Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Kalkini
1 SP35252 Uttarkandi-Mathabhanga Sub-project:Re-excavation of Dakkhin kandi Khal (Ch.0+000km to Ch.3+100km), Re-excavation of Dakkhin kandi Br. Khal-1(Ch.0+000km-Ch.0+593km), Re-excavation of Dakkhin kandi Br. Khal-2(Ch.0+000km-Ch.0+950km),Re-excavation of Chai c 9.9800 143.300 LCS 143.300 30/04/2020 100 21/08/2020 On going
2 SP34112 Alipur-Enayetnagar Sub-project:Re-excavation of Uttor -Majher kandi Khal (Ch.0+000km to Ch.2+729km), Re-excavation of Junior Madrasa Khal(Ch.0+000km-Ch.0+765km), Re-excavation of kata khali Khal (Ch.0+000km-Ch.0+680km),Re-excavation of Model School Khal 14.5000 221.480 LCS 221.480 30/04/2020 100 21/08/2020 On going
3 SP35240 Palordi-Alinagar Sub-project:Re-excavation of Jhorerpar Khal 4.50 km (Ch.3+900km-Ch.8+400km), Re-excavation of Kasimpur Khal 0.70km (Ch.0+000km-Ch.0+700km,Re-excavation of Lamchori Khal 0.63 km(Ch.0+000km-Ch.0+630km),Re-excavation of Minajdi Khal 1.80 km( 14.9700 136.310 LCS 136.310 30/04/2019 100 21/08/2020 Completed.
4 SP35238 Auliar Char Sub-project : Re-excavation of Gazaria Khal(Ch.0+000km to Ch.8+670km),Re-excavation of Gazaria kechur Khal (Ch.0+000km to Ch.0+850km), Re-excavation of Shibpur Khal (Ch.0+000km-Ch.4+800km), Re-excavation of Dhakar Hati Shaks Khal (Ch.0+000km- 15.7000 232.730 LCS 232.730 30/04/2019 100 21/08/2020 On going
5 SP34114 Char-Laksmipur Sub-project : Re-excavation of Khan Bari 1.10 km Khal(Ch.0+000km to Ch.1+000km),Re-excavation of Hindu Para 1.50 km Khal (Ch.0+000km to Ch.1+500km) and Re-excavation of Ray Sardar Bari 1.10 km Khal (Ch.2+000km-Ch.3+100km) 3.7000 68.040 LCS 68.040 30/04/2019 100 21/08/2020 Completed.
Total : 58.8500 (Km) 801.86 (Lac) 801.86 (Lac)