Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bagatipara
1 W.630 Construction of Doyarampur UP Complex 147.680 147.680 30/07/2019 100 25/08/2020 Final
2 Baraigram
1 W.576 Construction of Jonael UP Complex 119.180 119.180 19/05/2019 100 25/08/2020 Final
2 W.328 Construction of Baraigram UP Complex 69.620 69.620 01/03/2013 100 25/08/2020 Final
3 W.481 Construction of 7 no Chandai UP Complex 89.400 89.400 02/12/2017 100 25/08/2020 On going
3 Gurudaspur
1 W.559 Construction of Moshinda UP Complex 146.770 146.770 14/07/2020 95 25/08/2020 On going
4 Lalpur
1 W.495 Construction of Bilmaria UP Complex 94.980 94.980 30/12/2018 100 25/08/2020 Final
5 Natore-s
1 W.198 Construction of 7 no Tebaria UP Complex 81.510 81.510 08/11/2016 100 25/08/2020 Final
2 UP/Nat-03 Construction of Tebaria UP 81.150 81.150 11/08/2016 30 02/05/2016
6 Singra
1 W.603 Construction of Sukas UP Complex 123.180 123.180 31/07/2019 100 25/08/2020 Final
2 W.002 Construction of 5 no Chamary UP Complex 83.540 83.540 15/03/2016 100 25/08/2020 Final
3 W.038 Construction of 11 no Chaterdighi UP Complex 85.330 85.330 31/12/2016 100 25/08/2020 Final
4 UP/Nat-02 Construction of Chaterdighi UP 85.330 85.330 19/06/2016 35 02/05/2016
5 UP/Nat-01 Construction of Chamari UP 83.530 83.530 15/03/2016 100 02/05/2016
Total : 0.0000 (Km) 1291.20 (Lac) 1291.20 (Lac)