SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
|
1
|
Chatak
|
|
1
|
(Pack No:HFMLIP/Sunam/17-18/W-203),
|
Maintenance of Chhatak UZ HQ-Companiganj (Chanbari) via Chaigaon Road at Ch. 00m-5600m (Part Chhatak) under Chhatak Upazila, Dist. Sunamganj. (Road ID:690232008)
|
5.6000
|
332.986
|
M/S Israth Builders, Mohammadpur,Dhaka
|
332.986
|
31/07/2018
|
18/03/2019
|
100
|
13/08/2020
|
Final bill paid
|
|
2
|
(Package No : HFMLIP/SUN/2015-16/W-88),
|
Rehabilitation of Noarai-Baliura Road by RCC at Ch: 00-5500m, Upazilla: Chhatak, District: Sunamganj (Rd ID: 690232005)
|
5.5000
|
195.896
|
M/S AMINUL HAQUE & CO
|
195.896
|
01/07/2016
|
31/05/2017
|
100
|
13/08/2020
|
Final bill paid
|
|
3
|
HFMLIP/SUN/2015-16/W-88
|
Rehabilitation of Noarai-Baliura Road by RCC at Ch: 00-5500m, Upazilla: Chhatak, District: Sunamganj (Rd ID: 690232005)
|
5.5000
|
195.900
|
M/S AMINUL HAQUE & CO
|
195.900
|
01/07/2016
|
31/05/2017
|
100
|
12/08/2020
|
Final Bill Paid
|
|
|
2
|
Derai
|
|
1
|
HFMLIP/SUN/2015-16/W-47
|
Improvement of Nagergaon Ferryghat-Nasir Bazar via Tarapasa Bazar Road at Ch 1350-1426m & 1654-4660 m at Upazilla: Derai , District: Sunamganj (RD ID:690294018
|
3.0820
|
214.740
|
Kazi Nasim Uddin
|
214.740
|
20/03/2016
|
19/03/2017
|
100
|
25/06/2024
|
|
|
2
|
HFMLIP/SUN/14-15/W-19
|
Improvement of Boalia Bazar - Bhaitgaon via Dhaipur Community road at Ch 000 - 2900m, (Road ID: 690294017), Non-Submergible
|
1.9000
|
129.693
|
LCS
|
129.693
|
03/09/2015
|
17/11/2015
|
100
|
12/08/2020
|
FB u/p
|
|
3
|
HFMLIP/SUN/2015-16/W-48
|
Improvement of Akilsha Bazar -Nasni Bazar Road at Ch 1000-3120 m by RCC at District: Sunamganj (RD ID: 690294020), Non-Submergible
|
2.1200
|
149.902
|
M/S Kazi Nasim Uddin
|
149.902
|
02/05/2016
|
13/03/2017
|
100
|
12/08/2020
|
Final bill paid
|
|
4
|
HFMLIP/SUN/2014-15/W-01
|
Improvement of Tarapasa Bazar to Chilura Via Tong Ghar road at Ch. 1000-2980m, (Road ID: 690294012), Submergible
|
1.9800
|
110.928
|
LCS
|
110.928
|
24/05/2015
|
10/02/2016
|
100
|
12/08/2020
|
Final bill paid
|
|
5
|
HFMLIP/SUN/2015-16/W-47
|
Improvement of Nagergaon Ferryghat-Nasir Bazar via Tarapasa Bazar Road at Ch 1350-1426m & 1654-4660 m at District: Sunamganj (RD ID:690294018), Submergible
|
3.0820
|
214.739
|
Kazi Nasim Uddin, Sunamganj
|
214.739
|
20/03/2016
|
19/03/2017
|
100
|
12/08/2020
|
Final bill paid
|
|
6
|
HFMLIP/SUN/2015-16/W-46
|
Improvement of Boalia Bazar -Bhaitgaon via Dhaipur Road at Ch 2900-5750 m at District: Sunamganj (Rd ID: 690294017), Non-Submergible
|
2.8500
|
218.214
|
kazi Nasim Uddin
|
218.214
|
20/03/2016
|
20/12/2017
|
100
|
12/08/2020
|
Final bill paid
|
|
7
|
HFMLIP/SUN/2015-16/W-48
|
Improvement of Akilsha Bazar -Nasni Bazar Road at Ch 1000-3120 m by RCC
|
2.1200
|
149.900
|
M/S Kazi Nasim Uddin
|
149.900
|
02/05/2016
|
20/04/2017
|
100
|
10/08/2020
|
Final bill paid
|
|
8
|
HFMLIP/SUN/2015-16/W-46
|
Improvement of Boalia Bazar -Bhaitgaon via Dhaipur Road at Ch 2900-5750 m at Upazilla: Derai , District: Sunamganj (Rd ID:690294017
|
2.8500
|
218.210
|
kazi Nasim Uddin
|
218.210
|
20/03/2016
|
19/03/2017
|
100
|
10/08/2020
|
Final bill paid
|
|
9
|
HFMLIP/SUN/14-15/W-19
|
Improvement of Boalia Bazar - Bhaitgaon via Dhaipur Community road at Ch 000 - 2900m, Upazila: Derai, (Road ID: 690294017)
|
1.9000
|
129.690
|
LCS
|
129.690
|
03/09/2015
|
17/11/2015
|
100
|
10/08/2020
|
Final bill paid
|
|
10
|
HFMLIP/SUN/2014-15/W-01
|
Improvement of Tarapasa Bazar to Chilura Via Tong Ghar road at Ch. 1000-2980m, Upazila: Derai, (Road ID: 690294012)
|
1.9800
|
110.930
|
LCS
|
110.930
|
24/05/2015
|
10/02/2016
|
100
|
10/08/2020
|
Final bill paid
|
|
11
|
HFMLIP/Sunam/16-17/EW-113
|
Re-excavation of Dolua-Meghna-Pukrail Dair khal at Ch 00-2000 m Upazila: Derai, District: Sunamganj
|
2.0000
|
0.000
|
LCS
|
0.000
|
|
|
0
|
21/09/2017
|
Work delayed due to flood
|
|
|
3
|
Dharmapasha
|
|
1
|
HFMLIP/SUN/2015-16/EW-164
|
Re-excavation of Shimultola Beel in Bir Dikkhin Maizbari under Upazila: Dharmapasha, District: Sunamganj
|
|
9.060
|
LCS
|
9.060
|
|
28/06/2018
|
100
|
27/06/2024
|
|
|
2
|
HFMLIP/SUN/2015-16/EW-163
|
Re-excavation of Korcha Beel in Razandrapur village under Upazila: Dharmapasha, District: Sunamganj
|
|
8.790
|
LCS
|
8.790
|
|
19/03/2019
|
100
|
27/06/2024
|
|
|
3
|
HFMLIP/SUN/16-17/EW-167
|
Re-excavation of Korcha Khal at ch 00-730m in Razandrapur village under Upazila: Dharmapasha, District: Sunamganj
|
0.7300
|
9.230
|
LCS
|
9.230
|
|
15/03/2019
|
100
|
27/06/2024
|
|
|
4
|
HFMLIP/SUN/16-17/EW-166
|
Re-excavation of Shimultola Cekondair and Chottonia Beel connectivity (Sona Moral) Khal at ch 00-2500m under Upazila: Dharmapasha, District: Sunamganj
|
2.5000
|
22.080
|
LCS
|
22.080
|
|
19/03/2019
|
100
|
27/06/2024
|
|
|
5
|
HFMLIP/SUN/16-17/EW-145
|
Re-excavation of Shimultola khal at Ch 00-400m in Bir Dakkin, Maizbari, Solbe village under Upazila: Dharmapasha, District: Sunamganj
|
0.4000
|
5.140
|
LCS
|
5.140
|
|
15/06/2018
|
100
|
27/06/2024
|
|
|
6
|
HFMLIP/SUN/2015-16/EW-60
|
Re-excavation of Nadikulma khal at Ch 00-1200m Upazila: Dharmapasha, District: Sunamganj
|
1.2000
|
8.040
|
LCS
|
8.040
|
|
10/03/2017
|
100
|
27/06/2024
|
|
|
7
|
HFMLIP/SUN/2015-16/W-97
|
Construction of Open Sales platform, Multipurpose Shed, RCC Road, CC road and Tubewell at Badshaganj Bazar, Upazila: Dharmapasha, Dist: Sunamganj
|
|
33.130
|
M/S Hasna Enterprise
|
33.130
|
01/10/2016
|
28/07/2017
|
100
|
25/06/2024
|
Final bill paid
|
|
8
|
HFMLIP/SUN/16-17/W-130
|
Improvement of Joysree GC-Maddhanagar via Chamerdani UPC Road by RCC at Ch : 4050m-5800m Upazila: Dharmapasha District: Sunamganj (Road ID: 690322007))
|
1.7500
|
172.290
|
AKM Abdul Quddus_Talukder Nirman (JV)
|
172.290
|
11/04/2017
|
22/04/2018
|
100
|
25/06/2024
|
Final Bill paid
|
|
9
|
HFMLIP/SUN/16-17/W-129
|
Improvement of Joysree GC-Maddhanagar via Chamerdani UPC Road by RCC at Ch : 2300-4050m Upazila: Dharmapasha District: Sunamganj (Road ID: 690322007))
|
1.7500
|
174.920
|
AKM Abdul Quddus_Talukder Nirman (JV)
|
174.920
|
11/04/2017
|
22/04/2018
|
100
|
25/06/2024
|
Final Bill paid
|
|
10
|
HFMLIP/SUN/16-17/W-116
|
Improvement of Moddhanagar GC Kalmakanda UZ HQ via Ragunathpur Bazar Road at Ch : 2200-5200m Upazila: Dharmapasha, District: Sunamganj (Road ID: 690934021) (Pack No. )
|
3.0000
|
313.760
|
Sheik Hemayet Ali-Saiful Mondal (JV)
|
313.760
|
23/04/2017
|
22/04/2018
|
100
|
25/06/2024
|
|
|
11
|
HFMLIP/Sunam/17-18/W-183
|
Improvement of Joysree GC-Moddhanagar GC Via Chamerdani UPC Road at Ch. 5800-11100m by RCC under Dist. Sunamganj.(Road ID: 690322007), Submergible
|
5.3000
|
744.100
|
Samiran & Shahil (JV), Ukilpara, Netrokona
|
744.100
|
01/03/2018
|
31/05/2019
|
100
|
13/08/2020
|
Final Bill paid
|
|
12
|
HFMLIP/SUN/16-17/W-129
|
Improvement of Joysree GC-Maddhanagar via Chamerdani UPC Road by RCC at Ch : 2300-4050m District: Sunamganj (Road ID: 690322007), Submergible
|
1.7500
|
174.921
|
AKM Abdul Quddus_Talukder Nirman (JV)
|
174.921
|
11/04/2017
|
22/04/2018
|
100
|
13/08/2020
|
Final Bill paid
|
|
13
|
HFMLIP/SUN/16-17/W116
|
Improvement of Moddhanagar GC Kalmakanda UZ HQ via Ragunathpur Bazar Road at Ch : 2200-5200m District: Sunamganj (Road ID: 690322011), Submergible
|
3.0000
|
313.760
|
Sheik Hemayet Ali-Saiful Mondal (JV)
|
313.760
|
23/04/2017
|
22/04/2018
|
100
|
13/08/2020
|
Work is Complete
|
|
14
|
HFMLIP/SUN/16-17/W-122
|
Improvement of Moddhanagar GC Kalmakanda UZ HQ via Ragunathpur Bazar Road by RCC at Ch : 00-2200m, District: Sunamganj (Road ID: 690322011), Submergible
|
2.2000
|
212.525
|
M. A Wahed -New Asha Traders (JV)
|
212.525
|
23/04/2017
|
22/04/2018
|
0
|
13/08/2020
|
Letter for cencelation (11.9.2019)
|
|
15
|
HFMLIP/SUN/16-17/W-130
|
Improvement of Joysree GC-Maddhanagar via Chamerdani UPC Road by RCC at Ch : 4050m-5800m District: Sunamganj (Road ID: 690322007), Submergible
|
1.7500
|
172.285
|
AKM Abdul Quddus_Talukder Nirman (JV)
|
172.285
|
11/04/2017
|
22/04/2018
|
100
|
12/08/2020
|
Final Bill paid
|
|
16
|
HFMLIP/SUN/16-17/W122
|
Improvement of Moddhanagar GC Kalmakanda UZ HQ via Ragunathpur Bazar Road by RCC at Ch : 00-2200m Upazila: Dharmapasha, District: Sunamganj (Road ID: 690322011) (Pack No. )
|
2.2000
|
212.530
|
M. A Wahed -New Asha Traders (JV)
|
212.530
|
23/04/2017
|
22/04/2018
|
0
|
12/08/2020
|
Letter for cencelation (11.9.2019)
|
|
17
|
HFMLIP/SUN/2015-16/EW-165
|
Re-excavation of Shimultola Cekondair Beel under Upazila: Dharmapasha, District: Sunamganj
|
|
1087706.000
|
LCS
|
1087706.000
|
|
|
0
|
21/09/2017
|
1 no Beel Work delayed due to flood
|
|
18
|
HFMLIP/SUN/2015-16/EW-61
|
Re-excavation of Shimultola khal at Ch 00-600m Upazila: Dharmapasha, District: Sunamganj
|
0.6000
|
788918.000
|
LCS
|
788918.000
|
|
|
0
|
21/09/2017
|
Work delayed due to flood
|
|
19
|
HFMLIP/SUN/ 2014-15/W-06
|
Re-Excavation of Canal from Ashamura Sluice Gate-Shanghai Haor at Chainage-200-2200m, Upazila: Dakkin Sunamganj
|
2.0000
|
1851235.000
|
LCS
|
1851235.000
|
|
|
100
|
21/09/2017
|
|
|
|
4
|
Doarabazar
|
|
1
|
(Pack No:HFMLIP/Sunam/17-18/W-247)
|
Maintenance of Baliura GCM-Dowarabazar UZ HQ Road at Ch. 00m-10600m (Part Chhatak) under Dowarabazar Upazila, Dist. Sunamganj. (Road ID:690332002)
|
10.6000
|
1953.283
|
M/S Saleh - Islam JV, Laxipur, Faridpur
|
1953.283
|
21/11/2018
|
20/05/2020
|
35
|
13/08/2020
|
Work ongoing
|
|
2
|
(Pack No:HFMLIP/Sunam/17-18/W-202)
|
Maintenance of Banglabazar-Haquenagar Bazar Road at Ch. 00m-6770m under Doarabazar Upazila, Dist. Sunamganj. (Road ID:6900333006)
|
3.5000
|
466.878
|
JV of NI-HK Mohila College Road, Sunamganj
|
466.878
|
15/03/2018
|
14/03/2019
|
85
|
13/08/2020
|
Work ongoing
|
|
|
5
|
Shantiganj
|
|
1
|
HFMLIP/SUN/16-17/EW-144
|
Re-excavation of Kaldora-Nakdora Beel under West Pagla Unoin at Upazila: South Sunamganj, District: Sunamganj
|
|
20.000
|
LCS
|
20.000
|
|
10/04/2020
|
100
|
25/06/2024
|
|
|
2
|
HFMLIP/SUN/16-17/EW-143
|
Re-excavation of Honua-Sonua Beel under West Birgaon Unoin at Upazila: South Sunamganj, District: Sunamganj
|
|
15.100
|
LCS
|
15.100
|
|
15/04/2020
|
100
|
25/06/2024
|
|
|
3
|
HFMLIP/SUN/16-17/EW-142
|
Re-excavation of Noluar Beel under Shimulback Union, Upazila: South Sunamganj, District: Sunamganj
|
|
10.830
|
LCS
|
10.830
|
|
25/03/2019
|
100
|
25/06/2024
|
|
|
4
|
HFMLIP/SUN/16-17/EW-138
|
Re-excavation of Honua-Sonua & Ihar Kara connecting khal at Ch 00-2100 m Upazila: South Sunamganj, District: Sunamganj
|
2.1000
|
34.280
|
LCS
|
34.280
|
|
27/02/2018
|
100
|
25/06/2024
|
|
|
5
|
HFMLIP/SUN/2015-16/EW-74
|
Re-excavation of Lumar Dair Beel -Jagoria Humaira Putka and Boro Beel Connecting Canal at Ch 00-3000m Upazila: South Sunamganj, District: Sunamganj
|
3.0000
|
37.470
|
LCS
|
37.470
|
|
23/02/2017
|
100
|
25/06/2024
|
|
|
6
|
HFMLIP/SUN/2015-16/W-68
|
Rehabilitation of Shantiganj Bazar (UZHQ) Rajaniganj Bazar (Patharia GC ) via Dungria (Joykalash) Road at Ch. 00-5510m, Upazilla: South Sunamganj , District: Sunamganj
|
5.5100
|
246.590
|
M/S Sonarbangla Traders & Md Taibur Rahman
|
246.590
|
07/05/2016
|
18/07/2017
|
100
|
25/06/2024
|
|
|
7
|
HFMLIP/Sunam/17-18/W-180
|
Improvement of Ganiganj RHD-Jibdhara Road at Ch. 2050-4050m by RCC underDist. Sunamganj. (Road ID: 690934021), Submergible
|
2.0000
|
251.261
|
M/S Suhag Enterprise,Kula-ura,Moulvibazar
|
251.261
|
15/03/2018
|
28/02/2019
|
0
|
12/08/2020
|
Alignment problem with BWDB Cancelation U/P
|
|
8
|
HFMLIP/Sun/15-16/W-100
|
Improvement of Ganiganj RHD-Jibdara Road by RCC at Ch 1000-2050m District: Sunamganj (Road ID: 690934021), Submergible
|
1.0500
|
75.865
|
by LCS
|
75.865
|
20/06/2016
|
30/12/2016
|
100
|
12/08/2020
|
Final bill paid
|
|
9
|
(Pack No:HFMLIP/Sun/17-18/W-194)
|
Maintenance of Patharia UP (Goniganj)-Muradpur Bazar Via Thekia Bazar Road at Ch. 00m-2100 m under Dhakkin Sunamganj Upazila, Dist. Sunamganj. (Road ID: 690933010)
|
2.1000
|
340.204
|
M/S Suhag Enterprise
|
340.204
|
08/01/2018
|
31/12/2018
|
95
|
12/08/2020
|
Variation Date 4.9.2019
|
|
10
|
(Package No : HFMLIP/SUN/2015-16/W-68),
|
Rehabilitation of Shantiganj Bazar (UZHQ) Rajaniganj Bazar (Patharia GC ) via Dungria (Joykalash) Road at Ch. 00-5510m, Upazilla: South Sunamganj , District: Sunamganj
|
5.5100
|
246.587
|
M/S Sonarbangla Traders & Md Taibur Rahman
|
246.587
|
07/05/2016
|
18/07/2017
|
65
|
12/08/2020
|
Work ongoing
|
|
11
|
HFMLIP/SUN/2015-16/W-96
|
Improvement of Ganiganj RHD-Jibdara road by RCC (Ch 00-1000m), , District: Sunamganj. (Road ID: 690934021), Submergible
|
1.0000
|
70.396
|
by LCS
|
70.396
|
25/05/2016
|
30/12/2016
|
100
|
12/08/2020
|
Final bill paid
|
|
12
|
HFMLIP/SUN/2015-16/W-45
|
Rehabilitation of pavement works of RHD-Kamrupdolan Madrassa Road at Ch 00-873 m at Upazilla: South Sunamganj , District: Sunamganj (Road ID: 690934025)
|
0.8730
|
54.600
|
M/S Tushar Construction
|
54.600
|
14/03/2016
|
16/06/2016
|
100
|
10/08/2020
|
Final Bill Paid
|
|
13
|
HFMLIP/SUN/2015-16/W-100
|
Improvement of Ganiganj RHD-Jibdara Road by RCC at Ch 1000-2050m Upazila: Dhakkin Sunamganj, District: Sunamganj
|
1.0500
|
75.870
|
by LCS
|
75.870
|
20/06/2016
|
30/12/2016
|
100
|
10/08/2020
|
Final bill paid
|
|
14
|
HFMLIP/SUN/2015-16/W-96
|
Improvement of Ganiganj RHD-Jibdara road by RCC (Ch 00-1000m), Upazilla: South Sunamganj , District: Sunamganj. (Road ID: 690934021)
|
1.0000
|
70.400
|
by LCS
|
70.400
|
25/05/2016
|
30/12/2016
|
100
|
10/08/2020
|
Final bill paid
|
|
15
|
HFMLIP/SUN/2014-15/W-03
|
Improvement of Ashamura pry. School-Puran Kandagaon road at Chainage 1450-4100m.
(Road ID : 690934048), Submergible
|
2.6500
|
152.252
|
LCS
|
152.252
|
30/06/2015
|
29/05/2016
|
100
|
10/08/2020
|
Final bill paid
|
|
|
6
|
Sulla
|
|
1
|
(Package No : HFMLIP/SUN/2015-16/W-93
|
Rehabilitation of Sullah HQ -Paharpur GC Road (Azmirigonj) via Protabpur Bazar Road by at Ch: 00-6400m, Upazilla: Sulla, District: Sunamganj (Rd ID: 690862004)
|
6.4000
|
682.429
|
M/S Nurul Islam
|
682.429
|
07/10/2016
|
30/05/2018
|
100
|
13/08/2020
|
Work ongoing
|
|
2
|
HFMLIP/SUN/2015-16/W-93
|
Rehabilitation of Sullah HQ -Paharpur GC Road (Azmirigonj) via Protabpur Bazar Road by at Ch: 00-6400m, Upazilla: Sulla, District: Sunamganj (Rd ID: 690862004)
|
6.4000
|
682.430
|
M/S Nurul Islam
|
682.430
|
07/10/2016
|
30/05/2018
|
100
|
12/08/2020
|
Work ongoing
|
|
|
7
|
Sunamganj-s
|
|
1
|
HFMLIP/SUN/16-17/EW-125
|
Re-excavation of Korchar Haor Khashiar Khara khal at Ch 00-2000 m Upazila: Sunamganj Sadar, District: Sunamganj
|
2.0000
|
32.240
|
LCS
|
32.240
|
|
13/01/2019
|
100
|
25/06/2024
|
|
|
2
|
HFMLIP/SUN/ 2014-15/W-07
|
Re-Excavation of Canal from Dakuar Khal at Chainage-200-1700m, Upazila: Sadar Sunamganj,
|
1.5000
|
13.740
|
LCS
|
13.740
|
|
16/05/2016
|
100
|
25/06/2024
|
|
|
3
|
HFMLIP/SUN/2015-16/W-49
|
Rehabilitation of Bitgonj GC-Jalalpur Road at Ch 00-736m at Upazilla: Sunamganj Sadar , District: Sunamganj (RD ID:690893015)
|
0.7360
|
52.100
|
M/S Rajib Enterprise
|
52.100
|
20/03/2016
|
26/06/2016
|
100
|
25/06/2024
|
Final Bill Paid
|
|
4
|
HFMLIP/SUN/16-17/W-126
|
Improvement of RHD Jonigaon-Joynagar Road by RCC at Ch : 00-1950 & 2150-2460m Upazila: Sunamganj Sadar, District: Sunamganj (Road ID: 690893001)
|
2.4600
|
195.010
|
MD. RENU MIAH
|
195.010
|
11/04/2017
|
24/05/2018
|
100
|
25/06/2024
|
|
|
5
|
HFMLIP/SUN/16-17/W-121
|
Improvement of RHD (Haluargaon) Islampur RCC Road (Laxmansree) at Ch : 00-30000m Upazila: sunamganj Sadar, District: Sunamganj (Road ID: 690894022)
|
3.0000
|
328.850
|
M/S Milon Kanti Dey
|
328.850
|
04/04/2017
|
28/02/2018
|
100
|
25/06/2024
|
Work order cencelled/Joint measurement taken
|
|
6
|
HFMLIP/SUN/16-17/W-117
|
Improvement of Katair Joynagar GC Road (Noagaon) Kandirgaon Village Road at Ch : 00-2500m Upazila: Sunamganj Sadar, District: Sunamganj (Road ID: 690495111)
|
2.5000
|
240.990
|
Md. Nurul Haque
|
240.990
|
02/04/2017
|
10/08/2018
|
100
|
25/06/2024
|
Final Bill paid
|
|
7
|
HFMLIP/SUN/2015-16/W-76
|
Improvement of Tukerghat-Bahadurpur road at Ch. 1700-3130m, Upazilla: Sunamganj Sadar , District: Sunamganj. (Road ID: 690894005)
|
1.4300
|
86.490
|
Aminul Islam Selim
|
86.490
|
12/05/2016
|
11/05/2017
|
100
|
25/06/2024
|
|
|
8
|
HFMLIP/SUN/2015-16/W-70
|
Improvement of RHD Janigaon-Joynagar Bazar Road by BC at Ch. 2600-4700m, Upazilla: Sunamganj Sadar , District: Sunamganj
|
2.1000
|
154.110
|
Kazi Nasim Uddin
|
154.110
|
12/05/2016
|
11/05/2017
|
100
|
25/06/2024
|
|
|
9
|
HFMLIP/SUN/2015-16/W-44
|
Improvement of Kathair Joynagar Road to Narkila GPS (Kathair) at Ch 00-1000 m at Upazilla: Sadar , District: Sunamganj (Road ID: 690895038)
|
1.0000
|
65.130
|
M/S Rafiul Trading
|
65.130
|
07/03/2016
|
16/12/2016
|
100
|
25/06/2024
|
Final bill paid
|
|
10
|
HFMLIP/SUN/2014-15/W-15
|
Improvement of Tokerghat to Bahadurpur road at Ch. 700-1700m, Upazila: Sunamganj Sadar, (Road ID: 690894005)
|
1.0000
|
56.530
|
LCS
|
56.530
|
17/08/2015
|
31/12/2015
|
100
|
25/06/2024
|
Final bill paid
|
|
11
|
HFMLIP/SUN/2014-15/W-15
|
Improvement of Tokerghat to Bahadurpur road at Ch. 700-1700m, (Road ID: 690894005), Non-Submergible
|
1.0000
|
56.529
|
LCS
|
56.529
|
17/08/2015
|
31/12/2015
|
100
|
13/08/2020
|
Final bill paid
|
|
12
|
HFMLIP/SUN/2015-16/W-70
|
Improvement of RHD Janigaon-Joynagar Bazar Road by BC at Ch. 2600-4700m, District: Sunamganj, Non-Submergible
|
2.1000
|
154.106
|
Kazi Nasim Uddin
|
154.106
|
12/05/2016
|
11/05/2017
|
60
|
13/08/2020
|
1500m WBM Complated. Work cenceled (25/11/2019) final bill u/p
|
|
13
|
(Package No : HFMLIP/SUN/2015-16/W-49)
|
Rehabilitation of Bitgonj GC-Jalalpur Road at Ch 00-736m at Upazilla: Sunamganj Sadar , District: Sunamganj (RD ID:690893015)
|
0.7360
|
52.096
|
M/S Rajib Enterprise
|
52.096
|
20/03/2016
|
19/09/2016
|
100
|
13/08/2020
|
Final Bill Paid
|
|
14
|
(Package No : HFMLIP/SUN/2015-16/W-45),
|
Rehabilitation of pavement works of RHD-Kamrupdolan Madrassa Road at Ch 00-873 m at Upazilla: South Sunamganj , District: Sunamganj (Road ID: 690934025)
|
0.8730
|
54.597
|
M/S Tushar Construction
|
54.597
|
14/03/2016
|
16/06/2016
|
100
|
13/08/2020
|
Final Bill Paid
|
|
15
|
HFMLIP/Sunam/17-18/W-182
|
Improvement of R&H (Rabarbari)-Baishber-Joynagar GC Road at Ch. 00-3015m by RCC under , Dist. Sunamganj. (Road ID:690892009), Non-Submergible
|
3.0150
|
346.941
|
M/S Nurul Islam, Mohila College Road, Sunamganj
|
346.941
|
10/12/2017
|
22/11/2018
|
70
|
13/08/2020
|
Work ongoing
|
|
16
|
HFMLIP/Sunam/17-18/W-181
|
Improvement of Bahadurpur RHD-Nurulla Village Road at Ch. 00-2725m by RCC under Dist. Sunamganj.(Road ID:690894073), Submergible
|
2.7250
|
306.013
|
M/s Belal Enterprise & M/s Nurul Haque_JV, Hazipara, Sunamganj
|
306.013
|
10/12/2017
|
22/11/2018
|
50
|
13/08/2020
|
Work Stop
|
|
17
|
HFMLIP/SUN/2015-16/W-44
|
Improvement of Kathair Joynagar Road to Narkila GPS (Kathair) at Ch 00-1000 m at , District: Sunamganj (Road ID: 690895038), Non-Submergible
|
1.0000
|
65.126
|
M/S Rafiul Trading
|
65.126
|
07/03/2016
|
16/12/2016
|
100
|
13/08/2020
|
Final bill paid
|
|
18
|
HFMLIP/SUN/16-17/W-126
|
Improvement of RHD Jonigaon-Joynagar Road by RCC at Ch : 00-1950 & 2150-2460m District: Sunamganj (Road ID: 690893001), Submergible
|
2.2600
|
195.011
|
MD. RENU MIAH
|
195.011
|
11/04/2017
|
11/02/2018
|
100
|
12/08/2020
|
Final bill Under Process
|
|
19
|
HFMLIP/SUN/16-17/W-121
|
Improvement of RHD (Haluargaon) Islampur RCC Road (Laxmansree) at Ch : 00-30000m District: Sunamganj (Road ID: 690894022), Submergible
|
3.0000
|
328.853
|
M/S Milon Kanti Dey
|
328.853
|
04/04/2017
|
28/02/2018
|
15
|
12/08/2020
|
Work order cencelled/Joint measurement taken
|
|
20
|
HFMLIP/SUN/16-17/W-117
|
Improvement of Katair Joynagar GC Road (Noagaon) Kandirgaon Village Road at Ch : 00-2500m District: Sunamganj (Road ID: 690495111), Submergible
|
2.5000
|
240.986
|
Md. Nurul Haque
|
240.986
|
02/04/2017
|
28/02/2018
|
96
|
12/08/2020
|
Final Bill paid
|
|
21
|
HFMLIP/SUN/2015-16/W-76
|
Improvement of Tukerghat-Bahadurpur road at Ch. 1700-3130m, District: Sunamganj (Road ID: 690894005), Non-Submergible
|
1.4300
|
141.225
|
Aminul Islam Selim
|
141.225
|
12/05/2016
|
11/05/2017
|
100
|
12/08/2020
|
Final bill paid (recast)
|
|
22
|
HFMLIP/SUN/2015-16/EW-75
|
Re-excavation of Roua Gojaria Pichla Beel Connecting Khal at Ch 00-2000m Upazila: Sunamganj Sadar, District: Sunamganj
|
2.0000
|
1900039.000
|
LCS
|
1900039.000
|
|
|
75
|
21/09/2017
|
|
|
|
Total :
|
167.7020 (Km)
|
5641509.69 (Lac)
|
5641509.69 (Lac)
|
|
|
|
|
|
|
|