Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Chatmohar
1 CIB-Pab-W-70 Const. of 96 m long PSC Girder Bridge over Gomani river at Ch.10930m on Mirjapur GC-Saikola GC road under Chatmohar Upazila, District: Pabna 10.9300 822.280 MD: Alomgir Zahan & Khairul Kobir Rana (JV) 822.280 07/01/2019 02/12/2021 100 23/02/2025 Final Bill Paid
2 Faridpur
1 CIB-Pab-W-69 Const. of 280 m long PSC Girder Bridge over Boral river at Ch.15100m on Ershadnagar Hat-Demra UP office road under Faridpur Upazila, District: Pabna 15.1000 2913.170 ICL-SEHA-JV,I/D Central Road, Ghope Jashore. 2913.170 01/09/2020 30/06/2025 82 23/02/2025
Total : 26.0300 (Km) 3735.45 (Lac) 3735.45 (Lac)