SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Thakurgaon-s
1 PD CLBUURP, W-254 a) Const. of RCC Bridge on Shibganj GC-Choto Khochabari NWH via Fershadangi Road at Ch. 5280m 691.170 MR.Ram babu .Thakurgaon 691.170 01/03/2011 28/06/2013 100 31/03/2019
2 PD CLBUURP, W-254A b) Remaining Work for Const.of RCC Bridge on Shibganj GC-Choto Khochabari NWH via Fershadangi Road at Ch. 5280m. 616.300 M/S HORI RAM 616.300 11/07/2013 13/05/2014 100 31/03/2019
Total : 0.0000 (Km) 1307.47 (Lac) 1307.47 (Lac)