1
|
IRIDP-2/HOB/DW-15
|
(a) Improvement of Jabaida Katun Atimkhana Road – Heibotpur Via Zahorpur Road at (Ch:- 0.00- 500.00m). (b) Construction of 1 No Drain Culvert on the Same Road at (Ch: 75m -1.00x0.600x0.600mRoadWay7.00m).
|
0.5000
|
24.540
|
Mr. Robindra kumer paul
|
24.540
|
21/02/2016
|
02/03/2017
|
100
|
23/12/2018
|
|
|
2
|
IRIDP-2/HOB/DW-14
|
(a) Improvement of Nabigonj-Rudragram Road Chowdory Bazar via Nich Chowki Road at (Ch:- 0.00- 1000.00m). (b) Construction of 2 Nos Drain Culvert on the Same Road at (Ch:- 618m& 695m 1.00x0.600x0.600m RoadWay 7.00m).
|
1.0000
|
52.090
|
M/S. Mortuja Hasan
|
52.090
|
21/02/2016
|
02/03/2017
|
100
|
23/12/2018
|
|
|
3
|
IRIDP-2/HOB/DW-13
|
(a) Improvement of Sayedpur–Inathgonj Road Kamargaon– Durgapur Bazar–Nurgaon Madrasha Road at (Ch:1000.00- 2000.00m). (b) Construction of 1 No Drain Culvert on the Same Road at (Ch: 1502m, 1.00x0.600x0.600mRoadWay7.00m).
|
1.0000
|
47.600
|
M/S. Neon Enterprise
|
47.600
|
21/02/2016
|
30/11/2017
|
100
|
23/12/2018
|
|
|
4
|
IRIDP-2/HOB/DW-12
|
Improvement of Nabigonj Habigonj Road –Purangaon Halim Ullah house to Purangaon Dakkin Road at (Ch:- 0.00- 500.00m).
|
0.5000
|
27.070
|
M/S. Kuhinoor Enterprise
|
27.070
|
31/03/2016
|
01/04/2017
|
100
|
23/12/2018
|
|
|
5
|
IRIDP-2/HOB/DW-11
|
Improvement of Goplar Bazar–Gurarai Bazar Road Boithakhal GPS-South Fakir Bari House via Mukam Connecting Road at (Ch: 0.00- 500.00m).
|
0.5000
|
20.670
|
M/S. Nishath Enterprise
|
20.670
|
18/02/2016
|
15/05/2017
|
100
|
23/12/2018
|
|
|
6
|
IRIDP-2/HOB/DW-10
|
(a) Improvement of Inathgonj Bazar – Inathganj Collage ( By pass) Road at (Ch:- 73.00- 583.00m) (b) Construction of 1 No Drain Culvert on the Same Road at (Ch: 223m 1.00x0.600x0.600m Road Way 7.00m).
|
-0.1470
|
26.370
|
Md. Abdul Quayum
|
26.370
|
28/02/2016
|
15/05/2017
|
100
|
23/12/2018
|
|
|
7
|
IRIDP-2/HOB/DW-9
|
(a) Improvement of Nabigonj Sherpur road–Maspara via Choitpur Road at Ch:- 691.00-1466.00m. (b) Construction of 1 No Drain Culvert on the Same Road at (Ch: 864m, 1.00x0.600x0.600m Road Way 7.00m).
|
0.7750
|
37.190
|
M/S. Neon Enterprise
|
37.190
|
21/02/2016
|
02/03/2017
|
100
|
23/12/2018
|
|
|
8
|
IRIDP-2/HOB/DW-8
|
(a) Improvement of Sader Ghat Natun Bazar–Itakhola Islampur Road at Ch:- 0.00-925m.(b) Construction of Drain Culvert on the Same Road at (Ch: 243m, 1.00x0.600x0.600m Road Way 7.00m.)
|
0.9250
|
46.450
|
M/S. Neon Enterprise
|
46.450
|
21/02/2016
|
02/03/2017
|
100
|
23/12/2018
|
|
|
9
|
IRIDP-2/HOB/DW-7
|
(a) Improvement of Kurshi Bas Stand-MP Abdul Munim Chowdhary Babu Road via Kurshi Mukum road ( Kurshi Bas Stand-Kurshi House of Rabban Khan Road via Kurshi Mukum) at Ch:- 0.00-1200.00m (b) Construction of 3 nos Drain Culvert Same as Road at (Ch: 320m,625m
|
1.2000
|
65.690
|
M/S. Neon Enterprise
|
65.690
|
21/02/2016
|
15/05/2017
|
100
|
23/12/2018
|
|