Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Gangni
1 IRIDP-2/MHR/DW-15 Improvement of Hogalbaria Hatkhola-Udoynagar Ghat road (Ch. 900-1387.23m). 0.4870 24.999 M/S. Anarul Trader's 24.999 15/03/2016 29/12/2016 100 23/12/2018  
2 Meherpur-s
1 IRIDP-2/MHR/DW-10 Improvement of Sholmari GC.-Meherpur via Rudronagar-Kamdebpur road (Ch. 3300-3887m). 0.5870 29.990 M/S. Jony Enterprise 29.990 07/02/2016 15/08/2016 100 23/12/2018  
2 IRIDP-2/MHR/DW-9 Improvement of Gopalpur R&H-Beltalapara road (Ch. 2429-3005m). 0.5760 29.815 M/S. Khan Enterprise 29.815 26/01/2016 15/08/2016 100 23/12/2018  
3 IRIDP-2/MHR/DW-8 Improvement of Digirpara-Jowbaria pakurtala road (Ch. 1776-2606m). 0.8300 44.830 M/S. Jony Enterprise 44.830 26/01/2016 15/08/2016 100 23/12/2018  
4 IRIDP-2/MHR/DW-7 Improvement of Mohajonpur UP-Tengramari via Shahebpur-Islampur road (Ch. 1070-1840m). 0.7700 39.934 M/S. Biswas Construction 39.934 12/02/2016 11/08/2016 100 23/12/2018  
5 IRIDP-2/MHR/DW-6 Improvement of Kuthipara-Kulbaria via Kutubpur UP Office road (Ch. 962-1488m). 0.5260 29.772 Anchal Bhattacharyya 29.772 26/01/2016 15/08/2016 100 23/12/2018  
6 IRIDP-2/MHR/DW-5 Improvement of Baribanka Amtola-Bazitpur road (Ch. 486-1256m). 0.7670 40.011 Shalahuddin Ahmed 40.011 07/02/2016 15/08/2017 100 23/12/2018  
7 IRIDP-2/MHR/DW-4 Improvement of Jadabpur-Buripota UP-Shalika road (Ch. 6100-6635m). 0.5350 27.612 Md. Mohafidul Haque 27.612 26/01/2016 15/08/2016 100 23/12/2018  
8 IRIDP-2/MHR/DW-3 Improvement of Musurivaza-Juginda road (Ch. 550-1032m). 0.4820 24.999 M/S. Biswas Construction 24.999 07/02/2016 15/08/2016 100 23/12/2018  
9 IRIDP-2/MHR/DW-2 a) Improvement of Fatepur Pry. School-Fatepur Madhopara road (Ch. 0-765m).b) Construction of 1 no Culvert 0.625x0.600m at Ch. 200m. 0.7650 41.095 Shalahuddin Ahmed 41.095 03/01/2016 15/08/2016 100 23/12/2018  
10 IRIDP-2/MHR/DW-1 Improvement of Govipur-Horirampur road (Ch. 615-1390m) 0.7750 39.801 M/S. Biswas Construction 39.801 07/02/2016 15/08/2016 100 23/12/2018  
3 Mujib nagar
1 IRIDP-2/MHR/DW-14 Improvement of Dariapur Dashkhinpara Mosque-Kodamtola more via Chowrasta more road (Ch. 0-362m). 0.3620 18.996 Md. Mizanur Rahman Fazlu 18.996 21/01/2016 11/12/2016 100 23/12/2018  
2 IRIDP-2/MHR/DW-13 Improvement of Poranpur Tatultala more - Tangramara Kalytala more road (Ch. 0-652m). 0.6520 33.590 M/S. Biswas Construction 33.590 07/02/2016 20/09/2016 100 23/12/2018  
3 IRIDP-2/MHR/DW-12 Improvement of Komorpur Sosthitola-Anarul Brick field road (Ch. 0-465m). 0.4650 24.196 Shalahuddin Ahmed 24.196 03/02/2016 15/08/2016 100 23/12/2018  
4 IRIDP-2/MHR/DW-11 Improvement of Anandobash Gagimtola-House of Ayub Chairman road (Ch. 0-410m). 0.4100 21.574 Md. Mizanur Rahman Fazlu 21.574 24/01/2016 15/08/2016 100 23/12/2018  
Total : 8.9890 (Km) 471.21 (Lac) 471.21 (Lac)