SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
|
1
|
Azmiriganj
|
|
1
|
HILIP/HAB/UZR-003
|
Azmirigonj Paharpur Road by RCC Pavement at Ch. 00.00m-1000.00m under Azmirigonj Upazila.
|
1.0000
|
103.385
|
Md. Moksod Ahmed
|
103.385
|
|
|
100
|
19/01/2019
|
|
|
|
2
|
Baniachong
|
|
1
|
HILIP/15/WD4/VR-HAB/Ban-39
|
Improvement of Ekrampur Bazar – Balla Madhupur Road at (Ch.8000 - 10000m) with 4 nos U-Drain size 0.75m×0.75 at ch. 8250m, 8800m, 9250m & 9750m under Baniachang Upazila, Dist.-Habiganj
|
2.0000
|
133.824
|
LCS
|
133.824
|
|
|
100
|
19/01/2019
|
|
|
2
|
HILIP/15/WD4/VR-HAB/Ban-38
|
Improvement of Ekrampur Bazar – Balla Madhupur Road at (Ch.6000 - 8000m) with 4 nos U-Drain size 0.75m×0.75 at ch. 6300m, 6800m, 7250m & 7800m under Baniachang Upazila, Dist.-Habiganj.
|
2.0000
|
133.874
|
LCS
|
133.874
|
|
|
100
|
19/01/2019
|
|
|
3
|
|
Part-B) Improvement of Ekrampur Bazar – Balla Madhupur Road at (Ch.4500 - 6000m) under Baniachang Upazila, Dist.-Habiganj.
|
1.5000
|
94.052
|
LCS
|
94.052
|
|
|
100
|
19/01/2019
|
|
|
4
|
HILIP/15/WD4/VR-HAB/Ban-25
|
Part-A) Improvement of Ekrampur Bazar – Balla Madhupur Road at (Ch.3000 - 4500m) under Baniachang Upazila, Dist.-Habiganj.
|
1.5000
|
94.323
|
LCS
|
94.323
|
|
|
100
|
19/01/2019
|
|
|
5
|
HILIP/14/WD15/VR-HAB/Ban-78
|
Improvement of Korcha Ariamugur road at CH-4480m - 5080 m with 01 nos. U-Drain in size 0.75m x 0.75 m at Ch. 3930 m under Baniachanj Upazila , Dist- Hobiganj
|
0.6000
|
36.379
|
LCS
|
36.379
|
|
25/06/2016
|
80
|
19/01/2019
|
|
|
6
|
HILIP/14/WD15/VR-HAB/Ban-56
|
Improvement of Community RCC Road Ekram Bazar--Balla Madhupur Road at Ch. 1600-3000m .under Baniachanj Upazila , Dist- Hobiganj
|
1.4000
|
75.609
|
LCS
|
75.609
|
|
15/04/2016
|
80
|
19/01/2019
|
|
|
7
|
HILIP/14/WD15/VR-HAB/Ban-55
|
Improvement of Community RCC Road Ekram Bazar-Balla Madhupur Road at Ch. 0.00-1600.00m under Baniachanj Upazila , Dist- Hobiganj
|
1.6000
|
88.282
|
LCS
|
88.282
|
|
15/04/2016
|
80
|
19/01/2019
|
|
|
8
|
HILIP/14/WD15/VR-HAB/Ban-53
|
Improvement of Korcha Ariamugur road at CH-1980m - 4480m under Baniachanj Upazila , Dist- Hobiganj
|
2.5000
|
141.101
|
LCS
|
141.101
|
|
07/03/2016
|
100
|
19/01/2019
|
|
|
9
|
HILIP/14/WD15/VR-HAB/Ban-26
|
Improvement of Community Road by Habiganj-Sujatpur Road to Mokrompur Road at( Ch 0.00 m - 2000 m),with 65 m Protection Work
|
2.0000
|
121.639
|
LCS
|
121.639
|
|
17/01/2016
|
100
|
19/01/2019
|
|
|
10
|
HILIP/13/WD15/HAB-3
|
Construction of Community CC Block work on Karcha - Araimugur Road at Ch 0+00m - 2+000m
|
2.0000
|
106.712
|
LCS
|
106.712
|
|
18/03/2014
|
100
|
19/01/2019
|
|
|
11
|
HILIP/15/WD3/UNR-HAB/Ban-19
|
Part-A) Improvement of Kagapasha UP office -Chamakpur bazaar at ch 00m- 1440m under Baniachang Upazila, Dist.- Habiganj. ID: 636113010
Part-B)Const. of 2 nos. RCC box culvert at ch. 350m & 1300m on the same alignment.
|
1.4400
|
118.891
|
M/S Zillur Enterprise, 3/10 Gulisthan Shopping Complex, Dhaka-1000
|
118.891
|
|
30/06/2016
|
100
|
19/01/2019
|
|
|
12
|
HILIP/15/WD5/UNR-HAB/Ban-14
|
Improvement of Kagapasha UP Office – Chamakpur Bazar road at ch. 1440-4440m. with 2 nos Box Culvert size (4.00mx4.00m) at ch. 3670m, 4290m and 3 nos Box Culvert size (0.75mx0.75m) at ch. 1800m, 2650m, 3200m under Baniachang Upazila, Dist.- Habiganj.
|
3.0000
|
295.387
|
Challenger M. Hasan. B. Jaman Road, Habiganj
|
295.387
|
|
29/04/2017
|
0
|
19/01/2019
|
|
|
13
|
HILIP/15/WD5/UNR-HAB/Ban-10
|
Improvement of Bithangal GC – Monduri UP Office Road at ch. 5080 – 6086m under Baniachang Upazila, Dist.- Hobigonj.
|
1.0060
|
74.338
|
M/S Hasan Enterprise, TA road, B. Baria.
|
74.338
|
|
14/02/2017
|
0
|
19/01/2019
|
|
|
14
|
HILIP/14/WD5/UNR-HAB/Ban-20
|
Improvement of Kagapasha UP Office - Chamakpur Bazar at (Ch. 4440 m - 6440 m), With 4 Nos U-Drains at Ch .5170 m ,5440 m,5865m, &6410m under under Baniachong Upazila.Habiganj,
|
2.0000
|
160.911
|
M/S Hasan Enterprise, B.Baria
|
160.911
|
|
26/04/2016
|
87
|
19/01/2019
|
|
|
15
|
HILIP/14/WD5/UNR-HAB/Ban-03
|
Improvement of Bithangal GC-Monduri UP Office Road via Bijoypur at (Ch. 3080 m - 5080 m), & 5 Nos Box Culvert Size-1X1.50mX1.5m.Ch2980m, 3420m,3640m,3705m,4150m on same road under Baniachong Upazila.Habiganj,
|
2.0000
|
181.330
|
M/S Hasan Enterprise.T.A. Road Brahmanbaria.
|
181.330
|
|
06/10/2016
|
100
|
19/01/2019
|
|
|
16
|
HILIP/13/WD5/HAB-9
|
Improvement of Bithangal GC-Monduri UP Office Road via Bijoypur at Ch. 2040m-3080m under Baniachong Upazila.
|
1.0400
|
90.359
|
M/S. Rabbi Traders, Shahrashti, Chandpur.
|
90.359
|
|
31/03/2016
|
100
|
19/01/2019
|
|
|
17
|
HILIP/HAB/UNR-001
|
(i) Improvement of Bithangal GC-Monduri UP Office Road via Bijoypur at Ch. 1080.00m - 2040.00m
(ii) Construction of 6 Nos Drain Culvert 1 x 1.00m x 1.00m on the Same at Ch. 1294m, 1414m, 1744m, 2064m, 2444m & 2714.00m
(iii) Construction of Protection work at Ch. 1220m at culvert approach on the Same Road.
|
0.9600
|
94.804
|
Md. Kohinoor Alam, Bogla Bazar, Habiganj.
|
94.804
|
|
28/05/2014
|
100
|
19/01/2019
|
|
|
18
|
HILIP/15/WD2/UZR-Hab/Ban-12
|
(A) Improvement of Baniachang GC- Paharpur GC road via Adarsha Bazaar Ariamugor at ch: 6250m-8630.00m & under Baniachang Upazila, Dist.- Habiganj.
(B) Const. of 3 nos. RCC box-culvert size 0.75mx0.75 at ch 6350m, 6800m & 8250m no the same alignmant.
|
2.3800
|
224.284
|
M/S Maitry Builders, Brahmanbaria
|
224.284
|
|
|
100
|
19/01/2019
|
|
|
19
|
HILIP/15/WD2/UZR-Hab/Ban-10
|
Improvement of Habigonj Nabigonj R&H at Imambari – Baniachang via Gunnee, Barauria road under ch: 6035-803.00m under Baniachang Upazila, Dist.- Habiganj.
|
2.0000
|
174.147
|
Md. Mizanur Rahman Shamim, Nasratpur, Habiganj
|
174.147
|
|
27/07/2017
|
100
|
19/01/2019
|
|
|
20
|
HILIP/15/WD4/UZR-HAB/Ban-06
|
Improvement of Baniachang GC – Pharpur GC road via Adarsha Bazar Ariamugur at ch. 4250-6250m. with 1 no 2x4.00mx4.00mm Box Culvert at ch. 4315m and 3 nos Box Culvert 0.75mx0.75m at ch.5100m,5650m,6000m under Baniachang Upazila, Dist.- Habiganj. ID NO-636112008
|
2.0000
|
195.716
|
M/S Maitry Builders, B. Baria
|
195.716
|
|
28/03/2017
|
100
|
19/01/2019
|
|
|
21
|
HILIP/14/WD4/UZR-HAB/Ban-04
|
Improvement of Baniachang GC - Phaharpur GC Road Via Adarsha BazarAriamugor at ,(Ch.2250 m-4250 m )under Baniachang Upazila ,Habiganj .
|
2.0000
|
165.980
|
M/S Hasan Enterprise
|
165.980
|
|
06/10/2016
|
100
|
19/01/2019
|
|
|
22
|
HILIP/13/WD4/HAB-4
|
Improvement of Baniachong GC - Paharpur GC via Adarsha Bazar Road at Ch. 1250m-2250m under Baniachong Upazila
|
1.0000
|
84.091
|
MA-Ak(J.V) Shaistanagar, Habiganj
|
84.091
|
|
02/03/2015
|
100
|
19/01/2019
|
|
|
|
3
|
Habiganj-s
|
|
1
|
HILIP/16/WD3/UNR-HAB/Azm-02
|
Part-A Improvement of Shibpasha UP – Pasimbag Bazar via Mokleszen Road at ch. 2660 – 5560m under Azmiriganj Upazila, Dist.- Hobigonj.
Part-B) Const. of 1 no RCC Box Culvert size (4.00mx4.00m) at ch.5550m on the same alignment.
Part-C) Const. of 3 nos RCC Box Culvert size (2.50mx2.50m) at ch. 2670m, 2870m & 3250m on the same alignment.
Part-D) Const. of 2 nos RCC Box Culvert size (1.50mx1.50m) at ch. 2970m & 5010m on the same alignment.
|
2.9000
|
230.152
|
MAMCL-MAKC JV
|
230.152
|
|
07/04/2018
|
100
|
19/01/2019
|
|
|
|
4
|
Lakhai
|
|
1
|
HILIP/14/WD15/VR-HAB/Lak-41
|
Improvement of Bulla DC Road to East Bulla Road at( Ch 1000 m - 1200 m) under Lakhai Upazila , Dist- Hobiganj
|
0.2000
|
11.900
|
LCS
|
11.900
|
|
10/12/2016
|
100
|
19/01/2019
|
|
|
2
|
HILIP/14/WD15/VR-HAB-01
|
Improvement of DC road Hazi Bari -Sutang River from (Ch-0.00m- 1830 m)
|
1.8300
|
112.008
|
LCS
|
112.008
|
|
20/01/2016
|
92
|
19/01/2019
|
|
|
3
|
HILIP/13/WD15/HAB-2
|
Construction of Community CC Block work on Lakhai H/Q – Lakhai Bazar via Lakhai UP Office Road at Ch 0+00m - 1+080m
|
1.0800
|
66.689
|
LCS
|
66.689
|
|
30/04/2015
|
100
|
19/01/2019
|
|
|
4
|
HILIP/13/WD15/HAB-1
|
Construction of Community CC Block work on Bulla Dc Road – East Bulla Road at Ch 0+00m - 1+000m
|
1.0000
|
61.712
|
LCS
|
61.712
|
|
15/04/2015
|
100
|
19/01/2019
|
|
|
5
|
HILIP/15/WD5/UNR-HAB/Lak-11
|
Improvement of Murakari UP Office – Lakhaii UP Office via Krishnapur Bazar Road at ch. 4700 – 5200m at ch. under Lakhai Upazila, Dist.- Hobigonj.
|
0.5000
|
40.754
|
Md. Golam Faruk, Shaistanagor, Habiganj.
|
40.754
|
|
22/01/2017
|
100
|
19/01/2019
|
|
|
6
|
HILIP/14/WD5/UNR-HAB/Lak-25
|
Improvement of Murakuri UP Office - Lakhai UP Office Via Krishnopur Bazar Road at (Ch. 3200 m - 4700 m), with 2 Nos RCC Culvert & 03 nos. U-Drain at Ch-4100m, 4500m 4170m, 4560m and 4695m under Lakhai Upazila.Habiganj,
|
1.5000
|
133.278
|
M/S Hasan Enterprise, B.Baria
|
133.278
|
|
20/09/2016
|
90
|
19/01/2019
|
|
|
7
|
HILIP/14/WD5/UNR-HAB/Lak-13
|
Improvement of Murakuri UP Office - Lakhai UP Office Via Krishnopur Bazar Road at (Ch. 2200 m - 3200 m), & 2 Nos U-Drains at Ch .426 m ,471 m. under Lakhai Upazila.Habiganj,
|
1.0000
|
90.971
|
M/S Longon Enterprise, Nasir Nagar, B.Baria
|
90.971
|
|
01/03/2016
|
100
|
19/01/2019
|
|
|
8
|
HILIP/HAB/UNR-002
|
Improvement of Murakori UP Office – Lakhai UP Office via Krisnapur Bazar Road at Ch. 0.00m – 264.00m & 400.00m – 2140.00m under Lakhai Upazila.
|
1.9550
|
182.580
|
Md. Taj Uddin, Anowarpur, Habiganj.
|
182.580
|
|
28/11/2014
|
100
|
19/01/2019
|
|
|
9
|
HILIP/16/WD2/UZR-HAB/Lak-02
|
Part-A) Improvement of Lokra – Madna Bazar Road at ch. 7865.00 - 12200.00m). under Lakhai Upazila, Dist.-Habiganj
|
4.3350
|
407.987
|
M/S Hasan Enterprise, B.Baria
|
407.987
|
|
|
100
|
19/01/2019
|
|
|
10
|
HILIP/14/WD4/UZR-HAB/Lak-12
|
Improvement of Lokra - Madna Bazar Road at (Ch. 6865-7865m). With 3nos U-Drain at ch. 7035m,7257m,7280m, & 1 nos Box Culvert at ch.7322m Under Lakhai Upzila, Dist.-Habiganj.
|
1.0000
|
107.071
|
Md. Taz Uddin Anwarpur , Habiganj
|
107.071
|
|
27/04/2016
|
100
|
19/01/2019
|
|
|
11
|
HILIP/HAB/UZR-002
|
Improvement of Lokra-Madna Bazar Road (03-Nos Bridge Approach) by Earth Filling, RCC Pavement & Slope Protection work at Ch. 1190m-1225m, 1454m-1519m, 2941m-3048m, 3275m-3414m, 3494m-3525m & 3565.50m – 3600.50m (Effective Length 481.00m) under Lakhai Upazila.
|
0.8900
|
85.546
|
M/S. Longon Enterprise, Nashir Nagar, B-Baria.
|
85.546
|
|
09/12/2014
|
100
|
19/01/2019
|
|
|
12
|
HILIP/HAB/UZR-001
|
(i) Improvement of Lokra-Madna Bazar Road at Ch. 4615.00m - 6565.00m
(ii) Construction of 5 Nos 0.625m Span U-Drain on the Same Road at Ch. 3048m, 5345m, 5755m, 6265m & 6515m
(iii) Construction of Top Slab for 1.85m Span Culvert on the Same Road at Ch. 4825m
|
1.9550
|
197.362
|
Md. Golam Faruk, Shaistanagar, Habiganj.
|
197.362
|
|
14/12/2014
|
100
|
19/01/2019
|
|
|
13
|
HILIP/15/WD3/UNR-HAB/Azm-21
|
Improvement of Shibpasha UP – Pasimbag Bazar via Mokleszen Road at ch. 2000 – 2660m under Azmiriganj Upazila, Dist.- Hobigonj.
|
0.6600
|
57.400
|
Md. Mizanur Rahman
|
57.400
|
|
27/07/2017
|
100
|
19/01/2019
|
|
|
|
5
|
Madhabpur
|
|
1
|
HILIP/15/WD5/UNR-HAB/Azm-12
|
Improvement of Shibpasha UP – Pasimbag Bazarv via Mokleszen Road at ch. 1000 – 2000m with 2 nos U-Drain size (0.625mx0.600m) at ch. 1480m & 1746m) under Azmiriganj Upazila, Dist.- Hobigonj.
|
1.0000
|
97.042
|
M/S Hasan Enterprise
|
97.042
|
|
12/02/2017
|
100
|
19/01/2019
|
|
|
|
6
|
Nabiganj
|
|
1
|
HILIP/14/WD5/UNR-HAB/Azm-12
|
Improvement of Shibpasha UP Office - Paschimbag Bazar Via Mokleszam Road at (Ch.0.00 m - 1000 m), under Ajmeriganj Upazila District: Habiganj.
|
1.0000
|
85.119
|
M/S S. Alam Enterprise,
|
85.119
|
|
24/02/2016
|
100
|
19/01/2019
|
|
|
|
Total :
|
61.7310 (Km)
|
4956.99 (Lac)
|
4956.99 (Lac)
|
|
|
|
|
|
|
|