Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Alamdanga
1 IRIDP-2/CHU/DW-5 (a) Improvement of Sohagpur (Bridge) - Jamjami Balika school Road. (Ch 00-860m)(b) Construction of 02 nos 0.625mx0.60m culvert at ch.433m & 480m.. 0.8600 49.904 M/S. Prema Construction 49.904 10/12/2015 22/07/2016 100 23/12/2018  
2 IRIDP-2/CHU/DW-4 Improvement of Osmanpur-Pragpur Rd. ( Ch 00-930m) 0.9300 53.313 Md.Ahsan Habib 53.313 15/12/2015 22/07/2016 100 23/12/2018  
3 IRIDP-2/CHU/DW-3 (a) Improvement of Hatboalia Sadarpur GCCR(Gadontola more) ( Ch 00-1000m)(b) Construction of 01 no 0.625mx0.60m culvert at ch.650m 1.0000 56.542 M/S. Madani Enterprise 56.542 30/12/2015 22/07/2016 100 23/12/2018  
4 IRIDP-2/CHU/DW-2 (a)Improvement of Chitla More-Rutanpur Bazar ( Ch 00-1290m) (b) Construction of 02 nos 0.625mx0.60m culvert at ch.360m & 800m. 1.2900 75.732 Md. Golam Mostofa 75.732 17/12/2015 22/07/2016 100 23/12/2018  
5 IRIDP-2/CHU/DW-1 (a) Improvement of Gholdari G.C-Chuadanga R&H ( Ch 00-2612m)(b) Construction of 05 nos 0.625mx0.60m culvert at ch.283m,415m,610m,874m & 1577m. 2.6120 180.397 M/S. Madani Enterprise 180.397 30/12/2015 02/05/2016 100 23/12/2018  
2 Chuadanga-s
1 IRIDP-2/CHU/DW-7 (a)Improvement of Joyrampur-Chuadanga road at ch-1275-1890m)(b) Construction of 02 nos 0.625mx0.60m culvert at ch.1525m& 1890m. 0.6150 22.602 M/S. Madani Enterprise 22.602 30/12/2015 22/07/2016 100 23/12/2018  
2 IRIDP-2/CHU/DW-6 Improvement of 6 mile R & H road-Shahapur primary School via Buropara village road (ch-00-1000m) 1.0000 58.396 M/S. Prema Construction 58.396 10/12/2015 25/02/2016 100 23/12/2018  
3 Damurhuda
1 IRIDP-2/CHU/DW-14 a)Chotobaldia Thamatha - Chotobaldia School Rd ( ch 97- 638m).b) Construction of 1nos culvert 0.625x0.600m at ch 90m. 0.5410 30.388 Md. Shaharin Haque Malik 30.388 13/12/2015 10/04/2016 100 23/12/2018  
2 IRIDP-2/CHU/DW-13 a)Puraton Bastopur Awal's House - Notun Bastopur Fakir's Hpuse (Hunumandanga Chourasta more) road ( ch 07-727m).b) Construction of 2nos culvert 0.625x0.600m at ch 194m & 239m. 0.7200 40.556 Md. Shafiul Kobir 40.556 09/07/2016 22/07/2016 100 23/12/2018  
3 IRIDP-2/CHU/DW-12 Begopara Brack More B.C road-Thana road via gulshan para ( ch 00-527m). 0.5270 30.308 MD. Amzad Hossain 30.308 17/12/2015 22/07/2016 100 23/12/2018  
4 IRIDP-2/CHU/DW-11 Damurhuda pope Furnitur-U.P. office ( ch 00-408m & ch 428-562m). 0.5420 25.326 MD. Amzad Hossain 25.326 17/12/2015 22/07/2016 100 23/12/2018  
5 IRIDP-2/CHU/DW-10 a) Fakirpara R & H to school road (ch 00-772m).b) Repair of 1nos culvert 0.625x0.600m at ch 714m. 0.7720 45.400 M/S Shopno Construction 45.400 20/12/2015 22/07/2016 100 23/12/2018  
6 IRIDP-2/CHU/DW-9 Talsari R&H-Horirampur (ch 2678-3543m). 0.8650 47.286 M/S. Madani Enterprise 47.286 30/12/2015 16/07/2016 100 23/12/2018  
7 IRIDP-2/CHU/DW-8 Chandrabash FRB – Kanidanga (ch 6233-7350m). 1.1170 60.807 M/S. Madani Enterprise 60.807 30/12/2015 19/06/2016 100 23/12/2018  
4 Jibannagar
1 IRIDP-2/CHU/DW-15 a)Banka Bazer-Katapol More..00-500mb) Construction of 3nos culvert 0.625x0.600m at ch 442m, 525m &760m. 0.5000 54.221 M/S. Madani Enterprise 54.221 30/12/2015 23/10/2016 100 23/12/2018  
Total : 13.8910 (Km) 831.18 (Lac) 831.18 (Lac)