Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Naogaon-s
1 UGIIP-III-2/ NAOG/UT+DR /02/2016 UGIIP-III-2/ NAOG/UT+DR /02/2016 8.1380 827.584 Ethen-PMPL-JV,Main Road, Naogaon 827.584 30/03/2017 27/03/2018 100 13/05/2019 na
2 UGIIP-III-2/NAOG/UT+DR /01/2016 UGIIP-III-2/NAOG/UT+DR /01/2016 3.8600 813.284 MT-DC-MRC (JV),Dewan Bazar,Main Road, Naogoan 813.284 04/02/2017 27/03/2018 100 13/05/2019 NA
3 UGIIP-III-I/ NAOG /DR+MF/01/ 2014 UGIIP-III-I/ NAOG /DR+MF/01/ 2014 683.478 M/s A.S Construction,E-799,Katirganj, Rajshahi 683.478 10/07/2015 05/07/2016 100 13/05/2019 No
4 UGIIP-III-I/ NAOG / UT / 01 / 2014 UGIIP-III-I/ NAOG / UT / 01 / 2014 12.5850 811.796 Ethen-Farid (JV), Main Road, Naogaon 811.796 07/05/2015 29/06/2016 100 13/05/2019 No
Total : 24.5830 (Km) 3136.14 (Lac) 3136.14 (Lac)