SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Chhagalniya
1 IRIDP-2/FNI/DW-115 a) Improvement of Nasirgram-kashipur Road from ch. 00-1320m.b) Construction of 3.00x3.00m culvert at ch. 1033m on the same road. 1.3200 58.300 M/S. Tulitushi Enterprise 58.300 30/03/2018 100 23/07/2019
2 IRIDP-2/FNI/DW-69 a) Improvement of East Modhugram Govt. Pry. School Road from ch. 00-770m.b) Construction of 03 nos 0.900x0.900m culvert at ch. 100,351& 542m on the same road. 0.7700 39.520 M/S. Tulitushi Enterprise 39.520 09/04/2018 100 23/07/2019
3 IRIDP-2/FNI/SMW-144 Maintenance of Mirjar Bazar-Uttar Jospur Road (South Jospur Pry. School Road) From Ch.00-800m & Mosque Connecting Link 370m. 1.1700 22.490 M/S. Kazi Construction 22.490 26/12/2017 100 09/07/2019
4 RIDP-2/FNI/DW-118 a) Improvement of Old DC road- Moulavi Moslay Uddin road (East Chhagalnaiya Mojumder Bari) Road ch. 00-1118m.b) Construction of 2.00x2.00m culvert at ch. 587m on the same road. 1.1180 44.590 M/S Bismillah Trading 44.590 31/01/2018 100 08/07/2019
5 IRIDP-2/FNI/DW-117 a) Improvement of Shahid Buddizibi Shafiqul Anower Mojumder Road from ch. 00-900m.b) Construction of 0.900x0.900m culvert at ch. 600m on the same road. 0.9000 39.960 M/S. Hoque Brothers 39.960 20/02/2018 100 08/07/2019
6 IRIDP-2/FNI/DW-71 a) Improvement of South Chagaria Samsuddin Road From Ch.960-1636m.b) Construction of 01 no 0.900x0.900m culvert at ch. 1600m on the same road. 0.6760 32.240 M/S. Kazi Construction 32.240 23/03/2017 100 08/07/2019
7 IRIDP-2/FNI/MW-70 Maintenance of Old DC Road & End of Champaknagar road (South Ballavbpur Road) From Ch.00-1050m. 1.0500 28.480 Faiz Ahmed 28.480 30/11/2016 100 08/07/2019
8 IRIDP-2/FNI/SDW-62 Construction of 2x 4.00mx4.00m RCC Box culvert on Captain leak road-East Debpur BDR (Sattnagar main road-Ahmed hossain road) road at ch. 2400m over Ghui khal. 15.700 M/S. Kazi Construction 15.700 20/03/2017 100 08/07/2019
9 IRIDP-2/FNI/DW-61 Improvement of Old DC road to Darogar hat (Koyara road-Shuvopur UP) road from ch. 00-900m. 0.9000 53.300 M/S Bhuiyan Enterprise 53.300 20/03/2017 100 08/07/2019
10 IRIDP-2/FNI/DW-60 Improvement of Samitir Bazar-Alokdia Vill. road from ch. 2250-3250m. 1.0000 50.200 M/S. Kazi Construction 50.200 18/07/2017 100 08/07/2019
11 IRIDP-2/FNI/SDW-54 a) Improvement of Diabibi Primary school from ch. 00-875m.b) Construction of 01 nos 0.900x0.900m culvert at ch. 447m on the same road. 0.8750 46.830 M/S. Kamal Hossain 46.830 16/02/2017 100 08/07/2019
12 IRIDP-2/FNI/MW-45 Maintenance of Darogar hat - Muhurigonj road (Subapur North Mondia road) from Ch. 00-555m 0 0 0 465,806.00 10 Oct 2016 488,357.59 14 Feb 2017 22 Nov 2016 100 0.5550 4.650 M/S. Kazi Construction 4.650 22/11/2016 100 08/07/2019
13 IRIDP-2/FNI/MW-44 Maintenance of Samitir bazar to Alokdia Village road (Samitir Bazar) road Ch.00-1660m. 1.6600 46.640 M/S. Goribshah Enterprise 46.640 06/12/2016 100 08/07/2019
14 IRIDP-2/FNI/MW-43 Maintenance of Old DC road - Muhurigonj road (Andarmanik Pry. School road ) from Ch.00-290m. 0.2900 4.100 M/S. Kazi Construction 4.100 10/10/2016 100 08/07/2019
15 IRIDP-2/FNI/MW-42 Maintenance of Satra Nadir Kul to Captain Leak (North Sattar-Mohamainya) road from Ch.00-509m. 0.5090 10.290 M/S. Kamal Hossain 10.290 06/06/2016 100 08/07/2019
16 IRIDP-2/FNI/MW-41 Maintenance of KB Hayder road- Chowdhury Bazar Mosque to Nurani Bazar Eidgha Contractor Mosque road (Middel Silua Pry. School) Shohel Chowdhury road from Ch. 00-540m 0.5400 8.270 M/S. Kamal Hossain 8.270 23/08/2016 100 08/07/2019
17 IRIDP-2/FNI/MW-40 Maintenance of Shubhapur Notun Bazar – India Border (Jaganath-Sonapur) road from ch. 00-3150m. 3.1500 80.120 M/S. Kazi Construction 80.120 16/12/2016 100 08/07/2019
18 IRIDP-2/FNI/DW-39 Improvement of West Devpur Masterpara (Boli kona) road ch. 00-700m. 0.7000 61.420 M/S. Goribshah Enterprise 61.420 24/10/2016 100 08/07/2019
19 IRIDP-2/FNI/DW-38 a) Improvement of East Chhagoalnaiya Baganbari road from ch. 00-960m.b) Construction of 01 nos 2x4.00x4.00m culvert at ch. 229m on the same road. 0.9600 63.230 M/S. Hannan Construction 63.230 03/02/2017 100 08/07/2019
20 IRIDP-2/FNI/MW-31 Maintenance of Rejumia Bridge to Diabibi Bazar (Rejumia-Old Diabibi Bazar) Road from ch.00-1250m. 1.2500 22.090 Mr. Rahim Uddin 22.090 23/08/2016 100 08/07/2019
21 IRIDP-2/FNI/DW-11 Improvement of Tashilder road to Yousuf Chowdhury road (Bash para Noapara) road from ch. 990-1510m. 0.5200 26.690 M/S J.J & Sons 26.690 24/11/2016 100 08/07/2019
22 IRIDP-2/FNI/DW-10 Improvement of Vender Nur Ahamed road to East Chagalnaiya BDR road (East Chagalnaiya Zibon Shah Fokir) road from ch. 00-567m. 0.5670 26.800 M/S. Hannan Construction 26.800 06/06/2016 100 08/07/2019
23 IRIDP-2/FNI/DW-7 Improvement of Sattra Nadir Kul to Captain Leak road (North Sattar-Mohamaiya) road from ch. 1000-1566m. 0.5660 32.000 M/S. Kazi Construction 32.000 23/08/2016 100 07/07/2019  
24 IRIDP-2/FNI/DW-9 Improvement of Uttar Panua DC road to Santir hat road ( Master Ali Ahamed) road from ch. 450-787m. 0.3370 17.190 M/S Fulkuri Traders 17.190 25/06/2016 100 07/07/2019
25 IRIDP-2/FNI/DW-8 Improvement of old DC road to Muhurigonj road ( Andar manik Pry. School) road from ch. 743-1190m. 0.4470 26.550 M/S T Bhuuiyan Electric 26.550 29/06/2016 100 07/07/2019
26 IRIDP-2/FNI/DW-6 Improvement of KB Hayder road-Chowdhury Bazar Mosque road (Middel Silua Pry. School road) Shohel Chowdhury road from ch. 540-1118m. 0.5780 27.220 Mr. Rahim Uddin 27.220 20/09/2016 100 07/07/2019
2 Feni-s
1 IRIDP-2/FNI/MW-156 Maintenance of Lalpool Bus Stand-Killar dhuar-Laxmipur connecting Road from Ch.00-1917m. 1.9170 39.290 M/S. Setu Enterprise 39.290 14/02/2018 100 28/07/2019
2 IRIDP-2/FNI/DW-154 a) Improvement of South Chanua Bai Bai Zafar Iqbal Road from Ch.00-513m.b) Construction of 0.600x0.600m culvert at ch. 384m on the same road. 0.5130 30.140 M/S. Abir Aiman Enterprise 30.140 31/03/2018 100 28/07/2019
3 IRIDP-2/FNI/DW-153 a) Improvement of East Silonia Dawakhana Road from Ch.00-857m.b) Construction of 3 Nos 0.600x0.600m culvert at ch. 336,470 & 648m on the same road. 0.8570 55.250 M/S. Jerin Enterprise 55.250 22/04/2018 100 28/07/2019
4 IRIDP-2/FNI/DW-151 Improvement of Dharmapur Amin uddin School-Keramotia Mosque-Miazi Bari via Rakkhit Bari (Laskar Road) Road from Ch.00-500m. 0.5000 30.470 M/S. Vai Vai Enterprise 30.470 19/08/2018 100 28/07/2019
5 IRIDP-2/FNI/DW-150 Improvement of Subalpur Azim Mizi Road from Ch.00-340m. 0.3400 19.380 M/S. Jerin Enterprise 19.380 10/09/2018 100 28/07/2019
6 IRIDP-2/FNI/DW-149 a) Improvement of Motubricfield-Zafar ahmmed Rd Upto Gopalkrisna sadhu Road from Ch.900-1451m.b) Construction of 0.600x0.600m culvert at ch. 1205m on the same road. 0.5510 30.870 M/S. Abir Aiman Enterprise 30.870 30/05/2018 100 28/07/2019
7 IRIDP-2/FNI/DW-147 Improvement of Middle Sonapur Rahamania Road from Ch.500-1020m. 0.5200 28.480 M/S. Omi Enterprise 28.480 28/03/2018 100 28/07/2019
8 IRIDP-2/FNI/DW-146 Improvement of Silonia Bazer- West Silonia Pry. School Road from Ch.00-740m. 0.7400 47.480 M/S. SAK Enterprise 47.480 30/05/2018 100 28/07/2019
9 IRIDP-2/FNI/DW-145 Improvement of Dhalia-Mohammadpur-Sharasia Road from Ch.830-1330m. 0 0.5000 29.580 M/S. Monowar Hossain 29.580 18/05/2018 0 28/07/2019
10 IRIDP-2/FNI/DW-141 Improvement of Sundarpur Bazar. 24.850 M/S. Setu Enterprise 24.850 100 28/07/2019
11 IRIDP-2/FNI/DW-140 a) Improvement of Chunua Kantapukur Road from Ch.600-1222m.b) Construction of 0.600x0.600m culvert at ch. 1148m on the same road. 0.6220 37.140 M/S. Alif Enterprise 37.140 05/05/2018 100 25/07/2019
12 IRIDP-2/FNI/DW-139 a) Improvement of Tataiya Munshipukur- Chunua Road from Ch.00-1171m.b) Construction of 03 nos 0.600x0.600m culvert at ch. 332,702 & 1035m on the same road. 1.1710 70.130 M/S. Alif Enterprise 70.130 05/05/2018 100 25/07/2019
13 IRIDP-2/FNI/MW-114 Maintenance of Chanua Bhuiyar Dokan-Chanua Bazar -Natun Bazar-Fazilpur UP Office Road from Ch.00-1300 m. 1.3000 47.050 M/S. Jerin Enterprise 47.050 05/11/2017 100 25/07/2019
14 IRIDP-2/FNI/DW-110 a) Improvement of Middle Laxmipur Master Rice Mill to Hazi Bari Road from Ch.00-875mb) Construction of 03 nos 0.600x0.600m culvert at ch. 75,228 & 465m on the same road. 0.8750 54.230 M/S. Jerin Enterprise 54.230 27/03/2018 100 25/07/2019
15 IRIDP-2/FNI/DW-109 Improvement of Fazilpur Badamtali (Hazi Rehan Uddin Bhuiyan Jam E-Mosque) Road from Ch.00-555m & Link 65.00m.b) Construction of 03 nos 0.600x0.600m culvert at ch. 90,195 & 435m on the same road. 0.6200 39.740 M/S. Alif Enterprise 39.740 15/09/2017 100 25/07/2019
16 IRIDP-2/FNI/MW-106 Maitenance of Chonua Intervillage Road from ch.00-1242m. 1.2420 30.460 M/S. Jerin Enterprise 30.460 08/04/2017 100 25/07/2019
17 IRIDP-2/FNI/MW-104 a) Maitenance of North South Khane Bari Road from Ch.00-1680mb) Construction of 04 nos 0.600x0.900m culvert at ch. 303,478,776 & 1200m on the same road. 1.6800 42.550 Mr. Rahim Uddin 42.550 28/05/2017 100 25/07/2019
18 IRIDP-2/FNI/MW-103 Maitenance of Saifulla Khandakar Road from Ch.00-1500m. 1.5000 25.780 M/S. Setu Enterprise 25.780 05/05/2017 100 25/07/2019
19 IRIDP-2/FNI/SDW-97 a) Improvement of Box Bazar Mozid Pukur-Henu Bhuiyan Bari Road from ch. 00-324m.b) Construction of 01 no 0.600x0.600m culvert at ch. 90m on the same road.c) Improvement of Tahashil Dighi Maddham Haqdee Prmary School to Tenduler Ghat Road from ch. 00-430m. 0.7540 37.520 M/S. Kamrul Enterprise 37.520 12/05/2017 100 25/07/2019
20 IRIDP-2/FNI/DW-96 a) Improvement of Chotadhali-Biroli Road (Biroli School road) from ch. 1100-1942m.b) Construction of 01 no 0.600x0.600m culvert at ch. 1410m on the same road. 0.8420 44.180 M/S. Chowdhury Enterprise 44.180 01/01/2018 100 25/07/2019
21 IRIDP-2/FNI/DW-95 a) Improvement of Balua Chowmohaani-Momtaz Meah Hat Road from ch. 3089-3880m.b) Construction of 01 no 0.600x0.600m culvert at ch. 3755m on the same road.c) Construction of 01 no 1x2.50x2.50m culvert at ch. 3240m on the same road. 0.7910 41.170 M/S. Setu Enterprise 41.170 10/11/2017 100 25/07/2019
22 IRIDP-2/FNI/DW-94 a) Improvement of Jatrasiddi-Daulatpur Road from ch. 2300-3438m.b) Construction of 01 no 1x2.50x2.50m culvert at ch. 2882m on the same road. 1.1380 68.580 M/S. Setu Enterprise 68.580 15/11/2017 100 25/07/2019
23 IRIDP-2/FNI/DW-93 a) Improvement of Muktizoddha Samsul Hoque Pori Road (Voter Dokan to Feni Comilla old road) from ch. 00-1070m.b) Construction of 01 no 1.20x0.600m culvert at ch. 198m on the same road. 1.0700 61.120 M/S. Alif Enterprise 61.120 15/11/2017 100 24/07/2019
24 IRIDP-2/FNI/DW-92 a) Improvement of Baraiya Taj Mohammed Bhuiyan Bari Road from ch.00-1005m.b) Construction of 04 nos 0.600x0.600m culvert at ch. 65,195,436 & 727m on the same road. 1.0050 53.650 M/S. Alif Enterprise 53.650 25/11/2017 100 24/07/2019
25 IRIDP-2/FNI/DW-91 a) Improvement of Baraiya Bhuiyan Bari Eidgha Road from ch.00-500m.b) Construction of 01 no 0.600x0.900m culvert at ch. 60m on the same road. 0.5000 24.130 M/S. Kamrul Enterprise 24.130 12/05/2017 100 24/07/2019
26 IRIDP-2/FNI/SDW-80 Improvement of Kashempur Baoair-Baskar Road from ch. 1950-2150m. 0.2000 9.460 Maya Enterprise 9.460 23/02/2017 100 23/07/2019
27 IRIDP-2/FNI/MW-37 Maintenance of National Highway-Padua B.O.P Road Ch. 00-2600m. 2.6000 21.340 M/S. Setu Enterprise 21.340 27/11/2016 100 23/07/2019
28 IRIDP-2/FNI/MW-36 Maintenance of Fazilpur Pubail Highway Road from Ch.00-1940m. 1.9400 26.130 M/S. Alif Enterprise 26.130 17/02/2017 100 23/07/2019
29 IRIDP-2/FNI/MW-35 a) Maintenance of Devipur Bisic Road from Ch. 00-1250m.b) Construction of 01 no 0.600mx0.600m culvert at ch. 92m on the same road. 1.2500 32.320 M/S. Kamrul Enterprise 32.320 27/11/2016 100 23/07/2019
30 IRIDP-2/FNI/MW-34 Maintenance of Fazilpur Walia Madrasha (Rahim Ullah Market) Road from Ch.00-848m. 0.8480 9.360 M/S. Alif Enterprise 9.360 29/06/2016 100 23/07/2019
31 IRIDP-2/FNI/SDW-33 Improvement of Fazilpur Saheed Sydur Rahman Contractor road from ch. 525-808m and Connecting road 51m 0.2830 28.030 M/S. Alif Enterprise 28.030 28/10/2016 100 23/07/2019
32 IRIDP-2/FNI/DW-32 IRIDP-2/FNI/DW-32 a) Improvement of Ram Mohan road (Dhalia-Khorshid Master Bari) road from ch.00-1080m.b) Construction of 03 nos 0.625mx0.600m culvert at ch. 525,845 & 1004m on the same road. 1.0800 56.380 M/S. Setu Enterprise 56.380 27/11/2016 100 23/07/2019
33 IRIDP-2/FNI/DW-23 a) Improvement of Langrar shop KM hat via Katamobarakgona Road ch.930-2070m.b) Construction of 02 nos 0.600mx0.600m culvert at ch. 1370 & 1714m on the same road.c) Construction of 01 no 1x2.50x2.50m culvert at ch. 940m on the same road. 1.1400 59.920 M/S Builders Engineers Associates 59.920 20/09/2016 100 23/07/2019
34 IRIDP-2/FNI/DW-22 a) Improvement of Rampur Salamar ghat Road (Lemua Elias Road) ch.00-1270m.b) Construction of 01 no 0.900mx0.900m culvert at ch. 700m on the same road.c) Construction of 01 no 1x2.00x2.00m culvert at ch. 353m on the same road. 1.2700 67.410 M/S Robiul Hoque 67.410 22/08/2016 100 23/07/2019
35 IRIDP-2/FNI/DW-21 Improvement of Sonapur Chowrasta to Sreepur Road ch. 1000-2500m. 1.5000 69.750 M/S. Sumon and Brothers 69.750 23/08/2016 100 23/07/2019
36 IRIDP-2/FNI/DW-20 a) Improvement of South Tal Tala Road ( Panchgachia UP) ch. 400-1060m.b) Construction of 02 nos 0.900mx0.900m culvert at ch. 503 & 753m on the same road. 0.6600 37.140 M/S. Century Traders 37.140 23/08/2016 100 23/07/2019
37 IRIDP-2/FNI/DW-18 a) Improvement of Badrabad Silua Akramuzzaman Bari Napith Ghata (Laxmipur-Shahapur Satsati) road from ch.00-1233m.b) Construction of 03 nos 0.600mx0.600m culvert at ch. 271,661 & 793m on the same road. 1.2330 58.230 M/S Rahman Traders 58.230 26/06/2016 100 23/07/2019
38 IRIDP-2/FNI/DW-17 a) Improvement Daulatpur Patwary Tack to Kali Babur Bari road from ch.00-950m.b) Construction of 02 nos 0.600mx0.600m culvert at ch.160 & 452m on the same road. 0.9500 47.520 M/S. Setu Enterprise 47.520 11/10/2016 100 23/07/2019
39 IRIDP-2/FNI/DW-16 Improvement of Kalidah High School (Kali mondir) road from ch.00-685m. 0.6850 35.790 M/S Saj Enterprise 35.790 10/10/2016 100 23/07/2019
40 IRIDP-2/FNI/DW-15 a) Improvement of Miar Bazar-Marurar char road from ch.00-1043m.b) Construction of 03 nos 0.600mx0.600m culvert at ch. 400,760 & 906m on the same road. 1.0430 48.850 M/S. Setu Enterprise 48.850 22/08/2016 100 23/07/2019
3 Fulgazi
1 IRIDP-2/FNI/DW-178 a) Improvement of Boiragpur Dakkhin Para Road from ch. 00-350m Link 30m.b) Construction of 2nos 0.600x0.900m culvert at ch. 322 & 367m on the same road. 0.3800 30.820 M/S. Chowdhury Niha Enterprise 30.820 13/06/2019 10 23/07/2019
2 IRIDP-2/FNI/DW-177 a) Improvement of East Goniamora Road (Joinal Member House/ Nurul Islam Chirman Road) from ch. 00-300m Link 30m.b) Construction of 0.600x0.900m culvert at ch. 15m on the same road. 0.3300 28.480 M/S. Nasir Enterprise 28.480 19/06/2019 30 23/07/2019
3 IRIDP-2/FNI/DW-179 Improvement of Sufi Borhan Uddin Road Link (Fredom fighter Mastar Tofazzal Hossain Road) from ch. 00-400m. 0.4000 36.220 M/S. Hasanuzzaman Bhuiyan 36.220 07/04/2019 100 23/07/2019
4 IRIDP-2/FNI/SMW-172 Maintenance of Bairagpur Morhum Horihor Paul Road from Ch.00-140m. 0.1400 8.850 M/S. Hasnuzzaman Bhuiyan 8.850 20/08/2018 100 09/07/2019
5 IRIDP-2/FNI/DW-170 Improvement of Connecting road of Shomir Bank House-Ear Ahammad Dillar House (Freedom Fighter Shahab Uddin) Road Ch.180m. 0.1800 8.590 M/S. Alahi Enterprise 8.590 26/10/2018 100 09/07/2019
6 IRIDP-2/FNI/SMW-169 a) Maintenance of Shahid Shofiul Azam Road from Ch.00-1555m and Link 415m.b) Construction of 1x2.00x2.00m culvert at ch. 1210m on the same road. 1.9700 48.880 M/S. Alahi Enterprise 48.880 23/06/2018 100 09/07/2019
7 IRIDP-2/FNI/DW-125 Improvement of Osiuddin road (Amjad Hat) Road from ch. 1527-1835 m. 0.3080 13.860 M/S. Alahi Enterprise 13.860 02/12/2017 100 09/07/2019
8 IRIDP-2/FNI/DW-123 a) Improvement of Shomir Banik House-Air Ahmed Dilar House (Fredom Fighter Sahabuddin Road) Road from ch. 00-990m.b) Construction of 4 Nos 0.600x0.600m culvert at ch. 90,300,400 & 840m on the same road. 0.9900 53.730 M/S. Alahi Enterprise 53.730 02/02/2018 100 09/07/2019
9 IRIDP-2/FNI/DW-122 a) Improvement of Dhalia Momtaj uddin Road from ch. 00-210m.b) Construction of 2 Nos 0.600x0.600m culvert at ch. 27 & 82m on the same road. 0.2100 17.220 M/S Nahar Enterprise 17.220 10/05/2018 100 09/07/2019
10 IRIDP-2/FNI/DW-121 a) Improvement of Bandhua Osmania Hafezia Madrasha Road (Harun Chirman Road) Road from ch. 00-650m.b) Construction of 4 Nos 0.600x0.625m culvert at ch. 98,130,244 & 455m on the same road. 0.6500 47.890 M/S. Iqbal Traders 47.890 15/12/2017 100 08/07/2019
11 IRIDP-2/FNI/SDW-99 a) Improvement of Nurpur Boro Bari Zame Mosque Road from ch. 00-300m.b) Construction of 01 nos 0.600x1.200m culvert at ch. 103m on the same road. 0.3000 17.520 M/S. Sumon and Brothers 17.520 19/05/2017 100 08/07/2019
12 IRIDP-2/FNI/DW-78 a) Improvement of Shaheed Ear Ahmmed road. Ch.900-2100m.b) Construction of 04 nos 0.600x0.900m culvert at ch. 1335,1540,1658 &1953m on the same road. 1.2000 75.630 M/S. Alahi Enterprise 75.630 07/05/2017 100 08/07/2019
13 IRIDP-2/FNI/DW-77 a) Improvement of Anandapur Railway station road. Ch.00-700m.b) Construction of 01 no 0.600x0.900m culvert at ch. 95m on the same road. 0.7000 39.780 M/S. Iqbal Traders 39.780 29/08/2017 100 08/07/2019
14 IRIDP-2/FNI/DW-76 a) Improvement of Mawlana Abdul Rahim road. Ch.00-527.60m. Link 204.00+193.00+58.90+16.50mb) Construction of 01 no 0.600x0.900m culvert at ch. 425m on the same road. 1.0000 49.130 M/S. Al Aksa Enterprise 49.130 08/03/2017 100 08/07/2019
15 IRIDP-2/FNI/DW-75 a) Improvement of Basura village road (Prominent Football Late Kabir Ahmed Mazumder) Road. Ch:00-735m.b) Construction of 04 nos 0.600x0.900m culvert at ch. 130,200,326 & 710m on the same road. 0.7350 41.590 M/S. Nazims 41.590 08/05/2017 100 08/07/2019
16 IRIDP-2/FNI/SDW-53 Improvement of Nishi Pondit road from ch. 1479-1581m and Link road 114.00m. 0.2160 15.920 M/S. Alahi Enterprise 15.920 09/11/2016 100 08/07/2019
17 IRIDP-2/FNI/DW-47 a) Improvement of Islampur road from ch. 990-1560m.b) Construction of 01 no 0.750x0.750m culvert at ch. 1280m on the same road. 0.5700 34.180 M/S Mozumder Transport 34.180 20/11/2016 100 08/07/2019
18 IRIDP-2/FNI/DW-46 Improvement of Goniamora-Joypur road rom ch. 1000-1800m. 0.8000 36.870 M/S Siraj Mozumder 36.870 20/11/2016 100 08/07/2019
19 IRIDP-2/FNI/DW-14 a) Improvement of Mosleuddin Road-Sree Goshipur Zia Road ch. 00-900m.b) Construction of 02 nos 0.600mx0.600m culvert at ch.155 & 317m on the same road. 0.9000 51.410 M/S. Alahi Enterprise 51.410 04/09/2016 100 08/07/2019
20 IRIDP-2/FNI/DW-13 Improvement of Pachibaria Chandanbia Primary School Road ch. 1750-2510m. 0.7600 38.600 M/S Nahar Enterprise 38.600 09/10/2016 100 08/07/2019
21 IRIDP-2/FNI/DW-12 Improvement of Ratan Chowdhury (Basantapur) road ch,00-300m. 0.3000 17.650 M/S. Alahi Enterprise 17.650 23/08/2016 100 08/07/2019
4 Porshuram
1 IRIDP-2/FNI/RMW-160 a) Maintenance of Rajashpur bazar-SaldharUP bazar-Charigram Samity-Satkuchia-Kalapul-Changazi Bazar-Narania-Box Mohammad bazar Road from ch.4100-6310m. b) Construction of 1X3.00mX3.00m Culvert at ch. 6300m on the same roadc) Construction of 1X1.00mX1.00m Culvert at ch. 6300m on the same road 0 4 0 0 8,399,108.00 0.00 0 83.990 83.990 0 23/07/2019
2 IRIDP-2/FNI/MW-160 Maintenance of Rajashpur bazar-SaldharUP bazar-Charigram Samity-Satkuchia-Kalapul-Changazi Bazar-Narania-Box Mohammad bazar Road from ch.4100-6310m. 2.2100 35.200 M/S. Sufia Enterprise 35.200 01/03/2019 100 09/07/2019
3 IRIDP-2/FNI/DW-120 Improvement of Durgapur - Ratanpur to Beker Bazar Road from ch. 00-850m. 0.8500 20.180 M/S Liton Brothers 20.180 12/12/2017 100 08/07/2019
4 IRIDP-2/FNI/DW-119 Improvement of West Side of Bottali Bazar House of jamaluddin to Rangamatia Road from ch. 00-1645m. 1.6450 70.650 M/S. Tulitushi Enterprise 70.650 25/03/2018 100 08/07/2019
5 IRIDP-2/FNI/DW-74 a) Improvement of Uttar Tetessor Captain Leak road – Fulgazi Box Mahmud road Ch.1000-2190m.b) Construction of 01 nos 1.00x1.00m culvert at ch. 2293m on the same road. 1.1900 65.530 M/S. Tulitushi Enterprise 65.530 20/12/2017 100 08/07/2019
6 IRIDP-2/FNI/MW-73 a) Maintenance work of Solia Middle Juba Shanga road & Leck Nayeb bari Mazer Professor Kona road from Ch. 00-1702m.b) Construction of 02nos 0.600x0.900m culvert at ch. 647 & 737m on the same road. 1.7020 21.060 M/S. Tulitushi Enterprise 21.060 30/12/2016 100 08/07/2019
7 IRIDP-2/FNI/DW-72 a) Improvement of Uttar Tetssor Brick field-Captin Leck Rd-Jame Mosque road at Ch.00-665m.b) Construction of 01 nos 1.00x1.00m culvert at ch. 34m on the same road.c) Construction of 05 nos 0.600x0.900m culvert at ch. 333,435,478, 732 & 802m on the same road. 0.6650 35.370 M/S. Tulitushi Enterprise 35.370 12/10/2017 100 08/07/2019
8 IRIDP-2/FNI/DW-63 a) Improvement of Durgapur-Ratanpur to Beker Bazar road (Connecting road) from ch. 280-530m, 680-805m & 800-935m.b) Construction of 05 nos 0.600x0.900m culvert at ch. 333,435,478, 732 & 802m on the same road. 0.5100 34.050 M/S Liton Brothers 34.050 20/03/2017 100 08/07/2019
9 IRIDP-2/FNI/DW-5 a) Improvement of South Gothuma Mangazi Bazar to Hafiz Ahmedulla Road from ch.00-500m.b) Construction of 02 nos 0.625mx0.600m culvert at ch.91 & 275m on the same road.c) Construction of 01 no 3x2.50x2.50m RCC box culvert at ch.422m on the same road. 0.5000 37.160 M/S Sahab Uddin 37.160 25/01/2017 100 07/07/2019
10 IRIDP-2/FNI/DW-4 a) Improvement of Charigram Pir-oli-Shaldhar-Beker Bazar Road from ch.00-500m.b) Construction of 02 nos 0.625mx0.600m culvert at ch.26 & 217m on the same road. 0.5000 34.910 M/S Abdur Rosul Mozumder 34.910 10/11/2016 100 07/07/2019
11 IRIDP-2/FNI/DW-3 a) Improvement of Jayantinagor-Mohespuskarni Road from ch.00-1000m.b) Construction of 01 no 1x2.00x2.00m RCC box culvert at ch.777m on the same road.c) Construction of 03 nos 0.625mx0.600m culvert at ch.4, 450 & 995m on the same road. 1.0000 66.050 M/S Sahab Uddin 66.050 11/10/2016 100 07/07/2019
12 IRIDP-2/FNI/DW-2 a) Improvement of Chitolia Dhanmia Fakir’s Mazar to Satkuchia Road from ch.00-500m.b) Construction of 02 nos 0.625mx0.600m culvert at ch.143 & 253m on the same road. 0.5000 27.030 M/S Sahab Uddin 27.030 31/12/2016 100 07/07/2019
13 IRIDP-2/FNI/DW-1 Improvement of Tolatoli to Champaknagor Road (Champaknagor village Road from ch.00-500m. 0.5000 28.560 M/S. Tulitushi Enterprise 28.560 25/01/2017 100 07/07/2019
Total : 85.4490 (Km) 3782.28 (Lac) 3782.28 (Lac)