SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Golapganj
1 PD/CLBUURP/W-295A b) Remaining work for Const.of RCC bridge on Rakuarbazar (Badepasha UP)-Shantir bazar – Supatak Road at Ch. 3700m. over Boradal River. 212.900 M/s. Raj Construction 212.900 30/11/2014 100 31/03/2019
2 PD CLBUURP, W-295 a) Const.of RCC Bridge on Rakua Bazar (Badepasha UP)-Shantirbazar-Supatek road over Boradal river 254.940 M/S Aziz and Brothers 254.940 30/04/2012 100 31/03/2019
2 Gowainghat
1 PD CLBUURP, W-296 a)Const.of RCC Bridge on Gowainghat - Radanager Bazar GC to Jaflong Bazar road at Ch. 9540m 2528.000 M-N-O(JV) 2528.000 20/12/2013 28/02/2018 100 31/03/2019
2 PD CLBUURP, W-296A b)Remaining Work for Const.of RCC Bridge on Gowainghat-Radanager Bazar GC to Jaflong Bazar road at Ch.9540m 224.400 M/S. IC-ME(JV) 224.400 05/06/2016 30/06/2018 100 31/03/2019
3 Sylhet-s
1 PD CLBUURP, W-297 Const.of RCC Bridge on Badaghat-Mogalgoan UP office road 156.510 M/S Aziz and Brothers 156.510 01/11/2010 30/10/2011 100 31/03/2019
Total : 0.0000 (Km) 3376.75 (Lac) 3376.75 (Lac)