Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Joypurhat-s
1 IRIDP-2/JOY/DW-10 a)Improvement of Mozahidpur Pucca road-Ichua road (ch.00-500m). b)Construction of 1nos culvert 0.375x0.450m at Ch.266m. 0.5000 26.880 Kalicharam Agarwala 26.880 19/01/2016 15/12/2016 100 23/12/2018  
2 IRIDP-2/JOY/DW-9 Improvement of Mongalbari Hat ( Dogachi UP Office)-Durgadaha Bazar road (Ch. 2939m-3689m). 0.7500 39.340 Kalicharam Agarwala 39.340 19/01/2016 15/12/2016 100 23/12/2018  
3 IRIDP-2/JOY/DW-8 Improvement of Dogachi ( Uttar Joypur)-Baguan road (ch.00-750m) 0.7500 39.390 Classic Construction 39.390 20/01/2016 30/04/2017 100 23/12/2018  
4 IRIDP-2/JOY/DW-7 Improvement of Rangta Polikadoa-Mirgram Via Kadoa road ( ch. 4200m-4700m). 0.5000 26.490 M/S Mahadi Construction 26.490 21/01/2016 22/07/2016 100 23/12/2018  
5 IRIDP-2/JOY/DW-6 a)Improvement of Noapara-Mongalbari road (ch.1900m-2400m). b)Construction of 1nos culvert 0.625 x 0.600m at Ch.2080m. 0.5000 30.810 M/S Mahadi Construction 30.810 21/01/2016 22/07/2016 100 23/12/2018  
6 IRIDP-2/JOY/DW-5 a)Improvement of Gopalpur Baskata road (ch. 900m-1400m). b)Construction of 1nos culvert 0.900x0.900m at Ch.1250m. 0.5000 25.080 M/S Zahid Traders 25.080 26/01/2016 30/08/2016 100 23/12/2018  
7 IRIDP-2/JOY/DW-4 Improvement of Mongalbari-Pechulia Link road (Ch.00m-500m). 0.5000 25.560 MS Liton Traders 25.560 25/01/2016 10/12/2016 100 23/12/2018  
8 IRIDP-2/JOY/DW-3 Improvement of Dogachi UP Office-Jamtoli Via Dhalahar UP Office road (Ch. 714-1314m). 0.6000 34.230 Kalicharam Agarwala 34.230 19/01/2016 15/12/2016 100 23/12/2018  
9 IRIDP-2/JOY/DW-2 a)Improvement of Atthoka-Dhalahar road (ch. 00m-500m). b)Construction of 1nos culvert 0.625x0.600m at Ch.90m. c)Construction of 1nos culvert 0.375x0.450m at Ch.190m. 0.5000 26.450 Classic Construction 26.450 20/01/2016 30/04/2017 100 23/12/2018  
10 IRIDP-2/JOY/DW-1 Improvement of Paschim Dogachi-Pakurtali road (Ch. 1500m-2500m). 1.0000 49.070 M/S Didarul Haque & Sons 49.070 31/01/2016 01/07/2016 100 23/12/2018  
2 Panchbibi
1 IRIDP-2/JOY/DW-15 Improvement of Sultanpur Dewanbagi Mosque - Siddique Mondal house road (ch.00m-500m). 1.0000 21.610 M/S Rawshanara Enterprise 21.610 04/02/2016 16/06/2016 100 23/12/2018  
2 IRIDP-2/JOY/DW-14 Improvement of Berakhai Village road (ch. 00m -500m). 0.5000 21.770 M/S Kaderi Kibria 21.770 03/02/2016 23/06/2016 100 23/12/2018  
3 IRIDP-2/JOY/DW-13 Improvement of Koria-Lakma road (ch. 00m-500m) . 0.5000 25.500 Classic Construction 25.500 04/02/2016 30/04/2017 100 23/12/2018  
4 IRIDP-2/JOY/DW-12 Improvement of Kusumba UP Office-Berakhai Road ( ch.500m-765m & 900m-1330m). 0.2650 28.560 MS Liton Traders 28.560 21/01/2016 30/11/2016 100 23/12/2018  
5 IRIDP-2/JOY/DW-11 Improvement of Panial-Paglabazar-Barokandi road ( ch.7950m-8450m). 0.4999 25.860 M/S Kaderi Kibria 25.860 20/01/2016 30/06/2017 100 23/12/2018  
Total : 8.8649 (Km) 446.60 (Lac) 446.60 (Lac)