SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Monirampur
1 JMP/2022-23/DW-02 Improvement of Joka Mathpara Jamtola more-Sholokhada via Joka Sholokhada road (Ch. 00-2585m) by BC (Remaining Part). 2.5800 238.190 Mozahar Entp. 238.190 26/10/2023 23/04/2024 100 19/02/2024 Final
2 JMP/2022-23/DW-01 Improvement of Durbadanga Bazar - Gorvanga Bazar Road (Ch.00-1480m) by BC (Remaining Part). 1.4800 135.530 Mozahar Entp. 135.530 26/10/2023 23/04/2024 100 19/02/2024 Final
3 JMP/2022-23/DW-22 Improvement of Basudebpur Pottimore-Panchonathtala via Haradhon Chakrobati house Road (Ch.00-532m) by BC. Improvement of Galdah Maniktala-Galdah Bazar Rd (Ch.510-1395m) by BC. 1.4100 139.480 Mozahar Entp. 139.480 26/10/2023 23/04/2024 100 19/02/2024 Final
4 JMP/2022-23/DW-20 Improvement of Mahamudkati Biswasbari more - Majiali Bazar via Jogipol Road (Ch.00-2375m) by BC. 2.3750 221.920 Banantar Trading Ltd. 221.920 23/05/2023 20/09/2023 100 19/02/2024 Final
5 JMP/2022-23/DW-19 Improvement of Khathaltala more-Nowali Dhakil Madrasha Rd (Ch.00-2000m) by BC 2.0000 191.320 M/S Biswajit const. 191.320 23/05/2023 20/09/2023 100 19/02/2024 Final
6 JMP/2022-23/DW-18 Improvement of Mothurapur Mollahpara - Mothurapur end road (Ch.00-1475m) by BC Improvement of Panichatra Rice mill-giba Pry.School Rd (Ch.00-940m) by BC. 2.4150 250.920 Banantar Trading Ltd. 250.920 22/05/2023 20/09/2023 100 19/02/2024 Final
7 JMP/2022-23/DW-17 Improvement of Galdah Maniktala - Dighirpar Bazar Road (Ch.00-2082m) by BC Improvement of Parala Satgati Shashan - Parala RNGPS Road (Ch.00-960m) by BC. 3.0420 331.840 Banantar Trading Ltd. 331.840 22/05/2023 20/09/2023 100 19/02/2024 Final
8 JMP/2022-23/DW-16 Chakla Pry.School - H/O Moslem - H/O Billal Hujur's more road (Ch.00-1020m) by BC. 1.0200 116.560 M/S Alom Entp. 116.560 30/05/2023 28/09/2023 100 19/02/2024 Final
9 JMP/2022-23/DW-15 Improvement of Batbila - Mujgonni Road (Ch.00-2000m) by BC. 2.0000 179.680 M/S Masud Entp. 179.680 16/02/2023 17/05/2023 100 19/02/2024 Final
10 JMP/2022-23/ DW-14 Improvement of Sujatpur Pucca road - Baje Kultia End Road (Ch.00-1920m) by BC. 1.9200 199.950 M/S Biswajit Construction 199.950 21/02/2023 22/05/2023 100 19/02/2024 Final
11 JMP/2022-23/DW-13 Improvement of Amrojuta-Danga Mohisdia Rd (Ch.00-1310m) by BC. 1.3100 102.000 M/S Alom Entp. 102.000 08/03/2023 06/06/2023 100 19/02/2024 Final
12 JMP/2022-23/ DW-12 Improvement of Monohorpur Kacharibari - Kapalia Road (Ch.1000-2315m) by BC. 1.3150 117.990 M/S Alom Entp. 117.990 08/03/2023 06/06/2023 100 19/02/2024 Final
13 JMP/2022-23/DW-11 Improvement of Panchakori Kormokarpara-Gazipara-Rajbansipara road (Ch.00-1100m) By BC. 1.1000 114.440 M/S Sarder International 114.440 06/03/2023 04/06/2023 100 19/02/2024 Final
14 JMP/2022-23/DW-10 Improvement of Balianpur H/O Jako-H/O Motiar Rahman Rd (Ch.00-810m) by BC Improvement of Biprokona more - Konakola Risipara more road (Ch.00-885m) by BC 1.6950 152.480 M/S Kumkum Entp 152.480 03/06/2023 06/04/2024 100 19/02/2024 Final
15 JMP/2022-23/DW-09 Improvement of Mohisdia Dor Bari more - Alipur Pry.School Road (Ch.00-520m) by BC. Improvement of Panchakori Takerghat-Panchakori high School via Rajbonsipara Road (Ch.00-875m) by BC 1.3950 140.190 M/S Biswajit Construction 140.190 21/02/2023 22/05/2023 100 19/02/2024 Final
16 JMP/2022-23/DW-08 Improvement of Shoyli Bazar - Gangulia road (Ch.00-1866m) by BC 1.8660 185.810 M/S Sohel Construction 185.810 16/02/2023 17/05/2023 100 19/02/2024 Final
17 JMP/2022-23/DW-07 Improvement of Bahadurpur-Hogladanga Road (Ch.00-1480m) by BC. 1.4800 138.770 M/S Alom Entp. 138.770 08/03/2023 06/06/2023 100 19/02/2024 Final
18 JMP/2022-23/DW-06 Improvement of Hazirhat Khaitala-Panchkatia High school Rd (Ch.00-1450m) by BC 1.4500 144.200 M/S Biswajit Construction 144.200 03/01/2023 30/05/2023 100 19/02/2024 Final
19 JMP/2022-23/DW-05 Sundalpur bazar-Haridashkati UP via Salimpur Road (Ch.4209-6360m) by BC 2.1510 257.480 Sk. Idrish Ali 257.480 15/06/2023 13/10/2023 100 19/02/2024 Final
20 JMP/2022-23/DW-04 Gopalpur Sattar Shop-Dafaderpara Road (Ch.00-950m) by BC. Mallek Gazir's ponds -Batvila eastpara Jame Mosque Road (Ch.00-380m) by BC 1.3300 146.000 Jakaullah & Brothers 146.000 01/06/2023 29/09/2023 100 19/02/2024 Final
21 JMP/2021-22/DW-03 Gabukhali Bazar - Dhakkin Gabukhali Bridge road (Ch.00-1450m) by BC. Jhampa High School Bastutala -Southpara Community Clinic Rd (Ch.00-880m) by HBB. Champakona Dhakkinpara-Kobi Khola More Road (Ch.00-1500m) by BC. Rehabilitation of Taruapara-Rupdia (Ch.00-795m) Road by BC. Rehabilitation of Diganga Kutchlia High School(East side)-Atharopakia Road (Ch.00-2740m) by HBB. 7.3650 461.880 Kumkum Entp. 461.880 13/08/2022 12/08/2023 100 19/02/2024 Final
22 JMP/2022-23/DW-21 Improvement of Muragacha-Modonpur via Mahatabnagor Rd (Ch.2270-3800m) by BC (Remaining Part). 1.5300 140.970 Mozahar Entp. 140.970 26/10/2023 23/04/2024 100 19/02/2024
Total : 44.2290 (Km) 4107.60 (Lac) 4107.60 (Lac)