SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
1
|
Bhurungamari
|
1
|
RDRIIP/KUR/
TR-023
|
Tree Plantation work on Paglarhat – Pathardubi UP Road via Bashjani road. (Ch.00-6750m) (Effective length=2000m).
|
2.0000
|
2.986
|
LCS women
|
2.986
|
01/08/2015
|
31/07/2017
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
TR-022
|
Tree Plantation work on Paikerchara Bazar R&H RD – Andharijhar GC road via Deeperhat Road. (Ch.00-7030m) (Effective length=4000m).
|
4.0000
|
5.961
|
LCS women
|
5.961
|
01/08/2015
|
31/07/2017
|
100
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
TR-016
|
Tree Plantation work on Bhurungmari Hospital – Thana Ghat Bazar – Telai High School road. (Ch.4500-6500m).(effective length=2000m).
|
2.0000
|
2.989
|
LCS women
|
2.989
|
09/09/2014
|
30/06/2016
|
100
|
06/01/2019
|
|
4
|
RDRIIP/KUR/
TR-015
|
Tree Plantation work on Joymonirhat UP (R&H) - Deeperhat road. (Ch.2000-3000m).(effective length=1000m).
|
1.0000
|
1.500
|
LCS women
|
1.500
|
09/09/2014
|
30/06/2016
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
TR-014
|
Tree Plantation work on Bangosonahat – Shahi Bazar GC road. (Ch.1500-3500m).(effective length=2000m).
|
2.0000
|
2.989
|
LCS women
|
2.989
|
09/09/2014
|
30/06/2016
|
100
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
LCS-12
|
KzwoMÖvg †Rjvi f‚iæ½vgvix Dc‡Rjvaxb 10wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
191.2500
|
114.750
|
LCS
|
114.750
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
HB-07
|
Improvement of Deeperhat Rural Market under Char Bhurungamari UP.
|
1.0000
|
35.144
|
Md. Lutar Rahman Bokshi, Krishnopur, Kurigram.
|
35.144
|
18/09/2016
|
17/09/2017
|
100
|
06/01/2019
|
|
8
|
RDRIIP/KUR/
BR-026
|
Construction of 45.00m Long RCC Girder Bridge on Thanaghat-Shahebganj Border road over Fulkumar River at Ch. 155m.
|
45.0000
|
211.140
|
Ujjalreazuljv, Ghoshpara, Kurigram.
|
211.140
|
02/11/2016
|
11/11/2017
|
30
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
VR-367
|
Improvement of Bagvander - Debdebir bazar Road (St. From H/O Hamidul Haque & End Point H/O Khaibor Uddin) (Ch. 00-610m).
|
0.6100
|
34.606
|
M/S Hamid Traders, Dadamore, Kurigram.
|
34.606
|
02/11/2016
|
11/11/2017
|
100
|
06/01/2019
|
|
10
|
RDRIIP/KUR/
VR-330
|
Improvement of Moynatola bazar -Char Bhurungamari Road (Ch. 00-600m).
|
0.6000
|
31.862
|
M/S Hamid Traders, Dadamore, Kurigram.
|
31.862
|
18/08/2016
|
28/05/2017
|
100
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
VR-329
|
Improvement of RHD Road at Gochidanga Shapla more - Deeperhat at Deobond more Road (Ch. 2000-2625m).
|
0.6250
|
33.189
|
M/S Hamid Traders, Dadamore, Kurigram.
|
33.189
|
18/08/2016
|
28/05/2017
|
100
|
06/01/2019
|
|
12
|
RDRIIP/KUR/
VR-261
|
Improvement of Abdharijhar bazar - Char Dhaurarkuti Road (Ch. 2400-2900m).
|
0.5000
|
27.940
|
M/S Diago Enterprise, Nageswari, Kurigram.
|
27.940
|
29/03/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
13
|
RDRIIP/KUR/
VR-140
|
Improvement of Naliya Hamida Khanam High School Road (Ch. 2000-2600m).
|
0.6000
|
30.698
|
M/S Nuruzzaman
Kathalbari, Kurigram.
|
30.698
|
16/07/2015
|
25/01/2016
|
70
|
06/01/2019
|
|
14
|
RDRIIP/KUR/
VR-128
|
Improvement of Char Bhurungamari-Dakkhin Telai Sarola Road (Ch. 1000-1600m).
|
0.6000
|
31.494
|
M/S N.F Traders
Fulbari, Kurigram.
|
31.494
|
21/06/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
15
|
RDRIIP/KUR/
UN-229
|
Improvement of Bongosonahat UP - Chowdhurihat Road (Ch. 00-2000m).
|
2.0000
|
116.136
|
M/S Fahim Traders, R. K. Road, Kurigram.
|
116.136
|
11/04/2016
|
20/04/2017
|
100
|
06/01/2019
|
|
16
|
RDRIIP/KUR/UN-169
|
Improvement of Joymonirhat U.P-Manik kazi bazaar Road (Ch. 600-1600m).
|
1.0000
|
79.544
|
Md. Wahed Ali,
Fulbari, Kurigram.
|
79.544
|
19/10/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
17
|
RDRIIP/KUR/UN-168
|
Improvement of Joymonir Hat U.P (R&H) – Deperhat Road (Ch. 2000-3000m).
|
1.0000
|
85.504
|
Md. Wahed Ali, Fulbari, Kurigram.
|
85.504
|
19/10/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
18
|
RDRIIP/KUR/
UN-110
|
Improvement of Joymonirhat U.P-Manik kazi bazaar Road (Ch. 1600-2600m).
|
1.0000
|
56.884
|
Md. Redwanul Haque, Kathabari, Kurigram.
|
56.884
|
16/07/2015
|
25/04/2016
|
100
|
06/01/2019
|
|
19
|
RDRIIP/KUR/
UN-105
|
Improvement of Joymonir Hat U.P (R&H) – Deperhat Road (Ch. 1000-2000m).
|
1.0000
|
53.549
|
Md. Mahabubar Rahman, Ghoshpara, Kurigram.
|
53.549
|
16/03/2015
|
24/04/2016
|
100
|
06/01/2019
|
|
20
|
RDRIIP/KUR/
UN-019
|
Improvement of Joymonirhat U.P (R&H) – Deeperhat road (Ch. 00-1000m)
|
1.0000
|
54.215
|
M/S Basundhara, R, K road, Kurigram.
|
54.215
|
26/07/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
|
2
|
Chilmari
|
1
|
RDRIIP/KUR/
LCS-07
|
KzwoMÖvg †Rjvi wPjgvix Dc‡Rjvaxb 6wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
117.1833
|
70.310
|
LCS
|
70.310
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
VR-526
|
Improvement of Kharkaria Sluice gate - Madriapara Mondolerhat Road (Ch. 80-1180m).
|
1.1000
|
84.293
|
M/S Fahim Traders, R, K Road, Kurigram.
|
84.293
|
11/07/2017
|
20/07/2018
|
100
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
VR-525
|
Improvement of Modanmohon Primary School - Akkas Mia house Road (Ch. 00-950m).
|
0.9500
|
62.166
|
Md. Nowroj Hossain, Guptapara, Kurigram.
|
62.166
|
11/07/2017
|
20/07/2018
|
65
|
06/01/2019
|
|
4
|
RDRIIP/KUR/
VR-466
|
Improvement of Thanahat - Fokirehat Upazila Road at Baparirhat - Kajaldangahat Road (Ch. 1330-1830m).
|
0.5000
|
28.500
|
M/S Shamim Enterprise, Puraton Registreepara, Kurigram.
|
28.500
|
11/07/2017
|
20/04/2018
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
VR-465
|
Improvement of H/O Monsur mistree - Afjal mia Road (Ch. 00-1000m).
|
1.0000
|
71.772
|
Md. Redwanul Haque, Kanthalbari, Kurigram.
|
71.772
|
11/07/2017
|
20/07/2018
|
100
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
VR-139
|
Improvement of Thanahat – Jorgach UZR at Nasormore – Jorgach Bazar Road (Ch. 00-525m).
|
0.5250
|
33.772
|
M/S Zahurul Haque Dulal, Ghoshpara, Kurigram.
|
33.772
|
16/07/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
VR-138
|
Improvement of New Jorgach Bazar - BWDB Embankment at Khar Kharia (Vatto para) Road (Ch. 00-790m).
|
0.7900
|
47.301
|
M/S Ratan Traders
Hingonary, Kurigram.
|
47.301
|
16/07/2015
|
30/06/2017
|
50
|
06/01/2019
|
|
8
|
RDRIIP/NIL/
VR-042
|
Improvement of Thagerhat – Kanchkol Bazar Road (Ch. 00-500m).
|
0.5000
|
27.429
|
Sree Susan Chandra Sarkar, Khaligonj, Kurigram.
|
27.429
|
23/07/2015
|
30/07/2015
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/UN-263
|
Improvement of Ramna UP Office Near Shariferhat – Kalir bazar river Ghat Road (Ch. 1270-2200m).
|
0.9300
|
60.842
|
Sree Susan, Chandra Sarkar, Khalilgonj, Kurigram.
|
60.842
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
10
|
RDRIIP/KUR/
UN-102
|
Improvement of Sharifer hat – Khasim Bazar (Near Ramna UP Offoce) Road (Ch. 2400-3100m).
|
0.7600
|
49.097
|
M/S Nowroj Hossain, Guptapara, Rangpur.
|
49.097
|
10/05/2015
|
31/01/2017
|
100
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
UN-101
|
Improvement of Sharifer hat – Khasim Bazar (Near Ramna UP Offoce) Road (Ch. 1400-2400m).
|
1.0000
|
62.465
|
Sree Susan Chandro Sarker, Kaligonj Kurigram.
|
62.465
|
16/07/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
|
3
|
Fulbari
|
1
|
RDRIIP/NIL/
LCS-11
|
KzwoMÖvg †Rjvi dzjevox Dc‡Rjvaxb 6wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
117.1833
|
70.310
|
LCS
|
70.310
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
VR-500
|
Improvement of Bhangamore Talukdarpara - Pakirhat Road (Ch. 00-406m & 916-1700m).
|
1.1900
|
75.811
|
M/S Hajrat Ali, Horikesh, Kurigram.
|
75.811
|
11/07/2017
|
20/07/2018
|
45
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
VR-390
|
Improvement of Kharibari Grils High School - Rabitary Road (Ch. 00-600m).
|
0.6000
|
32.815
|
M/S Wahed Ali, Fulbari, Kurigram.
|
32.815
|
15/12/2016
|
25/12/2017
|
100
|
06/01/2019
|
|
4
|
RDRIIP/KUR/VR-312
|
Improvement of Kharibari Hat - Amtala Bazar Road (Ch. 1250-1850m).
|
0.6000
|
36.282
|
M/S Hamid Traders, Dadamore, Kurigram.
|
36.282
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
VR-207
|
Improvement of Ghogar Kuti GPS – H/O Hobibor – Borovita Pacca Road (Ch. 2224-3464m)
|
1.2400
|
69.002
|
M/S Hamid Traders, Dadamore, Kurigram.
|
69.002
|
01/10/2015
|
08/12/2016
|
100
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
VR-125
|
Improvement of Kadomtali –Monirer vita Road. (Ch. 00-600m).
|
0.6000
|
31.872
|
Md. Ayub Ali,
Kathalbari, Kurigram.
|
31.872
|
21/06/2015
|
31/12/2015
|
75
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
VR-124
|
Improvement of Majid Chairman House – House of Amjad Via House of Mannan Sardar (Ch. 1000-1600m).
|
0.6000
|
27.793
|
Md. Ayub Ali,
Kathalbari, Kurigram.
|
27.793
|
21/06/2015
|
31/12/2015
|
65
|
06/01/2019
|
|
8
|
RDRIIP/KUR/
VR-051
|
Improvement of Shah Bazar – Purbo Dhoniram GPS Road (Ch. 905-1460m).
|
0.5550
|
28.587
|
M/S Hamid Traders, Dadamore, Kurigram.
|
28.587
|
11/12/2014
|
31/12/2016
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
VR-043
|
Improvement of Borloi Hajir Bazar – Borovita Khoribari road via Deep tubewell (Ch. 00-600m).
|
0.6000
|
32.329
|
M/S Basundhara, R, K road, Kurigram.
|
32.329
|
22/06/2014
|
31/03/2015
|
100
|
06/01/2019
|
|
10
|
RDRIIP/KUR/UN-289
|
Improvement of Naodanga UP Office (Balarhat GC) - Balatary BOP Camp Road (Ch. 150-1650m).
|
1.5000
|
83.640
|
M/S Hamid Traders, Dadamore, Kurigram.
|
83.640
|
15/12/2016
|
25/12/2017
|
100
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
UZ-094
|
Improvement of Newashhi GC - Kurigram- Nageswari R&H near Kadomtala via Boulvir Road (Ch. 00-2300m).
|
2.3000
|
204.761
|
Ujjal Kumar Dey, Ghoshpara, Kurigram.
|
204.761
|
02/11/2016
|
11/11/2017
|
45
|
06/01/2019
|
|
|
4
|
Kurigram-s
|
1
|
RDRIIP/KUR/
TR-010
|
Tree Plantation work on Pateswari Bazar – Bhitorbond GC road.(Ch.00-7100m).(effective length=5000m).
|
5.0000
|
7.430
|
LCS women
|
7.430
|
27/08/2014
|
30/06/2016
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
LCS-50
|
KzwoMÖvg †Rjvi m`i Dc‡Rjvaxb 8wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
154.2166
|
92.530
|
LCS
|
92.530
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
3
|
RDRIIP/KUR/VR-314
|
Improvement of Muktaram GPS - Velong more via Rail Gate Road (Ch. 374-1070m).
|
0.6960
|
35.383
|
M/S Zahurul HAque Dulal, Ghoshpara, Kurigram.
|
35.383
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
4
|
RDRIIP/KUR/
VR-239
|
Improvement of Kurigram Anantopur GC Road - H/O Asswani Kumar House (Kektin Bridge) (Ch. 884-2084m).
|
1.2000
|
68.379
|
M/S Zahurul Haque Dulal, Ghoshpara, Kurigram.
|
68.379
|
22/02/2016
|
30/09/2017
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
VR-238
|
Improvement of Kalirpar - PK (Kanthalbari Collage Kalirpar) Road (Ch. 784-1384m).
|
0.6000
|
35.139
|
MD. Nuruzzaman, Khanthalbari, Kurigram.
|
35.139
|
22/02/2016
|
02/03/2017
|
100
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
VR-137
|
Improvement of Boshniar hat mosque - UP office road (Ch. 55-655m).
|
0.6000
|
30.491
|
M/S Aroshi Construction
Nageswari, Kurigram.
|
30.491
|
16/07/2015
|
25/01/2016
|
100
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
VR-122
|
Improvement of Boshniar hat deep tubewell - jotener hat road (Ch. 00-700m).
|
0.7000
|
35.573
|
M/S Khariul Enterprise
Trimohoni Bazar,
Kurigram.
|
35.573
|
21/06/2015
|
31/01/2017
|
100
|
06/01/2019
|
|
8
|
RDRIIP/KUR/
VR-121
|
Improvement of Khoirmia house - Solaiman Bhuia house Road (Ch. 00-600m).
|
0.6000
|
30.491
|
M/S Khariul Enterprise
Trimohoni Bazar,
Kurigram.
|
30.491
|
21/06/2015
|
31/01/2017
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
VR-041
|
Improvement of Muktaram GPS Pucca road - Gorberdola via Bazlur Master House under Belgacha UP Road (Ch. 593-1393m).
|
0.8000
|
42.259
|
M/S Rezu Construction, College Road, Kurigram.
|
42.259
|
05/06/2014
|
30/09/2016
|
100
|
06/01/2019
|
|
10
|
RDRIIP/KUR/
UN-147
|
Improvement of Tremohoni - Jotinerhat Road (Ch. 3658-3933m & 4490-5215m).
|
1.0000
|
51.858
|
M/S Zahurul Haque Dulal Ghoshpara, Kurigram.
|
51.858
|
18/08/2015
|
30/11/2016
|
100
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
UN-016
|
Improvement of H/O Solaiman (Khalilganj Bazar)-Halabot via Belgacha UP Road (Ch. 2940-3848m, Effective Length = 900.60m).
|
0.9000
|
54.516
|
M/S Khairul Enterprise, Trimohoni Bazar, Kurigram.
|
54.516
|
22/06/2014
|
31/03/2015
|
100
|
06/01/2019
|
|
|
5
|
Nageswari
|
1
|
RDRIIP/KUR/
LCS-10
|
KzwoMÖvg †Rjvi bv‡Mk^ix Dc‡Rjvaxb 14wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
265.3166
|
159.190
|
LCS
|
159.190
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
BR-031
|
Construction of 22.00m Long RCC Girder Bridge on Kamarpara - Shapkhawa Road at Ch. 180m.
|
22.0000
|
89.653
|
Md. Nuruzzaman. Kanthalbari, Kurigram.
|
89.653
|
15/12/2016
|
25/12/2017
|
100
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
BR-010
|
Construction of 72.00m Long RCC Girder Bridge on Berubari Girls GPS - Gachpari WAPDA Bazar raod at Ch. 1300.00m.
|
72.0000
|
400.132
|
M/S Shondi Traders, Belkuchi, Sirajgonj.
|
400.132
|
11/07/2016
|
31/10/2017
|
67
|
06/01/2019
|
|
4
|
RDRIIP/KUR/ CUL-003
|
Construction of 2 x 4.50m x 4.00m RCC box culvert on Kalarchar Asrayan (Kalarchar Bazar) - Astashirghat road at Ch. 3900m
|
9.0000
|
26.633
|
M/S Hamid Traders, Dadamore, Kurigram.
|
26.633
|
16/07/2015
|
25/01/2016
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/ CUL-002
|
Construction of 2 x 4.50m x 4.00m RCC box culvert on Kalarchar Asrayan (Kalarchar Bazar) - Astashirghat road at Ch. 2150m
|
9.0000
|
26.633
|
M/S Hamid Traders, Dadamore, Kurigram.
|
26.633
|
16/07/2015
|
25/01/2015
|
100
|
06/01/2019
|
|
6
|
RDRIIP/KUR/ CUL-001
|
Construction of 2 x 4.50m x 4.00m RCC box culvert on Kalarchar Asrayan (Kalarchar Bazar) - Astashirghat road at Ch. 1100m
|
9.0000
|
26.633
|
M/S Hamid Traders, Dadamore, Kurigram.
|
26.633
|
16/07/2015
|
25/01/2016
|
100
|
06/01/2019
|
|
7
|
RDRIIP/KUR/ CUL-005
|
Construction of 3 x 4.50m x 4.00m RCC box culvert on Narayanpur UP – Narayanpur Nutun Hat (Aualer Ghat) road at Ch. 2800m
|
13.5000
|
34.688
|
M/S Aroshi Construction
Nageswari, Kurigram.
|
34.688
|
21/06/2015
|
31/12/2015
|
100
|
06/01/2019
|
|
8
|
RDRIIP/KUR/ CUL-004
|
Construction of 3 x 4.50m x 4.00m RCC box culvert on Narayanpur UP – Narayanpur Nutun Hat (Aualer Ghat) road at Ch. 1250m
|
13.5000
|
34.688
|
M/S Hamid Traders, Dadamore, Kurigram.
|
34.688
|
16/07/2015
|
25/01/2016
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
VR-386
|
Improvement of Gachpari Madrasha - Bamondanga GPS Road (Ch. 00-800m).
|
0.8000
|
51.328
|
A S Rejaul Karim. Kurigram.
|
51.328
|
02/11/2016
|
11/11/2017
|
0
|
06/01/2019
|
|
10
|
RDRIIP/KUR/
VR-313
|
Improvement of Beruabri Girls Primary School - Thakurer more road (Ch. 00-635m).
|
0.6350
|
45.914
|
M/S Md. Mahabubar Rahman, Ghoshpara, Kurigram.
|
45.914
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
VR-271
|
Improvement of Masurkhamar - Sapkhawa Dakhil Madrasha Road (Ch. 00-700m).
|
0.7000
|
43.068
|
Aroshi Construction, Nageswari, Kurigram.
|
43.068
|
28/04/2016
|
15/06/2017
|
40
|
06/01/2019
|
|
12
|
RDRIIP/KUR/
VR-270
|
Improvement of Chowdhuripara more - Abdul Baten Secretary house via Baparitary School Road (Ch. 00-1000m).
|
1.0000
|
67.028
|
Md. Redwanul Haque, Kathalbari, Kurigram.
|
67.028
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
13
|
RDRIIP/KUR/
VR-130
|
Improvement of Kachakata Degree College more (Sankosh Bridge) – Kachakata BOP Camp via Kachakata Bazar Road (00-1808m).
|
1.8080
|
98.887
|
M/S Hamid Traders, Dadamore, Kurigram.
|
98.887
|
21/06/2015
|
30/12/2016
|
100
|
06/01/2019
|
|
14
|
RDRIIP/KUR/
VR-050
|
Improvement of Mokhter Kuti Mosque – Jolapara Road (Ch. 00-600m).
|
0.6000
|
33.842
|
M/S Hamid Traders, Dadamore, Kurigram.
|
33.842
|
11/12/2014
|
20/06/2015
|
100
|
06/01/2019
|
|
15
|
RDRIIP/KUR/UN-290
|
Improvement of Gagla GC - Santospur UP via Mokteerkuti Road (Ch. 2200-3546m).
|
1.3460
|
91.703
|
Md. Nowroj Hossain, Guptapara, Rangpur.
|
91.703
|
15/12/2016
|
25/12/2017
|
100
|
06/01/2019
|
|
16
|
RDRIIP/KUR/UN-264
|
Improvement of Kachakata UP - Gabtolla bazar road (Ch. 00-2000m).
|
2.0000
|
120.526
|
Aroshi Construction, Nageswari, Kurigram.
|
120.526
|
02/11/2016
|
11/11/2017
|
100
|
06/01/2019
|
|
17
|
RDRIIP/KUR/
UN-243
|
Improvement of Bhiterbond UZR - Kaligonj UP Office road (Ch. 00-665m).
|
0.6650
|
51.111
|
M/S Fahim Traders, R, K Road, Kurigram.
|
51.111
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
18
|
RDRIIP/KUR/
UN-242
|
Improvement of Pairadanga Bazar - Hasnabad UP Office road (Ch. 1770-2770m).
|
1.0000
|
68.390
|
Md. Nuruzzaman, Kanthalbari, Kurigram.
|
68.390
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
19
|
RDRIIP/KUR/
UN-025
|
Improvement of Nageswari GC – Kachakata Bazar Road (Ch.12100-12600m) (Effective Length = 453m).
|
0.4530
|
24.447
|
M/S Nuruzzaman, Kathalbari, Kurigram.
|
24.447
|
11/12/2014
|
20/05/2015
|
100
|
06/01/2019
|
|
20
|
RDRIIP/KUR/
UN-024
|
Improvement of Hasnabad UP - Pakhirhat Road (Ch.1000-2185m).
|
1.1850
|
63.564
|
M/S Hamid Traders, Dadamore, Kurigram.
|
63.564
|
11/12/2014
|
20/06/2015
|
100
|
06/01/2019
|
|
21
|
RDRIIP/KUR/
UN-020
|
Improvement of Bhitorband UP – Chandipur Bazar Road (Ch.1300-1921m).
|
0.6210
|
35.503
|
M/S Hamid Traders, Dadamore, Kurigram.
|
35.503
|
11/12/2014
|
31/12/2016
|
100
|
06/01/2019
|
|
22
|
RDRIIP/KUR/UZ-089
|
Improvement of Gagla Bazar - Dighirpar via Chilakhana Road (Ch. 4800-6790m).
|
1.9900
|
106.957
|
M/S Belal Construction, Kalilgonj, Kurigram.
|
106.957
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
|
6
|
Rajarhat
|
1
|
RDRIIP/KUR/
LCS-
|
KzwoMÖvg †Rjvi ivRvinvU Dc‡Rjvaxb 7wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
133.8750
|
80.325
|
LCS
|
80.325
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
VR-551
|
Improvement of Nazimkhan UP Patowari bari Pukurpar - H/O Nurul Haque at Umarmojid UP at Taluk Subal Mouja Road. (Ch. 00-1185m).
|
1.1850
|
81.987
|
M/s. Fahim Traders, R.K Road, Kurigram
|
81.987
|
24/07/2017
|
23/07/2018
|
100
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
VR-499
|
Improvement of Kadmertol Panchmatha (Sukdeb) - Nazimkhan - Ratigram Road via H/O Gopal Dillar Road (Ch. 00-500m).
|
0.5000
|
33.056
|
M/S Sutapa Construction, Rajarhat, Kurigram.
|
33.056
|
11/07/2017
|
20/04/2018
|
100
|
06/01/2019
|
|
4
|
RDRIIP/KUR/
VR-498
|
Improvement of Shekdev Madrasha - Sonalurkutee via Kalirhat (Ch. 00-500m).
|
0.5000
|
33.581
|
M/S Sutapa Construction, Rajarhat, Kurigram.
|
33.581
|
11/07/2017
|
20/04/2018
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
VR-470
|
Improvement of Kanuram-Nafadanga Rajarhat Road (Ch. 00-1000m).
|
1.0000
|
68.074
|
M/S K M Abu Bakar, College Road, Kurigram.
|
68.074
|
11/07/2017
|
20/07/2018
|
100
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
VR-462
|
Improvement of Paschim Debattar Mukbul Miah House - RHD - Advocate Motiar Miah House Road (Ch. 00-1080m).
|
1.0800
|
83.843
|
Md. Abdul Mottaleb, Rajarhat, Kurigram.
|
83.843
|
11/07/2017
|
20/07/2018
|
0
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
VR-461
|
Improvement of Basrah Madrasha - Jarijar - Tutapaikar Bazar (Basrah - Jarijar via Unus Ali Hose ) Road (Ch. 00-1000m).
|
1.0000
|
63.474
|
M/S Khairul Enterprise, RK Road, Kurigram.
|
63.474
|
11/07/2017
|
20/07/2018
|
100
|
06/01/2019
|
|
8
|
RDRIIP/KUR/
VR-460
|
Improvement of Forkerhat Tograihat UZR - Forkerhat Rajarhat UZR via Gumaru Vimsitola GPS Road (Ch. 00-660m).
|
0.6600
|
43.500
|
M/S Hajrat Ali, Horikesh, Kurigram.
|
43.500
|
11/07/2017
|
20/04/2018
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
VR-388
|
Improvement of Rajarhat Shantinagore - Upazila road via Mohilla Colleage Road (Ch. 00-1000m).
|
1.0000
|
61.811
|
Md. Abdul Mottaleb, Rajarhat, Kurigram.
|
61.811
|
02/11/2016
|
11/11/2017
|
100
|
06/01/2019
|
|
10
|
RDRIIP/KUR/
VR-326
|
Improvement of Mokterpara GPS - Jatinerhat road (Ch. 00-500m).
|
0.5000
|
29.071
|
M/S Sutapa Construction, Rajarhat, Kurigram.
|
29.071
|
18/08/2016
|
28/05/2017
|
100
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
VR-325
|
Improvement of China Bazar - Sarishabarihat Road (China Bazar Char Gotia Sham Clinic via Sharisabari Monnaf Sharker Chaiman House Road) (Ch. 00-500m).
|
0.5000
|
27.713
|
M/S Sutapa Construction, Rajarhat, Kurigram.
|
27.713
|
18/08/2016
|
28/05/2017
|
100
|
06/01/2019
|
|
12
|
RDRIIP/KUR/
VR-311
|
Improvement of Kaykuri Madrasha - Choto Mohismuri via H/O Dr. Baten Road (Ch. 1480-1980m).
|
0.5000
|
29.947
|
M/S Zahurul Haque Dulal, Ghoshpara, Kurigram.
|
29.947
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
13
|
RDRIIP/KUR/
VR-257
|
Improvement of Paschim Debattar Mouza - Burirhat via Bancharhat Road (Ch. 00-500m).
|
0.5000
|
31.708
|
M/S Khariul Enterprise
Trimohoni Bazar,
Kurigram.
|
31.708
|
29/03/2016
|
09/10/2016
|
100
|
06/01/2019
|
|
14
|
RDRIIP/KUR/
VR-144
|
Improvement of Ghorialdhanga High School - Dina Mouza Road (Ch. 00-500m).
|
0.5000
|
26.125
|
M/S Fahim Traders
PK Road, Kurigram.
|
26.125
|
16/07/2015
|
25/01/2016
|
100
|
06/01/2019
|
|
15
|
RDRIIP/KUR/
VR-143
|
Improvement of Paddantari - Ketatari Road (Ch. 00-500m).
|
0.5000
|
28.863
|
M/S Shaim Enterprise Puraton Registreepara, Kurigram.
|
28.863
|
16/07/2015
|
31/01/2017
|
100
|
06/01/2019
|
|
16
|
RDRIIP/KUR/
VR-142
|
Improvement of Boddyar Bazar - Nefardarga Road - Paikpara GPS via Sollardolla Road (Ch. 00-500m).
|
0.5000
|
29.386
|
M/S Zahurul Haque Dulal, Ghoshpara, Kurigram.
|
29.386
|
16/07/2016
|
30/11/2016
|
100
|
06/01/2019
|
|
17
|
RDRIIP/KUR/
UN-226
|
Improvement of Millerpar Bazar - Biddananda UP office via Sukdeb Road (Ch. 1000-1426m, 1855-2228m & 2889-4780m).
|
2.5000
|
157.085
|
Md. Abdul Mottaleb, Rajarhat, Kurigram.
|
157.085
|
29/03/2016
|
09/04/2017
|
70
|
06/01/2019
|
|
18
|
RDRIIP/KUR/
UN-148
|
Improvement of Rajarhat - Lalmonir Hat Border (R &H) (Ch. 4800-6300m).
|
1.5000
|
78.920
|
Md. Abdul Mottaleb, Rajarhat, Kurigram.
|
78.920
|
18/08/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
19
|
RDRIIP/KUR/
UN-108
|
Improvement of Chakirpashar UP office - Nakkatihat (Ch. 00-1250m).
|
1.2500
|
66.691
|
M/S Basundhara, R. K. Road, Kurigram.
|
66.691
|
16/07/2015
|
31/01/2017
|
100
|
06/01/2019
|
|
20
|
RDRIIP/KUR/
UN-107
|
Improvement of Rajarhat - Lalmonir Hat Border (R&H) (Ch. 3300-4800m).
|
1.5000
|
95.524
|
M/S Fahim Traders, R. K. Road, Kurigram.
|
95.524
|
16/07/2015
|
25/04/2015
|
100
|
06/01/2019
|
|
|
7
|
Rajibpur
|
1
|
RDRIIP/KUR/
LCS-08
|
KzwoMÖvg †Rjvi ivwRecyi Dc‡Rjvaxb 3wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
61.6333
|
36.980
|
LCS
|
36.980
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
VR-464
|
Improvement of Barobar P/School - Amkhoua Ghat Road (Ch. 1000-1500m).
|
0.5000
|
27.668
|
M/S K M Abu Bakar, College Road , Kurigram.
|
27.668
|
11/07/2017
|
20/04/2018
|
100
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
VR-310
|
Improvement of Baliamari GC– UZR No. 2001 near sluice gate via Miapara Road (Ch. 1000-1500m).
|
0.5000
|
29.001
|
M/S Akash Traders, Rajibpur, Kurigram.
|
29.001
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
4
|
RDRIIP/KUR/
VR-309
|
Improvement of UZR No. 2003 at Shimultala – UNR No. 3010 near Amir Chand house via Eatimkhana Non GPS Road (Ch. 00-500m).
|
0.5000
|
38.473
|
M/S Murad Traders, Khalilgonj, Kurigram.
|
38.473
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
VR-123
|
Improvement of UZR No. 2002 VR No. 4033 near the house of Goni via Akbar Hossain Chairman House Road (Ch. 450-950m).
|
0.5000
|
46.774
|
M/S Akash Traders
Rajibpur, Kurigram.
|
46.774
|
21/06/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
UN-259
|
Improvement of Mohongonj UP - Kawniarchar Bazar Road (Ch. 1640-3540m).
|
1.9000
|
121.155
|
M/S Md. Mahabubar Rahman, Ghoshpara, Kurigram.
|
121.155
|
01/08/2016
|
30/09/2017
|
100
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
UN-109
|
Improvement of Road from Baliamari GC (Near House of Insan Ali)-Rajibpur UP (S. Mill More) Road (Ch. 3310-3950m).
|
0.6400
|
37.910
|
M/S K.M Abu Bakar, Collage road, Kirigram.
|
37.910
|
01/06/2015
|
10/12/2015
|
100
|
06/01/2019
|
|
8
|
RDRIIP/KUR/
UN-103
|
Improvement of Baliamari GC (Near House of Insan Ali) – Rajibpur UP Road (S.Mill More) Road (Ch. 2260-3310m).
|
1.0500
|
66.834
|
M/S Akash Traders, Rajibpur, Kurigram.
|
66.834
|
16/07/2015
|
30/09/2016
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
UN-017
|
Improvement of Baliamari GC (Near House of Insan Ali) – Rajibpur UP Road (S.Mill More) Road (Ch. 4315-5315m).
|
1.0000
|
54.034
|
M/S Akash Traders, Rajibpur, Kurigram.
|
54.034
|
22/06/2014
|
31/03/2015
|
100
|
06/01/2019
|
|
|
8
|
Rowmari
|
1
|
RDRIIP/KUR/
VR-463
|
Improvement of Jadurchar Notungram house of Kazimuddin - North side house of Rahim Bosak (Ch. 00-1000m).
|
1.0000
|
55.017
|
M/S K M Abu Bakar, College Road , Kurigram.
|
55.017
|
11/07/2017
|
20/07/2018
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
VR-440
|
Improvement of R&H Road (Near LTB) - H/O Joynal Chairman Road (Ch. 00-800m).
|
0.8000
|
54.781
|
M/S Akash Traders. Rajibpur, Kurigram.
|
54.781
|
11/07/2017
|
20/07/2018
|
100
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
VR-333
|
Improvement of Ulipur border - Kazaikata regulator road Road (Ch. 00-500m).
|
0.5000
|
26.073
|
Shohidul Islam, Rowmari, Kurigram.
|
26.073
|
18/08/2016
|
28/05/2017
|
70
|
06/01/2019
|
|
4
|
RDRIIP/KUR/
VR-332
|
Improvement of Khedaimari - Ghugumari via Pakhiura more Road (Ch. 1000-1500m).
|
0.5000
|
26.073
|
Shohidul Islam, Rowmari, Kurigram.
|
26.073
|
18/08/2016
|
28/05/2017
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
VR-331
|
Improvement of Boalmari GPS School - Shoulmari Road (Ch. 1000-1800m).
|
0.8000
|
49.913
|
Shamim Enterprise, Puraton Registreepara, Kurigram.
|
49.913
|
18/08/2016
|
28/08/2017
|
70
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
VR-141
|
Improvement of Pakhiura Kheyaghat - Shonapur Road (Ch. 1720-2220m).
|
0.5000
|
28.063
|
M/S Sughondha Builders, Dadamore, Kurigram.
|
28.063
|
16/07/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
VR-129
|
Improvement of Char Shoulmari hat - Kazikata Hat Road (Ch. 00-500m).
|
0.5000
|
26.398
|
M/S Khariul Kabir Rana, Rangpur
|
26.398
|
21/06/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
8
|
RDRIIP/KUR/
LCS-09
|
KzwoMÖvg †Rjvi ‡iÅ gvix Dc‡Rjvaxb 6wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
117.1833
|
70.310
|
LCS
|
70.310
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
BR-015
|
Construction of 75.00m long RCC Girder bridge on New Shoulmari River Ghat - Char Boalmari road Ch.1000m.
|
72.0000
|
318.264
|
IB-NUS (JV), Islampur, Jamalpur.
|
318.264
|
11/07/2016
|
31/10/2017
|
70
|
06/01/2019
|
|
10
|
RDRIIP/KUR/
BR-034
|
Construction of 51.00m Long RCC Girder Bridge on Rowmari H/Q - Faluarchar Ghat via Modabaparir ghat at Ch. 1456.
|
51.0000
|
247.918
|
Md. Abdul Hakim, Aditmari, Lalmonirhat.
|
247.918
|
11/07/2017
|
30/10/2018
|
98
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
UN-319
|
Improvement of Chatlakanda(Mater vita)-Tura road via Shoulmari Road. (Ch. 00-1000m).
|
1.0000
|
62.376
|
M/S Akash Traders. Rajibpur, Kurigram.
|
62.376
|
11/07/2017
|
20/07/2018
|
100
|
06/01/2019
|
|
12
|
RDRIIP/KUR/
UN-268
|
Improvement of Taluarchar Feeder road - Shoulmari UP Office Road (Ch. 1000-2000m).
|
1.0000
|
79.151
|
Shohidul Islam, Rowmari, Kurigram.
|
79.151
|
18/08/2016
|
28/08/2017
|
100
|
06/01/2019
|
|
13
|
RDRIIP/KUR/
UN-112
|
Improvement of Horindara gram FRB-Boraikandi via Takanigram Road Takan (Ch. 2150-3150m).
|
1.0000
|
65.620
|
M/S Khairul Enterprise, Trimohonibazar, Kurigram.
|
65.620
|
21/06/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
14
|
RDRIIP/KUR/
UN-111
|
Improvement of Horindara gram FRB-Boraikandi via Takanigram Road Takan (Ch. 1150-2150m).
|
1.0000
|
67.204
|
M/S Khairul Enterprise, Trimohonibazar, Kurigram.
|
67.204
|
21/06/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
15
|
RDRIIP/KUR/
UN-106
|
Improvement of Shoulmari UP (Boraikandi Bazar) - Pakhiuria Embt.Road (Ch. 1530-2530m).
|
1.0000
|
57.931
|
M/S Khairul Enterprise, Trimohonibazar, Kurigram.
|
57.931
|
16/07/2015
|
25/04/2016
|
100
|
06/01/2019
|
|
16
|
RDRIIP/KUR/
UN-018
|
Improvement of Kashiabari-Bakribeel Road (Ch. 1000-2000m).
|
1.0000
|
60.597
|
Shohidul Islam, Rowmari, Kurigram.
|
60.597
|
22/06/2014
|
31/03/2015
|
100
|
06/01/2019
|
|
17
|
RDRIIP/KUR/UZ-088
|
Improvement of Rowmari - Baliamari GC road via Chuliarchar (Rowmari Portion) Road (Ch. 7244-7694m).
|
0.4500
|
34.436
|
Shohidul Islam, Rowmari, Kurigram.
|
34.436
|
01/09/2016
|
15/09/2017
|
100
|
06/01/2019
|
|
18
|
RDRIIP/KUR/UZ-071
|
Improvement of Rowmari - Baliamari GC road via Chuliarchar (Rowmari Portion) Road (Ch. 5930-7244m).
|
1.3140
|
104.567
|
M/S K, M Abu Bakar College Road, Kurigram.
|
104.567
|
01/10/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
|
9
|
Ulipur
|
1
|
RDRIIP/KUR/
LCS-06
|
KzwoMÖvg †Rjvi Dwjcyi Dc‡Rjvaxb 13wU BDwbq‡bi MÖvgxY `yt¯â€™ gwnjv‡`i Øviv moK iÿYv‡eÿY KvR|
|
246.8000
|
148.080
|
LCS
|
148.080
|
01/07/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
2
|
RDRIIP/KUR/
BR-018
|
Construction of 57.00m Long RCC Girder Bridge on Janotar Hat - Buraburir Hat at ch. 1500m.
|
57.0000
|
311.938
|
Md. Abdul Hakim, Aditmari, Lalmonirhat.
|
311.938
|
01/08/2016
|
30/06/2017
|
95
|
06/01/2019
|
|
3
|
RDRIIP/KUR/
VR-469
|
Improvement of Gunaigach UP office - Nagrakura Ghat Road (Ch. 3600-4000m).
|
0.4000
|
23.118
|
Md. Rezaul Karim, Palashbari, Kurigram.
|
23.118
|
11/07/2017
|
20/04/2018
|
100
|
06/01/2019
|
|
4
|
RDRIIP/KUR/
VR-468
|
Improvement of KC Rd(Minabazar) - Nazimkhan GC via Pandul UP Road (Ch. 4000-4500m).
|
0.5000
|
37.882
|
M/S Fahim Traders, PK Road, Kurigram.
|
37.882
|
11/07/2017
|
20/04/2018
|
100
|
06/01/2019
|
|
5
|
RDRIIP/KUR/
VR-467
|
Improvement of Ulipur - Anantapur UZR (Khudi Mango Tree) - Dhamsreeni UP Office Road (Ch. 1500-2000m).
|
0.5000
|
33.304
|
M/S Sutapa Construction, Rajarhat, Kurigram.
|
33.304
|
11/07/2017
|
20/04/2018
|
92
|
06/01/2019
|
|
6
|
RDRIIP/KUR/
VR-328
|
Improvement of Md. Hibur Bari - Abdul Jabber Bapari bari Road (Ch. 00-420m).
|
0.4200
|
34.930
|
M/S Jewel Traders, Krishnopur, Kurigram.
|
34.930
|
18/08/2016
|
28/05/2017
|
100
|
06/01/2019
|
|
7
|
RDRIIP/KUR/
VR-266
|
Improvement of KC Road (Bottala) - Modhopara Primary School via Hazir Hat Road (Ch. 00-500m).
|
0.5000
|
29.281
|
M/S Shamim Enterprise, Kurigram.
|
29.281
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
8
|
RDRIIP/KUR/
VR-265
|
Improvement of Latif Razia Madrasha - Madhupur Primary School Road (Ch. 00-500m).
|
0.5000
|
32.773
|
Md. Khairul Kabir Rana, Guptapara, Rangpur.
|
32.773
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
9
|
RDRIIP/KUR/
VR-127
|
Improvement of Nazimkhan UP-Thutapaikor hat. Road (Ch. 00-500m).
|
0.5000
|
25.290
|
M/S Hamid Traders, Dadamore, Kurigram.
|
25.290
|
21/06/2015
|
31/12/2016
|
100
|
06/01/2019
|
|
10
|
RDRIIP/KUR/
VR-126
|
Improvement of Ulipur Nazimkhan GC Road Gazirdargah - Nazimkhan Thetarai Road (Ch. 1200-1700m).
|
0.5000
|
32.632
|
M/S Hamid Traders, Dadamore, Kurigram.
|
32.632
|
21/06/2015
|
15/12/2016
|
100
|
06/01/2019
|
|
11
|
RDRIIP/KUR/
VR-044
|
Improvement of Kadamtola Hat - Nazimkhan GC & UP Road (Ch. 1000-1800m).
|
0.8000
|
44.959
|
M/S Basundhara, R, K road, Kurigram.
|
44.959
|
23/07/2015
|
30/07/2015
|
100
|
06/01/2019
|
|
12
|
RDRIIP/KUR/
UN-308
|
Improvement of Pandul UP Office - Forker Hat GC Road. (Ch. 00-500m).
|
0.5000
|
38.229
|
M/S M M Traders, Ulipur, Kurigram.
|
38.229
|
11/07/2017
|
20/04/2018
|
20
|
06/01/2019
|
|
13
|
RDRIIP/KUR/UN-266
|
Improvement of Thetraihat UP - Shatdargahat Road (Ch. 00-1000m).
|
1.0000
|
64.001
|
M/S R N Traders, Krishnopur, Kurigram.
|
64.001
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
14
|
RDRIIP/KUR/UN-265
|
Improvement of Thetraihat UP - Nagrakurahat Road (Ch. 00-1000m).
|
1.0000
|
64.594
|
M/S Hamid Traders, Dadamore, Kurigram.
|
64.594
|
01/08/2016
|
30/06/2017
|
100
|
06/01/2019
|
|
15
|
RDRIIP/KUR/UN-236
|
Improvement of Durgapur UP - Buraburi Hat Road (Ch. 100-1100m).
|
1.0000
|
69.514
|
M/S Hamid Traders, Dadamore, Kurigram.
|
69.514
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
16
|
RDRIIP/KUR/UN-235
|
Improvement of KC Road at Maltibari Bazar -Dharanibari UP office (Majbil hat) Road (Ch. 00-1000m).
|
1.0000
|
59.069
|
M/S Sunflower Trade Inter, Rampura, Kurigram.
|
59.069
|
28/04/2016
|
07/05/2017
|
70
|
06/01/2019
|
|
17
|
RDRIIP/KUR/UN-234
|
Improvement of Mina Bazar - Pandul UP Office Road (Ch. 00-1000m).
|
1.0000
|
68.744
|
M/S Hamid Traders, Dadamore, Kurigram.
|
68.744
|
28/04/2016
|
07/05/2017
|
100
|
06/01/2019
|
|
18
|
RDRIIP/KUR/
UN-136
|
Improvement of Tobokpur UP- Barua Tobokpur Hat Road (Ch. 00-1000m).
|
1.0000
|
53.159
|
M/S Hamid Traders, Dadamore, Kurigram.
|
53.159
|
18/08/2015
|
30/06/2017
|
35
|
06/01/2019
|
|
19
|
RDRIIP/KUR/
UN-135
|
Improvement of Tobakpur UP - Adarsha Bazar Road (Ch. 00-1000m).
|
1.0000
|
54.059
|
M/S Hamid Traders, Dadamore, Kurigram.
|
54.059
|
18/08/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
20
|
RDRIIP/KUR/
UN-104
|
Improvement of Nazimkhan GC - Thatrai UP via Daldalia UP Road (Ch. 1100-2176m).
|
1.0760
|
59.170
|
M/S Nowroj Hossain, Guptapara, Rangpur.
|
59.170
|
01/06/2015
|
30/09/2016
|
100
|
06/01/2019
|
|
21
|
RDRIIP/KUR/
UZ-055
|
Improvement of Durgapur Bazar - Nazimkhan GC via Pandul UP & Khochabari hat Road (Ch. 5400-6400m).
|
1.0000
|
75.340
|
M/S Zahurul Haque Dulal Ghoshpara, Kurigram.
|
75.340
|
21/06/2015
|
31/01/2017
|
100
|
06/01/2019
|
|
22
|
RDRIIP/KUR/
UZ-054
|
Improvement of Durgapur Bazar - Nazimkhan GC via Pandul UP & Khochabari hat Road (Ch. 4400-5400m).
|
1.0000
|
69.568
|
Md. Nuruzzaman, Khanthalbari, Kurigram.
|
69.568
|
21/06/2015
|
30/09/2016
|
100
|
06/01/2019
|
|
23
|
RDRIIP/KUR/
UZ-053
|
Improvement of Ulipur M.S.H/S - Ulipur Mondaler hat GC Road (Ch. 6313-7323m, Effective Length = 1000m).
|
1.0000
|
75.012
|
M/S Zahurul Haque Dulal Ghoshpara, Kurigram.
|
75.012
|
21/06/2015
|
30/06/2017
|
100
|
06/01/2019
|
|
24
|
RDRIIP/KUR/
UZ-052
|
Improvement of Ulipur M.S.H/S - Ulipur Mondaler hat GC Road (Ch. 5300-6313m, Effective Length = 1000m).
|
1.0000
|
70.872
|
M/S Sun Flowers Trade
International, Bonosshri,
Rampura, Dhaka.
|
70.872
|
21/06/2015
|
06/04/2016
|
100
|
06/01/2019
|
|
|
Total :
|
1898.2404 (Km)
|
9108.52 (Lac)
|
9108.52 (Lac)
|
|
|
|
|
|
|