1
|
SP25236/Baliaghata Subproejct
|
Construction of RCC Pumping Platform near Mohananda River (1no), Small Size Pumping Platfrom (2nos.) Construction of RCC Over Head Tank near Ajram Pond. Re-Construction of 1-500mm dia UPVC Buried Pipe Lines, FF1 Line From Ch.(1343m to1483 m) Construction of 1-315mm UPVC Buried Pipe Line,NO line From Ch.(0.0 to 1550 m) Construction of 1-250mm dia UPVC Buried Pipe Branch Lines OP From Ch.(1550 m+1920 m) Construction of 1-250mm dia UPVC Buried Pipes Branch Lines PP2 From Ch.(1920 m+2720 m) Construction of 1-250mm dia UPVC Buried Pipes Branch Lines OQ From Ch.(1550 m+1870 m) Construction of 1-250mm dia UPVC Buried Pipes Branch Lines QQ2 From Ch.(1870 m+2670 m) Non-Tender Items: 125mm Brick Work, Supplying, Fitting, Fixing MS grills
|
|
201.510
|
Borsa enter prize & Rithin Enter Prize
|
201.510
|
14/12/2020
|
10/10/2021
|
100
|
13/08/2024
|
Completed
|
2
|
SP25235/Kashimpur CAD Sub-project
|
Re-Construction of 1-500mm dia UPVC Buried Pipe C-D-E-F Line From (Ch: 0.00m-1236.00m.) Construction of RCC Open Branch Canal BR-5 from (Ch: 0.00m-450.00m.) Project Identification Signboard. Const. of Laying 1-450mm dia Upvc Buried Pipe Branch Canal-1, line C-C4-1 from RCC Sump to Header Tank Near Asmail Land). Length= 1350m - 2023-24 Const. of Laying 1-250mm dia Upvc Buried Pipe Branch Line C4-C5 (Asmail Land to South side). Length= 300m - 2023-24 Const. of RCC Open Irrigation Canal Line C-D (0.50m X 0.50m) (South side of Existing RCC Sump). Length= 280m. & Sump Extension - 2023-24
|
|
243.254
|
OTM
|
243.254
|
25/04/2024
|
28/06/2022
|
50
|
13/08/2024
|
Ongoing
|
3
|
SP25227/Hatnabad Subproject
|
Construction of RCC Irrigation Open Canal Line: B-B1 From Ch.0+000 km to 0+150 km Construction of RCC Irrigation Open Canal Line: C1-C2 From Ch.0+000 km to 0+110 km. Plastering & Bottom Patent Stone of Brick Main and Plastering & Bottom Patent Stone & Vertical Extension Brick Branch Canal Line: E-F from Ch.0+500 km to 685 km Construction of RCC Irrigation Open Canal Line: F-F1 From Ch.0+000 km to 0+150 km. Laying of 1-250mm Dia Upvc Buried Pipe Line: G-G1 from Ch. 0+000 km to 0+700 km Laying of 1-250mm Dia Upvc Buried Pipe Line: G-G2 from Ch. 0+000 km to 0+150 km Laying of 2-280mm Dia Upvc Buried Pipe Line: G-H from Ch. 0+000 km to 1+650 km Laying of 1-250mm Dia Upvc Buried Pipe Line: H-H1 from Ch. 0+000 km to 0+500 km Laying of 1-250mm Dia Upvc Buried Pipe Line: H-H2 from Ch. 0+000 km to 0+650 km Laying of 1-250mm Dia Upvc Buried Pipe Line: H-H3 from Ch. 0+000 km to 0+380 km Laying of 1-250mm Dia Upvc Buried Pipe Line: H-H4 from Ch. 0+000 km to 0+300 km Construction of Brick Header Tank ( 3.60m x 3.60 m x 2.10m ) near Mirdha Pond Construction of Rcc Pump Operating Platform (2-3.0m x 2.0m ) at Existing Header Tank & Mirdha Pond & (1-6.0m x 2.0m) at River Bank, 28 Nos Brick Name Plate, 2 Nos. SPISP & 2 Nos. SPIP. Laying of 1-280mm Dia uPVC Buried Pressure Pipe Line G-H from Ch. 0+000km to 1+650km - 2023-24
|
|
221.094
|
OTM
|
221.094
|
30/04/2024
|
16/01/2024
|
92
|
13/08/2024
|
Ongoing
|
4
|
SP12037/Dudhai-Bhanpur Khal WCS Subproject
|
Dudhai - Bhanpur Khal Re-excavation (ch0.00-2500m) Reference Line Section (4nos) (ch 100m, 1200m, 1800m, 2400m), SP Identification signboard (2Nos.)
|
|
31.924
|
LCS
|
31.924
|
28/01/2021
|
10/04/2021
|
100
|
13/08/2024
|
Completed
|