Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bhurungamari
1 SP15262 Char-Bhurugamari Subproject: Re-sectioning of Embankment at (Ch.0+000 km to Ch. 8+100km) 8.1000 112.040 LCS 112.040 20 21/08/2020 On going
2 Rowmari
1 SP25311 Dhanar-Char Subproject:Re-sectioning of Dhanar-Char of 8.814 km Embankment (Ch.0+546km to Ch. 9+360km) 8.8100 129.350 LCS 129.350 16/10/2019 100 21/08/2020 Completed.
Total : 16.9100 (Km) 241.39 (Lac) 241.39 (Lac)