SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
|
1
|
Fulchari
|
|
1
|
PRO/GAI/SUN/RMP/19-20/ MW-113
|
1. Estimate of Wages for Rural road maintenance by LCS (Material & Wages) work on Erandabari U.P H/Q-Algarchar bazar at ch.1170-2250m.
2. Fulchari UP H/Q-Kalurpara kheya ghat via Parul govt. P/S at ch.00-2500m.
3. Purba Fulchari Notun Hat - Kheya ghat via Adarsa gram at ch.1170-2000m.
4. Pachim Khatiamary H/O Jalal Member-Gucha gram at ch.00-1000m.
5 Uttar khatiamari H/O Moksed- (H/O Jafor) Dhakin khatiamary at ch.00-950m.
|
6.3600
|
13.272
|
|
13.272
|
|
|
0
|
30/12/2020
|
LCS team formation on going, Estimate approved on 14-06-20
|
|
|
2
|
Gaibandha-s
|
|
1
|
PRO/GAI/SAD/UNR/20-21/W-136
|
Improvement of Bituminous carpeting Road on Pulbandhi Bazar-Ramchandrapur UP Office via Bloali UP office & Gonirjan Bridge Road at Ch.7627m-8057m Under Gaibandha Sadar Upazila, District Gaibandha. id 132243029
|
0.4300
|
42.389
|
MD. SHAHID RANA JV
|
42.389
|
30/11/2020
|
29/11/2021
|
100
|
28/09/2022
|
Final bill paid
|
|
2
|
PRO/GAI/GAI-S/UNR/18-19/W-06
|
Improvement of Bituminous carpeting Road on Pulbandhi Bazar-Ramchandrapur UP Office via Bloali UP office & Gonirjan Bridge Road at Ch.3600m-4150m & 4496m-7600m. including Costruction of 10 U- drain (.600mx0.625m) Pulbandhi Bazar-Ramchandrapur UP Office via Bloali UP office & Gonirjan Bridge Road at Ch.3660m, 3984m, 4030m, 4073m, 5197m, 6115m, 6280m, 6695m, 7525m & 7591m Under Gaibandha Sadar Upazila, District Gaibandha. id 132243029
|
3.6540
|
304.358
|
M/S Basundhara, Kurigram
|
304.358
|
11/05/2019
|
31/12/2020
|
100
|
28/09/2022
|
Final bill paid
|
|
3
|
PRO/GAI/SAD/UNR/
20-21/W-136
|
Improvement of Bituminous carpeting Road on Pulbandhi Bazar-Ramchandrapur UP Office via Bloali UP office & Gonirjan Bridge Road at Ch.7627m-8057m Under Gaibandha Sadar Upazila, District Gaibandha. id 132243029
|
0.4300
|
42.389
|
|
42.389
|
|
|
0
|
30/12/2020
|
Estimate Approved on 13-8-20
|
|
4
|
PRO/GAI/GAI-S/UNR/
18-19/W-06
|
Improvement of Bituminous carpeting Road on Pulbandhi Bazar-Ramchandrapur UP Office via Bloali UP office & Gonirjan Bridge Road at Ch.3600m-4150m & 4496m-7600m. including Costruction of 10 U- drain (.600mx0.625m) Pulbandhi Bazar-Ramchandrapur UP Office via Bloali UP office & Gonirjan Bridge Road at Ch.3660m, 3984m, 4030m, 4073m, 5197m, 6115m, 6280m, 6695m, 7525m & 7591m Under Gaibandha Sadar Upazila, District Gaibandha. id 132243029
|
3.6540
|
304.358
|
M/S Basundhara, Kurigram
|
304.358
|
11/05/2019
|
21/04/2020
|
60
|
30/12/2020
|
|
|
5
|
PRO/GAI/GAI_S/RMP/19-20/ MW-115
|
Estimate of Wages for Rural road maintenance by LCS (Material & Wages) work on Salam bazar- Balata bazar via Mouja malibari Eidgah at ch. 00-2500m
|
2.5000
|
36.393
|
|
36.393
|
|
|
0
|
30/12/2020
|
LCS team formation on going, Estimate approved on 14-06-20
|
|
6
|
PRO/GAI/SAD/VR/18-19/W-11
|
Improvement of Bituminous Carpeting Road on Ruper –Eslighat via Pramanik para Road at Ch.1500m-2980m including Costruction of 3 U- drain (0.600mX0.625m) at Ch.1280m,2300m,2640m. Under Gaibandha Sadar Upazila, District Gaibandha.
|
1.4800
|
218.475
|
RSL Enterprise, gaibandha
|
218.475
|
11/05/2019
|
21/04/2020
|
100
|
30/12/2020
|
Final Bill Paid
|
|
7
|
PRO/GAI /GAI-S/VR/18-19/W-08
|
Improvement of Bituminous Carpeting Road on Fulbari-Badiakhali hat Road At Ch0.00m-1623m. &2300m-3100m. including Costruction of 10 U- drain (0.600mx0.625m) Fulbari-Badiakhali hat Road atCh0.00m-1623m. &2300m-3100m. Under Gaibandha Sadar Upazila, District Gaibandha.
|
2.4230
|
168.313
|
Md. Abdul Latif Hakkani, Gaibandha
|
168.313
|
11/05/2019
|
24/03/2020
|
75
|
30/12/2020
|
XEN Issued letter to Contractor regarding Time Extension.
|
|
|
3
|
Sadullapur
|
|
1
|
PRO/GAI/SAG/UNR/20-21/W-135
|
Improvement of Bhangamora Bazar-School bazar – Padumshahor UP Road at Ch: 3526m-6386m Under Upazila:Saghata, District: Gaibandha.
|
2.8600
|
267.732
|
Md.Shamim Ahammed Mondal JV
|
267.732
|
29/11/2020
|
28/11/2021
|
100
|
28/09/2022
|
|
|
2
|
PRO/GAI/SAD/UNR/18-19/W-12
|
Improvement of Bituminous Road on Bhatgram U.P office-Nagbari Bazar via Burir Bazar Road at Ch. Ch.2627m-3627m. including Costruction of 2 Nos U-Drain 0.600mx0.625m ,at Ch.2768m,3110m and Costruction of 1 Nos (2.00mx2.00m)Cross Drainges Structure and Bhatgram U.P office-Nagbari Bazar via Burir Bazar Road at Ch. 3260.0mUnder Shdullapur, District Gaibandha.
|
1.0000
|
87.797
|
Md. Mahomudun Nobi, Pirganj, Rangpur
|
87.797
|
13/04/2019
|
08/03/2020
|
100
|
28/09/2022
|
Final Bill Paid
|
|
3
|
PRO/GAI/SAD/UNR/20-21/RW- 188
|
Rehabilitation of Bhatgram U.P Office - Nagbari Bazar via Burir Bazar Road at Ch: 00m-1000m. Under Shadullapur upazila, District: Gaibandha
|
1.0000
|
14.509
|
H. S. Enterprise
|
14.509
|
18/05/2021
|
17/05/2022
|
100
|
28/09/2022
|
|
|
4
|
PRO/GAI/SAD/UNR/20-21/RW- 186
|
Rehabilitation of Chandiapur bazar-Rahmatpur GC via Rasulpur bazar Road at Ch: 00m-1000m. Under Shadullapur upazila, District : Gaibandha
|
1.0000
|
22.713
|
H. S. Enterprise
|
22.713
|
18/05/2021
|
17/05/2022
|
100
|
28/09/2022
|
|
|
5
|
PRO/GAI/SAD/UNR/20-21/RW- 185
|
Rehabilitation of Moshbandhi-Mirpur Road at Ch: 4240m-5240m. Under Shadullapur upazila, District: Gaibandha
|
1.0000
|
19.133
|
H. S. Enterprise
|
19.133
|
18/05/2021
|
17/05/2022
|
100
|
28/09/2022
|
|
|
6
|
PRO/GAI/SAD/UNR/18-19/W-10
|
Improvement of Bituminous Carpeting Road on. Mohisbandi-Mirpur Road at Ch.1235m-3235. including Costruction of 1 Nos U-Drain 0.600mx0.625m Mohisbandi-Mirpur Road at Ch.2725.0m.Under Shdullapur, District Gaibandha.
|
2.0000
|
175.245
|
M/S SAJIN TRADERS JV
|
175.245
|
14/05/2019
|
21/03/2020
|
100
|
28/09/2022
|
Final bill paid
|
|
7
|
PRO/GAI/SAD/UNR/18-19/W-09
|
Improvement of Bituminous Carpeting Road on khorda Rasulpur-Chandiapur Road at Ch.0.00m-2000m. including Costruction of 7 Nos U-Drain khorda Rasulpur-Chandiapur Road at Ch.85m, 526m, 880m, 925m, 1048m, 1343m, & 1835m. and 1Nos (2.00x2.00) m Cross Drainges Structure at Ch.710.0m. Under Shdullapur, District Gaibandha.
|
2.0000
|
186.328
|
Md.Khademul Islam Jewel, Gaibandha
|
186.328
|
11/05/2019
|
15/09/2020
|
100
|
28/09/2022
|
Final bill paid
|
|
8
|
PRO/GAI/GAI-S/VR/18-19/W-07
|
Improvement of Dholvanga-Mohipur Bazar Road at Ch: 00m-1000m including Construction of 2 Nos (0.625x0.600) m U-Drain at Ch: 355m & 388m and 1x2.50mx2.00 m RCC Box Culvert at Ch: 330m Under Upazila:Sadullapur, District: Gaibandha.
|
1.0000
|
230.323
|
Md.Shoeb Hossain Mona, Gaibandha
|
230.323
|
09/06/2020
|
08/06/2021
|
20
|
30/12/2020
|
|
|
9
|
PRO/GAI/SAD/UNR/19-20/W- 72
|
Improvement of Naldanga GC-Ramzibon UP officeRoad at Ch: 1500m-2500m including Construction of 1Nos (0.625x0.600) m U-Drain Under Upazila:Sadullapur, District:Gaibandha.
|
1.0000
|
110.492
|
Md.Shoeb Hossain Mona, Gaibandha
|
110.492
|
09/06/2020
|
08/06/2021
|
20
|
30/12/2020
|
|
|
10
|
PRO/GAI/SAD/UNR/19-20/W- 68
|
Improvement of Bhatgram UP office –Jamalpur Bazar Road at Ch: 00m-2000m including Construction of 11 Nos (0.625x0.600) m U-Drain at Ch: 45m, 320m, 472m, 775m, 800m,1265m, 1360m, 1430m, 1550m, 1785m &1919m and 1x2.50mx2.00 m RCC Box Culvert on at Ch: 1275m Under Upazila:Sadullapur, District: Gaibandha
|
2.0000
|
97.526
|
|
97.526
|
28/05/2020
|
28/05/2021
|
20
|
30/12/2020
|
|
|
11
|
PRO/GAI/SAG/RMP/19-20/ MW-116
|
1. Estimate of Wages for Rural road maintenance by LCS (Material & Wages) work on Naldanga G.C.-Ramzibon U.P. office. Road at ch. 00-780m.
2. Idilpur U.P. office-Dhaperhat U.P. office road at ch. 00-2000m.
3. Khorda Rasulpur-chandiapur roadat ch. 00-1020m.
4. Bhatgram U.P office-Jamalpur Bazar at ch.00-2000m.
5 Chandiapur bazar-Rahmatpur GC via Rasulpur bazar at ch.00-2000m.
|
7.8000
|
23.741
|
|
23.741
|
|
|
0
|
30/12/2020
|
LCS team formation on going, Estimate approved on 14-06-20
|
|
12
|
PRO/GAI/SAG/VR/18-19/W-13
|
Improvement of Bituminous Road on Shdullapur Dhaperhat G.C road at Boxigonj Bazar toDhaperhat-Madarhat Road via Ambagan Road at Ch.0.00m-2480m. including Costruction of 11 Nos U-Drain 0.600mx0.625m at Ch.335m,720m,877m,1190m,1300m,1388m,1477m,1765m,1880m,1972m,&2226m. Under Shdullapur, District Gaibandha.
|
2.4800
|
77.644
|
Md. Abdul Latif Hakkani, Gaibandha
|
77.644
|
21/05/2019
|
02/05/2020
|
75
|
30/12/2020
|
|
|
|
4
|
Saghata
|
|
1
|
PRO/GAI/SAD/UNR/20-21/RW- 187
|
Rehabilitation of Idilpur U.P.office-Dhaperhat U.P.office Road at Ch: 00m-1020m. Under Shadullapur upazila, District: Gaibandha
|
1.0200
|
17.080
|
H. S. Enterprise
|
17.080
|
18/05/2021
|
17/05/2022
|
100
|
28/09/2022
|
|
|
2
|
PRO/GAI/SAD/UNR/19-20/W- 71
|
Improvement of Bhangamora Bazar-School bazar – Padumshahor UP Road at Ch: 3526m-6386m Under Upazila:Saghata, District: Gaibandha.
|
2.8600
|
191.651
|
|
191.651
|
|
|
0
|
30/12/2020
|
Estimate Approved on 13-8-20
|
|
3
|
PRO/GAI/SAG/RMP/19-20/ MW-117
|
1. Estimate of Wages for Rural road maintenance by LCS (Material & Wages) work on Dighal Kandi- Digholkandi H/O Sonaullah Mirja at ch.00-2700m.
2. Chakili H/O Vikku sarker - Folia Bazar road at ch. 00-1900m.
|
4.6000
|
32.101
|
|
32.101
|
|
|
0
|
30/12/2020
|
LCS team formation on going, Estimate approved on 14-06-20
|
|
4
|
PRO/GAI/GAI_S/RMP/19-20/ MW-114
|
Improvement of Bituminous Road on Bonarpara H/O Mozammel Huq –BonarparaH/O akbar Ali Road at ch.600m-2930m. including Costruction of 10 Nos U-Drain 0.600mx0.625m at Ch.673m,735m,816m,925m,1387m,1760m,1920m,1987m,2150m,2493m.and Costruction of 3 Nos Slope Drain at Ch.1496m, 1745m, 2075m, and Costruction of 3 Nos (2.00mx2.00m) Cross Drainges Structure on Bonarpara H/O Mozammel Huq –BonarparaH/O akbar Ali Roadat Ch.2395m,2590m, 2787m. Under Saghata, District Gaibandha.
|
2.3300
|
13.312
|
M/S SAJIN TRADERS JV
|
13.312
|
13/05/2019
|
25/03/2020
|
100
|
30/12/2020
|
Work Completed. XEN Issued letter to Contractor regarding Time Extension.
|
|
5
|
PRO/GAI/SAG/VR/18-19/W-14
|
Improvement of Bituminous Road on Gatia H/O Taibor Master-Chitholia H/O Mahatab Member Road at Ch.0.00m-800m. including Costruction of 4 Nos U-Drain 0.600mx0.625m at Ch20m,135m,290m,&700m Under Saghata, District Gaibandha.
|
0.8000
|
215.629
|
Md. Jakir Hossain, Gaibandha
|
215.629
|
21/04/2019
|
06/04/2020
|
100
|
30/12/2020
|
Final Bill Paid
|
|
|
5
|
Sundarganj
|
|
1
|
PRO/KUR/CHI/UNR/18-19/W-21
|
Estimate of Wages for Rural road maintenance by LCS (Material & Wages) work on Kapashia UP Office to Kashim Bazar- WAPDA Embankment via H/O Nesab Chairman (Kajir Char Ahammed Nagar Bazar) road, at Ch. 00-2300m.
|
2.3000
|
41.590
|
|
41.590
|
|
|
0
|
30/12/2020
|
LCS team formation on going, Estimate approved on 14-06-20
|
|
|
Total :
|
59.9810 (Km)
|
2954.49 (Lac)
|
2954.49 (Lac)
|
|
|
|
|
|
|
|