Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Joypurhat-s
1 SP15221/Hatigara-Kamalpur WCS Subproject Re-excavation of Hatigara-Kamalpur Khal Reference line section (6nos.) Basher Shako (2nos, L=34m) Construction of WMCA Office and WRS Maintenance (weir) 136.622 LCS 136.622 15/04/2020 30/04/2020 100 13/08/2024 Completed
2 Kalai
1 SP24143/Kadirpur-Bakhara Subproject Re-excavation Kadirpur-Bakhra Khal Reference line section (5nos.) and Basher Shako (3nos, L=42m) Maintenance of Water Structure 51.042 LCS-11 51.042 24/02/2022 30/04/2022 100 13/08/2024 Completed
2 SP13091/Kanmona-Haraboti WCS Subproject Harabati Khal re-xcavation (Ch:0.00m - 10000m) Const. of 05 Nos. Ref. lined Section on 01 Khal, SP Identf. sign board 2, SP Area Indication Post 2 Nos. 137.439 LCS 137.439 25/03/2024 50 13/08/2024 Ongoing
3 Khetlal
1 SP15220/Pathanpara-Koitahar WCS Subproject Re-excavation of Patahnpara - Koitahar Khal (Ch-0+000km to 7+600km) Ref. Lined Section 7 Nos. On 1 Khals, And SP Identf. Signboard (2 nos.) Rehabilitation of Pathanpara - Koitahar Khal WRS (2v-1.5mx1.8m) -. Construction of WMCA office building 63.589 OTM 63.589 24/02/2022 30/04/2022 100 13/08/2024 Completed
4 Panchbibi
1 SP61015/Shekta Chaksamser Khal Subproject Re-exacavation of Shekta-Chak Samser Khal (Ch-0+300km to 4+590km) Re-exacavation of Shekta-Chak Samser Branch Khal (Ch-0+000km to 2+202km) Ref. Lined Section 6 Nos. On 2 Khal And SP Identf. Signboard (2 nos.) Shekta-Chak Samser Khal WRS-1 (2v-1.5mX2.5m) at Ch. 0+710 km Construction of WMCA office building. Shekta-Chak Samser Khal WRS-2 (2v-1.5mX1.5m) at Ch. 3+560 190.886 OTM, Md. Sohel,Santahar,Bogra. 190.886 22/03/2022 30/04/2022 100 13/08/2024 Completed
2 SP44109/Jhinaigari Khal Subproject Jhenaigari Khal re-excavation (Ch:0.00 - 7500m) Const. of 08 Nos. Ref. lined Section on 1 Khal 83.276 LCS 83.276 07/03/2024 25/04/2024 100 13/08/2024 Completed
3 SP22015/Amirpur-Barail Subproject Amirpur Borail khal & Branch khal- 1 re-excavation(ch.00-6100m&ch.00-870m) Referenced line section(5 Nos.) 56.017 SABANA MUSTARIN 56.017 05/03/2018 30/04/2018 100 13/08/2024 Completed
4 SP15277/Boyra-Srikrishnapur DR & WCS Subproject WMCA Office and Others Boyra-Srikrishnapur khal re-excavation(ch.00-6800m) Referenced line section(5 Nos.) 106.298 TOFAZZOL 106.298 07/07/2019 30/04/2018 100 13/08/2024 Completed
5 SP13078/Baharampur FCD Subproject Re-sectioning of Bahrampur Embankment (Ch-0+000km to 1+300km) and SP Identification Signboard & Post (2Nos.) 22.583 LCS 22.583 13/11/2023 25/04/2024 100 13/08/2024 Completed
Total : 0.0000 (Km) 847.75 (Lac) 847.75 (Lac)