Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Borhanuddin
1 PD CLBUURP, W-281 Const. of RCC Bridge on Khayer hat-Joyer hat-Borhanuddin-Ranijong Banglabazar road at Ch. 9300m. 281.010 Md Rasal Islam 281.010 04/02/2013 04/01/2015 100 12/03/2019
2 Charfassion
1 PD CLBUURP, W-282A b) Remaining Work for Const. of PC Bridge over Sultaner Kheaghat on Dularhat road at Ch. 7300m over Maya river. 413.150 Nabarun Traders 413.150 30/06/2019 100 25/01/2021
2 PD CLBUURP, W-282 a) Const. of RCC Bridge over Sultaner Kheaghat on Dularhat Shasibhushan Anjurhat, Anjurhat road at Ch. 17650m. 3265.640 Nabarun Trader 3265.640 19/11/2013 22/08/2017 100 08/07/2019
3 Lalmohan
1 LBC/Bhola/03/Remaining Remaining work of Const. of PC Girder Bridge on Nazirpur-West Char Umed via Farajgonj Up road at Ch. 3800m 377.230 Nabarun Traders & HM Cor (JV) 377.230 21/06/2020 5 23/02/2021
2 PD CLBUURP, W-283 Const. of PC Girder Bridge on Nazirpur-West Char Umed via Farajgonj Up road at Ch. 3800m. 1243.900 Nabarun Trader 1243.900 19/11/2013 15/06/2018 100 25/08/2020
Total : 0.0000 (Km) 5580.93 (Lac) 5580.93 (Lac)