Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Lauhajong
1 IRIDP-2/MUN/DW-8 a) Improvement of Kalma-Hasail via Das para Road from ch. 00-1205m.b) Construction of 01 no 1x4.00mx4.00m culvert at ch.1025m on the same road. 1.2050 77.420 M/S N. Jahan Enterprise 77.420 25/04/2016 31/12/2017 100 23/12/2018  
2 IRIDP-2/MUN/DW-7 Improvement of Gholtoli-Apor Road via Boro Mokam Road from ch. 400-1700m. 1.3000 81.910 M/S Chamak Enterprise 81.910 25/04/2016 30/03/2018 100 23/12/2018  
3 IRIDP-2/MUN/DW-6 Improvement of Suripara Choudhuri House - Atigaon Kurigaon via poshimpara Road from ch. 00-800m. 0.8000 54.390 M/S Dolon Enterprise 54.390 23/03/2016 23/12/2016 100 23/12/2018  
4 IRIDP-2/MUN/DW-5 Improvement of Nagerhatbazar Child Clinic-Noyanakandi Nayabari Road from ch.00-725m. 0.7250 53.260 M/S Tania Construction 53.260 10/04/2016 10/01/2017 100 23/12/2018  
2 Munshiganj-s
1 IRIDP-2/MUN/DW-15 Constraction of RCC Pucca Ghat near Uttar Bagershar Shikder bari Mosque. 4.000 M/S Metali Corporation 4.000 27/03/2016 30/05/2017 100 23/12/2018  
2 IRIDP-2/MUN/DW-14 Constraction of RCC Pucca Ghat near Mosque attached of Mohakhali Union High Schoo. 4.000 M/S. Samrat Traders 4.000 30/03/2016 30/05/2017 100 23/12/2018  
3 IRIDP-2/MUN/DW-13 Constraction of RCC Pucca Ghat under Rajarchar Bridge. 4.000 M/S Khan Enterprise 4.000 30/03/2016 10/05/2017 100 23/12/2018  
4 IRIDP-2/MUN/DW-12 Constraction of RCC Pucca Ghat in front of river on Uttar Charmusura School. 4.000 M/S Metali Corporation 4.000 08/08/2016 30/04/2017 100 23/12/2018  
5 IRIDP-2/MUN/DW-11 Constraction of RCC Pucca Ghat near NadirGhat end of Dhalikandi Road. 4.000 M/S Metali Corporation 4.000 27/03/2016 30/04/2017 100 23/12/2018  
6 IRIDP-2/MUN/DW-10 Constraction of RCC Pucca Ghat near Nalbunia khal. 4.000 M/S Metali Corporation 4.000 07/04/2016 30/05/2018 100 23/12/2018  
7 IRIDP-2/MUN/DW-9 Constraction of RCC Pucca Ghat near H/O Kalu member over khal. 4.000 M/S Khan Enterprise 4.000 30/03/2016 29/01/2017 100 23/12/2018  
3 Tongibari
1 IRIDP-2/MUN/SDW-4 Improvement of Betka UZR (Khilpara)-Paikpara (R&H)Via Box Pool Road from Ch. 00-796m & Link road 250m. 0.7960 87.690   87.690 0 23/12/2018  
2 IRIDP-2/MUN/DW-3 a) Improvement of Durabati (R&H) -Arial Bazar Road from ch. 1000-2000m. b) Construction of 01 no 1x4.50mx4.50m culvert at ch.1235m on the same road. 1.0000 56.770 M/S. Bhai Bhai Construction 56.770 26/04/2016 30/01/2017 100 23/12/2018  
3 IRIDP-2/MUN/DW-2 Improvement of Aldi Still Bridge’s South side-West Aldi Govt. Pry.School–Semulia Govt.Pry. School Road from ch.00-1100m. 1.1000 48.590 M/S. Bhai Bhai Construction 48.590 06/10/2016 05/04/2018 100 23/12/2018  
4 IRIDP-2/MUN/DW-1 Improvement of Nayagaon Julhash-Chairman bari Road from ch.00-865m 0.8650 68.030 M/S Chamak Enterprise 68.030 02/04/2016 20/04/2018 100 23/12/2018  
Total : 7.7910 (Km) 556.06 (Lac) 556.06 (Lac)