Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Gopalganj-s
1 IPCP/GOPAL/SADAR/P/18-19/1.01 Improvement of Khalia school pond Improvement of Madhupur asrayon pond Improvement of Madhupur gucchogram pond Improvement of Ohab school pond Improvement of Thutamandra girls school pond 8.3500 85.590 M/S Showrove Traders 85.590 15/01/2019 10/06/2019 0 17/02/2019 Improvement of Madhupur asrayon pond - 10% Progress Improvement of Ohab school pond - 20% Progress
2 Kotwalipara
1 IPCP/GOPAL/KOTA/P/18-19/3.01 Improvement of Harinahati school pond 0.3800 12.920 M/S Showrove Traders 12.920 22/01/2019 10/06/2019 5 17/02/2019  
Total : 8.7300 (Km) 98.51 (Lac) 98.51 (Lac)