1
|
SP62028/Bazitpur DR Subproject
|
Re-excavation of Balokdia Sarder Barir Khal (Ch-0+000km to 1+900km) Re-excavation of Uttam Nagar Dasher Barir (Part-1) Khal (Ch-0+000km to 0+990km) Re-excavation of Uttam Nagar Dasher Barir (Part-2) Khal (Ch-0+000km to 1+235km) Re-excavation of Bajitpur Khal (Ch-0+000km to 2+300km) Re-excavation of Kalyankati Khal (Ch-0+000km to 1+860km) Re-excavation of Gagan Sailatala Khal (Ch-0+000km to 1+493km) Re-excavation of Shibaikati Grameen Bank Khal (Ch-0+000km to 3+300km) Re-excavation of Gagan Bazar Khal (Ch-0+000km to 3+115km) Re-excavation of Alokdia Chowkider Barir Khal (Ch-0+00km to 1+580km) Ref. Lined Section 22 Nos. On 9 Khals, And SP Identf. Signboard (2 nos.) Construction of WMCA office
|
|
157.960
|
OTM
|
157.960
|
13/01/2023
|
|
97
|
13/08/2024
|
Ongoing
|
|
2
|
SP46239/Kirtipasha Subproject
|
Re-exacavation of Badhakhali Khal (Ch-0+00km to 2+600km) Re-exacavation of Khardarbahar Khal (Ch-0+000km to 1+800km) Re-exacavation of Dumuria Khal (Ch-0+000km to 1+650km) Re-exacavation of Andir Khal (Ch-0+000km to 0+700km) Re-exacavation of Kamli Kanda Khal (Ch-0+000km to 0+560km) Ref. Lined Section 13 Nos. On 5 Khals, And SP Identf. Signboard (2 nos.) Construction of WMCA office building Sangkar Dhabal Khal re-xcavation (Ch:0.00m - 1600.00m) 2023-24 Uttar Basin Khal re-xcavation (Ch:0.00m - 700.00m) 2023-24 Khajura Branch Khal 1 re-xcavation (Ch:0.00m - 750.00m) 2023-24 Andir Khal re-xcavation (Ch:0.00m - 150.00m) 2023-24 Const. of 06 Nos. Ref. lined Section on 03 Khals and SP Area Indication Post 2 Nos. | 2023-24
|
|
93.768
|
OTM
|
93.768
|
29/05/2022
|
29/05/2022
|
79
|
13/08/2024
|
Ongoing
|
|
3
|
SP46235/Ashiar DR Subproject
|
Nur Muhammad Barir Khal Re-excavation(ch0.00-1800m) Talukdar Barir Khal Re-excavation(ch0.00-1200m) Noya Barir Khal Re-excavation(ch0.00-950m) Karim Shikdar Barir Khal Re-excavation(ch0.00-1750m) Gawchar Pali Khal Re-excavation(ch0.00-1500m) Reference Lined Section 10 Nos. On 5 Khals, And SP Identification Signboard (2 nos.) Construction of WMCA Office, Electrification Works and Furniture Supply
|
|
77.496
|
OTM
|
77.496
|
20/04/2021
|
30/04/2021
|
100
|
13/08/2024
|
Completed
|
|
4
|
SP44117/Deulkathi-Binnapara Subproject
|
Re-Excavation of Astakhan Majhibarir Khal (Ch.0+000 Km to 1+900 Km) Re-Excavation of Dewolkathi Berpasha Khal (Ch.0+000 Km to 3+200 Km) Re-Excavation of Binnapara Biler Khal (Ch.0+000 Km to 2+100 Km) Re-Excavation of Shudharam Branch Khal (Ch.0+000 Km to 0+900 Km) Const. of 11 Nos. Reference lined Section on 4 Khals, SP Identf. sign board 2 Nos. and SP Indication Post 2 Nos.
|
|
63.820
|
LCS
|
63.820
|
02/03/2023
|
28/05/2023
|
100
|
13/08/2024
|
Completed
|
|
5
|
SP44106/Sachilapur Subproject
|
Ref. Lined Section 11 Nos. On 6 Khals, And SP Identf. Signboard (2 nos.) Re-excavation of Bepari Barir Khal (Ch-0+00km to 2+450km) Re-excavation of Yousufdee Khal (Ch-0+000km to 1+300km) Re-excavation of Bepari Barir Branch Khal (Ch-0+000km to 0+600km) Re-excavation of Khan Barir Khal (Ch-0+000km to 0+400km) Re-excavation of Dattar Khal (Ch-0+000km to 0+350km) Re-excavation of Mafiruddin Khal (Ch-0+000km to 0+400km) Rehabilitation of WMCA office -
|
|
60.669
|
OTM
|
60.669
|
24/01/2023
|
30/05/2022
|
100
|
13/08/2024
|
Completed
|
|
6
|
SP44104/Sarengal Subproject
|
Ashutash Mazumdar Barir Khal Re-excavation (Ch: 0.00 - 2010 m) ChannuDev Barir Khal Re-excavation (Ch: 0.00 - 1700 m) Sheikh Mujibar Barir Khal Re-excavation (Ch: 0.00 - 650.00 m) Chatarji Barir Khal Re-excavation (Ch: 0.00 - 650.00 m) Kali Barir Khal Re-excavation (Ch: 0.00 - 600 m) Pakmahar GPS Khal Re-excavation (Ch: 0.00 - 650.00 m) Galaikhala Khal Re-excavation (Ch: 0.00 - 500.00 m) Mawlana Jahiruddin Khal Re-excavation (Ch: 0.00 - 300.00 m) Reference Lined Section (12 nos.) + SP Identification Signboard (2 nos.) Abdul Haque Talukdar Barir Khal re-xcavation (Ch:0.00m - 1260.00m) 2023-24 Badal Khan Barir Khal re-xcavation (Ch:0.00m - 670.00m) 2023-24 Masud Khan Barir Khal re-xcavation (Ch:0.00m - 650.00m) 2023-24 Mir Adbul Barir Khal re-xcavation (Ch:0.00m - 400.00m) 2023-24 Sarengal Madrasha Khal re-xcavation (Ch:0.00m - 325.00m) 2023-24 Mridha Barir Khal re-xcavation (Ch:0.00m - 315.00m) 2023-24 Const. of 07 Nos. Ref. lined Section on 06 Khals, SP Identf. sign board 2, SP Area Indication Post 2 Nos. | 2023-24
|
|
99.393
|
LCS
|
99.393
|
25/01/2021
|
26/04/2021
|
86
|
13/08/2024
|
Ongoing
|
|
7
|
SP44077/Saorakathi Subproject
|
Construction of 9 RCC reference-line sections in 4 canals, and SP Signboard Re-excavation of Ramzankathi Napitbari khal
(Ch: 0.00m to 2495m) Re-excavation of Nur Mohammad Shikdarbari khal
(Ch: 0.00m to 1910m) Re-excavation of Haoladarbarir khal
(Ch: 0.00m to 1200m) Re-excavation of Majed Mollikbarir khal
(Ch: 0.00m to 900m) Sharif Bari Khal re-xcavation (Ch:0.00m - 1590.00m) 2023-24 Shaiz Uddin Barir Khal re-xcavation (Ch:0.00m - 2310.00m) 2023-24 Abid Mulla Barir Khal re-xcavation (Ch:0.00m - 1450.00m) 2023-24 Jorapul Khal re-xcavation (Ch:0.00m - 850.00m) 2023-24 Gohuder Hat Khal re-xcavation (Ch:0.00m - 800.00m) 2023-24 Const. of 10 Nos. Ref. lined Section on 05 Khals, SP Identf. sign board 2, SP Area Indication Post 2 Nos. | 2023-24
|
|
116.004
|
LCS
|
116.004
|
25/04/2023
|
28/05/2023
|
77
|
13/08/2024
|
Ongoing
|
|
8
|
SP22002/Nabogram Subproject
|
Betora khal re-excavation (Ch.00-1500m) Rampura khal re-excavation (Ch.00-3000m) Napitkhali khal re-excavation (Ch.00-2300m) Gudighata khal re-excavation (Ch.00-600m) Referenced line section 9 Nos. Bamboo bridge 9 Nos. Ganginar Khal re-xcavation (Ch:0.00m - 3100.00m) 2023-24 Const. of 03 Nos. Ref. lined Section on 01 Khal, SP Identf. sign board 2, SP Area Indication Post 2 Nos. | 2023-24
|
|
105.206
|
LCS
|
105.206
|
26/03/2024
|
30/04/2019
|
87
|
13/08/2024
|
Ongoing
|
|
9
|
SP15236/Natullabad DR Subproject
|
Shah Bangol khal Re-excavation(ch.00-1500m) Latimsar khal Re-excavation(ch.00-1350m) Hazi Barir khal Re-excavation(ch.00-1800m) Khalifa Barir khal Re-excavation(ch.00-650m) Sikder Barir khal Re-excavation(ch.00-425m) Referenced line section(9 Nos.) Bamboo bridge(9 Nos.) WMCA Office and Others
|
|
68.460
|
OTM
|
68.460
|
25/03/2019
|
30/04/2019
|
100
|
13/08/2024
|
Completed
|
|
10
|
SP15233/Ponabalia DR Subproject
|
Kalia Barir Khal re-excavation (Ch:0.00-2100m) Baritala Khal re-excavation (Ch:0.00-2350m) Nager Bari Khal re-excavation (Ch:0.00-1250m) Hazragati Khal re-excavation (Ch:0.00-2050m) Balmari Khal re-excavation (Ch:0.00-0.500m) Ichalia Khal re-excavation (Ch:0.00-1350m) Dhalu Fakirbari Khal re-excavation (Ch:0.00-2400m) Kulitala Khal re-excavation (Ch:0.00-2350m) Const. of 20 Nos. Ref. lined Section on 8 Khals, SP Identf. sign board 2, SP Indication Post 2 and Demarcation Post. 44 Nos.
|
|
120.845
|
LCS
|
120.845
|
21/12/2023
|
|
81
|
13/08/2024
|
Ongoing
|
|
11
|
SP14206/Basanda DR Subproject
|
Re-Excavation of NarBarir Khal (Ch.0+000 Km to 2+030 Km) Re-Excavation of Bousher Khal (Ch.0+700 Km to 2+025 Km) Re-Excavation of Bousher Branch Khal (Ch.0+000 Km to 0+600 Km) Re-Excavation of Chawpala Khal (Ch.0+000 Km to 1+330 Km) Re-Excavation of Raja Miar Khal (Ch.0+000 Km to 1+790 Km) Const. of 10 Nos. Ref. lined Section on 5 Khals, SP Identf. sign board 2 and SP Indication Post 2
|
|
62.158
|
LCS
|
62.158
|
25/04/2023
|
29/05/2023
|
100
|
13/08/2024
|
Completed
|
|
12
|
SP13059/Binoykathi DR Subproject
|
Khagutia khal re-excavation(ch.00-2460m) Dokkhin Manpasa khondoker barir khal re-excavation(ch.00-18500m) Khagutia Majhibarir khal re-excavation(ch.00-650m) Bishnudia Hawladar barir khal re-excavation(ch.00-1000m) Referenced line section(8 Nos.) Bamboo bridge(7 Nos.)
|
|
60.539
|
LCS
|
60.539
|
28/02/2019
|
30/04/2019
|
100
|
13/08/2024
|
Completed
|
|
13
|
SP11009/Kafurkathi Khal DR Subproject
|
Poschim Kafurkathi rambala barir khal re-excavation(ch.00-1775m) Kafurkathi Sunil beparir khal re-excavation(ch.00-1650m) Sotodaskathi Sorojit Howladar barir khal re-excavation(ch.00-1516m) Poschim Kafurkathi majhi barir khal re-excavation(ch.00-350m) Referenced line section(7 Nos.) Bamboo bridge(7 Nos.) Construction of WMCA Office(12m X 6m), Electrification Works and Furniture Supply
|
|
120.726
|
OTM
|
120.726
|
26/04/2021
|
25/04/2019
|
100
|
13/08/2024
|
Completed
|