
|
Slope Protection at ch. 374-391m(RS), 416-442m(BS) & 460-491m(LS)=100m on Pakhorpar LGED Bridge to Paikerbari Community Clinic at Ch. 0 to 660m Road , under Sadullahpur UP, Kotalipara Upazila, Gopalganj.
|
0.1000
|
4.680
|
Ashima/Sema
|
4.680
|
|
|
0
|
19/01/2019
|
|
|
34
|
LCS/SP/17-18/KOTA-12
|
Slope Protection work on Kurpala Sultan Fakri House to Kagdanga Kheyaghat Road via Kurpala Madrasha & Gucchogram at ch. 168-193mRS, 499-514mRS, 546-581mRS, 615-622m RS & 630-645mRS under Pinjuri UP, Kotalipara Upazila, Gopalganj.
|
0.1000
|
4.520
|
Nurjahan/Hosneara
|
4.520
|
07/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
35
|
LCS/DS/17-18/KOTA-11
|
Construction of 2 Nos. U-drain (0.900m×0.900m) on Bot Bari Ashok Babur Bari to Assaram road ch. 294m & 620m under Radhaganj UP of Kotalipara Upazila, Gopalganj.
|
|
4.446
|
Dalia/Nomita
|
4.446
|
|
|
0
|
19/01/2019
|
|
|
36
|
LCS/DS/17-18/KOTA-10
|
Construction of 5 Nos. Single Vent U-drain (0.900m×0.900m) on Kusla UP to Tupuria R&H road at ch. 400m, 100m, 1500m, 1750m & 2180 under Kusla UP of Kotalipara Upazila, Gopalganj.
|
|
9.249
|
Tajrin/Rahimon
|
9.249
|
07/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
37
|
LCS/DS/17-18/KOTA-09
|
Construction of 1 No. Single Vent U-drain (0.900m×0.900m) on Kurpala Sultan Fakri House to Kagdanga Kheyaghat Road via Kurpala Madrasha & Gucchogram at ch. 0 - 2575m under Pinjuri UP, Kotalipara Upazila, Gopalganj.
|
|
1.682
|
Nurjahan/Hosneara
|
1.682
|
07/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
38
|
LCS/DS/17-18/KOTA-08
|
Construction of 4 Nos. Single Vent U-drain (0.900m×0.900m) on Uttar nayerbari GPS to West-North Nayer Bari Rashid Boyati Bari at ch. 0m-1085m under under Sadullahpur UP, Kotalipara Upazila, Gopalganj.
|
|
7.046
|
Minoty/Sabita
|
7.046
|
07/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
39
|
LCS/HBB/17-18/KOTA-07
|
G2: 1650 - 2575m
|
0.9250
|
37.801
|
Uzzaly/Minoty
|
37.801
|
10/01/2018
|
30/04/2018
|
20
|
19/01/2019
|
|
|
40
|
LCS/HBB/17-18/KOTA-06
|
G1: 1000 - 1650m
|
0.6500
|
35.997
|
Rabeya/Tahera
|
35.997
|
10/01/2018
|
30/04/2018
|
60
|
19/01/2019
|
|
|
41
|
LCS/HBB/17-18/KOTA-05
|
Detail estimate for Improvement of Road by HBB on Pakhorpar LGED Bridge to Paikerbari Community Clinic at Ch. 0 to 660m Road , under Sadullahpur UP, Kotalipara Upazila, Gopalganj.
|
0.6600
|
28.182
|
Susoma/Banani
|
28.182
|
07/01/2018
|
30/04/2018
|
25
|
19/01/2019
|
|
|
42
|
LCS/EW/17-18/KOTA-04
|
Raising/Re-shaping of Earthen road Embankment on Sadullahpur UPC-Noyerbari Bazar-Pirerbari Bazar Road , Ch. 0 to 4000m (effective=3937m) under Sadullahpur UP, Kotalipara Upazila, Gopalganj.
|
3.9370
|
41.147
|
|
41.147
|
|
|
0
|
19/01/2019
|
|
|
43
|
LCS/EW/17-18/KOTA-03
|
Raising/Re-shaping of Earthen road Embankment on Bot Bari Ashok Babur Bari to Assaram road ch. 0m-700m under Radhaganj UP of Kotalipara Upazila, Gopalganj.
|
0.7000
|
12.443
|
Bina/Taslima
|
12.443
|
15/02/2018
|
30/06/2018
|
100
|
19/01/2019
|
|
|
44
|
LCS/EW/17-18/KOTA-02
|
Improvement of Earthen Shoulders on Horinahati BD road to Pochim GPS BC road at ch. 0m-645m under under Sadullahpur UP, Kotalipara Upazila, Gopalganj.
|
0.6450
|
3.640
|
Rohima/Kabita
|
3.640
|
07/02/2018
|
30/06/2018
|
100
|
19/01/2019
|
|
|
45
|
LCS/EW/17-18/KOTA-01
|
Raising/Re-shaping of Earthen road Embankmen on Uttar nayerbari GPS to West-North Nayer Bari Rashid Boyati Bari at ch. 0m-1085m under under Sadullahpur UP, Kotalipara Upazila, Gopalganj.
|
1.0850
|
14.214
|
Minu/Dipu
|
14.214
|
11/02/2018
|
30/06/2018
|
100
|
19/01/2019
|
17-18
|
|
|
4
|
Muksudpur
|
|
1
|
LCS/TP/20-21/Muksud/04
|
Tree Plantation & One year Caretaking of Mondolgati Pacca Road Sayed Daroga house Road from ch. 00m-500m under Muksudpur Upazila, Dist: Gopalgonj.
|
0.5000
|
1.261
|
|
1.261
|
|
|
0
|
11/10/2020
|
|
|
2
|
LCS/TP/20-21/Muksud/03
|
Tree Plantation & One year Caretaking of Ujani UP Complex-Patkelbari Hat Road from ch. 3000m-5000m under Muksudpur Upazila, Dist: Gopalgonj.
|
2.0000
|
4.986
|
|
4.986
|
|
|
0
|
11/10/2020
|
|
|
3
|
LCS/TP/20-21/Muksud/02
|
Tree Plantation & One year Caretaking of Tengrakhola – Jalirpar GC Road from ch. 18300m-19300m under Muksudpur Upazila, Dist: Gopalgonj.
|
1.0000
|
2.503
|
|
2.503
|
|
|
0
|
11/10/2020
|
|
|
4
|
LCS/TP/20-21/Muksud/01
|
Tree Plantation & One year Caretaking of Murad Kazi (Boalia) house to Rasulpur-Krishanpur Road from ch. 1750m-3250m under Kotalipara Upazila, Dist: Gopalgonj.
|
1.5000
|
3.744
|
|
3.744
|
|
|
0
|
11/10/2020
|
|
|
5
|
LCS/Market/17-18/Muksud/04
|
Development of Bolonarayaon Market (MSP, FS, OSP, Tube-well & Internal CC road) under 05 No Bahugram Union Muksudpur Upazila, Gopalganj.
|
|
22.537
|
Alo/Rani
|
22.537
|
02/07/2018
|
02/08/2019
|
1
|
11/10/2020
|
FB Paid
|
|
6
|
LCS/Market/17-18/Muksud/03
|
Development of Gohala Market (Internal CC Road, Guide wall & Twin Toilet) under Gohala UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
24.336
|
Shelina/Papiya
|
24.336
|
22/01/2018
|
21/05/2018
|
1
|
11/10/2020
|
FB Paid (CC road less in length approx 50m)
|
|
7
|
LCS/Market/17-18/Muksud/02
|
Development of Haldivita Market (Interanl CC Road) Under 09 No Batikamari Union of Muksudpur Upazila, Dist: Gopalganj.
|
|
8.571
|
Farida/Tulu
|
8.571
|
02/07/2018
|
02/08/2019
|
1
|
11/10/2020
|
FB paid
|
|
8
|
LCS/Market/17-18/Muksud/01
|
Development of Salina Box (Gerakhola) Bazar (Construction of Internal CC Road with surface) under Gobindapur UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
22.268
|
Rubia/Hosneara
|
22.268
|
19/06/2017
|
31/01/2018
|
1
|
11/10/2020
|
FB Paid
|
|
9
|
LCS/Market/16-17/Muksud/01
|
Development of Fularpar Bazar (Construction of 1 No Muli Purpose shed, 1 No Deep Tube well & Internal road) under Gobindapur UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
7.922
|
Salina/Rubi
|
7.922
|
19/06/2017
|
28/02/2018
|
1
|
11/10/2020
|
FB Paid
|
|
10
|
LCS/Ghat/19-20/Muksud/01
|
Construction of Boat Landing Station at Dhranda Khal adjacent to Dhranda GPS & Dhranda Bazar Under 04 No Khanderpara Union Muksudpur Upazila, Dist- Gopalganj.
|
|
8.375
|
Lakkhi/ Abola
|
8.375
|
15/02/2020
|
30/07/2020
|
1
|
11/10/2020
|
FB Paid
|
|
11
|
LCS/SP/17-18/Muksud/02
|
Slope Protection work on Faruk Khan High School Connecting road at ch.382m-402m (Both side) under 03No Gobindopur UP of Muksudpur Upazila, Dist: Gopalganj. ID No:33558-5578
|
|
1.844
|
Awsona / Shahar
|
1.844
|
02/07/2018
|
02/08/2019
|
1
|
11/10/2020
|
FB Paid
|
|
12
|
LCS/SP/17-18/Muksud/01
|
Construction of Slope Protection work on Bahara Alim Madrasha to Mirez Member House Road at Ch.560m-630m(R/S) Under Batikamari UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
3.307
|
Sabina/ Anowara
|
3.307
|
14/02/2018
|
15/06/2018
|
1
|
11/10/2020
|
FB Paid (Join with HBB)
|
|
13
|
LCS/SP/16-17/Muksud/05
|
Slope Protection work on Khabir Kha House –Atik Sheikh House road at different chainage under Gobindopur UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
2.296
|
Pari/Rani
|
2.296
|
21/01/2018
|
15/05/2018
|
1
|
11/10/2020
|
FB Paid (Join with HBB)
|
|
14
|
LCS/SP/16-17/Muksud/04
|
Slope Protection work on Vakuri road (Sam Mamber)-Puran Muksudpur via Vakuri GPS at different chainage under Gobindopur UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
3.673
|
Riziya/Monimala
|
3.673
|
09/01/2018
|
08/05/2018
|
1
|
11/10/2020
|
FB Paid (Join with HBB)
|
|
15
|
LCS/SP/16-17/Muksud/03
|
Slope Protection work on Pachuria Bazar-Miravita via UP connecting road at different chainage under Pashergati UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
3.903
|
Ratna/Rupa
|
3.903
|
18/02/2018
|
25/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
16
|
LCS/SP/16-17/Muksud/02
|
Slope protection work on Pulin Pal House-Janbag Mukter Sheikh House road at ch. 1095m-1127m (L/S) under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
1.348
|
Moriom/Sabina
|
1.348
|
29/05/2017
|
31/12/2017
|
1
|
11/10/2020
|
FB Paid
|
|
17
|
LCS/SP/16-17/Muksud/01
|
Slope protection work on Purbo Korikhan Sanowar House-Korikain Paschim Para Monsur Sheikh House road at ch. 310-360m (R/S) 550m-568m (L/S) under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
2.864
|
Hasna/ Farida
|
2.864
|
15/02/2018
|
15/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
18
|
LCS/DS/17-18/Muksud/02
|
Construction of 1 No. U-drain (0.900m×0.900m) on Millik Sreerampur BC road to Har Bhanga R&H road at ch.0.00m-825m under 08 No Moharajpur UP of Muksudpur Upazila, Dist: Gopalganj. ID No:33558-5577
|
|
1.711
|
Salina/Ambia
|
1.711
|
18/02/2018
|
17/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
19
|
LCS/DS/17-18/Muksud/01
|
Construction of 2 nos.U-drain (0.90m×0.90m) Single vent on Vattacharjo Khalasi Bari to Nur Mohammad House Road at Ch.130m & 350m Under 12 No Gohala Union of Muksudpur, Dist: Gopalganj.
|
|
3.368
|
Tuli/Laki
|
3.368
|
21/01/2018
|
21/02/2018
|
1
|
11/10/2020
|
FB Paid
|
|
20
|
LCS/DS/16-17/Muksud/03
|
Construction of 1 no U-drains (0.900m´ 0.900m) on Pachuria Bazar-Miravita via UP connecting road at ch. 350m under Pashergati UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
1.452
|
Ratna/Rupa
|
1.452
|
19/06/2017
|
25/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
21
|
LCS/DS/16-17/Muksud/02
|
Construction of 1no Drainage structure (0.900m ´ 0.900m) on Pulin Pal House-Janbag Mukter Sheikh House road at ch. 1145m under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
1.576
|
Moriom/Sabina
|
1.576
|
29/05/2017
|
31/12/2017
|
1
|
11/10/2020
|
FB Paid
|
|
22
|
LCS/DS/16-17/Muksud/01
|
Construction of 2nos Drainage structure (0.900m´0.900m) on Purbo Korikhan Sanowar House-Korikain Paschim Para Monsur Sheikh House road at ch. 213m & 630m under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj.
|
|
3.153
|
Hasna/ Farida
|
3.153
|
15/02/2018
|
15/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
23
|
LCS/CC/17-18/Muksud/03
|
Improvement of road by CC Block on Faruk Khan High School Connecting road at Ch.0m-405m under 03 No Gobindopur UP of Muksudpur Upazila, Dist: Gopalganj. ID No:33558-5578
|
0.4050
|
18.974
|
Awsona / Shahar
|
18.974
|
02/07/2018
|
02/08/2019
|
1
|
11/10/2020
|
FB Paid
with S/P
|
|
24
|
LCS/CC/17-18/Muksud/02
|
Improvement of road by CC Block on 173 No. Chowgacca GPS connecting road ch.0-84m Under 08 No Moharajpur Union, Muksudpur Upazila, Gopalganj.
|
0.0740
|
4.198
|
Salina/Ambia
|
4.198
|
18/02/2018
|
17/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
25
|
LCS/CC/17-18/Muksud/01
|
Improvement of road by CC Block on 114 No. Monirkandi GPS connecting road ch.0-103m Under 12 No Gohala Union, Muksudpur Upazila, Gopalganj.
|
0.1030
|
5.121
|
Eti/Zuma
|
5.121
|
02/07/2018
|
30/12/2018
|
1
|
11/10/2020
|
FB Paid
|
|
26
|
LCS/HBB/19-20/Muksud/03
|
Imp. of road by HBB on Ujani Rahuthor Road to Dr. Tarun Mondol House from ch. 00m-160m & 27m Slope Protection (Ch. 63m-90m L/s) on the Same road under 05 No Ujani Union Muksudpur Upazila, Dist- Gopalganj.
|
0.1600
|
9.044
|
Minu/Rina
|
9.044
|
05/02/2020
|
06/06/2020
|
1
|
11/10/2020
|
FB Paid
|
|
27
|
LCS/HBB/19-20/Muksud/02
|
Imp. of road by HBB on Pashargati UP Office-Janbag Nuton Bazar (Pream Bazar) via Bahirbug Road (Approach work) from ch. 500m-560m 02 No Pashargati Union under Muksudpur Upazila, Dist- Gopalganj. ID No: 335583015 Salvaged Cost: 7947.00
|
0.0600
|
3.083
|
Sahida /Jahura
|
3.083
|
06/02/2020
|
04/06/2020
|
1
|
11/10/2020
|
FB Paid
|
|
28
|
LCS/HBB/19-20/Muksud/01
|
Improvement of Road by HBB on Koholdia Main Road to Kachabari Bridge Road at ch. 0.0m-754m (Effective Length 742.00m) (75m Palisading work ch. 244m-269m R/S and 395m-445m L/S) under Batikamari Union under Muksudpur Upazila, Dist- Gopalganj. ID No: 3355855
|
0.7420
|
42.196
|
Sabina /Rebeka
|
42.196
|
25/03/2020
|
10/08/2020
|
0
|
11/10/2020
|
work stop due to flood
|
|
29
|
LCS/HBB/17-18/Muksud/03
|
Improvement of Road by HBB on Bahara Alim Madrasha to Mirez Member House Road at Ch.0m-1000m Under 02 No Pashargati UP of Muksudpur Upazila, Dist: Gopalganj.
|
1.0000
|
31.324
|
Sabina /Anowara
|
31.324
|
14/02/2018
|
15/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
30
|
LCS/HBB/17-18/Muksud/02
|
Improvement of Road by HBB on Maddha Bangram khanka Mosque to Boro Bangram Mazad Matubbar House via kundopara Road at Ch750m-1550m under 8 no. Moharajpur UP of Muksudpur Upazila. Group-2
|
0.8000
|
25.819
|
Afifa/Panna
|
25.819
|
01/02/2018
|
31/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
31
|
LCS/HBB/17-18/Muksud/01
|
Improvement of Road by HBB on Maddha Bangram khanka Mosque to Boro Bangram Mazad Matubbar House via kundopara Road at Ch0.0m-750m under 8 no. Moharajpur UP of Muksudpur Upazila. Group-1
|
0.7500
|
24.182
|
Jharna/Laki
|
24.182
|
01/02/2018
|
31/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
32
|
LCS/HBB/16-17/Muksud/03
|
Improvement of road by HBB on Khabir Kha House –Atik Sheikh House road at ch. 0.0m-560m under Gobindopur UP of Muksudpur Upazila, Dist: Gopalganj.
|
0.5600
|
19.342
|
Pari/Rani
|
19.342
|
02/01/2018
|
15/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
33
|
LCS/HBB/16-17/Muksud/02
|
Improvement of road by HBB on Vakuri road (Sam Mamber)-Puran Muksudpur via Vakuri GPS at ch. 0.0m-1005m under Gobindopur UP of Muksudpur Upazila, Dist: Gopalganj.
|
1.0050
|
34.846
|
Riziya/Monimala
|
34.846
|
09/01/2018
|
08/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
34
|
LCS/HBB/16-17/Muksud/01
|
Improvement of road by HBB on Pachuria Bazar-Miravita via UP connecting road at ch. 0.0m-960m under Pashergati UP of Muksudpur Upazila, Dist: Gopalganj.
|
0.9600
|
33.523
|
Ratna/ Rupa
|
33.523
|
19/06/2017
|
25/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
35
|
LCS/EW/19-20/Muksud/03
|
Raising/Re-Shaping of Earthen road Embankment of Vabrashur Purbo Para Asad Shop to Uttar Para Raod from Ch. 00-300m under 05 No Vabrashur Union under Muksudpur Upazila, Dist- Gopalganj. ID No: 335585592
|
0.3000
|
5.972
|
Usha/ Badana
|
5.972
|
01/03/2020
|
30/09/2020
|
0
|
11/10/2020
|
work stop due to flood
|
|
36
|
LCS/EW/19-20/Muksud/02
|
Raising/Re-Shaping of Earthen road Embankment of Kalia Uttarpara bridge to Kalia Purbopara Laskor Bari Muchi khal Road from Ch. 00-725m, with 02 Nos Link road 25.00m & 65m at Ch. 175m & 350m, under 07 No Vabrashur Union under Muksudpur Upazila, Dist- Gop
|
0.8150
|
13.579
|
Badana/ Shilpi
|
13.579
|
01/03/2020
|
30/09/2020
|
0
|
11/10/2020
|
work stop due to flood
|
|
37
|
LCS/EW/19-20/Muksud/01
|
Raising/Re-Shaping of Earthen road Embankment of Mondolgati Pacca Road to Sayed Daroga House Road Ch. 00-490m under 05 No Vabrashur Union under Muksudpur Upazila, Dist- Gopalganj. ID No: 335583015
|
0.4900
|
14.166
|
Salina/ Rahima
|
14.166
|
15/02/2020
|
27/08/2020
|
0
|
11/10/2020
|
work stop due to flood
|
|
38
|
LCS/EW/17-18/Muksud/06
|
Raising/Re-Shaping Earthen road Embankment on Millik Sreerampur BC road to Har Bhanga R&H road at ch.0.00m-825m under 08 No Moharajpur UP of Muksudpur Upazila, Dist: Gopalganj. ID No:33558-5577
|
0.8250
|
6.900
|
Sikha/Renu
|
6.900
|
18/02/2018
|
17/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
39
|
LCS/EW/17-18/Muksud/05
|
Raising/Re- shaping of Earthen road Embankment on Bahara Alim Madrasha to Mirez Member House road at ch.1000m-1597m under 9 No Batikamari Union Muksudpur Upazila, Gopalganj. ID : 33558-5466
|
0.5970
|
4.834
|
Sonia/Kajol
|
4.834
|
14/02/2018
|
15/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
40
|
LCS/EW/17-18/Muksud/04
|
Raising/Re- shaping of Earthen road Embankment on Hazragati Bridge to North Border road at ch.400m-810m under 15 No Kasalia UP of Muksudpur Upazila, Dist: Gopalganj. ID : 33558-5477 Group-2
|
0.4100
|
7.950
|
Ruhul/Ekram
|
7.950
|
18/03/2018
|
31/01/2019
|
1
|
11/10/2020
|
FB Paid
|
|
41
|
LCS/EW/17-18/Muksud/03
|
Raising/Re- shaping of Earthen road Embankment on Hazragati Bridge to North Border road at ch.0m-400m under 15 No Kasalia UP of Muksudpur Upazila, Dist: Gopalganj. ID : 33558-5477 Group-1
|
0.4000
|
7.206
|
Josna/Rexona
|
7.206
|
18/03/2018
|
31/01/2019
|
1
|
11/10/2020
|
FB Paid
|
|
42
|
LCS/EW/17-18/Muksud/02
|
Raising/Re-Shaping of Earthen Road Embankment on Vattacharjo Khalasi Bari to Nur Mohammad House Road at Ch.0.00m-365m Under 12 No Gohala Union of Muksudpur, Dist: Gopalganj.
|
0.3650
|
5.896
|
Khadiza/Shoba
|
5.896
|
22/01/2018
|
21/05/2018
|
0
|
11/10/2020
|
Cont. Finalize due to land problem and bill paid as per work done
|
|
43
|
LCS/EW/17-18/Muksud/01
|
Raising/Re-Shaping of Earthen Road Embankment on Alipur GPS to Kohaldia Abdul Khalek House Road at Ch.0m-535m Under 09 No. Batikamari Union of Muksudpur Upazila, Dist: Gopalganj.
|
0.5350
|
4.703
|
Doli/Uzzala
|
4.703
|
10/03/2018
|
17/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
44
|
LCS/EW/16-17/Muksud/04
|
Improvement of road by earth work on Pulin Pal House-Janbag Mukter Sekh House road at ch. 940m-1265m under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj. Group-2
|
0.3250
|
8.310
|
Ratna/ Monika
|
8.310
|
12/04/2017
|
31/08/2018
|
1
|
11/10/2020
|
FB Paid
|
|
45
|
LCS/EW/16-17/Muksud/03
|
Improvement of road by earth work on Pulin Pal House-Janbag Mukter Sekh House road at ch. 0.0m-940m under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj. Group-1
|
0.9400
|
10.178
|
Rozina/ Saheda
|
10.178
|
12/04/2017
|
31/08/2018
|
1
|
11/10/2020
|
FB Paid
|
|
46
|
LCS/EW/16-17/Muksud/02
|
Improvement of road by earth work on Korikhan Paccim Para Mnsur Sekh House–Purbo Korikhan Sanowara House road at ch. 400m-905m under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj. Group-2
|
0.5040
|
7.570
|
Masura/Kulsum
|
7.570
|
05/02/2018
|
05/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
47
|
LCS/EW/16-17/Muksud/01
|
Improvement of road by earth work on Korikhan Paccim Para Mnsur Sekh House–Purbo Korikhan Sanowara House road at ch. 0.0m-400m under Pasargati UP of Muksudpur Upazila, Dist: Gopalganj. Group-1
|
0.4000
|
8.012
|
Alomgir /Shahin
|
8.012
|
05/02/2018
|
05/06/2018
|
1
|
11/10/2020
|
FB Paid
|
|
48
|
LCS/Khal/17-18/MUK-31
|
Re-excavation of Khal on Krisnadia Dhirandro Nath Bahar Bari to Kumer Nadi via Muktizoddha Abdul Samad Bari Khal at ch. 0-125m under Pashergati UP of Muksudpur Upazila, Gopalganj.
|
0.1250
|
1.438
|
|
1.438
|
|
|
0
|
19/01/2019
|
|
|
49
|
LCS/Ghat/17-18/MUK-30
|
Construction of Boat Landing Station at Dhranda Khal adjacent to Dhranda GPS & Dhranda Bazar under Khanderpara UP, Muksudpur Upazila, Gopalganj.
|
|
22.740
|
|
22.740
|
|
|
0
|
19/01/2019
|
|
|
50
|
LCS/MD/17-18/MUK-29
|
Development Bolonarayaon Market (MSP, FS, OSP, Tube-well, & Internal CC road) Under 05 No Bahugram Union, Muksudpur, Gopalganj. Salvage- 217,517.00
|
|
22.537
|
Alo/Rani
|
22.537
|
|
|
0
|
19/01/2019
|
|
|
51
|
LCS/MD/17-18/MUK-28
|
Development Gohala Market Development work (Internal CC Road, Guide wall & Twin Toilet) Under Gohala Union, Muksudpur, Gopalganj. Salvage- 211,423.00
|
1.0000
|
24.336
|
Shelina/Papiya
|
24.336
|
22/01/2018
|
21/05/2018
|
100
|
19/01/2019
|
|
|
52
|
LCS/MD/17-18/MUK-27
|
Development Janbag Market Development work (1no Twin Toilet & 1 no Tube-well) Under 02 No Pashergati Union, Muksudpur, Gopalganj.
|
1.0000
|
6.445
|
|
6.445
|
|
|
0
|
19/01/2019
|
|
|
53
|
LCS/MD/17-18/MUK-26
|
Development Haldivita Market work (Internal CC Road ) Under 09 No Batikamari Union, Muksudpur, Gopalganj.
|
1.0000
|
8.571
|
Farida/Tulu
|
8.571
|
|
|
0
|
19/01/2019
|
|
|
54
|
LCS/SP/17-18/MUK-25
|
Construction of Slope Protection work atat ch. 77-117m(LS), 121-139m(LS), 481-502m((RS), 560-579m(RS) on Moharajpur(UZR) to Uzani(UZR) via Bhabrasure UP Offcie Road at Ch.0 - 1000m Under 08 No Moharajpur Union, Muksudpur Upazila, Gopalganj.
|
0.0980
|
4.718
|
|
4.718
|
|
|
0
|
19/01/2019
|
|
|
55
|
LCS/SP/17-18/MUK-24
|
Construction of Slope Protection work ate Road at Ch.382m-402m(B/S) on Faruk Khal High School connecting road at Ch. 0.00m – 405.00m under Gobindopur Union, Muksudpur Upazila, Gopalganj.
|
0.0400
|
1.844
|
Salina/shahana
|
1.844
|
|
|
0
|
19/01/2019
|
|
|
56
|
LCS/SP/17-18/MUK-23
|
Construction of Slope Protection work ate Road at Ch.355m-370m(Both Side), & 385m-400m(RS) Under 15 No Kasalia UP,Muksudpur Upazila,Gopalganj.
|
0.0450
|
2.057
|
|
2.057
|
|
|
0
|
19/01/2019
|
|
|
57
|
LCS/SP/17-18/MUK-22
|
Construction of Slope Protection work at Ch.560m-630m (R/S) on Improvement of Road by HBB on Bahara Alim Madrasha to Mirez Member House Road at Ch.0.00m -1000m Under09 No Batikamari Union,Muksudpur,Gopalganj.
|
0.0700
|
3.307
|
|
3.307
|
|
|
0
|
19/01/2019
|
|
|
58
|
LCS/DS/17-18/MUK-21
|
Construction of outlet drain from Krisnadia Dhirandro Nath Bahar Bari to Kumer Nadi under Pashergati UP, Muksudpur Upazila, Gopalganj.
|
|
3.829
|
|
3.829
|
|
|
0
|
19/01/2019
|
|
|
59
|
LCS/DS/17-18/MUK-20
|
Construction of 1 No. U-Drain (0.900mx0.90m) on Millik Sreeampur BC Road Har Bhanga R&H Road at Ch.0m-825m Under Moharajpur Union, Muksudpur,Gopalganj.
|
|
1.711
|
Salina/Ambia
|
1.711
|
18/02/2018
|
|
100
|
19/01/2019
|
|
|
60
|
LCS/DS/17-18/MUK-19
|
Construction of 2 No. U-Drain (0.900mx0.90m) on Bahara Alim Madrasha to Mierj Member House road at ch. 1200m &1400m Under 09 No Batikamari UP of Muksudpur Upazila,Gopalganj.
|
|
3.430
|
|
3.430
|
|
|
0
|
19/01/2019
|
|
|
61
|
LCS/DS/17-18/MUK-18
|
Construction of 2 No. U-Drain (0.900mx0.90m) on Hazaragati Bridge to North Border road at ch. 220m &525m Under 15 No Kasalia UP of Muksudpur Upazila,Gopalganj.
|
|
3.455
|
|
3.455
|
|
|
0
|
19/01/2019
|
|
|
62
|
LCS/DS/17-18/MUK-17
|
Construction of 1 No. U-Drain (0.900mx0.90m) Single Vent at Ch.940m on Pulinpal House –Janbag Mukter Sheikh House Road Under 02 No Pashargati Union,Muksudpur,Gopalganj.
|
|
1.786
|
|
1.786
|
|
|
0
|
19/01/2019
|
|
|
63
|
LCS/DS/17-18/MUK-16
|
Construction of 2 nos. U-Drain (0.900mmx0.900mm) Single Vent at Ch.100m & 350m on Earthen Road Embankment on Vattacharjo Khalasi Bari to Nur Mohammad House Road at Ch.0.00m-365m Under 12 No Gohala Union,Muksudpur,Gopalganj
|
|
3.368
|
Tuli/Laki
|
3.368
|
21/01/2018
|
21/02/2018
|
100
|
19/01/2019
|
|
|
64
|
LCS/CC/17-18/MUK-15
|
Improvement of Road by CC Block on Faruk Khal High School connecting road at Ch. 0.00m – 405.00m under Gobindopur Union, Muksudpur Upazila, Gopalganj.
|
0.4050
|
18.974
|
Salina/shahana
|
18.974
|
|
|
0
|
19/01/2019
|
|
|
65
|
LCS/CC/17-18/MUK-14
|
Improvement of Road by CC Block on 173 No. Chowgacca GPS connecting road at Ch. 0.00m – 84.00m under 08 Moharajpur Union, Muksudpur Upazila, Gopalganj.
|
0.0840
|
4.198
|
Salina/Ambia
|
4.198
|
18/02/2018
|
17/06/2018
|
100
|
19/01/2019
|
|
|
66
|
LCS/CC/17-18/MUK-13
|
Improvement of Road by CC Block on 114 No. Monirkandi GPS connecting road at Ch. 0.00m – 103.00m under 12 No Gohala Union, Muksudpur Upazila, Gopalganj.
|
0.1030
|
5.121
|
Salina/Ambia
|
5.121
|
|
|
0
|
19/01/2019
|
|
|
67
|
LCS/BC/17-18/MUK-12
|
Improvement of Road by CC Block on Tarail GPS connecting road at Ch. 0.00m – 73.00m under 05 No Bahugram Union, Muksudpur Upazila, Gopalganj.
|
0.0730
|
3.643
|
|
3.643
|
|
|
0
|
19/01/2019
|
|
|
68
|
LCS/BC/17-18/MUK-11
|
Imprivement of road by BC on Moharajpur(UZR) to Uzani(UZR) via Bhabrasure UP Offcie Road at Ch.0 - 1000m Under 08 No Moharajpur Union, Muksudpur Upazila, Gopalganj. Salvage- 23,46,915.00
|
1.0000
|
60.222
|
|
60.222
|
|
|
0
|
19/01/2019
|
|
|
69
|
LCS/HBB/17-18/MUK-10
|
Improvement of Road by HBB on Pasargati UP Office to Janbag Nutun Bazar (Prem Bazar) via Bahirbag Road (Approach work) at Ch.500.00m -560m Under 02 No Pashargati Union,Muksudpur,Gopalganj. Salvage- 6,231.00
|
0.0600
|
2.269
|
|
2.269
|
|
|
0
|
19/01/2019
|
|
|
70
|
LCS/HBB/17-18/MUK-09
|
Improvement of Road by HBB on Bahara Alim Madrasha to Mirez Member House Road at Ch.0.00m -1000m Under Batikamari Union,Muksudpur,Gopalganj. Salvage- 52,372.00
|
1.0000
|
31.324
|
Sabina/Anowara
|
31.324
|
14/02/2018
|
15/06/2018
|
30
|
19/01/2019
|
|
|
71
|
LCS/EW/17-18/MUK-08
|
G2: 750-1550m
|
0.8000
|
25.819
|
Afifa/Panna
|
25.819
|
01/02/2018
|
31/05/2018
|
75
|
19/01/2019
|
|
|
72
|
LCS/EW/17-18/MUK-07
|
G1: 0-750m
|
0.7500
|
24.182
|
Jharna/Lakkhi
|
24.182
|
01/02/2018
|
31/05/2018
|
80
|
19/01/2019
|
|
|
73
|
|
Improvement of Road by HBB on Maddha Bangram Khanka House via Kundopara Road, Ch. 0.00m – 1550.00m under Moharajpur UP, Muksudpur Upazila, Gopalganj.
|
|
0.000
|
|
0.000
|
|
|
0
|
19/01/2019
|
|
|
74
|
LCS/EW/17-18/MUK-06
|
Raising/Re-Shaping Earthen Road Embankment on Millik Sreeampur BC Road Har Bhanga R&H Road at Ch.0m-825m Under Moharajpur Union, Muksudpur,Gopalganj.
|
0.8250
|
6.900
|
Shikha/Renu
|
6.900
|
18/02/2018
|
27/06/2018
|
100
|
19/01/2019
|
|
|
75
|
LCS/EW/17-18/MUK-05
|
Raising/Re-Shaping Earthen Road Embankment on Bahara Alim Madrasha to Mirej Member House road at Ch.1000m-1597m Under 09 No Batikamari Union, Muksudpur,Gopalganj.
|
0.5970
|
4.834
|
Sonia/Kajol
|
4.834
|
14/02/2018
|
15/06/2018
|
100
|
19/01/2019
|
|
|
76
|
LCS/EW/17-18/MUK-04
|
G2: 400-810m
|
0.8100
|
7.950
|
Ruhul/Ekram
|
7.950
|
18/03/2018
|
31/01/2019
|
100
|
19/01/2019
|
|
|
77
|
LCS/EW/17-18/MUK-03
|
G1: 0-400m
|
0.8100
|
7.206
|
Josna/Rexona
|
7.206
|
18/03/2018
|
31/01/2019
|
100
|
19/01/2019
|
|
|
78
|
LCS/EW/17-18/MUK-02
|
Detail estimate for Raising/Re-Shaping Earthen Road Embankment on Vattacharjo Khalasi Bari to Nur Mohammad House Road at Ch.0.00m-365m Under 12 No Gohala Union,Muksudpur,Gopalganj
|
0.3650
|
5.896
|
khadiza/shova
|
5.896
|
22/01/2018
|
21/05/2018
|
100
|
19/01/2019
|
|
|
79
|
LCS/EW/17-18/MUK-01
|
Detail estimate for Raising/Re-Shaping Earthen Road Embankment on Alipur GPS to Kohaldia Abdul Khalek House Road at Ch.0.00m-535m Under 09 No Batikamari Union, Muksudpur,Gopalganj.
|
0.5350
|
4.703
|
doly./uzzola
|
4.703
|
10/03/2018
|
17/06/2018
|
75
|
19/01/2019
|
17-18
|
|
|
5
|
Tungipara
|
|
1
|
LCS/TP/20-21/Tungi-01
|
Tree Plantation & One year Caretaking of Kushli Hat GC to Dharabashail GC road via Mittradanga Sonakhali Road from ch. 7800m-11800m under Tungipara Upazila, Dist: Gopalgonj.
|
4.0000
|
9.952
|
|
9.952
|
|
|
0
|
11/10/2020
|
|
|
2
|
LCS/Maint./17-18/Tungi-01
|
Detail estimate for Maintenance of BC road on Patgati Maddhapara H/O Nader Mollah –Patgati Bottala (UZR) road via H/O Helaluddin Maulana (Shahrpara) Ch: 0.0m to 678m under Patgati UP of Tungipara Upazila, Dist: Gopalganj.
|
0.6780
|
18.500
|
Aroti/Jesmin
|
18.500
|
29/03/2018
|
30/12/2018
|
0
|
11/10/2020
|
It will start soon
|
|
3
|
LCS/Marktet/16-17/Tungi-Maint.-01
|
Development of Gopalpur Market (Construction of 1 No Muli Purpose shed, 1 No Fish shed, Open shed Platform & Internal road) under Gopalpur UP of Tungipara Upazila, Dist: Gopalganj.
|
|
16.195
|
Suniti/Archona
|
16.195
|
09/05/2017
|
15/01/2018
|
1
|
11/10/2020
|
FB Paid
|
|
4
|
LCS/Ghat/17-18/Tungi-01
|
Construction of 1 no Boat Landing Station at Borni Baor adjacent to Kushli Hat under Kushli UP of Tungipara Upzila, Dist: Gopalgonj.
|
|
19.825
|
Shahanara /Arju
|
19.825
|
29/03/2018
|
31/12/2018
|
0
|
11/10/2020
|
Not start due to higher rate of mat
|
|
5
|
LCS/SP/17-18/Tungi-02
|
Slope protection work on Singipara Bazar Krishi Biponi- Sreramkandi More via Hamid Sk road Kheyaghat- H/O Hamid Sk road, ch. 172m-188m(RS), 188m-202m (LS) 551-570m (LS) & 616m-629m (LS) under Kushli UP of Tungipara Upazila, Dist: Gopalganj.ID : 33591-4
|
|
2.986
|
Abejan/Banu
|
2.986
|
12/02/2018
|
30/06/2018
|
0
|
11/10/2020
|
Not start due to higher rate
|
|
6
|
LCS/SP/17-18/Tungi-01
|
Slope protection work on South Bashuria H/O Aiub Mia attached jame mosque to Uttar Para Jame mosque road at ch.690m-695m (RS) under Kushli UP of Tungipara Upazila, Dist: Gopalganj.ID : 33591-4104
|
|
0.274
|
Abejan/Banu
|
0.274
|
12/02/2018
|
30/06/2018
|
0
|
11/10/2020
|
Not start due to higher rate
|
|
7
|
LCS/DS/17-18/Tungi-01
|
Construction of 1 No. U-drain (0.900m×0.900m) on South Bashuria H/O Aiub Mia attached jame mosque to Uttar Para Jame mosque road at ch.420m under Kushli UP of Tungipara Upazila, Dist: Gopalganj.
|
|
1.922
|
Abejan/Banu
|
1.922
|
12/02/2018
|
30/06/2018
|
1
|
11/10/2020
|
Work complete
|
|
8
|
LCS/DS/16-17/Tungi-01
|
Construction of 2nos. U-drains (0.900m´ 0.900m) on Krishi Biponon (Asad Sheikh House) to Bridge road via Basuria Jame Mosque road at ch. 250m & 1070m under Kushli UP of Tungipara Upazila, Dist: Gopalganj.
|
|
2.935
|
Banu/Jamila
|
2.935
|
16/05/2017
|
13/12/2017
|
1
|
11/10/2020
|
FB Paid
|
|
9
|
LCS/BC/17-18/Tungi/BC-03
|
Improvement of road by BC on Singipara Bazar Krishi Biponi- Sreramkandi More via Hamid Sk road Kheyaghat- H/O Hamid Sk road, ch. 0m-1001m under Kushli UP of Tungipara Upazila, Dist: Gopalganj.
|
1.0010
|
33.745
|
Shamoly/Shoba
|
33.745
|
06/03/2018
|
06/12/2018
|
0
|
11/10/2020
|
On going
|
|
10
|
LCS/BC/17-18/Tungi-02
|
Improvement of road by BC on South Bashuria H/O Aiub Mia attached jame mosque to Uttar Para Jame mosque road, ch. 480m-930m under Kushli UP of Tungipara Upazila, Dist: Gopalganj. Group-2
|
0.4500
|
25.497
|
Monj/Archona
|
25.497
|
18/02/2018
|
30/06/2018
|
0
|
11/10/2020
|
On going
|
|
11
|
LCS/BC/17-18/Tungi-01
|
Improvement of road by BC on South Bashuria H/O Aiub Mia attached jame mosque to Uttar Para Jame mosque road, ch. 0m-480m under Kushli UP of Tungipara Upazila, Dist: Gopalganj. Group-1
|
0.4800
|
31.805
|
Maloti/Suniti
|
31.805
|
18/02/2018
|
30/06/2018
|
0
|
11/10/2020
|
On going
|
|
12
|
LCS/HBB/17-18/Tungi-H-02
|
Improvement of road by HBB on Nilfa Liakot Khan House to (4006) BC road near the H/O Babu Mollah at ch.0m-422m under Kulshli UP of Tungipara Upazila, Dist: Gopalganj.
|
0.4220
|
17.341
|
Hasiara/Jarina
|
17.341
|
02/01/2018
|
01/05/2018
|
1
|
11/10/2020
|
FB Paid
|
|
13
|
LCS/HBB/17-18/Tungi-H-01
|
Improvement of road by HBB on Nilfa (5011) BC road near the H/O Rashid Fakir to (4006) BC road near the H/O Kobed Shikder at ch.0m-533m under Kulshli UP of Tungipara Upazila, Dist: Gopalganj.
|
0.5330
|
19.396
|
Moni/Miniya
|
19.396
|
02/01/2018
|
15/06/2018
|
0
|
11/10/2020
|
FB Paid as work done
|
|
14
|
LCS/EW/16-17/Tungi-E-02
|
Improvement of road by earth work on Krishi Biponon (Asad Sheikh House) to Bridge road via Basuria Jame Mosque road at ch. 810m-1205 under Kushli UP of Tungipara Upazila, Dist: Gopalganj. Group-2
|
0.3950
|
9.837
|
Halima/Sukura
|
9.837
|
16/04/2017
|
28/02/2018
|
1
|
11/10/2020
|
FB Paid
|
|
15
|
LCS/EW/16-17/Tungi-E-01
|
Improvement of road by earth work on Krishi Biponon (Asad Sheikh House) to Bridge road via Basuria Jame Mosque road at ch. 0.0m-810m under Kushli UP of Tungipara Upazila, Dist: Gopalganj. Group-1
|
0.8100
|
9.931
|
Pinzina/Anju
|
9.931
|
16/04/2017
|
28/02/2018
|
1
|
11/10/2020
|
FB Paid
|
|
16
|
LCS/Rd.Main/17-18/TUNGI-18
|
Detail estimate for Maintenance of BC road on Patgati Maddhapara H/O Nader Mollah -Patgati Bottala UZR road via H/O Helaluddin Maulana (Shahrpara) ch. 0-678m under Patgati UP, Tungipara Upazila, Gopalganj. Salvage- 61,842 Tk.
|
0.6780
|
18.500
|
Aroti/Jesmin
|
18.500
|
29/03/2018
|
30/12/2018
|
0
|
19/01/2019
|
|
|
17
|
LCS/Ghat/17-18/TUNGI-17
|
Construction of Boat Landing Station at Borni Baor adjacent to Kushli Hat under Kushli UP, Tungipara Upazila, Gopalganj.
|
|
19.825
|
Shahanara/Arju
|
19.825
|
29/03/2018
|
31/12/2018
|
0
|
19/01/2019
|
|
|
18
|
LCS/Ghat/17-18/TUNGI-16
|
Construction of Boat Landing Station at Modhumoti River adjacent to Khalek Bazar under Kushli UP, Tungipara Upazila, Gopalganj.
|
|
19.825
|
Aduri/Minia
|
19.825
|
29/03/2018
|
31/12/2018
|
0
|
19/01/2019
|
|
|
19
|
LCS/Ghat/17-18/TUNGI-15
|
Construction of Boat Landing Station at Shaldha River adjacent to 32 no. Char Gopalpur GPS & Cyclone Shelter under Dumuria UP, Tungipara Upazila, Gopalganj.
|
|
19.825
|
|
19.825
|
|
|
0
|
19/01/2019
|
|
|
20
|
LCS/SP/17-18/TUNGI-14
|
Slope protection work at different chainages on Singipara R&H to Patgati GC Road at Ch. 1700 – 7400m Under under Kushli & Patgati UP, Tungipara Upazila, Gopalganj.
|
0.6600
|
31.065
|
|
31.065
|
|
|
0
|
19/01/2019
|
|
|
21
|
LCS/SP/17-18/TUNGI-13
|
Slope protection work on Singipara Bazar Krishi Biponi- Sreramkandi More via Hamid SK road, ch. 0m-1001m under Kushli UP of Tungipara Upazila, Dist: Gopalganj.
|
0.0620
|
2.986
|
Abejan/Vanu
|
2.986
|
12/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
22
|
LCS/SP/17-18/TUNGI-12
|
Slope protection work on South Bashuria H/O Aiub Mia attached jame mosque to Uttar Para Jame mosque road at ch. 690m-695m (RS) under Kushli UP of Tungipara Upazila, Dist: Gopalganj.
|
0.0050
|
0.274
|
Abejan/Vanu
|
0.274
|
12/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
23
|
LCS/DS/17-18/TUNGI-11
|
Construction of 1 No U-drain (0.900m×0.900m) on South Bashuria H/O Aiub Mia attached jame mosque to Uttar Para Jame mosque road at ch. 420m under Kushli UP of Tungipara Upazila, Dist: Gopalganj.
|
|
1.922
|
Abejan/Vanu
|
1.922
|
12/02/2018
|
30/06/2018
|
0
|
19/01/2019
|
|
|
24
|
LCS/DS/17-18/TUNGI-10
|
Construction of 2 No U-drain (0.900m×0.900m) on H/O Ex-chairman Akbar Munshi House to Plo Bridge road at ch. 270m & 770m under Barni UP of Tungipara Upazila, Dist: Gopalganj.
|
|
3.946
|
|
3.946
|
|
|
0
|
19/01/2019
|
|
|
25
|
LCS/BC/17-18/TUNGI-09
|
Imprivement of road by BC on Singipara Bazar Krishi Biponi- Sreramkandi More via Hamid SK road ch. 0m-1001m under Kusli UP of Tungipara Upazila, Dist: Gopalganj. Salvage- 103,806.00
|
1.0010
|
33.745
|
shaymoli/sova
|
33.745
|
06/03/2018
|
06/12/2018
|
12
|
19/01/2019
|
|
|
26
|
LCS/BC/17-18/TUNGI-08
|
G2: 480-930
|
0.4500
|
25.497
|
Monju/Orchana
|
25.497
|
18/02/2018
|
30/06/2018
|
15
|
19/01/2019
|
|
|
27
|
LCS/BC/17-18/TUNGI-07
|
G1: 0-480m
|
0.4800
|
31.805
|
Moloti/Suniti
|
31.805
|
18/02/2018
|
30/06/2018
|
15
|
19/01/2019
|
|
|
28
|
|
Imprivement of road by BC on South Bashuria H/O Aiub Mia attached jame mosque road, ch. 0 to 930m under Kusli UP of Tungipara Upazila, Dist: Gopalganj.
|
|
0.000
|
|
0.000
|
|
|
0
|
19/01/2019
|
|
|
29
|
LCS/HBB/17-18/TUNGI-06
|
Improvement of Road by HBB on Borni Mittircabati R&H to Baladanga R&H via House of Faikh Miah, Ch. 4360-5200m under Patgati UP, Tungipara Upazila, Gopalganj.
|
0.8400
|
37.552
|
|
37.552
|
|
|
0
|
19/01/2019
|
|
|
30
|
LCS/HBB/17-18/TUNGI-05
|
Improvement of Road by HBB on Pakurtia Bazar (VR-A-4016) near Jahider Mill to Kata Khal via Kalam Sk. House, Ch. 0-400m under Dumuria UP, Tungipara Upazila, Gopalganj
|
0.4000
|
15.611
|
|
15.611
|
|
|
0
|
19/01/2019
|
|
|
31
|
LCS/HBB/17-18/TUNGI-04
|
Improvement of Road by HBB on Nilfa Liakot Khan House to (4006) BC road near house of Babu Mollah at Ch. 0 to 422m , under Kushli UP, Tungipara Upazila, Gopalganj.
|
0.4220
|
17.341
|
Hasiara/Jorina
|
17.341
|
02/01/2018
|
01/05/2018
|
60
|
19/01/2019
|
|
|
32
|
LCS/HBB/17-18/TUNGI-03
|
Improvement of Road by HBB on Nilfa(5011) BC road near the house of Rashid Fakir to (4006) BC road near the house of Kobed Shikder at Ch. 0 to 533m , under Kushli UP, Tungipara Upazila, Gopalganj. Salvage-27,594.00
|
0.5330
|
19.396
|
Moni/Miniya
|
19.396
|
02/01/2018
|
15/06/2018
|
100
|
19/01/2019
|
|
|
33
|
LCS/EW/17-18/TUNGI-02
|
Raising /Re-shaping of Earthen road Embankment on Singipara R&H to Patgati GC Road at Ch. 1700 – 7400m Under under Kushli & Patgati UP, Tungipara Upazila, Gopalganj
|
5.7000
|
47.765
|
|
47.765
|
|
|
0
|
19/01/2019
|
|
|
|
Total :
|
157.9700 (Km)
|
3121.66 (Lac)
|
3121.66 (Lac)
|
|
|
|
|
|
|
|