Physical Annual Target ofthe Project (FY: 2018-19)
(InLakh Taka)
Name of Important Components
(With quantity)
Cost as per DPP
Target of current year
(2018-19)
Financial
Physical
1
2
3
4
1. Improvement of Upazila road (19.52Km)
1514.74
111.06
1.43 km
2. Improvement of Union road (57.49 Km)
3790.41
523.50
7.32 km
3. Improvement of Village road (999.20 Km)
56183.61
6761.91
109.67 km
4. Bridge on Upazila road (43.20 m)
296.05
0.00
0.00 m
5.Culvert on Upazila road (29.50 m)
83.40
26.80
9.50 m
6.Culvert on Union road (48.50 m)
128.48
7.Bridge on Village road (345.00 m)
1631.45
448.04
99.00 m
8.Culvert on Village road (865.80 m)
1779.07
212.37
80.00 m
9. Widening & strengthening (23.58 km)
1773.93
71.44
1.15km
10. Development of Growth Centre (10 Nos)
478.97
0.00 nos.
11.Slope Protection (2122.76 sq. m)
380.98
10.48
112.76 sqm
12. Maintenance of Rural Roads (201.30 km.)
5201.46
204.40
10.00 km