Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Alamdanga
1 SP45212/Nauda Durgapur - Maddamath Subproject Re-excavation of Nauda Durgapur khal (Ch: 0.00 - 1000 m) Reference Lined Section 2 nos. (Ch-100m & 800m) and SP Identification Signboard (2 nos.) Repair & Maintenance of Regulator (Rubber Seal, Gear box , block placing etc.) (Size 1V-1.50mX1.80m.) Repair & Maintenance of WMCA Office Building (Tube well, Painting etc.) (Size 12.00mX6.00m.) 21.046 Md.Tokbul Hossain 21.046 27/12/2023 30/12/2023 60 13/08/2024 Ongoing
2 SP24163/Bhangabari-Amanjhola Beel Subproject Re-excavation of Amonjhola khal (Ch: 0.00 - 1780 m) Ref. Lined Section (2 nos.) and SP identification Signboard (2 nos.) 28.224 Md.Mominul 28.224 15/09/2020 30/04/2021 100 13/08/2024 Completed
2 Chuadanga-s
1 SP14138/Kamri-Paksia Beel FCD Subproject Kamria Paksia khal re-excavation(ch.1000-3040m) Referenced line section 65.766 Rahima Khatun 65.766 22/03/2018 30/04/2018 100 13/08/2024 Completed
3 Damurhuda
1 SP14172/Barade-Kamarpara FCD Subproject Baradi Kamarpara Khal Re-excavation(Ch-0+000km to 1+000km) RCC Ref. Lined Section 1 Nos. Repair of WMCA office- Repair of Box Culvent Repair of 2Vent Regulator -. 21.122 Mr.Muntaz Hossain 21.122 08/05/2022 30/12/2022 100 13/08/2024 Completed
2 SP14136/Gopalkhali FCD Subproject Gopalkhali khal re-excavation(ch.00-1000m) Referenced line section(2 Nos.) Bamboo bridge(1 Nos.) 22.006 Sajjad Ahmed 22.006 13/12/2018 28/04/2019 100 13/08/2024 Completed
3 SP12018/Razukhali Khal FCD Subproject Rajukhali khal re-excavation(ch.00-2750m) Referenced line section(3 Nos.) Bamboo bridge(3 Nos.) 36.643 LCS 36.643 19/02/2019 30/04/2019 100 13/08/2024 Completed
4 Jibannagar
1 SP15286/Aruar Khal DR & WCS Subproject Re-excavation of Aruar khal (Ch: 0.00 - 2040 m) Weir (2v) maintaenance at Aruar khal. Reference lined section (3nos.), Bamboo bridge (3nos.) and SP identification signboard (2nos.) 22.367 Razu Ahmed 22.367 30/04/2020 30/04/2020 100 13/08/2024 Completed
2 SP15231/Digrir Beel DR Subproject Re-excavation of Kazia Khal (Ch: 0.00 - 4200.00 m) Re-excavation of Digrir Khal (Ch: 0.00 - 0.800 m) Reference Lined Section (7 nos.) and SP Identification Signboard (2 nos.) 45.443 Mst.Taz Nahar 45.443 25/01/2021 30/04/2021 100 13/08/2024 Completed
3 SP15230/Shankheri & Ruer Beel FCD Subproject Sakharia Ruier khal re-excavation(ch.00-1000m) Referenced line section 13.932 Md.Shakwat 13.932 13/03/2018 30/04/2018 100 13/08/2024 Completed
Total : 0.0000 (Km) 276.55 (Lac) 276.55 (Lac)