1
|
CoCC2-01
|
(a) Reconstruction of road Start from Kazipara road (Pry. School) to Kazipara road (Graveyard) via Kazipara area by B.C. from I.S.G. (b) Development of road from Old Ctg road (Chowara cattle market) to Dhaka – Chittagong Highway(matiara) via hindu para+ 1 bridge (30m)
(c) Reconstruction of road from Lacsam road to Airport road, and Kazipara road via herapur ,Mostapur, Laxminagar, Disabond and Kazipara
(d) Construction of Drain (RCC/Briek/ Pipe) from EPZ khal to Laxminagar Chowmohony, Asrayon, Airport road.by RCC
|
CGP
|
cumilla-s
|
|
3.20
|
|
|
1041.12
|
MAMCL-PC-SAS(JV)
|
1040.87
|
|
17/12/2017
|
16/12/2018
|
0
|
|
|
|
|
2
|
CoCC2-02
|
(a) Reconstruction of road Start from Dhaka-Chittogong Highway road (Joypur) to Kotbari road (Singapur Market) area by B.C. from I.S.G.
(b) Reconstruction of road Start from Kotbari road (Beltoly school gate) to Batabaria moszid by B.C. from I.S.G.
(c) Development of Monipur road (from Batabaria to City Boundary) by B.C. from I.S.G.
(d) Reconstruction of road Start from Kotbari road (Gondmoty moszid) to Museum road (Shalbon High school & opposite side of BARD Boundary) & Gabtoly Beby Stand via Bagmara & Lalmai area. Link : Morapara road & Mannan Darbesh house road by B.C. from I.S.G.
(e) Repairing of Museum road (Kotbari road to University) by Base Course and B.C.
|
CGP
|
cumilla-s
|
|
21.82
|
|
|
3816.06
|
RAB-RC(PVT)LTD,M/S HOQUE ENTERPRISE (JV)
|
3815.70
|
|
20/06/2018
|
26/10/2019
|
0
|
|
|
|
|
3
|
ICGP B2 CoCC-03
|
Part: 1, Road Improvement
a) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road to Airport Road (Laxmipur Chownohony) Via Gram Chowara And Laxmipur By B.C From I.SG.( Ch. 0+000 to 02+ 855 m). b) Reconstruction of Road Start From Old Dhaka-Chittagong Highway road (Near City Corporation Office) Via Raypur, Dayapur. Link From Doyapur Madrasa to Dhaka-Chittagong Highway Road By B.C From I.SG. (Ch. 0+000 to 02+ 772 m). c) Contraction of Road Start From Dhaka-Chittagong Highway Road to Airport Road, Domoria Road & Tarapaia Road Via Laxminagar, Laxmipur Katcha Road By B.C (Ch. 00+00 to 02+ 284 m) Link -1(Ch. 0+ 000 To 0+ 278) Link -2(Ch. 0+000 To 0+ 625) d) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road (Old Chowara) to Rajapara (Near Post Office) Via Domoria, Tarapaia & Noapara By B.C From I.S.G (Ch. 0+000 to 03+302m) e) Reconstruction of Dhaneshor Road (From Old Dhaka - Chittagong Highway Road to Airport Road) By B.C From I.S.G. (Ch.0+000 to 02+368m). f) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road to Airport Road Via Goalmothon & Rajapara By B.C From I.S.G (Ch.0+000 to 02+812m). Link -1 (Ch.0+000 to 0+700) g) Reconstruction of Road Start From Old Dhaka-Chittagong Highway Road (Chowara Madrasha & Chira Mill) to Dhaka-Chittagong Highway Road (Matiara & Chashapara) By B.C From I.S.G.(Ch.0+000 to 1+148m). Link -1 (Ch.0+000 to 0+657) Link-2 (Ch.0+000 to 0+539)
Part: 2, Drainage
a) Contruction of Drain (RCC) From Laxmipur Khal to Dhaka- Chittagong Highway Besides Airport Road & From Doyapur Madrasa (Ch. 0+000-0+712)Link -1 (Ch.0+000-1+372) b) Contruction of Drain (RCC) From Sonaichori Khal to Funka Industries Besides Old Dhaka-Chittagong Highway Road.(Ch.0+000-2+449)
|
CGP
|
cumilla-s
|
|
24.87
|
|
|
4260.58
|
HASAN TECHNO BUILDERS,TAHER BROTHERS LTD (JV)
|
4259.42
|
|
20/06/2018
|
26/10/2019
|
0
|
|
|
|
|
4
|
ICGP B2 CoCC04
|
(c) Re-construction of 8m span R.C.C. Bridge at Kazipara.
(d) Re-construction of 8m span R.C.C. Bridge at Near Noagah Chowmohony over katakhali khal.
(h) Construction of 3X5.0mX4.0m RCC Box Culvert at Rececourse Khalpar
|
CGP
|
cumilla-s
|
|
0.04
|
|
|
528.05
|
HASAN BUILDERS
|
528.05
|
|
17/12/2017
|
16/12/2018
|
0
|
|
|
|
|
5
|
ICGP B2 CoCC09
|
b) (i) Reconstruction of drain from Akther Hamid Khan road to Morden Hospital and Nowgaon chowmohoni (Laksam road) via RAB office, Ch.0+000-1+063.
b) (ii) Reconstruction of drain from Akther Hamid Khan road to Morden Hospital and Nowgaon chowmohoni (Laksam road) via RAB office, Link, Ch.0+000-0+341.
c) (i) Reconstruction of Rampur road from Kourt bari road (Cantonment gate and opposite side of land office) to Kourt bari road (Moynamoty Housing) via Rampur area, Ch.0+000-1+690. 1 x 1 m x 1 m Size Box Culvert at Ch.0+603, 0+825, 0+928, 1+207, 1+351, 1+385. & 1 x 3 m x 1.5 m Size Box Culvert at Ch.1+325,& 1x1.5mx1.5m box culvert at Ch.1+588.
c) (ii) Reconstruction of Rampur road from Kourt bari road (Cantonment gate and opposite side of land office) to Kourt bari road (Moynamoty Housing) via Rampur area, Link, Ch.0+000-0+593. 1 x 1.5 m x 1.5 m Size Box Culvert at Ch.0+476.
f) (ii) Reconstruction of drain from Laksam road to Easin market via Mirpukurpar, Ch.0+000-0+402.
g) Reconstruction of drain from Thomson bridge - EPZ (North side) - Housing Estate - Medical College near Bakhrabad Gas office.Ch.0+000-2+450. & Link drain At Ch.1+755(R/S), Ch.0+000-0+250.
|
CGP
|
cumilla-s
|
|
6.79
|
|
|
1466.38
|
Hasan builders
|
1466.22
|
|
17/12/2017
|
16/12/2018
|
0
|
|
|
|
|
6
|
CoCC2-05
|
(a) Excavation of Khal from Medical Hospital to EPZ road with beautification. ( Ch. 00 + 00 to 00 + 800 m.)
(b) Excavation of Airport khal (EPZ poket gate to Gopenathpur khal/Canal) . ( Ch. 00 + 00 to 05 + 000 m.)
(c) Excavation of Unaishar khal (South- Westen side of EPZ wall to Gopenathpur khal/Canal via Kazipara-Hirapur) with beautification ( Ch. 00 + 00 to 7 + 000 m.)
(d) Excavation of Kuchaitoly khal (Kuchaitoly to Gopenathpur khal/Canal via Donessor-Rajapara-Tarapaia) . ( Ch. 00 + 00 to 15 + 000 m.)
(e) Excavation of Sonaichori khal/Canal (from Pathankot to Gopenathpur khal/Canal via Chowara Bazar Matiara) . ( Ch. 00 + 00 to 06 + 000 m.)
|
CGP
|
cumilla-s
|
|
28.47
|
|
|
1665.06
|
HASAN TECHNO BUILDERS,TAHER BROTHERS LTD (JV)
|
1663.91
|
|
09/07/2018
|
03/09/2019
|
0
|
|
|
|
|
7
|
CoCC2-08
|
b) Construction of Drain, Footpath & Road at Fazlul Hoque Road (From Kandirpar to Rajgonj) (Ch. 0+00 to 0+729) and Construction of Drain & Footpath from Post Office or Circuit House to Rajgonj (Ch. 0+000 to 0+626).
c) Re-construction of Drain Judge Court-Eidgah-Stadium Market-New Market-Kandirpar to Circit House road side Khal at Hotel Salauddin (Ch. 0+000 to 1+900).
|
CGP
|
cumilla-s
|
|
5.02
|
|
|
1506.45
|
Rana builders
|
1565.77
|
|
22/01/2018
|
21/01/2019
|
0
|
|
|
|
|
8
|
CoCC2-06
|
Installation of 9 nos production Tube-wells including pump house with all other accessories in ward no 01 to 27
|
CGP
|
cumilla-s
|
|
|
|
|
568.09
|
MSST-MCS JV
|
584.56
|
|
27/11/2018
|
26/11/2019
|
0
|
|
|
|
|
9
|
CoCC2-07
|
Installation of street lighting system in different areas of CoCC (2550 Nos. GI Pole with 2550 Nos. LED Street light Including all accessories)
|
CGP
|
cumilla-s
|
|
|
|
|
2068.61
|
PDL-IEL-MDHV(JV)
|
1949.60
|
|
22/01/2018
|
21/01/2019
|
0
|
|
|
|
|
10
|
CIB-Com-W-58
|
Const. of 570m long PSC Girder Bridge over Gomoti river on Daudkandi GC-BataKandi GC via Mohonpur Lanchghat road at Ch. 2050m under Daudkandi Upazila, District: Cumilla
|
CIBRR
|
daudkandi
|
419362005
|
|
570.00
|
34
|
5874.65
|
"MD.Moyen Uddin (Bashi) Limited & MS Jakir Enterprise (JV) "
|
6687.31
|
19/07/2020
|
26/07/2020
|
01/06/2025
|
48
|
2252.46
|
34
|
05/02/2025
|
|
11
|
CIB-Com-W-57
|
"Const. of 97m Bridge Over Titas River On Kalagacia Bridge-Kriparampur GPS Road at Ch.247m under Homna Upazila,District: Cumilla
[Road ID: 419545047] CIB-Com-W-57. "
|
CIBRR
|
homna
|
419545047
|
|
97.00
|
62
|
1019.95
|
M/S Mostafa Kamal , Pro : Md. Mostafa Kamal
|
1116.70
|
10/04/2022
|
17/04/2022
|
07/09/2024
|
90
|
695.44
|
62
|
05/02/2025
|
|
12
|
CIB-Com-W-52.
|
Const. of 45m long Bridge over Karjon Khal on Laksam UP H/Q - Chitoshi ( Maulana Bazar) Via Shiriyang Road at Ch. 8225 m under Laksam Upazila, District: Cumilla
|
CIBRR
|
laksham
|
419722005
|
|
45.00
|
65
|
0.00
|
M/S Mostafa Kamal,Brahmanbaria
|
791.36
|
05/08/2021
|
12/08/2021
|
30/05/2025
|
80
|
372.76
|
65
|
05/02/2025
|
|
13
|
CIB-Com-W-113
|
Const. of 43m long Bridge over Dakatia River on Chunati Bridge to Monohorpur Road at Ch. 0.00 m under Laksam Upazila, District: Cumilla
|
CIBRR
|
laksham
|
419725059
|
|
43.00
|
36
|
630.39
|
Kasem Traders Of The New Trade Link ( JV)
|
737.11
|
11/05/2022
|
18/05/2022
|
06/03/2024
|
50
|
268.92
|
36
|
05/02/2025
|
|
14
|
CIB-Com-W-118
|
"Construction of 35 m bridge on Curzon canal at 1200 m chainage on Jalal Memorial High School via Maulana Bazar road from Kagaiya Torab Ali High School under Laksam upazila, District: Cumilla (Road ID: 419724087).
CIB-Com-W-118."
|
CIBRR
|
laksham
|
419724087
|
|
35.00
|
34
|
382.96
|
Faridpur Jannat Construction Ltd, Hasina Tower (8th Floor), Mujib Sarak, Faridpur Sadar, Faridpur.
|
421.18
|
14/06/2022
|
21/06/2022
|
09/04/2024
|
40
|
143.00
|
34
|
05/02/2025
|
|
15
|
CIB-Com-W-55
|
Const. of 495m long PSC Girder Bridge With 144m RCC Viaduct over Meghna Branch river on Calibanga bazar to Islampur road at Ch. 1900m under Meghna Upazila, District: Cumilla
|
CIBRR
|
meghna
|
419884031
|
|
495.00
|
0
|
7905.22
|
Navana Construction Ltd. Hous#28/A, Road#83, Gulshan-2, Dhaka-1212
|
380.72
|
05/05/2019
|
12/05/2019
|
14/05/2022
|
100
|
0.00
|
0
|
05/02/2025
|
|
16
|
CIB-Com-W-56
|
Const. of 472m long PSC Girder Bridge over Meghna Branch river on Boraia Kandi Village to Tulatuli Bazar road at Ch. 2000 m under Meghna Upazila, District: Cumilla
|
CIBRR
|
meghna
|
419884032
|
|
472.00
|
70
|
0.00
|
MD.MOYENUDDIN (BASHI) LIMITED-HAMIDA TRADERS LIMITED (JV)
|
5386.90
|
19/07/2021
|
26/07/2021
|
01/03/2025
|
81
|
3806.12
|
70
|
05/02/2025
|
|
17
|
CIB-Com-W-25
|
Const. of 675m long PSC Girder Bridge over Meghna Branch river on Araila (Muddarkandi) Ghat to Haripur-Rampur UP road at Ch. 1069m under Meghna Upazila, Dist. Comilla
|
CIBRR
|
meghna
|
419884004
|
1.07
|
675.00
|
37
|
10433.73
|
MIL-MCS-JV
|
9895.71
|
07/09/2021
|
14/09/2021
|
20/04/2025
|
46
|
3670.27
|
37
|
05/02/2025
|
|
18
|
CIB-Com-W-55(b)
|
Const. of 636.70m long PSC Girder Bridge over Meghna Branch river on Calibanga bazar to Islampur road at Ch. 1900m under Meghna Upazila, District: Cumilla [Road ID: 419884031]. CIB-Com-W-55(b)
|
CIBRR
|
meghna
|
419884031
|
|
636.70
|
4
|
8328.77
|
MIL-MCS-Joint Venture.
|
9575.80
|
28/08/2023
|
04/09/2023
|
03/09/2026
|
20
|
372.00
|
4
|
05/02/2025
|
|
19
|
CIB-Com-W-105
|
Const. of 81m long Bridge over Dakatia River On Mandargaon Bazar-Dakhin Jalom UPC Road at Ch.2648m under Monohorganj Upazila,District: Cumilla
|
CIBRR
|
monohorganj
|
419903010
|
|
81.00
|
50
|
1405.42
|
MAX INFRASTRUCTURE Ltd.27,Dilkusha C/A Baitul Hussain Building,6th Floor,Dhaka
|
1612.59
|
17/11/2021
|
24/11/2021
|
28/02/2025
|
65
|
811.05
|
50
|
05/01/2025
|
|
20
|
CIB-Com-W-130
|
Const. of 81m long PSC Girder Bridge over Dakatia river on Shantir Bazar-Pipodda road at Ch.3270m under Nangalkot Upazila, District: Comilla
|
CIBRR
|
nangalkot
|
419874130
|
|
81.00
|
100
|
517.94
|
Rana Builders (Pvt) Ltd-M/s Hassan Builders-M/s Zaman Traders JV
|
522.81
|
25/01/2018
|
01/02/2018
|
30/11/2020
|
100
|
522.60
|
100
|
05/02/2025
|
|
21
|
CIB-Com-W-129
|
Const. of 150m long PSC Girder Bridge over Dakatia river on Dhalua Bazar GC Dorkar road at Ch.5500m under Nangalkot Upazila, District: Cumilla [Road ID: 419872012]
|
CIBRR
|
nangalkot
|
Road ID: 419872012
|
|
150.00
|
82
|
0.00
|
M/S Kohinoor EnterPrise, Dadpur Lodge,Kawnia 1st Lane, Barishal Sadar, Barishal.
|
1479.30
|
01/03/2021
|
08/03/2021
|
30/11/2023
|
90
|
1308.83
|
82
|
05/02/2025
|
|
22
|
CRMIDP/COM/W-453
|
Brammonpara Bazar
|
CRMIDP
|
brahmanpara
|
|
|
|
12
|
277.00
|
MA Zaher Ltd-M/S Anower Foundation
|
265.82
|
11/07/2022
|
|
28/07/2022
|
20
|
32.58
|
12
|
28/07/2022
|
|
23
|
CRMIDP/COM/W-457
|
Kadoir Bazar
|
CRMIDP
|
chouddagram
|
|
|
|
61
|
278.00
|
"M/S M M Enterprise-M/S Mazumder Traders (JV) Vill- Unkot, Post. Unkot P.S. Chauddagram, Cumilla "
|
294.64
|
07/08/2019
|
|
30/06/2022
|
70
|
178.48
|
61
|
28/07/2022
|
|
24
|
CRMIDP/COM/W-458
|
Munshir Hat
|
CRMIDP
|
chouddagram
|
|
|
|
21
|
467.00
|
"M/S Rahana Construction Pro. Md Mohibul alam Mazumder, Vill-Noagram, Post. Sukchail, P.S. Chauddagram, Cumilla. "
|
494.98
|
06/08/2019
|
|
02/08/2022
|
40
|
105.08
|
21
|
28/07/2022
|
|
25
|
CRMIDP/COM/W-462
|
Bijra Bazar
|
CRMIDP
|
laksham
|
|
|
|
20
|
488.00
|
M/S H. Kabir Enterprise
|
531.29
|
16/07/2020
|
|
03/01/2022
|
35
|
106.31
|
20
|
28/07/2022
|
|
26
|
CRMIDP/COM/W-467
|
Hesakhal Bazar
|
CRMIDP
|
nangalkot
|
|
|
|
74
|
263.00
|
"M/S Meazi Enterprise Shreefolia, Nangalkot, Cumilla. "
|
262.72
|
16/09/2019
|
|
30/06/2022
|
90
|
194.47
|
74
|
28/07/2022
|
|
27
|
CRMIDP/COM/W-468
|
Choria Bazar
|
CRMIDP
|
nangalkot
|
|
|
|
75
|
283.00
|
"M/S Rahana Construction –M/S Arsad & Sons (JV) Pachim Bagisagaon, Adarsha Sadar, Cumilla "
|
295.29
|
08/08/2019
|
|
30/06/2022
|
85
|
222.44
|
75
|
28/07/2022
|
|
28
|
GCP-3/C-M25 ID 419094055
|
Periodic Maintenance (Overly) of Konagram-Egarogram Road at (Ch.00-2870m).(T.ID 181877)
|
GCP-3
|
barura
|
|
2.87
|
|
|
64.92
|
M/S Patowary Enterprise
|
64.69
|
|
23/04/2018
|
22/05/2018
|
40
|
|
|
|
|
29
|
GCP-3/C-M32 ID 419153007
|
Periodic Maintenance (Re-seal) of Uttar Chandla bazar (R & H) Madhabpur UP Office Road at ch.00-3415m)(T.ID 180802)
|
GCP-3
|
brahmanpara
|
|
3.42
|
|
|
67.37
|
M/S Shuvo Enterprise
|
64.00
|
|
24/05/2018
|
20/10/2018
|
50
|
|
|
|
|
30
|
GCP-3/C-M07 ID 419184074
|
Periodic Maintenance (Overlay) of Kalikapur Chamer DIGHI-Jangle biari more Road(Ch.00-1262m). (T. ID 162083)
|
GCP-3
|
burichong
|
|
1.26
|
|
|
22.65
|
M/S Akter Enterprise
|
22.65
|
|
01/03/2018
|
21/08/2018
|
100
|
|
|
|
|
31
|
GCP-3/C-W28 ID 419273017
|
a) Improvement of Chaigaria-Barera UPC Road from ch.1700-3060m. b) Construction of 257m proction work on the same road. (T. ID 162084)
|
GCP-3
|
chandina
|
|
1.36
|
|
|
112.74
|
M/S M M Enterprise
|
118.37
|
|
01/03/2018
|
04/04/2019
|
40
|
|
|
01/04/2019
|
|
32
|
GCP-3/C-W41 ID 419314238
|
a) Improvement of Durgapur uttar para Chiowmu-hany-kheish purba para Road ch.00-590m b) Construction of 0.60m Culvert on the same road.c) Construction of 72m proction work on the same road. (T. ID 174845)
|
GCP-3
|
chouddagram
|
|
0.59
|
|
|
45.49
|
M/S Janoni Varatis Store
|
47.77
|
|
20/05/2018
|
26/11/2018
|
70
|
|
|
01/04/2019
|
|
33
|
GCP-3/C-W42 ID 419315029
|
a) Improvement of Mestala (Mazumder bari) Suvapur GPS via Laxipur Road ch.1307-1948m b)Construction of 1.20m Culvert on the same road. c) Construction of 90m proction work on the same road. (T. ID 174846)
|
GCP-3
|
chouddagram
|
|
0.64
|
|
|
50.14
|
M/S Norjahan Traders
|
52.63
|
|
24/05/2018
|
30/11/2018
|
40
|
|
|
01/04/2019
|
|
34
|
GCP-3/C-W43 ID 419315171
|
a) Improvement of Dhaka Cty Highway-Kuliara-Ludiara Road ch.00-800m b) Construction of 1.80m Culvert on the same road. (T. ID 174847)
|
GCP-3
|
chouddagram
|
|
0.80
|
|
|
58.85
|
M/S Patowary Enterprise
|
61.79
|
|
20/05/2018
|
20/12/2018
|
100
|
|
|
01/04/2019
|
|
35
|
GCP-3/C-W36 ID 419315034
|
a) Improvement of Bulkara (Bhuyabari)-Patoary Bari Road Via Madrasha ch.00-1090m. b) Construction of 1.20m Culvert on the same road.c) Construction of 58m proction work on the same road.( ID174838)
|
GCP-3
|
chouddagram
|
|
1.09
|
|
|
75.32
|
M/S G S Fashion
|
79.09
|
|
15/05/2018
|
20/01/2019
|
70
|
|
|
|
|
36
|
GCP-3/C-W37 ID 419314127
|
a) Improvement of Harisarder Bazar-Jugirkhil-Gujra-Danushara Hafejia Madrasha road ch.2365-3265m b) Construction of 1.20m Culvert on the same road. c) Construction of 220m proction work on the same road. (T. ID 1174840)
|
GCP-3
|
chouddagram
|
|
0.90
|
|
|
73.67
|
M/S Abul Hasam
|
77.34
|
|
28/06/2018
|
04/03/2019
|
10
|
|
|
|
|
37
|
GCP-3/C-W38 ID 419314296
|
a) Improvement of Latif Shikder (Jame Msq)-Taiyashar ch.00-920m b) Construction of 0.60m Culvert on the same road.(T. ID 174842)
|
GCP-3
|
chouddagram
|
|
0.92
|
|
|
63.71
|
M/S Norjahan Traders
|
66.88
|
|
24/05/2018
|
30/01/2019
|
30
|
|
|
|
|
38
|
GCP-3/C-W40 ID 419315296
|
a) Improvement of Hilalnagar South para Msq-Kashinagar H/School Road ch.00-1570m.b) Const. of 4.20m Culvert on the same road. c) Const.of 134 m proction work on the same road.(T. ID 174844)
|
GCP-3
|
chouddagram
|
|
1.57
|
|
|
119.40
|
M/S Tanha Enterprise
|
125.35
|
|
09/05/2018
|
15/05/2019
|
70
|
|
|
|
|
39
|
GCP-3/C-W39 ID 419315211
|
a) Improvement of Ashadia Purbapara Julp dhokan-Baraipur road ch.600-1600m.b) Construction of 1.60m Culvert on the same road.c) Construction of 15m proction work on the same road (T.ID 174843)
|
GCP-3
|
chouddagram
|
|
1.00
|
|
|
73.23
|
M/S Abul Hasam
|
76.88
|
|
14/06/2018
|
20/02/2019
|
20
|
|
|
|
|
40
|
GCP-3/C-W66 ID 419314157 ID 419314163
|
(a.1) Improvement of Basantapur (Motin Member)-Nankora Mohila Madrasha-Dhaka Cht .Khathalgach road at ch. 230-1360m.(a.2)Const. of 3.60m Culvert on the same road.(b.1) Improvement of Anandapur-Kaliksha Madrasha road ch.00-885m.(b.2) Const.of 3.20m Culver
|
GCP-3
|
chouddagram
|
|
2.02
|
|
|
164.03
|
M/S Orpita Bricks Manutacturer
|
172.20
|
|
30/07/2018
|
|
0
|
|
|
|
|
41
|
GCP-3/C-M23 ID 419314009
|
Periodic Maintenance(Widening & Rehabilitation) of Felnaq high school-Pachimuri village-Fulmuri-Bahergora-Solakandi bazar Road (Ch.800-6425m) (T. ID 178356)
|
GCP-3
|
chouddagram
|
|
2.00
|
|
|
187.28
|
M/S Fatema Traders
|
196.58
|
|
29/05/2018
|
05/12/2018
|
100
|
|
|
|
|
42
|
GCP-3/C-M34 ID 419675018 ID 419675034 ID 419674021
|
(a) Rehabilitation (RCC Road) of Jagannathpur (Saw Mill)-Baba Shaheb Mazar Road (Ch.00-5km)(b)Reha-bilitation (RCC Road of Bodurpur-Ariora Road(Ch.00-635km)c)Periodic Maintenance (Overly) of Ratnabaria-Shimpur High School Road (00-50km) (T.ID 181886)
|
GCP-3
|
cumilla-s
|
|
2.68
|
|
|
194.73
|
M/S Mizanur Rahman
|
204.47
|
|
22/05/2018
|
18/11/2018
|
100
|
|
|
|
|
43
|
GCP-3/C-M35 ID 419675056 ID 419675057 ID 419674019
|
(a) Rehabilitation (RCC Road) of Dowlatpur T & T Chowmohany to Shahid Moktijudda Road (Ch.00-968 km (b) Rehabilitation (RCC Road) of Dowlalpur Saya-bitan to Afjal Khan Karigori Commerce Road (Ch,00 -385km) c) Periodic Maintenance (Overly) of Jambari Govt
|
GCP-3
|
cumilla-s
|
|
2.05
|
|
|
188.44
|
M/S Alamgir Hossain
|
197.86
|
|
19/06/2018
|
04/11/2019
|
100
|
|
|
|
|
44
|
GCP-3/C-M29 ID 419674008 ID 419674003
|
a) Periodic Maintenance (Overly) of Mona-gram-Bowara Bazar Road at (Ch.00-3387m). b) Periodic Maintenance (Overly) of Bashmongal Chowmo-hani-Toilkupi Bazar Road at (Ch.00-1555 & 2755-4220km) (T. ID 180799)
|
GCP-3
|
cumilla-s
|
|
6.41
|
|
|
114.40
|
M/S Rashid & Brothers
|
120.12
|
|
09/08/2018
|
08/06/2019
|
0
|
|
|
|
|
45
|
GCP-3/C-M51 ID 419675028 ID 419675050
|
(a) Periodic Maintenance (RCC Road) of Khamar Bari RHD-Araiora Kha para RHD Road Ch.00-1040m) (b) Periodic Maintenance (Reseal) of Dsanpur Madinagar-Eidha to Rongpur pacca Road(Ch.00-403m. (T. ID 205316)
|
GCP-3
|
cumilla-s
|
|
1.44
|
|
|
130.18
|
M/S Eshan Enterprise
|
136.69
|
|
08/10/2018
|
08/06/2019
|
90
|
|
|
|
|
46
|
GCP-3/C-W35 ID 419915018
|
a) Improvement of Changahata-Dattapur Road at ch.1200-2000m b) Construction of 118m proction work on the same road. (T.ID 162091)
|
GCP-3
|
cumilla-s daksin
|
|
0.80
|
|
|
59.01
|
M/S Abul Kashem Bricks
|
61.44
|
|
13/05/2018
|
19/12/2018
|
30
|
|
|
01/04/2019
|
|
47
|
GCP-3/C-W03 ID 419915026
|
a) Improvement of Asheckare Tulatoli-Pangab-Poroti Road at ch.00-2310m b) Construction of 69m proction work on the same road.(T.ID 166303)
|
GCP-3
|
cumilla-s daksin
|
|
2.31
|
|
|
158.36
|
M/S Zaman Traders
|
173.99
|
|
05/04/2018
|
11/04/2019
|
100
|
|
|
|
|
48
|
GCP-3/C-W05 ID 419915192
|
a) Improvement of (Comilla-Laksam) RHD-Asotola-Monoharpur Road at ch.00-1733m b) Construction of 133m proction work on the same road. (T.ID 167345)
|
GCP-3
|
cumilla-s daksin
|
|
1.73
|
|
|
123.39
|
M/S Zaman Traders
|
135.58
|
|
12/04/2018
|
18/04/2019
|
100
|
|
|
|
|
49
|
GCP-3/C-W06 ID 419915189
|
a) Improvement of Khgilpara-Kamarkua-Daksin Ciloniya-Gojaria-Lodoua-Kondra Road at ch.00-2000m b) Construction of 122m proction work on the same road. (T.ID 167363)
|
GCP-3
|
cumilla-s daksin
|
|
2.00
|
|
|
142.47
|
M/S Zaman Traders
|
156.55
|
|
05/04/2018
|
11/04/2019
|
100
|
|
|
|
|
50
|
GCP-3/C-W04 ID 419915190
|
a) Improvement of Gonti-Metallah-Montola Road Via Ishapura at ch.00-1530m. b) Construction of 141m proction work on the same road. (T.ID155793)
|
GCP-3
|
cumilla-s daksin
|
|
1.53
|
|
|
110.16
|
M/S Arsad & Sons
|
110.14
|
|
03/04/2018
|
09/04/2019
|
100
|
|
|
|
|
51
|
GCP-3/C-W07 ID 419914052
|
a) Improvement of Harirchar-Sharpur-Alishar Road at ch.00-850m. (T.ID 180807)
|
GCP-3
|
cumilla-s daksin
|
|
0.85
|
|
|
56.90
|
M/S Chowdhury Traders
|
59.71
|
|
21/06/2018
|
27/02/2019
|
20
|
|
|
|
|
52
|
GCP-3/C-W02 ID 419915199
|
a) Improvement of Donpur-Joykamtta road at ch.00-2310m. b) Construction of 179m proction work on the same road. (T.ID 180806)
|
GCP-3
|
cumilla-s daksin
|
|
2.31
|
|
|
74.25
|
M/S Nasir Traders
|
77.95
|
|
06/09/2018
|
06/03/2019
|
5
|
|
|
|
|
53
|
GCP-3/C-M39 ID 419913020
|
Periodic Maintenance (Overly) of Devipur-Board Office-Maruali-Akbaliya Road at (Ch.00-3330Ch.1674-3339m (T. ID 181891)
|
GCP-3
|
cumilla-s daksin
|
|
1.64
|
|
|
65.69
|
M/S Munni Enterprise
|
68.15
|
|
23/04/2018
|
31/10/2018
|
20
|
|
|
|
|
54
|
GCP-3/C-M28 ID 419914025 ID 419914020
|
a) Periodic Maintenance (Overly) of Kamalpur-Kachuarpar-Julal-Uttar Bagalpur Road at (Ch.00-3395m) b) Periodic Maintenance (Overly) of Subapur-Subamapur-Joshpur (BOP)-Murapara-Krishnagar-Kaneshtala at (Ch.00-3180m) (T. ID 180798)
|
GCP-3
|
cumilla-s daksin
|
|
6.58
|
|
|
145.95
|
M/S Mazumder Enterprise
|
145.66
|
|
19/04/2018
|
03/06/2018
|
80
|
|
|
|
|
55
|
GCP-3/C-M45 ID 419914087
|
Periodic Maintenance (Overly) of Shahpur Maruali-Durgapur Road at (ch.00-2133m) (T. ID 185844) (T.ID……......……)
|
GCP-3
|
cumilla-s daksin
|
|
2.13
|
|
|
47.52
|
M/S Shah Poran Enterprise
|
47.29
|
|
10/05/2018
|
09/11/2018
|
0
|
|
|
|
|
56
|
GCP-3/C-W26 ID 419363004
|
a) Improvement of Jinglatali UP Office Road at ch 1286-3190m. b) Construction of 798m proction work on the same road. (T. ID 160267)
|
GCP-3
|
daudkandi
|
|
1.90
|
|
|
204.65
|
M/S Liberty Traders
|
204.48
|
|
11/04/2018
|
17/04/2019
|
25
|
|
|
|
|
57
|
GCP-3/C-W27 ID 419364015
|
a) Improvement of Raypur bazar-Hatkhola Bazar Road at ch.00-200m.b) Construction of 354m proction work on the same road. (T.ID 160268)
|
GCP-3
|
daudkandi
|
|
0.20
|
|
|
60.27
|
M/S Tithi Enterprise
|
62.98
|
|
28/03/2018
|
03/12/2018
|
50
|
|
|
|
|
58
|
GCP-3/C-W44 ID 419365082
|
a) Improvement of Kalairkandi-Dawlaterkandi Road ch.00-1150m b) Construction of 50m proction work on the same road. (T. ID 174848)
|
GCP-3
|
daudkandi
|
|
1.15
|
|
|
83.39
|
M/S Liberty Traders
|
86.77
|
|
25/06/2018
|
01/02/2019
|
5
|
|
|
|
|
59
|
GCP-3/C-W46 ID 419364017
|
a) Improvement of Tulatuli bazar-Kawadi Nutan bazar Road ch00-600m b) Construction of 114m proction work on the same road. (T. ID 174850)
|
GCP-3
|
daudkandi
|
|
0.60
|
|
|
48.12
|
M/S Miazi Constraction
|
50.53
|
|
23/05/2018
|
29/11/2018
|
30
|
|
|
|
|
60
|
GCP-3/C-W45 ID 419364003
|
a)Improvement of Ginlataly Zinglatali-Mohananda bazar via Kallanpur Pry School Road ch.915-2000m b)Construction of 105m proction work on the same road. (T. ID 174849)
|
GCP-3
|
daudkandi
|
|
1.09
|
|
|
82.79
|
M/S Suchana Enterprise
|
86.93
|
|
14/05/2018
|
14/12/2018
|
5
|
|
|
|
|
61
|
GCP-3/C-M12 ID 419363016
|
Emergency Maintenance of Batnagar-Bazar-Talerseo bazar via Mohammad pur Purba up Office Road (ch.00-2556m) (T. ID 182601)
|
GCP-3
|
daudkandi
|
|
2.56
|
|
|
10.18
|
M/S Bhuiyan Traders
|
9.88
|
|
06/06/2018
|
12/07/2018
|
20
|
|
|
|
|
62
|
GCP-3/C-M01 ID 419364015
|
Periodic Maintenance (Widening & Rehabilitation) of Raipur Bazar Hatkhola Bazar Road (Ch.200-2423m).(T. ID 160269)
|
GCP-3
|
daudkandi
|
|
2.22
|
|
|
167.41
|
M/S Tithi Enterprise
|
174.94
|
|
28/03/2018
|
30/10/2018
|
40
|
|
|
|
|
63
|
GCP-3/C-W55 ID 419403010 ID419403024
|
a(i) Improvement of Dhamti UPC (Dhankhar) to Cholash Bazar Road at ch 1600-2480 & 2785-3850m. a(ii) Construction of 160m proction work on the same road. b(i) Improvement of Mohanpur UPC-Tulagaon Bazar via Kurain Madrasha Road at ch. 1191-1854m. b(ii) Co
|
GCP-3
|
debidwar
|
|
1.63
|
|
|
198.51
|
M/S Joy Construction
|
188.59
|
|
09/07/2018
|
15/05/2019
|
30
|
|
|
|
|
64
|
GCP-3/C-W54 ID 419404014
|
a) Improvement of C & B Nabpur-Juktagram Road at ch. 500-2500m b) Construction of 9.00m Culvert on the same road. C) Construction of 131m Proctive work on the same road.(T. ID 181880)
|
GCP-3
|
debidwar
|
|
2.00
|
|
|
162.77
|
M/S Joy Construction
|
154.63
|
|
09/07/2018
|
15/05/2019
|
20
|
|
|
|
|
65
|
GCP-3/C-W56 ID 419404036 ID419404072
|
a(i) Improvement of Saichapara Bazar-Sultanpur Road at ch 1328-2500m. a(ii) Construction of 219m proction work on the same road.b(i) Improve-ment of Jafarganj R & H-Shorab Chairman House Road at Ch.00-563m. b(ii) Construction of 2m Culvert on the same r
|
GCP-3
|
debidwar
|
|
1.74
|
|
|
141.19
|
M/S Joy Construction
|
134.13
|
|
09/07/2018
|
15/05/2019
|
25
|
|
|
|
|
66
|
GCP-3/C-W57 ID419405102 ID419404094
|
a(i) Improvement of Abdulapur GC Road-Gomti Ayli via Saker Bari Road ch. 00-700m. a(ii) Construction of 0.60m Culvert on the same road. b(i) Improvement of Debidwar R & H (Fakir Bari)-Gunaighat Arang Bazar via Hazi Ayenuddin Bari Road ch. 00-1500m. b(i
|
GCP-3
|
debidwar
|
|
2.20
|
|
|
168.83
|
M/S Joy Construction
|
160.39
|
|
10/07/2018
|
15/05/2019
|
15
|
|
|
|
|
67
|
GCP-3/C-W62 ID419405099 ID419405097
|
a(i) Improvement of Jrajapur Bablu Boumik House-Potia Para Salam Member House Road at ch.00-670 m & ch.5376-6130m a(ii)Construction of 166m Proctive work on the same road. b) Improvement of Sibnagar Bridge BWDB Ayil-Bali Bari Kheya Ghat Road at ch.00-100
|
GCP-3
|
debidwar
|
|
2.42
|
|
|
121.01
|
M/S Abdul Jalil
|
114.96
|
|
30/08/2018
|
30/07/2019
|
10
|
|
|
|
|
68
|
GCP-3/C-M37 ID 419402002
|
Periodic Maintenance (Rehabilitation) (Overty) of Charbakar RHD-Mohanpur GC Road at ch..4100m-9900m) (T. ID 181889)
|
GCP-3
|
debidwar
|
|
5.80
|
|
|
176.53
|
M/S Sumi Enterpreise
|
157.70
|
|
04/06/2018
|
10/02/2019
|
50
|
|
|
|
|
69
|
GCP-3/C-M36 ID 419403015 ID 419403002
|
(a) Periodic Maintenance (Rehabilita-tion) of Chotoshalg- har Bazar-Brashalghar TPC (Syedpur bazar) (Ch.00-157 4m) (b) Periodic Mantenance (Widening & Rehabilitation of Sultanpur UPC (Natioinal H Way)-Bakrikandi bazar Road at ch.(Ch.00-1970m)(T.ID181888)
|
GCP-3
|
debidwar
|
|
2.13
|
|
|
117.98
|
M/S Joy Construction
|
112.08
|
|
23/04/2018
|
12/12/2018
|
30
|
|
|
|
|
70
|
GCP-3/C-W01 ID 419724023
|
a) Improvement of Babukpara Bazar-Bizrz R & H Road (Ch.1260-3700m.b) Construction of 167m proction work on the same road.T.ID 166265)
|
GCP-3
|
laksham
|
|
2.44
|
|
|
173.35
|
M/S Farhana Builders
|
190.49
|
|
05/04/2018
|
11/04/2018
|
100
|
|
|
|
|
71
|
GCP-3/C-W58 ID 419724008 ID419724018
|
a(i) Improvement of Krishnapur R & H-Amdour R & H Road at ch.1290-2495m. a(ii) Construction of 337m proction work on the same road. b(i) Improvement of Krishnapur R & H-Digdair (Sholodana) Road at ch. 00-1000m b(ii) Constru-ction of 262m proction wo
|
GCP-3
|
laksham
|
|
2.21
|
|
|
181.77
|
M/S Arife Enterprise
|
189.04
|
|
24/06/2018
|
30/06/2019
|
50
|
|
|
|
|
72
|
GCP-3/C-W59 ID 419724028 ID 419724001 ID419724006
|
a(i) Improvement of Bamonda R & H-Aoushpara Road at ch.2570-2907m.b(i) Improvement of Satbariya-Nagtiya Road at ch.1865-2909m. b(ii) Construction of 230mproction work on the same road. road.c(i)Improvement of Barobam R & H- Chiloin Road at ch.160-2350m.
|
GCP-3
|
laksham
|
|
2.57
|
|
|
201.89
|
M/S Arif Enterprise
|
211.98
|
|
21/05/2018
|
26/09/2019
|
30
|
|
|
|
|
73
|
GCP-3/C-M54 ID 419722005
|
Periodic Maintenance(Widening & Rehabilitation) of Laksam Upazilla H/Q-Chitoshi RHD (Moulana bazar) via Seeyang Road at ch.00-3000m). (T. ID 215724)
|
GCP-3
|
laksham
|
|
3.00
|
|
|
195.86
|
M/S Farhana Builders
|
0.00
|
|
20/11/2018
|
30/06/2019
|
0
|
|
|
|
|
74
|
GCP-3/C-M55 ID 419723002
|
Periodic Maintenance (Widening & Rehabilitation) of Moham- mad pur-Gazirpar Road at ch.00-3330m). (T.ID215725)
|
GCP-3
|
laksham
|
|
3.33
|
|
|
212.34
|
M/S Farhana Builders
|
0.00
|
|
29/08/2018
|
29/03/2019
|
5
|
|
|
|
|
75
|
GCP-3/C-M27 ID 419724053
|
Periodic Maintenance (Overly) of Gunti Bazar-Bagla Bazar via Sakra Bazar Road at (Ch.00-2617m). (T.ID 181879)
|
GCP-3
|
laksham
|
|
2.62
|
|
|
54.82
|
M/S Arsad & Sons
|
54.81
|
|
23/04/2018
|
09/03/2019
|
100
|
|
|
|
|
76
|
GCP-3/C-W64 ID 419364045
|
a) Improvement of Baharkhola South Natun Bazar-Kathakhali to Vatharchar-Omrakanda Hiugh Way BC Road at ch.00-1040m b)Construction of 120m Proctive work on the same road. (T. ID 198508)
|
GCP-3
|
meghna
|
|
1.04
|
|
|
85.46
|
M/S National Trade System
|
89.72
|
|
22/09/2019
|
22/09/2019
|
10
|
|
|
|
|
77
|
GCP-3/C-M38 ID 419882003
|
Periodic Maintenance (Widening & Rehabilitation) of Chandanpur Manlkarchar Road ch..00-3330m(T. ID 181890)
|
GCP-3
|
meghna
|
|
3.33
|
|
|
177.18
|
M/S Shohag Enterprise
|
168.32
|
|
06/05/2018
|
12/12/2018
|
30
|
|
|
|
|
78
|
GCP-3/C-W34 ID 419902009
|
a) Improvement of Laksam H/Q-Natherpetue RHD via Munshir- hat GC Road (Monohargonj Portion) at ch.00-1260m & 2538-3758m.b) Construction of 0.625 m Culvert on the same road.c) Construction of 678m proction work on the same road. (T.ID162090)
|
GCP-3
|
monohorganj
|
|
2.48
|
|
|
259.12
|
M/S Farhana Builders
|
283.68
|
|
08/07/2018
|
14/07/2019
|
20
|
|
|
|
|
79
|
GCP-3/C-W32 ID 419903027
|
a) Improvement of Baishgaon UPS-Baishgaon Bazar via Saktola Road at ch.00-1100mb)Constru- ction of 1.875m Culvert on the same road c)Construction of 52m proction work on the same road. (T. ID 177319)
|
GCP-3
|
monohorganj
|
|
1.10
|
|
|
81.50
|
M/S Zaman Traders
|
89.46
|
|
22/03/2018
|
02/01/2019
|
100
|
|
|
|
|
80
|
GCP-3/C-W29 ID 419904097
|
a) Improvement of Mirzapur-South Bottala-Mirzapur Natun Bazar via Mirzapur Pri.School Road at ch. 00-960m.b) Construction of 0.625 m Culvert on the same road.c) Construc-tion of 257m proction work on the same road.(T.ID 172318)
|
GCP-3
|
monohorganj
|
|
0.96
|
|
|
77.13
|
M/S Zaman Traders
|
84.67
|
|
22/03/2018
|
26/04/2019
|
100
|
|
|
|
|
81
|
GCP-3/C-W30 ID 419905036
|
a) Improvement of Monohorgonj GC-Chikutia-Amtoli Bazar Road at ch. 600-1600m.b) Constru-ction of 0.625m Culvert on the same road.c) Construction of 1.250m proction work on the same road.(T.ID 162086)
|
GCP-3
|
monohorganj
|
|
1.00
|
|
|
83.65
|
M/S Ma Enterprise
|
83.56
|
|
01/03/2018
|
23/04/2019
|
20
|
|
|
|
|
82
|
GCP-3/C-W31 ID 419904073
|
a) Improvement of Alinakibpur-Raktomondar Hat via Baduara Road at ch.750-1670m.b) Construction of 0.625m Culvert on the same road.c) Const- ruction of 139m proction work on the same road(T. ID 172320)
|
GCP-3
|
monohorganj
|
|
0.92
|
|
|
74.06
|
M/S Zaman Traders
|
81.30
|
|
26/04/2018
|
07/10/2019
|
100
|
|
|
|
|
83
|
GCP-3/C-W61 ID 419812003
|
a.1)Improvement of Jafarganj GC-Panchpukuria road at ch.00-818 m & ch.5376-6130m.a.2) Construction of 180m Proctive work on the same road (T.ID198505)
|
GCP-3
|
muradnagar
|
|
1.57
|
|
|
146.85
|
M/S S.F International
|
154.00
|
|
10/09/2018
|
15/09/2019
|
0
|
|
|
|
|
84
|
GCP-3/C-M26 ID 419814016
|
Periodic Maintenance (Overly) of Muradnagar-Homna RHD to Ramchandrapur RHD Road at (Ch.00-1250m). (T. ID 181878)
|
GCP-3
|
muradnagar
|
|
1.25
|
|
|
31.51
|
M/S Refiq Traders
|
29.93
|
|
23/04/2018
|
23/05/2018
|
10
|
|
|
|
|
85
|
GCP-3/C-M46 ID 419813004
|
Periodic Maintenance (Widening & Rehabilitation) of Karoibari-Hydrabad Road at ch..00-3582m (T. ID 208486)
|
GCP-3
|
muradnagar
|
|
3.58
|
|
|
111.72
|
M/S Refiq Traders
|
117.30
|
|
29/08/2018
|
04/05/2019
|
10
|
|
|
|
|
86
|
GCP-3/C-W11 ID 419874220
|
a) Improvement of Makrabpur Azad Market-Olipur via Shahabapur Road at ch. 00-2500m b)Construction of 1.20m Culvert on the same road.c) Construc-tion of 412m proction work on the same road.(T.ID 170671)
|
GCP-3
|
nangalkot
|
|
2.50
|
|
|
185.30
|
M/S Fatema Traders
|
203.65
|
|
|
|
60
|
|
|
01/04/2019
|
|
87
|
GCP-3/C-W16 ID 419874171
|
a) Improvement of Bhakihati Primary School Aziapara Bazar Road at ch.00-1000m.b) Constru- ction of 257m proction work on the same road.(T.ID 181874)
|
GCP-3
|
nangalkot
|
|
1.00
|
|
|
77.53
|
M/S Alam Trading Corporation
|
81.40
|
|
|
|
60
|
|
|
01/04/2019
|
|
88
|
GCP-3/C-W17 ID 419874170
|
a) Improvement of Manikgonga-Chandpour Mosjgd Road at ch.00-2154m b) Construction of 1.20m Culvert on the same road.c)Construction of 238m proction work on the same road.(T.ID 171763)
|
GCP-3
|
nangalkot
|
|
2.15
|
|
|
139.29
|
M/s Ma moni Enterprice
|
148.97
|
|
|
|
10
|
|
|
01/04/2019
|
|
89
|
GCP-3/C-W10 ID 419874220
|
a) Improvement of Kashipur-Jeniara-Dhan-muri road at ch. 00-1470m. b) Construction of 208m proction work on the same road.(T.ID 181871)
|
GCP-3
|
nangalkot
|
|
1.47
|
|
|
105.89
|
M/S Ma Moni Enterprise
|
105.89
|
|
|
|
20
|
|
|
01/04/2019
|
|
90
|
GCP-3/C-W12 ID 419874215
|
a) Improvement of Madanpur Bhuiyan Bari Azain Road at ch.00-1285m. b) Construction of 1.20m Culvert on the same road. c)Construction of 130m proction work on the same road.(T.ID 171760)
|
GCP-3
|
nangalkot
|
|
1.29
|
|
|
92.43
|
M/S Madina Construction
|
96.96
|
|
|
|
20
|
|
|
01/04/2019
|
|
91
|
GCP-3/C-W13 ID 419874224
|
a) Improvement of Doulkher-Narayonbatur Road at ch.00-1035m b) Construction of 152m proction work on the same road. (T.ID 181872)
|
GCP-3
|
nangalkot
|
|
1.04
|
|
|
76.30
|
M/S Nur Ayasha Traders
|
969.57
|
|
|
|
60
|
|
|
01/04/2019
|
|
92
|
GCP-3/C-W23 ID 419874238
|
a) Improvement of Dayemchati-Hesakhal via Surid Technical College at ch. 00-1455m b)Construction of 1.20m Culvert on the same road.c)Construction of 504m proction work on the same road.(T.ID 160265)
|
GCP-3
|
nangalkot
|
|
1.46
|
|
|
121.45
|
M/S Nur Ayasha Traders
|
127.46
|
|
|
|
30
|
|
|
01/04/2019
|
|
93
|
GCP-3/C-W24 ID 419874238
|
a) Improvement of Maghua-Chiora Road at ch.00-1190m.b)Construction of 69m proction work on the same road. (T. ID 160266)
|
GCP-3
|
nangalkot
|
|
1.19
|
|
|
81.70
|
M/S Madina Construction
|
85.70
|
|
|
|
30
|
|
|
01/04/2019
|
|
94
|
GCP-3/C-W15 ID 419873030
|
a) Improvement of Padua Primary School Road at ch.00-1000m.b) Construction of 89m proction work on the same road. (T.ID 171760)
|
GCP-3
|
nangalkot
|
|
1.00
|
|
|
65.18
|
M/S Madina Construction
|
71.66
|
|
|
|
80
|
|
|
|
|
95
|
GCP-3/C-W18 ID 419873018
|
a) Improvement of Baiana-Karpati-Goharua-Manik-mura Road at ch.00-1498m b)Construc-tion1498m b)Construction of 1.80m Culvert on the same road. c) Construction of 174m proction work on the same road(T.ID 171832)
|
GCP-3
|
nangalkot
|
|
2.15
|
|
|
109.69
|
M/S Arsad & Sons
|
120.55
|
|
|
|
60
|
|
|
|
|
96
|
GCP-3/C-W19 ID 419873019
|
a) Improvement of Dhalua-Bisnapur-Changara-Noapara Chadia Bazar Road at ch.5600-6468m b)Construction of 1.20m Culvert on the same road.c) Construction of 102m proction work on the same road. (T.ID 171811)
|
GCP-3
|
nangalkot
|
|
0.87
|
|
|
64.26
|
M/S Latif Builders
|
66.51
|
|
|
|
50
|
|
|
|
|
97
|
GCP-3/C-W21 ID 419873027
|
a) Improvement of Montali Olipur Samir-khil Kestala Tilip Mowyra Gomkot Road at ch.2022-3787m b)Construction of 1.20m 1.20m Culvert on the same Road.C)Construc-ction of 280m proction work on the same road.(T. ID 181875)
|
GCP-3
|
nangalkot
|
|
1.77
|
|
|
128.78
|
M/S Nur Ayasha Traders
|
135.22
|
|
|
|
60
|
|
|
|
|
98
|
GCP-3/C-W14 ID 419873030
|
a) Improvement of Shahpur-Tua Hesakhal Road at ch.1870-3687m. b) Construction of 114m proction work on the same road. (T.ID 181873)
|
GCP-3
|
nangalkot
|
|
1.82
|
|
|
131.78
|
M/S Arsad & Sons
|
138.30
|
|
|
|
15
|
|
|
|
|
99
|
GCP-3/C-W08 ID 419915018
|
a) Improvement of Harirchar-Sharpur-Alishar Roiad at ch.00-850m.b) Construction of 122m proction work on the same road. (T.ID 172669)
|
GCP-3
|
nangalkot
|
|
1.48
|
|
|
106.03
|
M/S Arsad & Sons
|
116.10
|
|
|
|
65
|
|
|
|
|
100
|
GCP-3/C-W09 ID 419874205
|
a) Improvement of Koiya-Laxmipadua via Shebpur Road at ch.00-1590m.b) Construction of 1.80m Culvert on the same road.c)Construction of 182m proction work on the same road. (T.ID 180808)
|
GCP-3
|
nangalkot
|
|
1.59
|
|
|
114.66
|
M/S Nur Ayasha Traders
|
120.39
|
|
|
|
40
|
|
|
|
|
101
|
GCP-3/C-W20 ID 419874242
|
a) Improvement of Pachim Bampara-Batagaon-Tolatoli Nagooripara Road at ch.00-3300m b) Const.of 528m proction work on the same road. (T.ID 171812)
|
GCP-3
|
nangalkot
|
|
3.35
|
|
|
242.69
|
M/S Farhana Builders
|
266.85
|
|
|
|
100
|
|
|
|
|
102
|
GCP-3/C-W22 ID 419874142
|
a) Improvement of Narayanvatua-Narachow Road at ch.00-1700m.b) Construction of 1.20m Culvert on the same road c) Construction of 157m proction work on the same road.(T. ID 181876)
|
GCP-3
|
nangalkot
|
|
1.70
|
|
|
118.66
|
M/S Razu Enterprise
|
128.59
|
|
|
|
0
|
|
|
|
|
103
|
GCP-3/C-M11 ID 419872007
|
Periodic Maintenance (Re-Const)of Double Lane 3x3.00x 4.00m RCC Box culvert Nangalkot (Omargonj)-Tuguria RHD Road at ch.6270m (T. ID 174846)
|
GCP-3
|
nangalkot
|
|
|
|
|
41.77
|
M/S Madina Construction
|
43.65
|
|
03/05/2018
|
09/11/2018
|
0
|
|
|
|
|
104
|
GCP-3/C-M22 ID 419873004
|
Periodic Maintenance (Widening & Rehabilitation) of Daulkher-Kamarhat Road (Ch 00-2000m) ((T.ID 173898)
|
GCP-3
|
nangalkot
|
|
2.00
|
|
|
120.40
|
M/S Madina Construction
|
125.82
|
|
28/03/2018
|
21/08/2018
|
100
|
|
|
|
|
105
|
GCP-3/C-M30 ID 419874060 ID 419874216 ID 419874134
|
a) Periodic Maintenance (Overly) of Gohanua-Nischinta-pur-Kamarhat-Chatarpala Road at (Ch.2400-3870m) b) Periodic Maintenance (Overly) of Puria Bazar-Uttar Shaktoli Road at (Ch.00-1055m) c) Periodic Maintenance (Overly) of Shantir Bazar-Surfua BazarRoad
|
GCP-3
|
nangalkot
|
|
4.07
|
|
|
123.43
|
M/S Madina Construction
|
117.25
|
|
24/05/2018
|
30/11/2018
|
80
|
|
|
|
|
106
|
GCP-3/C-M31 ID 419874152 ID 419874075 ID 419874110
|
a) Periodic Maintenance (Overly) of Peria-Sreefolia Road via Principle Shiddiquer Rahman House Road at (Ch.00-1170m) b) Periodic Maintenance (Overly) of Goharua-Nischintapur Road at (Ch.00-1115m) c)Periodic Nischintapur
|
GCP-3
|
nangalkot
|
|
4.68
|
|
|
128.29
|
M/S Nur Ayasha Traders
|
121.88
|
|
23/04/2018
|
23/05/2018
|
0
|
|
|
|
|
107
|
GCP-3/C-M59 ID 419895022
|
Periodic Maintenance (Rehabilitation) of Gouripur- Homna Road to Ziakandi Purbapara Road (Ch.00-765m) (T. ID 220883)
|
GCP-3
|
titas
|
|
0.77
|
|
|
30.49
|
M/S Labanna Construction
|
30.19
|
|
18/11/2018
|
24/02/2019
|
0
|
|
|
|
|
108
|
GSIDP/COM/SDW-02
|
Improvement of Sibnagar Uttar para Madrasha Jame Mosjid. Union: Chandanpur, Latitude: 23.65401, Longitude: 90.67002
|
GSIDP
|
meghna
|
|
|
|
0
|
7.72
|
M/S. Salim Enterprise
|
15.43
|
11/09/2018
|
|
03/06/2019
|
100
|
0.00
|
0
|
20/03/2019
|
|
109
|
GSIDP/COM/SDW-03
|
Improvement of Chandanpur Uttar para Jame Mosjid. Union: Chandanpur, Latitude: 23.66125, Longitude: 90.6987
|
GSIDP
|
meghna
|
|
|
|
65
|
8.04
|
M/S. Shohag Enterprise
|
15.28
|
26/06/2018
|
|
03/06/2019
|
100
|
|
65
|
20/03/2019
|
|
110
|
GSIDP/COM/SDW-04
|
Improvement of Sonarchar Dhakhin para Jame Mosjid. Union: Gobindhapur, Latitude: 23.367571, Longitude: 90.4310986
|
GSIDP
|
meghna
|
|
|
|
100
|
8.36
|
M/S Muna Enterprise
|
15.88
|
20/06/2018
|
|
10/10/2018
|
100
|
7.94
|
100
|
20/03/2019
|
|
111
|
GSIDP/COM/SDW-05
|
Improvement of Sibnagar Eid Gha Field. Union: Chandanpur, Latitude: 23.6542, Longitude: 90.69007
|
GSIDP
|
meghna
|
|
|
|
100
|
5.92
|
M/S Lipi Enterprise
|
11.25
|
14/06/2018
|
|
08/10/2018
|
100
|
5.61
|
100
|
20/03/2019
|
|
112
|
GSIDP/COM/SDW-06
|
Improvement of Sibnagar Graveyeard. Union: Chandanpur, Latitude: 23.6571, Longitude: 90.70012
|
GSIDP
|
meghna
|
|
|
|
77
|
5.84
|
M/S. Shohag Enterprise
|
11.10
|
26/06/2018
|
|
03/06/2019
|
100
|
|
77
|
20/03/2019
|
|
113
|
IDFPC/CHAN/ 2018-2019/ W-01
|
1. a) Improvement of RCC Road (Ch. 0.00-314.57m, Width 3.050m $ Length 314.57m) St, from infront of the City cell Tower to res. Of Prof, Manun, In Ward # 01, Under Chandina Pourashva, District : Cumilla.
b) Improvement of BC Road (Ch. 0.00-258.30, Width 3.050m & Length 258.30m) St, from infront of the Gov, Hospital to res of Badal Furniture, In Ward # 01, Under Chandina Pourashva, District : Cumilla.
c) Construction of RCC Drain (Ch. 0.00-132.00m, Width 0.60m & Length 132.00m) St, from Res, of Proff. Mamun to North way rws, of Ayet Ali, In Ward # 01, Under Chandina Pourashva, District : Cumilla.
|
IDFPC
|
chandina
|
|
572.87
|
|
|
7840648.00
|
M/S. Zia Enterprise
|
7448615.00
|
23/07/2019
|
30/07/2019
|
|
100
|
|
|
06/12/2020
|
|
114
|
IDFPC/Chan/ 2019-2020/ W-02
|
Improvement of RCC Road(Ch. 00.00-359.00, width -1.80m & Length =359.00) & Construction of Brick Drain (ch.00.00-180.00m, Width = 0.900m & Length =180.00m) St from in front of Sub-register office of owapda Road five Storied Res. Building , In ward No. 01, Under Chanidna Poursashava, Cumilla.
Construction of RCC Road St. from Barak Shahab House of Asmoth Miah House road Under Chandina Pourashava , Cumilla.
Construction of RCC Road at Balashair Suruj Member New House – RNH road Under Chandina Pourashava , Cumilla, Ward no. 0 ( Ch.00-270m) .
Improvement of RCC Road at Wapda road H/O Jasim- East Side of Graveyard Road Under Chandina Pourashava , Cumilla, Ward no. 0( Ch.00-135m) .
|
IDFPC
|
chandina
|
|
884.00
|
|
47
|
7677040.86
|
M/S. ROBIN ENTERPRISE
|
7293188.80
|
07/10/2020
|
07/10/2020
|
|
50
|
|
47
|
06/12/2020
|
|
115
|
IDFPC/Chan/ 2019-2020/W-03
|
Const. of RCC Road st. from Girls School to latifpur road in ward no.05 road under Chandina Pourashava , Cumilla
"Improvement of RCC Road at Odalia Bridge (Odalia Majar) – West Side Shahjahan House road Under Chandina Pourashava , Cumilla, Ward no. 0
( Ch.00-165m) ."
Improvement of Unblock Road(Ch. 00.00-165.00, width -3.050m & Length =165.00) & St from in front of the Moharong Zame Mosque to west embank of Hoyale pond, In Ward No. 01, Under Chanidna Poursashava, Cumilla link Road, Improvement of Unblock Road(Ch. 00.00-53.64m, width -1.83m & Length =53.640m) & St. from Moharong House of Habib Cashier to South House of Saha Alam, In ward No. 01, Under Chanidna Poursashava, Cumilla.
Earth Filling of Mamun Prof. House – Khachhuairpar road at Chandina Pourashava , Cumilla
|
IDFPC
|
chandina
|
|
830.00
|
|
93
|
8009903.98
|
M/S. Laboni Sraboni Enterprise
|
7609408.80
|
30/09/2020
|
02/10/2020
|
|
98
|
|
93
|
06/12/2020
|
|
116
|
IDFPC/Chan/2019-2020/W-04
|
Maintenance of BC Road at Bhuyia Market Bridge – Boro Bhuiya Hosue Mosque Under Chandina Pourashava , Cumilla, Ward no. 0( Ch.00-135m)
Improvement of BC Road at BRDB to Sher Ali House road Under Chandina Pourashava, Cumilla (Ch. 00-385m) Part – A
Rehabiliation of BC Road at Abdulir Par Bridge – Chilora Bridge road Under Chandina Pourashava , Cumilla,(Ch.00-900m) .
|
IDFPC
|
chandina
|
|
1420.00
|
|
83
|
4940978.00
|
M/S Hafeza Enterprise
|
8493929.40
|
28/09/2020
|
30/10/2020
|
|
94
|
|
83
|
06/12/2020
|
|
117
|
IDFPC/Chan/ 2019-2020/W-05
|
Const. of RCC Drain St. from Jabber Market Mosque- Matribumi School road under Chandina Pourashava , Cumilla
Const. of Drain St. from Harong Dulal hosue – Infront of Anu Miah House road Under Chandina Pourashava , Cumilla.
Construction of brick masonary drain st. from back side of radowan ahmed college to (South way) cannel infront of the poura bhaban in ward no. 05 under Chandina Pourashava , Cumilla
Construction of brick masonary drain st. from Kurbanpur Ali Nawaj house- Tulatuli Khal in ward no. 0 under Chandina Pourashava , Cumilla
Improvement of RCC Drain St. from Hazi more to new High way road under Chandina Pourashava
|
IDFPC
|
chandina
|
|
|
|
61
|
6415755.47
|
M/Omar traders
|
6094967.70
|
07/10/2020
|
14/10/2020
|
|
65
|
|
61
|
06/12/2020
|
|
118
|
IDFPC/Chan/ 2019-2020/W-06
|
Re-Excavation of Infront of Poura canal with Development of Embankment Road at Pourashava under Chandina Pourashava , Cumilla
Const. of Garden and Rest House on Near Food Stoke – Govt. Hospital road under Chandina Pourashava , Cumilla
Const. of Poura Bhaban Vehicles Shade under Chandina Pourashava , Cumilla
|
IDFPC
|
chandina
|
|
|
|
5
|
15700242.00
|
M/S. Arsad & Sons
|
13015503.00
|
03/11/2020
|
05/11/2020
|
|
17
|
|
5
|
06/12/2020
|
|
119
|
IDFPC/Chau/2018-2019/W-01
|
"1.a) Rehabiliation of Dhaka Chattogram Hgh way to west Dhanmuri West by pass road at ch. 0.00-625m under Chouddagram Pourashava, Cumilla.
b) Construction of Bricks Drain at west Dhonmuri road under Chauddagram Pourashava cumilla (Ch. 450.00-700.00)"
2. Rehabiliation of Dhaka Chattagram High way to Sonakatia West bypass road under Chauddagram Pourashava cumilla (Ch. 0.00.-651m)
|
IDFPC
|
chouddagram
|
|
1276.00
|
|
|
9490485.00
|
M/S.Yulin Brothers
|
0.00
|
20/11/2019
|
27/11/2019
|
|
100
|
|
|
13/12/2020
|
|
120
|
IDFPC/Chau/2018-2019/W-02
|
1 a) Rehabiliation of Dhaka Chattagram High way Towards West side Panchara BSCIC road under Chauddagram Pourashava cumilla (Ch. 0.00.-1240m)
b) Construction of Protection wall road side of Panchara BSCIC road under Chauddagram Pourashava cumilla (Ch. 650.-700m)
|
IDFPC
|
chouddagram
|
|
1.24
|
|
|
7339614.00
|
|
7339614.00
|
20/11/2019
|
28/11/2019
|
|
100
|
|
|
13/12/2020
|
|
121
|
IDFPC/Chau/2018-2019/W-03
|
1.a Rehabiliation of Dhaka Chattagram High way to Falgunkara GPS road upto West bypass road under Chauddagram Pourashava cumilla (Ch.00.-668m)
b) Construction of Protection wall road side of Falgunkara GPS raoad under Chauddagram Pourashava cumilla (Ch. 30.00.-124m)
|
IDFPC
|
chouddagram
|
|
0.66
|
|
100
|
6706163.00
|
M/S. Tuhin Brothers
|
6706163.00
|
11/09/2019
|
19/09/2019
|
06/01/2020
|
60
|
|
100
|
13/12/2020
|
|
122
|
IDFPC/Chau/2019-2020/W-04
|
Part-A. Rehabilitation of Rmchandra pur 4 way junction to towards Dulal’s Shop Road under Chouddagram Pourashava. Cumilla (Ch. 370-610m)
Part-B. Rehabilitation of Brichandra nagar East Bypass to East way Border Road under Chouddagram Pourashava. Cumilla (Ch. 570-1003m)
Part-C. Improvement of RCC Road at Dhaka- Ctg. Highway to Natapara East bypass Road under Chouddagram Pourashava. Cumilla (Ch. 00-567m)
|
IDFPC
|
chouddagram
|
|
1.23
|
|
100
|
7542571.93
|
|
7542571.93
|
|
|
|
100
|
|
100
|
13/12/2020
|
|
123
|
IDFPC/Chu/2019-2020/W-05
|
Construction of RCC Road Road at Sener Khil East bypass Road to East way upto 3way Juntion under Chouddagram Pourashava. Cumilla (Ch. 00-500m)
Improvement of RCC Road at Gomar bari Chairman Bari road to North side Bir Muktijujodhya Siddique Miah’s house Road under Chouddagram Pourashava. Cumilla (Ch. 00-102m)
Part-A.Improvement of RCC Road at Chandi pur Molla kona to South side Bir Muktijodhya Ataur Rahman’s house Road under Chouddagram Pourashava. Cumilla (Ch. 360-720m)
|
IDFPC
|
chouddagram
|
|
0.50
|
|
100
|
9718742.93
|
M/S. Pranta Enterprise
|
9718742.93
|
26/11/2020
|
|
|
100
|
|
100
|
13/12/2020
|
|
124
|
IDFPC/Chu/2019-2020/W-06
|
Part –A. Construction of RCC Road Drain Dhaka –Ctg. Highway to East way of Ramroygram (Dhakbanglo Road) under Chouddagram Pourashava. Cumilla (Ch. 125.00m)
Part –B Improvement of RCC Work Dhaka-Ctg. Highway to Ramroygram (Dhakbanglo Road) under Chouddagram Pourashava. Cumilla (Ch. 420.00m)
Part-B.Construction of R.C.C dRAIN nOAPARA bcct Project’s Drain – South way Sonaichhari Khal under Chouddagram Pourashava, Cumilla. (Ch.00-0.132m) (Ch.00-0.132m
|
IDFPC
|
chouddagram
|
|
677.00
|
|
100
|
10009390.37
|
M/S.Pranta Enterprise
|
10009390.37
|
26/11/2020
|
|
|
100
|
|
100
|
13/12/2020
|
|
125
|
IDFPC/Chu/2019-2020/W-07
|
Part –A.Improvement of RCC Work Dhaka-Ctg. Highway to towards Ramroygram East para Road under Chouddagram Pourashava. Cumilla (Ch. 881.00m)
Part-B. Construction of Retaining Wall- Improvement of Dhaka-Ctg. Highway – towards East side Ramroygram East para Road under Chouddagram pourashava. Cumilla
Improvement of RCC Road at Dhaka- Ctg. Highway to Panchra Kanati Chowdury’s house Road under Chouddagram Pourashava. Cumilla (Ch. 00-420m)
|
IDFPC
|
chouddagram
|
|
1321.00
|
|
100
|
5520374.16
|
M/S.Pranta Enterprise
|
5520374.16
|
26/11/2020
|
|
|
100
|
|
100
|
13/12/2020
|
|
126
|
IDFPC/Chu/2019-2020/W-08
|
Part-A. Development of Noapara Graveyard Under Chouddagram Pourashava. Cumilla.
Part-B. Development of Gomar Bari East para Graveyard Under Chouddagram Pourashava. Cumilla.
Part-C. Improvement of Nabagram Graveyard near Master Bari (Retaining Wall) Under Chouddagram Pourashava, Cumilla.
Part-A. Development of Ramchandrapur Graveyard Under Chouddragram Pourashava,
Part-B. Development of Ramchandrapur House of F.F. Shamsul Hoque Graveyard Under Chouddagram Pourashava, Cumilla.
Part-C. Development of North Falgunkara Molla Bari Graveyard (Retaining Wall) Under Chouddagram Pourashava, Cumilla.
|
IDFPC
|
chouddagram
|
|
|
|
100
|
5520374.16
|
|
5520374.16
|
26/11/2020
|
|
|
100
|
|
100
|
13/12/2020
|
|
127
|
IDFPC/Chu/2019-2020/W-09
|
Part-A. Development of Chandipur Graveyard under Chouddagram Pourashava, Cumilla.
Maintainance of Chouddagram Poura Central Eidgah under Chouddagram Pourashava, Cumilla.
Development of Central Maha Smahan (Retaining Wall) under Chouddagram Pourashava, Cumilla.
Development of Gomar bari Training Center Graveyard under Chouddagram Pourashava, Cumilla.
Development of Sree pur Graveyard under Chouddagram Pourashava, Cumilla.
|
IDFPC
|
chouddagram
|
|
|
|
100
|
6577294.83
|
M/S. Pranta Enterprise
|
6577294.83
|
26/11/2020
|
|
|
100
|
|
100
|
13/12/2020
|
|
128
|
IDFPC/DAUD/2018-2019/W-03
|
Construction of RCC Road at Maizpara (from house of Asmot Chowdhury to Daudkandi R&H road) ch. 0.00-700m Under Daudkandi Pourashava,
( IDFPC/DAUD/2018-2019/W-03)
|
IDFPC
|
daudkandi
|
|
700.00
|
|
100
|
7671258.00
|
M/S. Hazera Enterprise
|
7287695.10
|
11/09/2019
|
19/09/2019
|
01/06/2020
|
100
|
|
100
|
31/12/2020
|
|
129
|
IDFPC/DAUD/2019-2020/W-05
|
Construction of RCC Road at Mizpara From Mizpara to west Dighirpar Road (Ch:0.00-500.00m, L=500m) wide=2.20m, CIP Road-09) Under Daudkandi Pourashava,
|
IDFPC
|
daudkandi
|
|
500.00
|
|
35
|
7595892.00
|
M/S.Liberty Traders
|
7595892.00
|
14/06/2020
|
21/06/2020
|
14/12/2020
|
60
|
|
35
|
31/12/2020
|
|
130
|
IDFPC/DAUD/2019-2020/W-06
|
Construction of RCC Drain with slab at Shobjikandi from House of Din Islam Mia to Gomati River (Ch:0.00-700.00m, CIP Drain-01) Under Daudkandi Pourashava, Cumilla.
|
IDFPC
|
daudkandi
|
|
700.00
|
|
|
13277441.00
|
F. M . Nafiz Ahmed
|
13270802.28
|
14/06/2020
|
21/06/2020
|
14/12/2020
|
25
|
|
|
31/12/2020
|
|
131
|
IDFPC/DAUD/2019-2020/W-07
|
Construction of RCC Road at Dighirpar from west Dighirpa Road to South Sotahnondi road (Ch:0.00-425.00m, L=425m, W=2.20m, CIP Road-18) Under Daudkandi Pourashava, Cumilla.
|
IDFPC
|
daudkandi
|
425
|
|
|
15
|
4555323.00
|
M/S. Saif construction
|
4555323.00
|
14/06/2020
|
21/06/2020
|
14/12/2020
|
100
|
|
15
|
31/12/2020
|
|
132
|
IDFPC/DAUD/2018-2019/W-01
|
a) Construction of RCC Road at Daudkandi Bazar (from Freedom fighter office to Changakandi ghat) ch. 0.00-160m Under Daudkandi Pourashava,
b)Construction of RCC Road at Daudkandi Bazar (fromShop of Bulbul mia to Old Ferry ghat) ch. 0.00-190m Under Daudkandi Pourashava,
|
IDFPC
|
daudkandi
|
|
350.00
|
|
64
|
3724442.00
|
F. M . Nafiz Ahmed
|
6118174.80
|
11/09/2019
|
19/09/2019
|
01/06/2020
|
94
|
|
64
|
05/12/2020
|
|
133
|
IDFPC/DAUD/2018-2019/W-02
|
a)Construction of RCC Road at Daudkandi Bazar (fromShop of Humayon hazi to River of Gomoti) Under Daudkandi Pourashava,
b) Construction of RCC Road at DaudkandiCentral Graveyards ch. 0.00-300m Under Daudkandi Pourashava,
|
IDFPC
|
daudkandi
|
|
500.00
|
|
46
|
5444835.00
|
F. M . Nafiz Ahmed
|
5172593.25
|
11/09/2019
|
19/09/2019
|
01/06/2020
|
60
|
|
46
|
05/12/2020
|
|
134
|
IDFPC/DAUD/2019-2020/W-04
|
Construction of RCC Road at Taltoli From Dhaka Ctg Highway to Taltali Bazar Bridge (Ch:0.00-760.00m, L=760m) wide=2.20m, CIP Road-22) Under Daudkandi Pourashava, Cumilla.
|
IDFPC
|
daudkandi
|
|
760.00
|
|
89
|
7811313.00
|
F. M . Nafiz Ahmed
|
7807407.34
|
14/06/2020
|
21/06/2020
|
14/12/2020
|
90
|
|
89
|
05/12/2020
|
|
135
|
IDFPC/DEBD/2018-2019/W- 01
|
1. Improvement of RCC Road St. From Cumilla-Sylhet High Way to Patakoya Bridge, In Ward No: 05 & 08, Under Debidwar Pourashava, From Chainage 0.00-976.00m,
|
IDFPC
|
debidwar
|
|
976.00
|
|
|
9608296.00
|
M/S.Kamal and Company
|
9127881.20
|
29/06/2020
|
06/07/2020
|
24/09/2020
|
100
|
|
|
02/12/2020
|
|
136
|
IDFPC/DEBD/2018-2019/W- 02
|
2 : (a) Construction of RCC Box Culvert at Sailchor korerpar R&H to Fotehabad Res. Of Narayan Chandra Bir Road Under Debidwar Pourashava at Chainage 00- 508m in ward No. 02&03.
(b) Construction of RCC Drain with Slab (Ch.0.00-214.00m, width 0.600m & length 214.00m) St. from debidwar-chandina road (Hilfol Foxol Mosque ) to Dubo Mia's Culvert, in Ward No 08 Under Debidwar Pourashava.
|
IDFPC
|
debidwar
|
|
|
508.00
|
|
6980026.00
|
M/S.Debidwar Bricks
|
6631024.10
|
23/06/2020
|
30/06/2020
|
21/09/2020
|
60
|
|
|
02/12/2020
|
|
137
|
IDFPC/DEBD/2019-2020/W-3
|
Construction of RCC Drain (Ch. 00.00-Ch. 193.00 width- 1.50m & Ch. 00.00-Ch.100.00m, Width–1.00m, Total Length = 293.00m) St. from Debidwar Central Zame Mosque to Res. of Dr.Mhabbot Ali & Debidwar Post Office to Res. Of Dr. Sirazul Islam, In ward No-05, Under Debidwar Pourashava, Cumilla.
|
IDFPC
|
debidwar
|
|
|
|
|
10676598.00
|
M/S. Ratul Enterprise
|
10142768.10
|
23/06/2020
|
30/06/2020
|
21/12/2020
|
30
|
|
|
02/12/2020
|
|
138
|
IDFPC/DEBD/2019-2020/W-4
|
Improvement of BC Road (Ch. 00.0-Ch. 1240.00m. Width = 3.050m & Length = 1240.0m) St. From Vinglabari Water Board to Boundary of Ward No: 04. In Ward No. 02 & 04, Under Debidwar Pourashava,
|
IDFPC
|
debidwar
|
1240
|
|
|
|
10412394.00
|
ALLARDAN ENTERPRISE
|
9891774.30
|
21/06/2020
|
28/06/2020
|
17/12/2020
|
70
|
|
|
02/12/2020
|
|
139
|
IDFPC/DEBD/2019-2020/W-5
|
Improvement of Connecting Road Between Debidwar- Chepara Road to Upzila Porishad office by RCC. In Ward No. 05, Under Debidwar Pourashava, Cumilla. (Ch.00-194.00, Length =194.00m, Width = 3.70m)
|
IDFPC
|
debidwar
|
194
|
|
|
|
4499022.00
|
M/S. Bhulyan & Brothers
|
4274070.90
|
21/06/2020
|
28/06/2020
|
17/09/2020
|
100
|
|
|
02/12/2020
|
|
140
|
IDFPC/DEBD/2019-2020/W-6
|
Improvement of BC Road (Ch. 00.0-Ch. 1500.00m. Width = 3.050m & Length = 1500.0m) St. From Fotehabad Kamar Bari to Gazaria Bridge of Ward No: 03. In Ward No. 02 & 04, Under Debidwar Pourashava, Cumilla.
|
IDFPC
|
debidwar
|
1500
|
|
|
|
14292963.00
|
M/S Sumi Enterprise
|
13578314.85
|
21/06/2020
|
28/06/2020
|
17/09/2020
|
65
|
|
|
02/12/2020
|
|
141
|
IDFPC/DEBD/2019-2020/W-8
|
Improvement of RCC Drain with Foothpath (Ch. 00.00- Ch. 866.00m width = 0.90m & Length = 1195.00m ) St. From Public Heath To Goyadhara Canal, In Word No. 05 &08. Debidwar Pourashava, Cumilla.
|
IDFPC
|
debidwar
|
|
|
|
|
30646703.00
|
Mohammad Eunus & Brothers
|
26356163.96
|
17/09/2020
|
24/09/2020
|
|
35
|
|
|
02/12/2020
|
|
142
|
IDFPC/DEBD/2019-2020/W-7
|
Improvement of (2x 2.50mx 3.00m) R.C.C Box Culvert at Chapanagar Cumilla – Sylhet highway to Fotehabad Res. Of Taher Master via Chapanagar Mohuri Bari Road at ch. 960.00m In ward no. 07, Under Debidwar Pourashava, Cumilla.
|
IDFPC
|
debidwar
|
960
|
|
|
|
1494683.00
|
Bin Salam Logostics
|
1419948.85
|
21/06/2020
|
28/06/2020
|
10/09/2021
|
60
|
|
|
02/02/2020
|
|
143
|
IDFPC/HOM/2019-2020/05
|
Construction of RCC drain starting from Homna Bus stand existing drain to Titas rever via Rajghat in ware No -04 (Ch. 470m-1450m ) under Homna Pourashava, Cumilla.
|
IDFPC
|
homna
|
|
1450.00
|
|
|
36449917.00
|
M/S. Abdur Razzak
|
32622703.00
|
10/09/2020
|
16/09/2020
|
15/09/2021
|
35
|
|
|
08/12/2020
|
|
144
|
IDFPC/HOM/2018-2019/06
|
Construction of HBB road starting from Latia – Goarivanga Bridge approach east side to Goarivanga Community Clinic in ward no-09 (Ch: 00-1460) under Homna Pourashava, Cumilla
|
IDFPC
|
homna
|
|
1.46
|
|
|
11980328.00
|
M/S. Ismat Enterprise
|
11959700.00
|
07/09/2020
|
14/09/2020
|
13/09/2021
|
22
|
|
|
08/12/2020
|
|
145
|
IDFPC/HOM/2018-2019/ 07
|
Electrical works of Installation Street Light at Homna Pourashava different ward (Length-6.00Km) under Homna Pourashava, Cumilla.
|
IDFPC
|
homna
|
|
|
|
|
21330229.00
|
|
18130703.00
|
07/09/2020
|
14/09/2020
|
13/09/2021
|
20
|
|
|
08/12/2020
|
|
146
|
IRIDP-2/COM/DW-5
|
a) Improvement of Etbarpur UPC- Maizkhar Road (Maizkhar Mohila Madrasha- Alikamura GPS Road) (Ch.2750-4000m)b) Construction of 2x3.00x3.50m RCC Box Culvert at ch. 4000m on the same road.
|
IRIDP-2
|
chandina
|
|
1.30
|
|
|
59.25
|
M/S Islam Trading
|
6.19
|
|
02/03/2016
|
30/08/2017
|
100
|
|
|
|
|
147
|
IRIDP-2/COM/DW-6
|
Improvement of Kaduti Bazar- Dherara Bazar –Orain- Taltala Road. (Ch. 3789-4289m)
|
IRIDP-2
|
chandina
|
|
0.50
|
|
|
28.70
|
M/S Anik Enterprise
|
2.78
|
|
07/03/2016
|
28/02/2018
|
100
|
|
|
|
|
148
|
IRIDP-2/COM/DW-7
|
a) Improvement of Badorpur- Maizkhar Road (Seraj Chairman Bari) (Ch.00-1250m)b) Construction of 1No. 1000mmx900mm Slab Culvert at ch. 1072m on the same road.
|
IRIDP-2
|
chandina
|
|
1.25
|
|
|
48.58
|
M/S Sejuti Enterprise
|
5.10
|
|
15/02/2016
|
21/09/2016
|
100
|
|
|
|
|
149
|
IRIDP-2/COM/DW-8
|
Improvement of Montherhat khola to Chilora (Amborpur) Road. (Ch. 1000-2000m)
|
IRIDP-2
|
chandina
|
|
1.00
|
|
|
36.46
|
M/S Sejuti Enterprise
|
3.83
|
|
22/02/2016
|
21/09/2016
|
100
|
|
|
|
|
150
|
IRIDP-2/COM/DW-9
|
Improvement of Suhilpur -Kabir Bhuyan Bari to Muradnagor GPS Road (Ch. 00-660m)
|
IRIDP-2
|
chandina
|
|
0.66
|
|
|
31.60
|
M/S Islam Trading
|
3.32
|
|
13/03/2016
|
30/03/2018
|
100
|
|
|
|
|
151
|
IRIDP-2/COM/DW-10
|
Improvement of Gollai Aziz Pradhan house to Mirakhola Pry. School Road (Ch.00-145m)
|
IRIDP-2
|
chandina
|
|
0.15
|
|
|
4.11
|
M/S Islam Trading
|
0.43
|
|
21/03/2016
|
19/09/2016
|
100
|
|
|
|
|
152
|
IRIDP-2/COM/DW-11
|
Improvement of Muradpur- Batagashi UPC Road (Muradpur- Batagashi Road) (Ch.1600-1997m)
|
IRIDP-2
|
chandina
|
|
0.39
|
|
|
26.46
|
Jhilik Enterprise
|
2.77
|
|
17/03/2016
|
31/03/2017
|
100
|
|
|
|
|
153
|
IRIDP-2/COM/DW-12
|
Improvement of Madhiya- Rahimanagor Road (St. from Kashimpur ) to Prof. Ali Ashraf GPS) (Ch.00-550m)
|
IRIDP-2
|
chandina
|
|
0.55
|
|
|
17.84
|
M/S Anik Enterprise
|
1.84
|
|
28/02/2016
|
01/08/2016
|
100
|
|
|
|
|
154
|
IRIDP-2/COM/DW-13
|
Improvement of Gallai Baro Dighi to Munshi Bari Road. (Ch.00-715m)
|
IRIDP-2
|
chandina
|
|
0.72
|
|
|
25.76
|
M/S Islam Trading
|
2.69
|
|
13/03/2016
|
12/08/2016
|
100
|
|
|
|
|
155
|
IRIDP-2/COM/DW-14
|
Improvement of Madhiya- Rahimanagor Joarpukuria Community Pry. School (Ch.00-1000m)
|
IRIDP-2
|
chandina
|
|
1.00
|
|
|
48.57
|
Moni Builders & Engineering Workshop
|
5.10
|
|
07/03/2016
|
25/04/2017
|
100
|
|
|
|
|
156
|
IRIDP-2/COM/DW-15
|
Improvement of Nowabpur- Darora Bazar Road (St. from Dollai Nowabpur College east side to Darora Bazar via Billal Bazar- Darora Bazar Road) (Ch.00-1034m)
|
IRIDP-2
|
chandina
|
|
1.03
|
|
|
50.38
|
M/S Islam Trading
|
5.29
|
|
13/03/2016
|
30/04/2018
|
100
|
|
|
|
|
157
|
IRIDP-2/COM/DW-1
|
a) Improvement of Dhaka- Ctg Highway- Satgoria Betiara Road (Ch. 00-672m)b) Construction of 4Nos. 600mmx900mm Slab Culvert at ch. 30m, 100m, 141m & 319m on the same road.
|
IRIDP-2
|
chouddagram
|
|
0.67
|
|
|
45.00
|
M/S Rehana Constraction
|
5.08
|
|
07/04/2016
|
05/12/2016
|
100
|
|
|
|
|
158
|
IRIDP-2/COM/DW-2
|
Improvement of Alishar-Jamalnagar-Joynagar Road (Ch. 00-750m).
|
IRIDP-2
|
cumilla-s
|
|
0.75
|
|
|
42.66
|
M/S Zaman Traders
|
4.48
|
|
31/01/2016
|
01/08/2016
|
100
|
|
|
|
|
159
|
IRIDP-2/COM/DW-3
|
Improvement of Changahata-Duttapur Road (Ch.00-1210m).
|
IRIDP-2
|
cumilla-s
|
|
1.21
|
|
|
55.91
|
M/S Abul Kasam Bricks
|
5.87
|
|
09/02/2016
|
31/12/2016
|
100
|
|
|
|
|
160
|
IRIDP-2/COM/DW-4
|
a) Improvement of Bholin Daksin UP (Buccy)- Porayty Bazar- Jamuna- Modianna Bazar Road (Ch. 6345-7180m).b) Construction of 1No. 625mmx600mm Slab Culvert at ch. 6508m on the same road.
|
IRIDP-2
|
cumilla-s
|
|
0.84
|
|
|
49.12
|
M/S Zaman Traders
|
5.16
|
|
30/01/2016
|
01/08/2016
|
100
|
|
|
|
|
161
|
MGSP/CND/W-01
|
a) Improvement of road from harong H/O Ansor Ali to Abdulir par Mor road at word no. 02 &03 under Chandina Pourashava.(ch. 0.00m to 1700m)
b) Improvement of road from Tolatali Moulabi bari Jame mosque towards south baniachong bridge & Kurbanpur bridge (Ch. 0.00m to 658m).
c) Improvement of Boro-Gobindapur Nathpara H/O. Shyamshundar - via Baro-gobindapur Ali Mia High School - Dhaka-Chittagong High way road.(at word no. 06) under- Chandina Pourashava. Ch.0.0 - 316 m.
d) Improvement of road from Srimontopur High School road to Kurbanpur Mosque at ward no. 09 under Chandina Pourashava Ch:0.0 to 585m.
e) IMPROVEMENT OF ROAD FROM
e1) Chandina poura bhobon East site Culvert to southway up to Chaycot mor at word no 07(Ch:0.0 to1000m)
e2) from shahapara to kazee para road at word no 05(Ch:0.0 to 293m)
e3) Upazila road to Chandina Bazer Ch:0.0 to 258m.
f) Construction of a drain from jute office south gate towards east and then north way canel at word no 05 under Chandina pourashava.(ch. 0.00m to 335m).
g) Construction of (a) R.C.C Drain from WAPDA more Mizan’s Shop to Moslem Driver’s Shop up to cross drain & H/O Ayat ali towards north main drain (ch. 0.00m to 250m).(b) brick drain from moharong jalal hujur house towards west up to old drain at word no.01 under Chandina Pourashava(ch. 0.00m to 233m).
|
MGSP
|
chandina
|
|
3.27
|
|
|
30745322.90
|
M.K Enterprise & T.H Enterprise
|
28576768.57
|
|
02/02/2016
|
30/11/2016
|
77
|
|
|
|
|
162
|
MGSP/CND/2015-16/W-02
|
(a) Construction of BC/RCC road and Street Lighting from Palki Cinema hall to Dhaka-Chittagong Highway via Hazi Moar BC road at Ch. 00m-1013m & Ch. 1459m-2296m
(b) Construction of BC/RCC road and Street Lighting from Palki Cinema hall to Hazi Moar RCC road at Ch. 1013m-1459m
(c) Construction of RCC drain with footpath starting from Palki Cinema hall to thana moar link Mukum bari to Dumuria canal at Ch. 00m-3454m and Construction of RCC drain staring from Rammohan road to Kudirpur canal at Ch. 00m-1100m
(d) Supplying fitting & fixing of street light starting from Palki Cinema hall to Hazi Moar Link (Upazilla) at Ch. 00m-2458m under Chandina Pourashava, District:Comilla.
|
MGSP
|
chandina
|
|
6.30
|
|
|
176117111.59
|
RT-QC-Bithi Enterprise (JV)
|
137315090.20
|
|
06/02/2017
|
01/02/2018
|
15
|
|
|
|
|
163
|
MGSP/CCC/W-01
|
(a) Improvement of Nazrul Avenue BC road from (i) Kandirpar Pubali Chattar To Dharmapur East Chowmohuni via Ranir Bazar (Ch.0.00-1300m), (ii) Dharmapur West Chowmuhuni to Daulatpur via Victoria Degree College (Ch. 1500m-2300m) (Total Length =2100m)
(b) Construction of Nazrul Avenue road side RCC Drain from (i) Kandirpar Pubali Chattar To Dharmapur East Chowmohuni via Ranir Bazar (Ch.0.00-1300m), (ii) Dharmapur West Chowmuhuni to Daulatpur via Victoria Degree College (Ch. 1500m-2300m) with cross Drain at Ch. 200.00m, (Total Length =2100m)
|
MGSP
|
cumilla-s
|
|
4.20
|
|
|
52771417.00
|
M/S. Haque Enterprise
|
35003404.83
|
|
01/05/2015
|
14/04/2016
|
100
|
|
|
|
|
164
|
MGSP/CCC/W-02
|
(a) Improvement of BC road from Chortha Chowmohani to EPZ road (Ch.0.00-700m) (Total Length =700m)
(b) Construction of RCC Drain with slab from Chortha Chowmohani to EPZ road (Ch.0.00-700m) with cross drain at ch. 250m, 300m, 370m, 410m, 520m, 590m, 630m, (Total Length =700m)
(c) Improvement of Mogotoly Shah Suja Mosque BC road (Ch.0.00-750m) (Total Length =750m)
(d) Improvement of Othindra Mohon Roy BC Road (Ch. 0.00-530m) (Total Length =530m)
(e) Improvement of Othindra Mohon Roy Road side RCC Drain & Slab(Ch. 0.00-530) with cross drain at ch. 100m, 220m, 350m, 480m, (Total Length =530m)
|
MGSP
|
cumilla-s
|
|
3.21
|
|
|
30865975.00
|
M/S. Bithi Enterprise
|
30863168.73
|
|
01/05/2015
|
20/04/2016
|
100
|
|
|
|
|
165
|
MGSP/CCC/W-03
|
(a) Improvement of Station BC road from Old Dhaka-Chittagong Road Badsha Mia Bazar Portion to Dharmapur East Chowmohoni (Ch. 0.00-800m) (Total Length =800m)
(b) Construction of road side RCC Drain & Slab from Station road from Old Dhaka-Chittagong Road Badsha Mia Bazar Portion to Dharmapur East Chowmohoni (Ch. 0.00-800m) with cross drain at ch. 230m, 450m, (Total Length =800m)
(c) Improvement of Abu Jahid BC Road (Ch.0.00-1450m) (Total Length =1450m)
|
MGSP
|
cumilla-s
|
|
3.05
|
|
|
34871819.00
|
Md. Abdul Mannan
|
32149735.04
|
|
25/05/2015
|
21/02/2016
|
100
|
|
|
|
|
166
|
MGSP/CCC/2015-16/W-04
|
Development of Bypass road from Amtoli to Tickarchor beside river Gomoty (Ch. 0+00 to 5+150m) under Comilla City Corporation.
|
MGSP
|
cumilla-s
|
|
5.15
|
|
|
113419728.00
|
M/s. M.A. Engineering-M/s. Ananta Enterprise
|
78367349.58
|
|
30/10/2016
|
19/01/2018
|
65
|
|
|
|
|
167
|
MGSP/CCC/2015-16/W-06
|
Development of Bypass road from Amtoli to Tickarchor (Vatpara to Jagonnathpur moar) beside river Gomoty (Ch. 5+150 to 10+309m) under Comilla City Corporation
|
MGSP
|
cumilla-s
|
|
5.16
|
|
|
114345329.00
|
RT-QC-Bithi Enterprise (JV)
|
113499853.35
|
|
20/10/2016
|
19/01/2018
|
60
|
|
|
|
|
168
|
MGSP/DAD/W-01
|
a) Development of road from Daudkandi R&H road to Daudkandi bazaar via old Farighat (Ch.0.00-1890.00m), Under Daudkandi Pourashava (Total Length= 1890m)
b) Development of road from Daudkandi Bazaar to Tuzarvanga KanuBepari house road(Ch. 0.00-518.00m), under Daudkandi Pourashava (Total Length= 518m)
c) Development of road from Daudkandi Toolplaza to Donarchar Wood Ghat road (Ch. 0.00-793.00m) under Daudkandi Pourashava (Total Length= 793m)
d) Construction of Drain from Daudkandi Toolplaza to Donarchar Wood Ghat road (Ch. 107.00m-747.00m), under Daudkandi Pourashava (Total Length=640.00m)
|
MGSP
|
daudkandi
|
|
3.84
|
|
|
31425219.00
|
M/S. R-TA Enterprise
|
29655641.11
|
|
13/07/2015
|
13/07/2016
|
100
|
|
|
|
|
169
|
MGSP/DAD/2015-16/W-02
|
(a) Construction of RCC Drain from Daudkandi R&H Road to old Ferri ghat on both side of the road with footpath on top of drain (Ch. 0+000 to 1+295m) under Daudkandi Pourashava.Total length-2667 m
(b) Construction of RCC Drain on both side of the road in Daudkandi Pailot High School to Old Petrol Pamp with footpath on top of drain (Ch. 0+000 to 500.00m) under Daudkandi Pourashava. Total length-1089m
(c) Supplying, fitting, and fixing of street light with pole from Daudkandi R&H to Daudkandi Toll Plaza via Daudkandi Bazar (Ch. 0+000 to 1+295m, & Ch. 0+000 to 0+425m) on both side under Daudkandi Pourashava.
(d) Development of RCC Road from R&H Road to Motel ghat via Daudkandi Model Thana.(Ch. 0+00 to 0+1295m and Ch. 0+000 to 0+425m) under Daudkandi Pourashava. Total length-1720m, wide-6 m
|
MGSP
|
daudkandi
|
|
8.92
|
|
|
152631365.00
|
SB-LT (JV)
|
131875839.00
|
|
05/09/2016
|
04/09/2017
|
44
|
|
|
|
|
170
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01582
|
RAMNAGAR PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
69.81
|
M/S Sayed Ali
|
66.32
|
|
24/09/2018
|
01/07/2019
|
0
|
|
|
|
|
171
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01766
|
CHARIPARA REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
52.81
|
M/S Jakir Traders
|
50.17
|
|
06/08/2018
|
08/05/2019
|
45
|
|
|
|
|
172
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01768
|
PASCHIM SHIDLAI REGI. PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
79.06
|
M/S. Tahara Construction
|
75.11
|
|
13/08/2018
|
15/05/2019
|
5
|
|
|
|
|
173
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01775
|
PURBA CHANDIPUR PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
74.93
|
M/S. Ramjan & Brothers
|
71.18
|
|
05/08/2018
|
08/05/2019
|
10
|
|
|
|
|
174
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01776
|
PURBA ASADNAGAR REG. PRAIMARY. SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
51.82
|
M/S Hazera Enterprise
|
49.23
|
|
13/08/2018
|
15/05/2019
|
20
|
|
|
|
|
175
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01780
|
PURBA ALUYA PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
53.79
|
Schme Enginerre.
|
51.10
|
|
26/09/2018
|
02/07/2019
|
40
|
|
|
|
|
176
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01781
|
PUSKUNIRPAR REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
72.08
|
M/S Tie Stone
|
68.48
|
|
04/10/2018
|
09/07/2019
|
20
|
|
|
|
|
177
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01782
|
MOGPUKURPAR REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
52.57
|
M/S Tie Stone
|
49.94
|
|
04/10/2018
|
09/07/2019
|
10
|
|
|
|
|
178
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01792
|
PASCHIM BARAKHOLA PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
75.07
|
M/S Rashid and Brothers
|
71.31
|
|
27/09/2018
|
03/07/2019
|
10
|
|
|
|
|
179
|
e-Tender/NBIDNNGPS/COM/BRA/2018-2019/W1-01833
|
DAKKHIN DULALPUR REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
brahmanpara
|
|
|
|
|
75.18
|
M/S. Aysha Enterprise
|
71.42
|
|
14/11/2018
|
20/08/2019
|
0
|
|
|
|
|
180
|
e-Tender/NBIDNNGPS/COM/CHA/2017-2018/W1-00381
|
CHANDIARA REG. PRIMORY SCHOOL
|
NBIDNNGPS
|
chandina
|
|
|
|
|
47.07
|
M/S. M.M Enterprise
|
42.36
|
|
26/04/2018
|
02/05/2019
|
80
|
|
|
|
|
181
|
e-Tender/NBIDNNGPS/COM/CHA/2017-2018/W1-00389
|
GARAMATA REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
chandina
|
|
|
|
|
68.67
|
M/S Mostafa Kamal
|
61.80
|
|
26/04/2018
|
02/05/2019
|
35
|
|
|
|
|
182
|
e-Tender/NBIDNNGPS/COM/CHA/2017-2018/W1-00455
|
LANAY PRIMARY SCHOOL
|
NBIDNNGPS
|
chandina
|
|
|
|
|
68.67
|
M/S. M.M Enterprise
|
61.80
|
|
26/04/2018
|
02/05/2019
|
25
|
|
|
|
|
183
|
e-Tender/NBIDNNGPS/COM/CHA/2017-2018/W1-00456
|
DOBARIYA PRIMARY SCHOOL
|
NBIDNNGPS
|
chandina
|
|
|
|
|
68.67
|
M/S Mostafa Kamal
|
61.80
|
|
26/04/2018
|
02/05/2019
|
65
|
|
|
|
|
184
|
e-Tender/NBIDNNGPS/COM/CHA/2017-2018/W1-00457
|
RARIRCHAR REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
chandina
|
|
|
|
|
65.00
|
M/S. M.M Enterprise
|
66.13
|
|
26/04/2018
|
02/05/2019
|
70
|
|
|
|
|
185
|
e-Tender/NBIDNNGPS/COM/CHA/2017-2018/W1-00458
|
RANICHARA REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
chandina
|
|
|
|
|
73.48
|
S. Ananta |Bikas Tripura
|
58.50
|
|
26/04/2018
|
02/05/2019
|
45
|
|
|
|
|
186
|
e-Tender/NBIDNNGPS/COM/CHA/2017-2018/W1-00459
|
CHOYGHOTIYA PRIMARY SCHOOL
|
NBIDNNGPS
|
chandina
|
|
|
|
|
47.33
|
S. Ananta |Bikas Tripura
|
42.60
|
|
26/04/2018
|
02/05/2019
|
90
|
|
|
|
|
187
|
e-Tender/NBIDNNGPS/COM/COM/2018-2019/W1-02108
|
JANGALIA ADARSHA GOVERNMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s
|
|
|
|
|
72.58
|
Md. Alamgir Hossain
|
76.18
|
|
06/01/2019
|
05/10/2019
|
10
|
|
|
|
|
188
|
e-Tender/NBIDNNGPS/COM/COM/2018-2019/W1-02109
|
KRISHNAPUR GOVERMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s
|
|
|
|
|
71.31
|
M/S Noorjahan Enterprise
|
74.73
|
|
|
|
10
|
|
|
|
|
189
|
e-Tender/NBIDNNGPS/COM/COM/2017-2018/W1-00565
|
CHOTA CHOLUNDA GOVERNMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s daksin
|
|
|
|
|
71.31
|
M/S. Hasan Enterprise
|
67.74
|
|
03/06/2018
|
10/06/2019
|
60
|
|
|
|
|
190
|
e-Tender/NBIDNNGPS/COM/COM/2017-2018/W1-00566
|
MUNSHI M.ALLI GOVERNMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s daksin
|
|
|
|
|
69.03
|
M/S R. N International
|
65.68
|
|
03/06/2018
|
10/06/2019
|
55
|
|
|
|
|
191
|
e-Tender/NBIDNNGPS/COM/COM/2017-2018/W1-00567
|
RAJOSHA GOVERNMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s daksin
|
|
|
|
|
68.67
|
M/S. Hamim & Brothers
|
65.24
|
|
03/06/2018
|
10/06/2019
|
0
|
|
|
|
|
192
|
e-Tender/NBIDNNGPS/COM/COM/2017-2018/W1-00568
|
MOHAMMAD PUR PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s daksin
|
|
|
|
|
72.65
|
M/S. Biplob Enterprise
|
69.02
|
|
03/06/2018
|
10/06/2019
|
60
|
|
|
|
|
193
|
e-Tender/NBIDNNGPS/COM/COM/2017-2018/W1-00569
|
LOLAI UTHAR PARA GOVERNMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s daksin
|
|
|
|
|
70.02
|
M/S. Hazera Enterprise
|
66.52
|
|
03/06/2018
|
10/06/2019
|
30
|
|
|
|
|
194
|
e-Tender/NBIDNNGPS/COM/COM/2017-2018/W1-00586
|
KUNDAR GHORA GOVERNMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
cumilla-s daksin
|
|
|
|
|
73.95
|
M/S. A Rahman Enterprise
|
70.25
|
|
03/06/2018
|
10/06/2019
|
0
|
|
|
|
|
195
|
e-Tender/NBIDNNGPS/COM/DAU/2017-2018/W1-00205
|
OLAN PARA REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
daudkandi
|
|
|
|
|
70.18
|
M/S. R-TA Enterprise
|
69.00
|
|
25/03/2018
|
02/05/2019
|
60
|
|
|
|
|
196
|
e-Tender/NBIDNNGPS/COM/DAU/2017-2018/W1-00262
|
MODAFARDI REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
daudkandi
|
|
|
|
|
72.47
|
M/S. Liberty Traders
|
72.34
|
|
29/03/2018
|
04/04/2019
|
40
|
|
|
|
|
197
|
e-Tender/NBIDNNGPS/COM/DAU/2017-2018/W1-00263
|
MALIKHIL BAKINAGAR REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
daudkandi
|
|
|
|
|
72.47
|
M/S. Faruk Enterprise
|
72.47
|
|
19/03/2018
|
26/03/2019
|
65
|
|
|
|
|
198
|
e-Tender/NBIDNNGPS/COM/DAU/2017-2018/W1-00460
|
CHARMAHMUDDI REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
daudkandi
|
|
|
|
|
69.90
|
M/S. Liberty Traders
|
69.66
|
|
29/03/2018
|
04/04/2019
|
90
|
|
|
|
|
199
|
e-Tender/NBIDNNGPS/COM/DAU/2017-2018/W1-00461
|
MOURA BARI REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
daudkandi
|
|
|
|
|
70.68
|
M/S. Faruk Enterprise
|
69.58
|
|
05/04/2018
|
11/04/2019
|
10
|
|
|
|
|
200
|
e-Tender/NBIDNNGPS/COM/DEB/2017-2018/W1-01219
|
JUCKTTAGRAM GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
debidwar
|
|
|
|
|
46.73
|
M/S. Anik Enterprise
|
44.40
|
|
04/06/2018
|
10/04/2019
|
80
|
|
|
|
|
201
|
e-Tender/NBIDNNGPS/COM/DEB/2017-2018/W1-01224
|
CHOTTA ALAMPUR GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
debidwar
|
|
|
|
|
65.00
|
M/S. Haque International.
|
61.75
|
|
31/05/2018
|
06/06/2019
|
60
|
|
|
|
|
202
|
e-Tender/NBIDNNGPS/COM/DEB/2017-2018/W1-01229
|
RAMPUR GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
debidwar
|
|
|
|
|
69.29
|
M/S. E.F Trade International.
|
65.83
|
|
06/06/2018
|
12/06/2019
|
60
|
|
|
|
|
203
|
e-Tender/NBIDNNGPS/COM/DEB/2017-2018/W1-01230
|
GUNAIGAR PACHKURI MUNSHI BARI GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
debidwar
|
|
|
|
|
69.00
|
M/S. E F Trade International
|
53.70
|
|
24/12/2018
|
24/09/2019
|
75
|
|
|
|
|
204
|
e-Tender/NBIDNNGPS/COM/DEB/2017-2018/W1-01234
|
KAMARCHAR GOVERNMENT PRIMARY SCHOOL
|
NBIDNNGPS
|
debidwar
|
|
|
|
|
68.67
|
M/S. Abul Hasem.
|
65.24
|
|
03/06/2018
|
09/06/2019
|
70
|
|
|
|
|
205
|
e-Tender/NBIDNNGPS/COM/DEB/2017-2018/W1-01355
|
ITAKHOLA GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
debidwar
|
|
|
|
|
71.31
|
Pioneer Construction.
|
67.74
|
|
05/06/2018
|
11/06/2019
|
75
|
|
|
|
|
206
|
e-Tender/NBIDNNGPS/COM/HOM/2017-2018/W1-00313
|
KACHARI KANDI GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
homna
|
|
|
|
|
70.17
|
M/S Sumi Enterprise
|
63.16
|
|
30/04/2018
|
06/05/2019
|
0
|
|
|
|
|
207
|
e-Tender/NBIDNNGPS/COM/HOM/2017-2018/W1-00383
|
ASADPUR GOBT. PRIMARY SCHOOL
|
NBIDNNGPS
|
homna
|
|
|
|
|
71.73
|
M/S MI Construction
|
70.65
|
|
30/04/2018
|
06/05/2019
|
95
|
|
|
|
|
208
|
e-Tender/NBIDNNGPS/COM/HOM/2017-2018/W1-00385
|
KHANDAKER CHOR GOVT PRAMARY SCHOOL
|
NBIDNNGPS
|
homna
|
|
|
|
|
73.47
|
M/S Amika Enterprise
|
69.80
|
|
29/05/2018
|
05/06/2019
|
10
|
|
|
|
|
209
|
e-Tender/NBIDNNGPS/COM/HOM/2017-2018/W1-00451
|
HOMNA ADARSHA GOVT PRIMARY SCHOOL
|
NBIDNNGPS
|
homna
|
|
|
|
|
68.67
|
M/S Sumi Enterprise
|
61.80
|
|
30/04/2018
|
06/05/2019
|
35
|
|
|
|
|
210
|
e-Tender/NBIDNNGPS/COM/HOM/2017-2018/W1-01231
|
BAGSITARAMPUR GOVT PRIMARY SCHOOL
|
NBIDNNGPS
|
homna
|
|
|
|
|
69.02
|
RASHID & BROTHERS
|
65.57
|
|
30/04/2018
|
06/05/2019
|
70
|
|
|
|
|
211
|
e-Tender/NBIDNNGPS/COM/LAK/2018-2019/W1-02266
|
THANGERPAR NGPS
|
NBIDNNGPS
|
laksham
|
|
|
|
|
82.83
|
M/S M Islam Trading
|
78.69
|
|
24/12/2018
|
30/09/2019
|
0
|
|
|
|
|
212
|
e-Tender/NBIDNNGPS/COM/LAK/2018-2019/W1-02267
|
DOMBARIA RNGPS
|
NBIDNNGPS
|
laksham
|
|
|
|
|
83.06
|
M/S Sufia Noor Trade Link
|
78.91
|
|
24/12/2018
|
30/09/2019
|
0
|
|
|
|
|
213
|
e-Tender/NBIDNNGPS/COM/MEG/2017-2018/W1-00452
|
CHANGA KANDI NATIONALISED PRIMARY SCHOOL
|
NBIDNNGPS
|
meghna
|
|
|
|
|
68.67
|
M/S. Nationational Trade System
|
64.82
|
|
09/05/2018
|
14/05/2019
|
73
|
|
|
|
|
214
|
e-Tender/NBIDNNGPS/COM/MEG/2017-2018/W1-00453
|
JOYNAGAR NATIONALISED PRIMARY SCHOOL
|
NBIDNNGPS
|
meghna
|
|
|
|
|
65.00
|
M/S. National Trade System
|
61.36
|
|
09/05/2018
|
14/05/2019
|
50
|
|
|
|
|
215
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01203
|
MADABPUR GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
70.09
|
Rashid & Brothers
|
66.58
|
|
10/05/2018
|
16/05/2019
|
30
|
|
|
|
|
216
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01204
|
KURAR PAR GOV. PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
69.02
|
E .F Enterpeise
|
65.57
|
|
10/05/2018
|
16/05/2019
|
60
|
|
|
|
|
217
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01205
|
NARASHINGHPUR REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
77.06
|
Tie Stone
|
73.21
|
|
10/05/2018
|
16/05/2019
|
75
|
|
|
|
|
218
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01208
|
KRISHNAPUR REGI PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
67.26
|
Ramim Enterprise
|
63.89
|
|
10/05/2018
|
16/05/2019
|
70
|
|
|
|
|
219
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01210
|
FULGHAR GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
70.28
|
Sayed Ali
|
66.76
|
|
10/05/2018
|
16/05/2019
|
70
|
|
|
|
|
220
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01225
|
KAZIATAL BARAPARA NON REG. GOVT. PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
72.81
|
M/S Golam Mohiuddin Enterprise
|
69.17
|
|
04/06/2018
|
10/06/2019
|
75
|
|
|
|
|
221
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01232
|
UTTOR GHORASHAL NON REG GOVT PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
69.91
|
Rashid & Brothers
|
66.42
|
|
10/05/2018
|
16/05/2019
|
95
|
|
|
|
|
222
|
e-Tender/NBIDNNGPS/COM/MUR/2017-2018/W1-01233
|
GONIPUR REGI. PRIMARY SCHOOL
|
NBIDNNGPS
|
muradnagar
|
|
|
|
|
73.98
|
Mofizul Islam Khan
|
70.28
|
|
10/05/2018
|
16/05/2019
|
65
|
|
|
|
|
223
|
e-Tender/NBIDNNGPS/COM/NAN/2017-2018/W1-00135
|
ATAKARA NON GOV. REG. PRIMARY SCHOOL
|
NBIDNNGPS
|
nangalkot
|
|
|
|
|
69.29
|
M/S Nur Ayasha Traders
|
69.22
|
|
04/04/2018
|
06/01/2019
|
50
|
|
|
|
|
224
|
e-Tender/NBIDNNGPS/COM/TIT/2017-2018/W1-00570
|
MACHHIMPUR AKBAR ALI REGI PRIMARY SCHOOL
|
NBIDNNGPS
|
titas
|
|
|
|
|
72.52
|
M/S Tie Stone
|
68.90
|
|
22/05/2018
|
29/05/2019
|
0
|
|
|
|
|
225
|
e-Tender/NBIDNNGPS/COM/TIT/2017-2018/W1-00571
|
KANAINAGAR PRIMARY SCHOOL
|
NBIDNNGPS
|
titas
|
|
|
|
|
70.24
|
M/S Shakil Enterprise
|
70.33
|
|
22/07/2018
|
25/07/2019
|
0
|
|
|
|
|
226
|
CW-09(b)/RCIP/COM
|
1. Improvement of Barura GC -Modaforganj RHD Road (Road ID419092013, Upazila: Barura, District: Comilla) 2. Improvement of Paranpur Bazar[ R&H]-Payelgacha UP office Road (Road ID419093004, Upazila: Barura, District: Comilla) 3. Improvement of Laksam H/Q - Natherpetua RHD via Munshirhat GC Road.(Monohargonj Portion) (Road ID419902009, Upazila: Monohorgonj, District: Comilla) Improvement of Laksam Upazilla HQ-Chitoshi RHD(Moulana bazar) via Sreeyang Rd. (Road ID419722005, Upazila: Laksham, District: Comilla)
|
RCIP
|
barura
|
419092013
|
27.23
|
0.00
|
29
|
3407.06
|
Masud Hi Tech Engineering Ltd. M/S Anwara Foundation MA Zaheer Ltd. (JV)
|
3883.00
|
12/04/2021
|
19/04/2021
|
18/04/2023
|
36
|
1113.04
|
29
|
31/08/2023
|
|
227
|
CW-09(a)/RCIP/COM
|
1.Improvement of Kadoir bazar(Suvapur UPC) -Banggodda GC Road via Unkot, Kayerdhari. (Road ID419313022, Upazila: Chouddagram, District: Comilla) 2.Improvement of Batisha NHW - Tarashail Bazar(Lal Msq) Road via Batisha Up,Debipur. (Road ID419313007, Upazila: Chouddagram, District: Comilla) 3.Improvement of Adra UP-Manikmura Bazar Road via Volainbazar & Ghoramaidan (Road ID419873008, Upazila: Nangalkot, District: Comilla)
|
RCIP
|
chouddagram
|
419313022 419313007 ID No-419873008
|
15.64
|
0.00
|
98
|
1709.27
|
M/S Zaman Traders, M/S Kohinoor Enterprise(JV)
|
1809.40
|
15/03/2021
|
21/03/2021
|
20/07/2022
|
100
|
1777.05
|
98
|
31/08/2023
|
|
228
|
CW-41(b)/RCIP/CUM
|
3. Improvement of Jafargonj GC to Barashalghar RHD via Yousufpur UPC Road. (Road ID419402006, Upazila: Debidwar, District: Comilla)
|
RCIP
|
debidwar
|
419402006
|
15.82
|
0.00
|
94
|
2216.86
|
MHA & MSE(JV)
|
2199.56
|
02/09/2020
|
09/09/2020
|
31/08/2022
|
100
|
2075.15
|
94
|
31/08/2023
|
|
229
|
CW-41(a)/RCIP/CUM
|
1. Improvement of Raypur NHW-Batakandi GC road via Masimpur (Road ID419892001, Upazila: Titas, District: Comilla) 2.Improvement of Roypur NHW - Batakandi G.C via Masimpur Road (Daudkandi part). (Road ID419362001, Upazila: Daudkandi, District: Comilla)
|
RCIP
|
titas
|
419892001
|
14.26
|
0.00
|
15
|
1838.57
|
MAE-MCL-MKU. JV
|
1898.00
|
27/07/2021
|
03/08/2021
|
01/02/2023
|
28
|
144.83
|
15
|
31/08/2023
|
|
230
|
CW-41(c)/RCIP/CUM
|
Improvement of Batakandi GC-DaudkandiGC Via Mohanpur Launch Ghat road (Titas Upazila Portion) (Road ID419892002, Upazila: Titas, District: Comilla)
|
RCIP
|
titas
|
419892002
|
11.50
|
0.00
|
37
|
1330.76
|
Noona-Mysha-BSL(JV)
|
1460.15
|
18/11/2020
|
25/11/2020
|
28/02/2023
|
46
|
538.42
|
37
|
31/08/2023
|
|
231
|
RERMP-3/CU MI/W-55
|
Maintenance of Rural
Roads Comilla ()
|
RERMP-3
|
cumilla-s
|
N/A
|
|
|
36
|
6241.50
|
N/A
|
6241.50
|
|
|
|
40
|
2295.00
|
36
|
26/12/2021
|
|
232
|
RIDP(CBC)/C-W135 419092003
|
Improvement of Adda - Khajuria Via Poyalgasha road Ch.830-1830m
|
RIDP-CBC
|
barura
|
|
1.00
|
|
|
76.99
|
M/S Hoque International
|
76.50
|
|
19/04/2016
|
28/06/2017
|
100
|
|
|
|
|
233
|
RIDP(CBC)/C-W282 419092003
|
Improvement of Adda GC-Perpety RHD road Ch.1830-2675m
|
RIDP-CBC
|
barura
|
|
0.85
|
|
|
65.70
|
M/S Jahangir khan Chowdory
|
65.70
|
|
05/02/2018
|
11/02/2019
|
15
|
|
|
|
|
234
|
RIDP(CBC)/C-W136 419093010
|
Improvement of (A) Aganagar UP office - Kemtoly Bazar road Ch1000-2006m (B) Construction of 1*1*1m box culvert Ch.1350m &1*3.50*3.00m Ch.1900m Box Culvert
|
RIDP-CBC
|
barura
|
|
1.06
|
|
|
75.42
|
M/S Mithila trading Corporation
|
75.00
|
|
19/04/2016
|
30/06/2017
|
100
|
|
|
|
|
235
|
RIDP(CBC)/C-W24 419094068
|
Improvement of Gompa community clenic to R&H Comilla-Chandpur via Gompa Govt. high school road at ch. 00-400m.
|
RIDP-CBC
|
barura
|
|
0.40
|
|
|
20.27
|
M/S Taslima Enterprise
|
21.28
|
|
01/08/2016
|
30/11/2017
|
100
|
|
|
|
|
236
|
RIDP(CBC)/C-W25 419095104
|
Improvement of Payalgacha-Narayanpur bazar road at ch. 1480-1921m.
|
RIDP-CBC
|
barura
|
|
0.44
|
|
|
22.24
|
M/S Sanam Enterprise
|
21.09
|
|
01/11/2015
|
30/11/2016
|
100
|
|
|
|
|
237
|
RIDP(CBC)/C-W26 419094071
|
(a) Improvement of Dhaka-Chittagonj highway to Boro Kalikapur-Eid gaon Khala Khal-Mothurapur road at ch. 00-1100m.(b) Const. Of 1x3.50x3.00m Single vent RCC Box culvert at ch. 5.00m
|
RIDP-CBC
|
barura
|
|
1.10
|
|
|
55.52
|
M/S Taslima Enterprise
|
58.28
|
|
15/10/2015
|
31/12/2016
|
100
|
|
|
|
|
238
|
RIDP(CBC)/C-W27 419095169
|
Improvement of Dogail Halder Alis House to Sudra Primary School road at ch. 00-700m. & 800-1100m.
|
RIDP-CBC
|
barura
|
|
1.00
|
|
|
46.66
|
M/S Taslima Enterprise
|
48.53
|
|
20/10/2015
|
31/12/2016
|
100
|
|
|
|
|
239
|
RIDP(CBC)/C-W28 419095181
|
Improvement of Choto Batua Chara bazar-Kashera road at ch. 00-400m.
|
RIDP-CBC
|
barura
|
|
0.40
|
|
|
21.39
|
M/S Jaba Enterprise
|
20.04
|
|
09/09/2015
|
30/04/2016
|
100
|
|
|
|
|
240
|
RIDP(CBC)/C-W145 419095171
|
Improvement of Kemtoly Bazar-Bagabaria MosQue road at ch. 00-915m.
|
RIDP-CBC
|
barura
|
|
0.92
|
|
|
48.40
|
M/S Arshad & Sons
|
48.73
|
|
19/04/2016
|
31/05/2017
|
100
|
|
|
|
|
241
|
RIDP(CBC)/C-W144 419094069
|
Improvement of Singur-Derera road at ch. 00-1000m.
|
RIDP-CBC
|
barura
|
|
1.00
|
|
|
52.08
|
M/S Sami Enterprise
|
51.65
|
|
05/05/2016
|
30/04/2018
|
100
|
|
|
|
|
242
|
RIDP(CBC)/C-W82 419094095
|
Improvement of Moisher-Poyalgasa Collage road via Dhuliamuri Govt. Primary school at ch. 2250-2500m & 2700-3450m.
|
RIDP-CBC
|
barura
|
|
1.00
|
|
|
50.25
|
M/S Shajon Enterprise
|
48.24
|
|
01/09/2015
|
30/11/2016
|
100
|
|
|
|
|
243
|
RIDP(CBC)/C-W147 419094004
|
Improvement of (A) Aganagar -Adamsar Bazar road ch.1197-1600m (B) Cons. Of 1x2.5x2.5m Box Culvert-Ch.1250m.
|
RIDP-CBC
|
barura
|
|
0.40
|
|
|
30.69
|
M/S Arshad & Sons
|
32.06
|
|
19/04/2016
|
30/04/2017
|
100
|
|
|
|
|
244
|
RIDP(CBC)/C-W148 419094056
|
Improvement of Poyalgasha Colledge - Halgaon Via Kalora road. ch. 2250-3254m.
|
RIDP-CBC
|
barura
|
|
1.00
|
|
|
49.19
|
M/S M.K Traders
|
49.00
|
|
24/04/2016
|
30/12/2017
|
100
|
|
|
|
|
245
|
RIDP(CBC)/C-W154 419094011.419094035
|
(A) Improvement of Jhalam Gastolbari-Mohidpur road. Ch.1554-2088m (B)Fenua-Nababpur road Ch.00-400m
|
RIDP-CBC
|
barura
|
|
0.93
|
|
|
48.52
|
M/S H.G.F International
|
47.97
|
|
24/05/2016
|
30/04/2018
|
100
|
|
|
|
|
246
|
RIDP(CBC)/C-W155.a
419095008.
419095174
|
(A) Improvement of Rammohan Sutarbari-Gopalnagar road. Ch.00-400m
(B)Poyalgasha-Kazkamta Via Safinagar road Ch.00-455m
|
RIDP-CBC
|
barura
|
|
0.86
|
|
|
48.00
|
M/S Arshad & Sons
|
50.39
|
|
08/06/2016
|
30/09/2017
|
100
|
|
|
|
|
247
|
RIDP(CBC)/C-W174 419095134
419095087
|
(A) Improvement of Narinda -Madhubpur-Bhaishkhola road at ch.00- 500m
(B) Improvement of Dewannagar-Fateharpar road at ch.525- 1090m
|
RIDP-CBC
|
barura
|
|
1.06
|
|
|
58.58
|
M/S Hamim & Brothers
|
58.44
|
|
27/10/2016
|
03/11/2017
|
100
|
|
|
|
|
248
|
RIDP(CBC)/C-W184 419095163
|
Improvement of (A) Sonaimori Latbari-Vateshwar Via Prymary School road) at ch.1000-1615m (B) Construction Of 2x3.00x3.00m Box Culvert at ch.1383M
|
RIDP-CBC
|
barura
|
|
0.62
|
|
|
47.88
|
M/S Raka Enterprise
|
47.78
|
|
31/10/2016
|
31/12/2017
|
100
|
|
|
|
|
249
|
RIDP(CBC)/C-W186 419094055
|
Improvement of (A) Kashedda Chowmohani-Jownagar-Batabaria road) at ch.1738-2248m (B) Construction Of 2x4.5x3.00m Box Culvert at ch.2233M
|
RIDP-CBC
|
barura
|
|
0.51
|
|
|
47.77
|
M/S The Construction
|
47.65
|
|
30/08/2016
|
28/02/2018
|
100
|
|
|
|
|
250
|
RIDP(CBC)/C-W146 419095183,
419095041
|
Improvement of (A) Shakpur DakhinJaula Bari Bridge-Kachiapukoria Belal Bari Bridge Via Shakpur Gazi Shafiqur Rahman house road ch. 00 - 400m (B) Pilgiri Sadim Ali house - Adda Krisnapur road Ch 00-405
|
RIDP-CBC
|
barura
|
|
0.81
|
|
|
45.54
|
M/S M.K Tradera
|
45.30
|
|
17/05/2016
|
31/10/2018
|
100
|
|
|
|
|
251
|
RIDP(CBC)/C-W273 419094046
|
Improvement Of Mogbari (R&H)-Silmori Bazar road ch.2235-3515m
|
RIDP-CBC
|
barura
|
|
1.28
|
|
|
73.76
|
M/S Farhana Builders
|
79.00
|
|
19/02/2018
|
25/10/2018
|
100
|
|
|
|
|
252
|
RIDP(CBC)/C-W275 419095005
|
Improvement Of Mirzanagar-Jagadashar road ch.00-625m
|
RIDP-CBC
|
barura
|
|
0.63
|
|
|
39.28
|
M/S Zaman Traders
|
43.19
|
|
26/04/2018
|
02/11/2018
|
100
|
|
|
|
|
253
|
RIDP(CBC)/C-W276 419095158
|
Improvement Of Jorpukoria High School-Dhanishawar Bazar road ch.1000-1531m
|
RIDP-CBC
|
barura
|
|
0.53
|
|
|
30.23
|
M/S Farhana Builders
|
33.24
|
|
26/04/2018
|
02/11/2018
|
100
|
|
|
|
|
254
|
RIDP(CBC)/C-W277 419094047
|
Improvement Of Amratali-Bashpur road ch.2820-3320m
|
RIDP-CBC
|
barura
|
|
0.50
|
|
|
31.52
|
M/S Farhana Builders
|
34.60
|
|
26/04/2018
|
02/11/2018
|
100
|
|
|
|
|
255
|
RIDP(CBC)/C-W278 419095157
|
Improvement Of Ekbaria-Khajuria-Perpeti via Anidkoda road ch.1000-1500m
|
RIDP-CBC
|
barura
|
|
0.50
|
|
|
29.80
|
M/S Farhana Builders
|
32.74
|
|
26/04/2018
|
02/11/2018
|
100
|
|
|
|
|
256
|
RIDP(CBC)/C-W279 419095148
|
Improvement Of Sultanpur-Joyag road ch.00-400m
|
RIDP-CBC
|
barura
|
|
0.40
|
|
|
22.98
|
M/S Sanom Enterprise
|
24.00
|
|
25/04/2018
|
03/11/2018
|
100
|
|
|
|
|
257
|
RIDP(CBC)/C-W280 419095180
|
Improvement Of Laxmipur (RHD)-Shahebbari-Noapara road ch.1000-1400m
|
RIDP-CBC
|
barura
|
|
0.40
|
|
|
26.73
|
M/S Sanom Enterprise
|
27.91
|
|
25/04/2018
|
03/11/2018
|
100
|
|
|
|
|
258
|
RIDP(CBC)/C-W291 419095049
|
Improvement Of Nalua Primary School-Nalua South Road ch.00-1277m
|
RIDP-CBC
|
barura
|
|
1.28
|
|
|
87.35
|
M/S Zaman Traders
|
96.00
|
|
26/04/2018
|
02/01/2019
|
100
|
|
|
|
|
259
|
RIDP(CBC)/C-SW24 419094074
|
Improvement Of (A) Amratoli Akushar road Ch.00-1350m (B) 3.00X2.00m BoX Culvert at Ch.5.00m & 4No U culvert (C) Protection work
|
RIDP-CBC
|
barura
|
|
1.35
|
|
|
77.87
|
M/S Siam Trading Corporation
|
77.76
|
|
01/08/2016
|
30/12/2018
|
60
|
|
|
|
|
260
|
RIDP(CBC)/C-W173 419095068
419095178
|
(A) Improvement of Pilgiri School -Adda Mia bari road at ch.1700- 220000m
(B) Improvement of Narayanpur-Fakir Bazar Via Payalgasha road at ch.00-400m
|
RIDP-CBC
|
barura
|
|
0.90
|
|
|
47.02
|
M/S Nur Enterprise
|
49.27
|
|
19/03/2017
|
17/02/2018
|
30
|
|
|
|
|
261
|
RIDP(CBC)/C-W185 419095086
|
Improvement of Arifpur Prymary School -Khosbash Bazar road) at ch.1000-1870m
|
RIDP-CBC
|
barura
|
|
0.87
|
|
|
52.56
|
M/S The Construction
|
52.44
|
|
30/08/2016
|
30/12/2018
|
60
|
|
|
|
|
262
|
RIDP(CBC)/C-W187 419094048
|
Improvement of (A) Chitushi Railway Station-NaluanChadpur road) at ch.00-700m (B) Construction Of 219m Protection Work
|
RIDP-CBC
|
barura
|
|
0.70
|
|
|
55.27
|
M/S A Rahman Enterprise
|
58.02
|
|
19/10/2016
|
30/05/2018
|
60
|
|
|
|
|
263
|
RIDP(CBC)/C-W292 419095019
|
Improvement Of Olitala-Arifpur-Dgirpar Road ch.00-614m & 789-926
|
RIDP-CBC
|
barura
|
|
0.75
|
|
|
55.98
|
M/S Mithila Trading Corporation
|
55.08
|
|
06/03/2018
|
12/11/2018
|
40
|
|
|
|
|
264
|
RIDP(CBC)/C-M59 419092008
|
Maintenance of Amratoli Bazar (R&H) Kalir Bazar Via Bataishari Bazar road at ch. 3100-3960m.
|
RIDP-CBC
|
barura
|
|
0.86
|
|
|
14.18
|
M/S Masuk Enterprise
|
13.21
|
|
02/08/2016
|
02/08/2016
|
100
|
|
|
|
|
265
|
RIDP(CBC)/C-M58 419094039
|
Maintenance of Rajapur-Aganagar UP road at ch. 00-2500m.
|
RIDP-CBC
|
barura
|
|
2.50
|
|
|
57.66
|
M/S Taslima Enterprise
|
54.32
|
|
30/11/2017
|
23/11/2017
|
100
|
|
|
|
|
266
|
RIDP(CBC)/C-M108 419094052
|
Periodic Maintenance of (Overlay) Moishair-Dogai-Narayanpur Bazar-Ekbaria road at ch.00-500m.
|
RIDP-CBC
|
barura
|
|
0.50
|
|
|
12.24
|
M/S Nazrul Enterprise
|
12.23
|
|
28/08/2017
|
13/02/2017
|
100
|
|
|
|
|
267
|
RIDP(CBC)/C-M109 419094030
|
Periodic Maintenance of (Overlay) Perpeti-Narindrapur-Shakpur (Perpeti bazar-Shakpur UP Office) road at ch.00-600m.
|
RIDP-CBC
|
barura
|
|
0.60
|
|
|
13.43
|
M/S M.K Traders
|
11.75
|
|
28/08/2017
|
15/06/2017
|
100
|
|
|
|
|
268
|
RIDP(CBC)/C-W175 419153006
|
Improvement of Chandla UP Office ( R&H) Darpanarayanpur-Kandughar bazar road at ch.1550-2550m
|
RIDP-CBC
|
brahmanpara
|
|
1.00
|
|
|
50.50
|
M/S Lokman Hossain
|
49.21
|
|
20/07/2016
|
28/02/2018
|
100
|
|
|
|
|
269
|
RIDP(CBC)/C-W164.a
419154039
419154014
419154035
|
Improvement Of (A) Tatera-Chatiani-Gopalnagor Bazar road Ch.670-1170m
(B) Chadla-Shidlai-Larucho Road at Ch.5000-5500m
(C) Mokimpur Bus Stand-Mokimpur Pty School Road.Ch.1377-1958m
|
RIDP-CBC
|
brahmanpara
|
|
1.58
|
|
|
79.63
|
M/S M.K Traders
|
78.64
|
|
23/06/2016
|
28/02/2018
|
100
|
|
|
|
|
270
|
RIDP(CBC)/C-W199. 419154014
419154011
|
Improvement Of (A) Chandla-Shidlai-Larachu road ch.5500-5930m
(B) Shidlai-Berakhola road ch.00-400m
|
RIDP-CBC
|
brahmanpara
|
|
0.83
|
|
|
39.44
|
M/S Nazrul Enterprise
|
36.49
|
|
22/01/2017
|
17/11/2017
|
100
|
|
|
|
|
271
|
RIDP(CBC)/C-W176 419154040
|
Improvement of Dhainnyadul R&H roadAshabari road (Sener Bazar) at ch.00-500m
|
RIDP-CBC
|
brahmanpara
|
|
0.50
|
|
|
24.67
|
M/S E.F Trade Int.
|
23.85
|
|
06/09/2016
|
12/05/2017
|
100
|
|
|
|
|
272
|
RIDP(CBC)/C-W213. 419154022
419154041
|
Improvement Of (A) Gopalnagar-Nalla road Ch.500-1000m
(B)Ashabari-Narayanpur-Shibpur-Bagra Bazar road Ch.380-880m
|
RIDP-CBC
|
brahmanpara
|
|
1.00
|
|
|
50.47
|
M/S M.A.Zaher
|
45.92
|
|
20/02/2017
|
26/02/2018
|
40
|
|
|
|
|
273
|
RIDP(CBC)/C-W214. 419155021
|
Improvement Of Chandpara-Gopalnagar road Ch.00-575m
|
RIDP-CBC
|
brahmanpara
|
|
0.58
|
|
|
30.90
|
M/S M.A.Zaher
|
28.32
|
|
20/02/2017
|
26/09/2017
|
60
|
|
|
|
|
274
|
RIDP(CBC)/C-W245 419154024
|
Improvement Of Zeroin-Chandipur-Alua Ferighat via Malapara Up Office road (Zeroin-Chandipur)ch.00-1250m
|
RIDP-CBC
|
brahmanpara
|
|
1.25
|
|
|
78.64
|
M/S Zakir Traders
|
71.47
|
|
06/04/2017
|
12/04/2018
|
30
|
|
|
|
|
275
|
RIDP(CBC)/C-W56 419152002
|
Improvement of Dulalpur GC-Jafargonj GC Road at Ch. 2910-3810m
|
RIDP-CBC
|
brahmanpara
|
|
0.90
|
|
|
38.61
|
M/S E.F Trade Int.
|
36.87
|
|
11/06/2015
|
03/02/2016
|
100
|
|
|
|
|
276
|
RIDP(CBC)/C-W57 419153005
|
Improvement of Bramanpara-Satiyani-Jeroin-Chandipur Malapara UP Office road at ch. 00-580m
|
RIDP-CBC
|
brahmanpara
|
|
0.58
|
|
|
27.65
|
M/S E.F. Trade Int.
|
25.72
|
|
11/06/2015
|
30/11/2015
|
100
|
|
|
|
|
277
|
RIDP(CBC)/C-W58 419154002
|
Improvement of Ramnagar Pachim Sandipur Monoharpur Kongshanagar road at ch. 1188-1688m.
|
RIDP-CBC
|
brahmanpara
|
|
0.50
|
|
|
21.53
|
M/S M.A Zaher
|
18.20
|
|
07/10/2015
|
13/02/2016
|
100
|
|
|
|
|
278
|
RIDP(CBC)/C-W59 419154003
|
Improvement of Pomkara Agaragram bazar road at ch. 1300-1800m.
|
RIDP-CBC
|
brahmanpara
|
|
0.50
|
|
|
21.53
|
M/S E.F Trade Int.
|
20.13
|
|
11/06/2015
|
18/12/2015
|
100
|
|
|
|
|
279
|
RIDP(CBC)/C-M57 419152002
|
Maintenance of Dulalpur GC-Jafargonj GC road at ch. 1892-2910m.
|
RIDP-CBC
|
brahmanpara
|
|
1.02
|
|
|
20.28
|
M/S Masuk Enterprise
|
19.67
|
|
02/08/2016
|
26/06/2016
|
100
|
|
|
|
|
280
|
RIDP(CBC)/C-M93 419182009
|
Maintenance ( Overlay) of Nimshar Collage-Chitoshi Railstation road via Kedarpur Bazar Barura powrashava-Poilgasha Collage-Nalua Chandpur road at ch.00-2100m.
|
RIDP-CBC
|
burichong
|
|
2.10
|
|
|
51.99
|
Md.Alamgir Hossain
|
47.78
|
|
03/12/2017
|
30/10/2017
|
100
|
|
|
|
|
281
|
RIDP(CBC)/C-W208 419182005
|
Improvement of Abidpur GC-Korpai Post Office NHW road Ch.1500-2500m
|
RIDP-CBC
|
burichong
|
|
1.00
|
|
|
72.18
|
M/S Priyanka Enterprise
|
69.60
|
|
27/02/2017
|
05/03/2018
|
60
|
|
|
|
|
282
|
RIDP(CBC)/C-W46 419183010
|
Improvement of Moynamoti UP Office-Gazaria bazar via Baraer road at ch. 00-500m
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
27.15
|
M/S Zahin Traders
|
27.10
|
|
07/12/2015
|
30/11/2016
|
100
|
|
|
|
|
283
|
RIDP(CBC)/C-W150 419183015
|
Improvement of Kabila GC- Moynamoti UP Shaheber bazar RHW road Ch.00-500m
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
26.79
|
M/S Priyanka Enterprise
|
27.98
|
|
05/05/2016
|
11/01/2017
|
100
|
|
|
|
|
284
|
RIDP(CBC)/C-W209 419183006
|
Improvement Of (A) Barella UP Office (Comilla Sylhet R&H)-Fultoli Bazar road ch.2640-2800m
|
RIDP-CBC
|
burichong
|
|
0.16
|
|
|
22.09
|
M/S Sikder Enterprise
|
18.94
|
|
14/02/2017
|
30/12/2018
|
75
|
|
|
|
|
285
|
RIDP(CBC)/C-W210 419183014
|
Improvement Of Burichong UP Office -Shadekpur bazar via Arag Anandapur road ch.3916-4536m
|
RIDP-CBC
|
burichong
|
|
0.62
|
|
|
39.92
|
M/S Saleh Ahmed
|
33.93
|
|
20/02/2017
|
26/09/2017
|
80
|
|
|
|
|
286
|
RIDP(CBC)/C-W20 419185150
|
Improvement of Korpai post office more (Mokam union Health complex) to Raja Mar Jangal to Piour bazar road at ch. 00-1000m
|
RIDP-CBC
|
burichong
|
|
1.00
|
|
|
53.44
|
M/S Mizan Traders
|
49.42
|
|
30/04/2015
|
28/02/2016
|
100
|
|
|
|
|
287
|
RIDP(CBC)/C-W43 419184005
|
Improvement of Porihalpara-NHW-Halgaon road at ch. 00-838m.
|
RIDP-CBC
|
burichong
|
|
0.84
|
|
|
45.59
|
M/S Akter Enterprise
|
47.85
|
|
16/06/2015
|
28/02/2017
|
100
|
|
|
|
|
288
|
RIDP(CBC)/C-W44 419185058
|
Improvement of Balarampur mosque-Panar pukurper road at ch. 00-500m.
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
27.11
|
M/S Akter Enterprise
|
28.46
|
|
16/06/2015
|
28/02/2016
|
100
|
|
|
|
|
289
|
RIDP(CBC)/C-W45 419184010
|
Improvement of Gazipur Diptubwel-Mithilapur Ferighat road at ch. 00-500m.
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
24.97
|
M/S Pioneer Construction
|
26.21
|
|
13/09/2015
|
20/04/2016
|
100
|
|
|
|
|
290
|
RIDP(CBC)/C-W91 419185141
|
Improvement of Paharpur Community Primary school-Hossen shop via Samad mollah house road at ch. 00-500m.
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
22.62
|
M/S Akter Enterprise
|
23.74
|
|
22/12/2015
|
31/12/2016
|
100
|
|
|
|
|
291
|
RIDP(CBC)/C-W112 419184086
|
Improvement of Chay Gram Bazar-Kalikrishnanagsr road at ch. 00-500m.
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
24.21
|
M/S Shamsunnahar Enterprise
|
25.41
|
|
27/01/2016
|
31/12/2016
|
100
|
|
|
|
|
292
|
RIDP(CBC)/C-W113 419185130
|
Improvement of Fakir Bazar Madrasha Pachimpara Graveyard Via khandaker Bari road at ch. 00-500m.
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
27.70
|
M/S Shamsunnahar Enterprise
|
29.07
|
|
27/01/2016
|
31/12/2016
|
100
|
|
|
|
|
293
|
RIDP(CBC)/C-W118
|
Improvement of Paharpur Comioniti Praymer School Paharpur Hossain Shop Via Samad Mollah House road at ch.5 00-1100m.
|
RIDP-CBC
|
burichong
|
|
0.60
|
|
|
29.27
|
M/S Akter Enterprise
|
30.73
|
|
21/03/2016
|
27/11/2016
|
100
|
|
|
|
|
294
|
RIDP(CBC)/C-W143 419184084
|
Improvement of Dharmanagar-Mirpur road at ch.17 00-2440m.
|
RIDP-CBC
|
burichong
|
|
0.74
|
|
|
32.31
|
M/S Akter Enterprise
|
35.14
|
|
11/04/2016
|
30/08/2017
|
100
|
|
|
|
|
295
|
RIDP(CBC)/C-W122 .a
419185133
419184061
|
Improvement of (A) Utturgram Uttarpara Jame Mosjeed road Via Manu Sarder house road Ch.00-610m.
(B) Pashim Monipur NHW-Panchkitta Bazar road Ch.631-1111m
|
RIDP-CBC
|
burichong
|
|
1.09
|
|
|
53.28
|
M/S Roki Auto house
|
55.93
|
|
01/02/2016
|
30/11/2016
|
100
|
|
|
|
|
296
|
RIDP(CBC)/C-W132.a
419185009
419185008
|
(A) Improvement of Pachora Madrasha - Fazlu Chairman house road Ch.00-490m
(B) Pachora Govt.Pri.School Pachura Shahidul Shop road. Ch.00-500m
|
RIDP-CBC
|
burichong
|
|
0.99
|
|
|
46.02
|
M/S Century Enterprise
|
0.00
|
|
24/04/2016
|
30/06/2017
|
100
|
|
|
|
|
297
|
RIDP(CBC)/C-W160 419185026
|
Improvement Of Dayarampur Bhuyan Bari Road.Ch.00-500m
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
30.00
|
M/S Zahin Traders
|
28.61
|
|
21/08/2016
|
25/10/2017
|
100
|
|
|
|
|
298
|
RIDP(CBC)/C-W177 419184089
|
Improvement of Bakshimul Bazar- Fakir Bazar Via Madabpur rail Line road at ch.00-500m
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
25.93
|
M/S Akter Enterprise
|
27.12
|
|
06/09/2016
|
29/10/2017
|
100
|
|
|
|
|
299
|
RIDP(CBC)/C-W256 419185050
|
Improvement Of Narayanshar NHW-Karimabad via barabari road ch.00-500m
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
24.55
|
Md.Delowar Hossain Babul
|
25.77
|
|
23/08/2017
|
01/03/2018
|
100
|
|
|
|
|
300
|
RIDP(CBC)/C-W211 419185019
|
Improvement Of Kalikapur Bazar -Kalikapur Village Internal road ch.00-1368m
|
RIDP-CBC
|
burichong
|
|
1.37
|
|
|
39.83
|
M/S Akter Enterprise
|
36.52
|
|
01/02/2017
|
31/10/2018
|
100
|
|
|
|
|
301
|
RIDP(CBC)/C-W255 419185021
|
Improvement Of Pachura Anu Mia house-Khanjanimura road ch.00-500m
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
32.85
|
M/S Nusrat Enterprise
|
32.29
|
|
28/06/2017
|
31/12/2018
|
100
|
|
|
|
|
302
|
RIDP(CBC)/C-W246 419185001
|
Improvement Of Haripur-Gungur Nadi road ch.550-1350m
|
RIDP-CBC
|
burichong
|
|
0.80
|
|
|
55.49
|
M/S B.H Construction
|
54.65
|
|
22/06/2017
|
27/06/2018
|
60
|
|
|
|
|
303
|
RIDP(CBC)/C-W247 419185033
|
Improvement Of Jagatpur Maddya para-Arshadnagar road via Mazed Mamber house road ch.00-500m
|
RIDP-CBC
|
burichong
|
|
0.50
|
|
|
45.35
|
M/S B.H Construction
|
47.61
|
|
08/04/2018
|
14/12/2018
|
30
|
|
|
|
|
304
|
RIDP(CBC)/C-W254 419185020
|
Improvement Of Pachura Bazar-Barashar nagar Pachura praymary school road ch.180-725m
|
RIDP-CBC
|
burichong
|
|
0.55
|
|
|
32.98
|
M/S Century Enterprise
|
32.89
|
|
11/06/2017
|
17/02/2018
|
10
|
|
|
|
|
305
|
RIDP(CBC)/C-W21 419273018
|
Improvement of Kaduti Bazar-Derera bazar(Joag UP) Orain-Taltala road at ch.2580-3680m
|
RIDP-CBC
|
chandina
|
|
1.10
|
|
|
61.90
|
M/S Lotas Enterprise
|
57.25
|
|
27/04/2015
|
28/02/2016
|
100
|
|
|
|
|
306
|
RIDP(CBC)/C-W97 419273015
|
(a) Improvement of Gomta-Batagashi-Mohonpur road at ch.5500-6500m (b) Protection work 41.00m same road.
|
RIDP-CBC
|
chandina
|
|
1.00
|
|
|
57.41
|
M/S Eashan Enterprise
|
55.62
|
|
01/02/2016
|
07/08/2017
|
100
|
|
|
|
|
307
|
RIDP(CBC)/C-W240 419273014
|
Improvement Of Barkari-(Muggarpar)Kaduti bazar road via Barkori UPC road ch.1500-2300m
|
RIDP-CBC
|
chandina
|
|
0.80
|
|
|
59.78
|
M/S Jhilik Enterprise
|
59.15
|
|
08/06/2017
|
14/06/2018
|
100
|
|
|
|
|
308
|
RIDP(CBC)/C-W22 419275098
|
Improvement of Maddamtala-Baniachong-Sreemontapur-Chandiyara road at ch. 00-1500m (Moddamtala to Chandiyara & Borkoit via Sreemontapur-Baniachong road)
|
RIDP-CBC
|
chandina
|
|
1.20
|
|
|
51.80
|
M/S Shamsunnahar Enterprise
|
51.80
|
|
20/04/2015
|
30/04/2016
|
100
|
|
|
|
|
309
|
RIDP(CBC)/C-W151 419274081
|
Improvement of Noritala Govt.Primary school-Kuarpar road at ch. 00-343m (Noritola-Keronkhal GPS at West side Of Late Muktijudda Delowar hossain house to R&H road) & Construction of 3x4x4.50m RCC box Culvert at Ch.315m
|
RIDP-CBC
|
chandina
|
|
0.34
|
|
|
51.96
|
M/S Jhilik Enterprise
|
48.24
|
|
17/05/2016
|
30/11/2017
|
100
|
|
|
|
|
310
|
RIDP(CBC)/C-W23 419275095
|
Improvement of Chandina Rammohan road-Av. Shahidul Islam road at ch. 500-1000m.
|
RIDP-CBC
|
chandina
|
|
0.50
|
|
|
26.18
|
M/S Shamsunnahar Enterprise
|
26.18
|
|
07/05/2015
|
30/04/2016
|
100
|
|
|
|
|
311
|
RIDP(CBC)/C-W115
|
Improvement of joywag South Market to South Noagaon road Ch.800-1300m
|
RIDP-CBC
|
chandina
|
|
0.50
|
|
|
31.06
|
M/S Anik Enterprise
|
29.48
|
|
02/03/2016
|
28/02/2018
|
100
|
|
|
|
|
312
|
RIDP(CBC)/C-W225 419274023
|
Improvement Of Singur -Derera road ch.1000-1525m
|
RIDP-CBC
|
chandina
|
|
0.53
|
|
|
34.12
|
M/S Anik Enterprise
|
33.77
|
|
30/05/2017
|
26/03/2018
|
100
|
|
|
|
|
313
|
RIDP(CBC)/C-W251 419274076
|
Improvement Of Ranichara-Banglabazar (Start from Vhomorkandi High school) to Karnafuli Bridge road ch.550-1050m
|
RIDP-CBC
|
chandina
|
|
0.50
|
|
|
40.12
|
M/S M.M Enterprise
|
40.11
|
|
30/05/2017
|
05/02/2018
|
60
|
|
|
|
|
314
|
RIDP(CBC)/C-W252 419275024
|
Improvement Of Panipara-Kamarkhola road ch.00-690m
|
RIDP-CBC
|
chandina
|
|
0.69
|
|
|
46.67
|
M/S M.M Enterprise
|
46.72
|
|
30/05/2017
|
05/02/2018
|
100
|
|
|
|
|
315
|
RIDP(CBC)/C-W239 419275185
|
(A)Improvement Of Bhuri village pacca road-Shalim house road ch.00-500m
|
RIDP-CBC
|
chandina
|
|
0.50
|
|
|
45.31
|
M/S Lotus Enterprise
|
45.25
|
|
30/04/2017
|
25/02/2018
|
100
|
|
|
|
|
316
|
RIDP(CBC)/C-W200. 419274002
|
Improvement Of Pihor-Borkoit road at ch.2000-2500m
|
RIDP-CBC
|
chandina
|
|
0.50
|
|
|
29.32
|
M/S Shetara Construction
|
30.78
|
|
16/04/2017
|
22/04/2018
|
20
|
|
|
|
|
317
|
RIDP(CBC)/C-W238 419274076
419275039
|
(A)Improvement Of Ranichara-Banglabazar road-Karnafully Bridge road ch.00-550m
(B)Improvement Of Suhilpur Adam Ali house-Muradnagor road ch.600-1100m
|
RIDP-CBC
|
chandina
|
|
1.05
|
|
|
70.59
|
M/S Shetara Construction
|
70.58
|
|
16/04/2017
|
22/04/2018
|
60
|
|
|
|
|
318
|
RIDP(CBC)/C-W253 419275063
|
Improvement Of Monther hatkhola-Chilora (Omberpur) road ch.00-500m
|
RIDP-CBC
|
chandina
|
|
0.50
|
|
|
34.60
|
M/S M.M Enterprise
|
34.59
|
|
30/05/2017
|
30/11/2018
|
60
|
|
|
|
|
319
|
RIDP(CBC)/C-BW12 419275039
|
Construction of 22m Girder Bridge on Suhilpur Adam Ali house-Muradnagar road.at Ch-1730m
|
RIDP-CBC
|
chandina
|
|
|
|
|
153.19
|
M/S Hasan Enterprise
|
137.87
|
|
17/09/2017
|
03/12/2018
|
40
|
|
|
|
|
320
|
RIDP(CBC)/C-M65 419272005
|
Maintenance of Mohichail-satadda-Badurpur road at ch. 00-1564m.
|
RIDP-CBC
|
chandina
|
|
1.56
|
|
|
36.76
|
M/S Shamsunnahar Enterprise
|
38.59
|
|
07/09/2016
|
25/06/2016
|
100
|
|
|
|
|
321
|
RIDP(CBC)/C-M131 419272001
|
Re-Construction of 1x4.00x4.00m Rcc Culvert on Chandina-Dollai-Nowabpur road at Ch.5570m
|
RIDP-CBC
|
chandina
|
|
|
|
|
22.19
|
M/S M.M Enterprise
|
19.97
|
|
04/07/2018
|
23/05/2018
|
100
|
|
|
|
|
322
|
RIDP(CBC)/C-M134 419272003
|
Periodic Maintenance (Overlay) of Chandina-Latifpur road at ch. 00-1800m.
|
RIDP-CBC
|
chandina
|
|
1.80
|
|
|
69.55
|
M/S M.M Enterprise
|
63.95
|
|
24/06/2018
|
03/03/2018
|
100
|
|
|
|
|
323
|
RIDP(CBC)/C-M132 419272005
|
Re-Construction of 2x4.00x4.00m Rcc Culvert on road at Ch.1760m
|
RIDP-CBC
|
chandina
|
|
|
|
|
31.75
|
M/S M.A.Zaher
|
29.37
|
|
02/07/2018
|
|
90
|
|
|
|
|
324
|
RIDP(CBC)/C-M39 413912009
|
Maintenance of (Rehabilitation) of Padua(NHW) Bazar-Gunabati GC road at ch. 3000-5837m.
|
RIDP-CBC
|
chouddagram
|
|
2.84
|
|
|
64.20
|
M/S Patowari Enterprise
|
67.39
|
|
15/06/2016
|
10/06/2016
|
100
|
|
|
|
|
325
|
RIDP(CBC)/C-M40 413912009
|
Maintenance of (Rehabilitation) of Padua(NHW) Bazar-Gunabati GC road at ch. 00-3000m.
|
RIDP-CBC
|
chouddagram
|
|
3.00
|
|
|
70.58
|
M/S Rehana Construction
|
74.09
|
|
23/06/2016
|
10/06/2016
|
100
|
|
|
|
|
326
|
RIDP(CBC)/C-M25 419313003
|
Maintenance of Latimi R&H-Railline-Bendarjola via Alkara up office Road at Ch. 00-3805m Under Chouddagram Upazila
|
RIDP-CBC
|
chouddagram
|
|
3.81
|
|
|
45.85
|
M/S Rehana Construction
|
48.13
|
|
19/08/2015
|
30/06/2015
|
100
|
|
|
|
|
327
|
RIDP(CBC)/C-M26 419313006
|
Re-Construction of 3x4.5x5.0m RCC Box Culvert on Protabpur (Uzirpur UP)-Darbesh bazar road at Ch 3480m Under Chouddagram Upazila.
|
RIDP-CBC
|
chouddagram
|
|
|
|
|
26.73
|
M/S Poly Enterprise
|
26.73
|
|
03/09/2015
|
03/09/2015
|
100
|
|
|
|
|
328
|
RIDP(CBC)/C-M105 419313003
|
Periodic Maintenance of (Re-Seal) Latimi R&H-Banderjola via Alkora UPC road ch. 3805-8012m.
|
RIDP-CBC
|
chouddagram
|
|
4.21
|
|
|
80.56
|
M/S Rehana Construction
|
80.54
|
|
30/05/2018
|
20/05/2018
|
100
|
|
|
|
|
329
|
RIDP(CBC)/C-M155 419313019
|
Periodic Maintenance (Re-Seal)) of Gunabati GC (UPC)-Batiara via Al-Amin Market-Gangra road ch.00-4260m & 6394-7291m.
|
RIDP-CBC
|
chouddagram
|
|
5.16
|
|
|
60.44
|
M/S Abul Hasem
|
66.18
|
|
25/10/2018
|
|
50
|
|
|
|
|
330
|
RIDP(CBC)/C-M24 419314008
|
Maintenance of Syedpur-Narayanpur Uttar para road at Ch. 00-1500m .
|
RIDP-CBC
|
chouddagram
|
|
1.50
|
|
|
31.14
|
M/S. Mahabub Enterprise
|
32.69
|
|
31/03/2016
|
15/03/2016
|
100
|
|
|
|
|
331
|
RIDP(CBC)/C-M27 419314189
|
Maintenance of Dhorkara-Shaktala Village Road at Ch. 00-1775m .
|
RIDP-CBC
|
chouddagram
|
|
1.78
|
|
|
39.45
|
M/S. Rehana Construction
|
39.45
|
|
30/09/2016
|
07/08/2016
|
100
|
|
|
|
|
332
|
RIDP(CBC)/C-W293 41935224
|
Improvement Of Amangonda (Takiamgach Koborastan) East side Babuchi village Road ch.1700-2300m & 2940-3225m
|
RIDP-CBC
|
chouddagram
|
|
0.89
|
|
|
51.13
|
M/S Poly Enterprise
|
54.71
|
|
18/03/2018
|
24/11/2018
|
100
|
|
|
|
|
333
|
RIDP(CBC)/C-W294 419315029
|
Improvement Of Mestala (Mazumder bari) -Shuvapur GPS Via Laxmipur Road ch.00-557m
|
RIDP-CBC
|
chouddagram
|
|
0.56
|
|
|
32.41
|
M/S Patowary Enterprise
|
32.41
|
|
27/03/2018
|
02/10/2018
|
100
|
|
|
|
|
334
|
RIDP(CBC)/C-SW43 419314146
419315348
419315347
|
Improvement Of (A) Gangra bazar-Satchar-Vajonkora west Para Mosque road ch.1030-1795m
Improvement Of (B) Ratonpur Helal Master house-Ratonpur Jame Mosque road ch.00-605m
Improvement Of (C) Rampur Soban Mia house-Subarnapur Master Jolil house road ch.00-2
|
RIDP-CBC
|
chouddagram
|
|
1.60
|
|
|
80.60
|
M/S R-Ta Enterprise
|
84.59
|
|
20/09/2017
|
26/09/2018
|
60
|
|
|
|
|
335
|
RIDP(CBC)/C-BW27 419314281
|
Construction of 30.06 Long RCC Girder Bridge on Hossainpur Moddompara eidgah-Bander bari Dumuria West para Modina bazar road at ch.60m
|
RIDP-CBC
|
chouddagram
|
|
|
|
|
152.30
|
M/S Poly Enterprise
|
152.30
|
|
11/03/2018
|
17/03/2019
|
60
|
|
|
|
|
336
|
RIDP(CBC)/C-BW35 419314054
|
Construction of 72.00 Long PSC Girder Bridge On krishnapur-Chalklaxmipur road at ch.900m
|
RIDP-CBC
|
chouddagram
|
|
|
|
|
324.00
|
M/S Poly Enterprise
|
340.00
|
|
14/02/2018
|
14/03/2019
|
50
|
|
|
|
|
337
|
RIDP(CBC)/C-W300 419315174
|
Improvement Of Rampur-Subarnapur-Aripukor -Al Amin Market Road ch.00-1310m
|
RIDP-CBC
|
chouddagram
|
|
1.31
|
|
|
89.19
|
M/S G.S Fashion
|
89.16
|
|
11/04/2018
|
17/04/2019
|
20
|
|
|
|
|
338
|
RIDP(CBC)/C-W301 419314211
|
Improvement Of Khillapara-Akshor Rajghat Road ch.00-840 & 900-960m
|
RIDP-CBC
|
chouddagram
|
|
1.44
|
|
|
59.79
|
M/S ABC Construction
|
63.97
|
|
03/04/2018
|
09/12/2018
|
70
|
|
|
|
|
339
|
RIDP(CBC)/C-W302 419314048
|
Improvement Of Chandul-Mothua Road ch.00-825m
|
RIDP-CBC
|
chouddagram
|
|
0.83
|
|
|
51.18
|
M/S Poly Enterprise
|
53.73
|
|
09/04/2018
|
15/12/2018
|
70
|
|
|
|
|
340
|
RIDP(CBC)/C-W304 419315273
|
Improvement Of Akab Bazar-Sorputi Road ch.00-2004m
|
RIDP-CBC
|
chouddagram
|
|
2.00
|
|
|
126.98
|
M/S Saiful Enterprise
|
133.31
|
|
11/04/2018
|
17/04/2019
|
70
|
|
|
|
|
341
|
RIDP(CBC)/C-W303 419314137
|
Improvement Of West Dekra-Narayankuri road to Alkora Bazar Road ch.1550-2665m
|
RIDP-CBC
|
chouddagram
|
|
1.12
|
|
|
79.92
|
M/S Finex Construction
|
87.47
|
|
31/07/2018
|
06/08/2019
|
10
|
|
|
|
|
342
|
RIDP(CBC)/C-W10 419312007
|
Improvement of Gunabati-Akdia road at Ch. 4423-5014m
|
RIDP-CBC
|
chouddagram
|
|
0.59
|
|
|
49.41
|
M/S Rehana construction
|
49.40
|
|
09/04/2015
|
30/04/2017
|
100
|
|
|
|
|
343
|
RIDP(CBC)/C-W244 419313025
|
Improvement Of Chouddagram (Upzila Parishad)-Khironshal Bazar-Mitalla road ch.4756-5293m
|
RIDP-CBC
|
chouddagram
|
|
0.54
|
|
|
32.95
|
M/S Poly Enterprise
|
34.76
|
|
28/06/2017
|
21/04/2018
|
100
|
|
|
|
|
344
|
RIDP(CBC)/C-W2 419314178
|
Improvement of Zatrapur-Hilalnagar-Dharmopur-Basantapur road at ch. 00-1418m.
|
RIDP-CBC
|
chouddagram
|
|
1.42
|
|
|
56.59
|
M/S Tanha Enterprise
|
56.59
|
|
22/02/2015
|
31/01/2016
|
100
|
|
|
|
|
345
|
RIDP(CBC)/C-W3 419315176
|
Improvement of Asrafpur-Komardoga road at ch. 75-675m.
|
RIDP-CBC
|
chouddagram
|
|
0.60
|
|
|
24.11
|
M/S Abir Enterprise
|
24.10
|
|
15/03/2015
|
31/05/2016
|
100
|
|
|
|
|
346
|
RIDP(CBC)/C-SW1 419315287
|
Improvement of Utter Lateme Master Mohammed Ali bari to Let. Situ mia bari via Rafiq bhuiyan bari road at ch. 00-275m
|
RIDP-CBC
|
chouddagram
|
|
0.28
|
|
|
15.40
|
M/S Saiful Enterprise
|
16.16
|
|
16/06/2015
|
31/01/2017
|
100
|
|
|
|
|
347
|
RIDP(CBC)/C-SW2 419314168
|
Improvement of Gobindapur bazar-Hazari para road at ch. 970-2090m
|
RIDP-CBC
|
chouddagram
|
|
1.12
|
|
|
45.62
|
M/S Shahajan Enterprise
|
47.89
|
|
11/06/2015
|
31/05/2017
|
100
|
|
|
|
|
348
|
RIDP(CBC)/C-SW3 419314284
|
Improvement of Mia Bazar GC-Asrafpur-Krisnapur road at ch. 90-436m
|
RIDP-CBC
|
chouddagram
|
|
0.35
|
|
|
13.55
|
M/S Abir Enterprise
|
13.55
|
|
15/03/2015
|
31/05/2017
|
100
|
|
|
|
|
349
|
RIDP(CBC)/C-SW6 419314123
|
Improvement of Bulkara-Buddin road at ch. 504-1376m
|
RIDP-CBC
|
chouddagram
|
|
0.87
|
|
|
36.45
|
M/S Abir Enterprise
|
38.26
|
|
22/03/2015
|
31/12/2016
|
100
|
|
|
|
|
350
|
RIDP(CBC)/C-SW7 419314157
419315284
|
(A) Improvement of Basanta pur Motin member-Nankara mohila Madrasha-Dhaka-Chittagonj(Kathal Gastala) road at ch. 3150-4000m.
(B) Nankara Maddampara Edris bhuiyan bari-Motin bari-Nankara Utterpara Esak Chowdhury bari road at ch. 00-353m & 391-792m.
|
RIDP-CBC
|
chouddagram
|
|
1.60
|
|
|
66.39
|
M/S Patawari Enterprise
|
69.69
|
|
31/03/2015
|
31/12/2015
|
100
|
|
|
|
|
351
|
RIDP(CBC)/C-SW9 419314216
|
Improvement opf Chandiskara-Satitala-Baraiya road at ch. 525-1687m.
|
RIDP-CBC
|
chouddagram
|
|
1.16
|
|
|
54.53
|
M/S Patawari Enterprise
|
56.51
|
|
31/03/2015
|
30/06/2016
|
100
|
|
|
|
|
352
|
RIDP(CBC)/C-SW-8 419315291
|
Improvement of Fulagram Digi-Kapowchatoly village road at Ch. 00-1137m
|
RIDP-CBC
|
chouddagram
|
|
1.14
|
|
|
39.60
|
M/S Abir Enterprise
|
41.54
|
|
23/04/2015
|
30/05/2016
|
100
|
|
|
|
|
353
|
RIDP(CBC)/C-W1 41915171
|
(a) Improvement of Dhaka Ctg Highway-Kuliara-Ludiara road at Ch 800-1253m & 1280-2310m (b) Construction of Brick culvert & Protective work on Dhaka Ctg Highway-Kuliara-Ludiara road
|
RIDP-CBC
|
chouddagram
|
|
1.48
|
|
|
76.54
|
M/S Maisha Enterprise
|
76.54
|
|
05/05/2015
|
31/03/2016
|
100
|
|
|
|
|
354
|
RIDP(CBC)/C-W12 419314131
|
Improvement of Naraonpur -Baiskara via Jospur madrasha-& Mandaria Road at Ch. 4410-5195m
|
RIDP-CBC
|
chouddagram
|
|
0.79
|
|
|
31.65
|
M/S Abul Hasem
|
33.22
|
|
20/04/2015
|
30/08/2015
|
100
|
|
|
|
|
355
|
RIDP(CBC)/C-SW10 419315289
|
Construction of 2x4.50x4.50m RCC Box culvert on Pachra-Fulmuri road over Baluzori khal.
|
RIDP-CBC
|
chouddagram
|
|
|
|
|
19.49
|
M/S Patawari Enterprise
|
20.46
|
|
31/03/2015
|
28/02/2016
|
100
|
|
|
|
|
356
|
RIDP(CBC)/C-W34 419314282
|
Improvement of Narchar South Para Jame mosque-Hilalnagar via Narchar GPS road at ch. 00-960m
|
RIDP-CBC
|
chouddagram
|
|
0.96
|
|
|
48.19
|
M/S Tanha Enterprise
|
50.58
|
|
16/07/2015
|
30/10/2016
|
100
|
|
|
|
|
357
|
RIDP(CBC)/C-W35 419314280
|
Improvement of Bor Kasnai-Sreefoltala road via Reazul Jannat Madrasha road at ch. 00-587m
|
RIDP-CBC
|
chouddagram
|
|
0.59
|
|
|
28.54
|
M/S Tanha Enterprise
|
29.97
|
|
16/07/2015
|
30/10/2016
|
100
|
|
|
|
|
358
|
RIDP(CBC)/C-W74 419314244
|
Improvement of Kashinagar-Jogirkandi-Joymangalpur road at ch. 3900-5019m
|
RIDP-CBC
|
chouddagram
|
|
1.12
|
|
|
72.51
|
M/S Abul Hasem
|
76.12
|
|
29/06/2015
|
30/12/2016
|
100
|
|
|
|
|
359
|
RIDP(CBC)/C-W75 419315274
|
Improvement of Lohari-Gandashi road at ch. 00-1015m
|
RIDP-CBC
|
chouddagram
|
|
1.02
|
|
|
46.54
|
M/S Erfan Enterprise
|
48.88
|
|
26/07/2015
|
31/01/2017
|
100
|
|
|
|
|
360
|
RIDP(CBC)/C-W76 419314261
|
Improvement of Anarpur-Kawiyoni-Taltala road at ch. 00-1810m
|
RIDP-CBC
|
chouddagram
|
|
1.62
|
|
|
66.24
|
M/s Janani varietie stor
|
69.53
|
|
14/07/2015
|
31/03/2016
|
100
|
|
|
|
|
361
|
RIDP(CBC)/C-W77 419314209
|
Improvement of Fakirhat (Mazar)-Durgapur-Girls School road at ch. 900-2100m
|
RIDP-CBC
|
chouddagram
|
|
1.20
|
|
|
52.11
|
M/S Mazumder Traders
|
54.71
|
|
16/07/2015
|
30/06/2016
|
100
|
|
|
|
|
362
|
RIDP(CBC)/C-W100 419315168
|
Improvement of Debipur-Sonapur Primary School-Boshkora road at ch. 1000-1780m
|
RIDP-CBC
|
chouddagram
|
|
0.78
|
|
|
39.72
|
M/S Patowari Enterprise
|
41.70
|
|
10/12/2015
|
31/01/2017
|
100
|
|
|
|
|
363
|
RIDP(CBC)/C-W101 419314262
|
Improvement of King Kachnoi-Bagigram road at ch.00-825m
|
RIDP-CBC
|
chouddagram
|
|
0.83
|
|
|
46.11
|
M/S Abul Hasem
|
48.40
|
|
09/12/2015
|
31/05/2017
|
100
|
|
|
|
|
364
|
RIDP(CBC)/C-W102 419314133
|
Improvement of Patadda bazar-Jamukara(Singgapur market) road at ch.1305-1765m
|
RIDP-CBC
|
chouddagram
|
|
0.46
|
|
|
22.03
|
M/S Patawari Enterprise
|
23.13
|
|
10/12/2015
|
31/01/2017
|
100
|
|
|
|
|
365
|
RIDP(CBC)/C-W103 419315196
|
Improvement of Athakara-Taltula MSQ road at ch.00-590m
|
RIDP-CBC
|
chouddagram
|
|
0.59
|
|
|
26.72
|
M/S Patawari Enterprise
|
28.05
|
|
10/12/2015
|
31/01/2017
|
100
|
|
|
|
|
366
|
RIDP(CBC)/C-W104 419314235
|
Improvement of Bijoypur-Shomespur road at ch.00-547m
|
RIDP-CBC
|
chouddagram
|
|
0.55
|
|
|
35.26
|
M/S Rehana construction
|
37.01
|
|
17/12/2015
|
30/12/2016
|
100
|
|
|
|
|
367
|
RIDP(CBC)/C-W111 419315144
|
Improvement of Ashadia Purbapara Julpa Dhokan-Baraipur road at ch.00-600m
|
RIDP-CBC
|
chouddagram
|
|
0.60
|
|
|
30.65
|
M/S Abul hasem
|
32.18
|
|
25/01/2016
|
31/12/2016
|
100
|
|
|
|
|
368
|
RIDP(CBC)/C-W119 419314128
|
Improvement of Dhaka Ctg Highway(Dulbari School)-Sufa Bazar road Ch.00-1250m
|
RIDP-CBC
|
chouddagram
|
|
1.25
|
|
|
59.02
|
M/S Saiful Enterprise
|
61.96
|
|
28/02/2016
|
05/03/2017
|
100
|
|
|
|
|
369
|
RIDP(CBC)/C-W120 419315029
|
Improvement of Meshtola (Mazumder Bari)-Shuvapur GPS Via Laxmipur road Ch.557-1307m
|
RIDP-CBC
|
chouddagram
|
|
0.75
|
|
|
35.28
|
M/S Patowari Enterprise
|
36.78
|
|
28/02/2016
|
28/02/2017
|
100
|
|
|
|
|
370
|
RIDP(CBC)/C-W134 419315101
|
(A) Improvement of Dhaka Ctg Highway- Uttur Betiyara - Kodalia road. Ch.00-1000m
|
RIDP-CBC
|
chouddagram
|
|
1.00
|
|
|
55.42
|
M/S Rehana Construction
|
58.18
|
|
11/04/2016
|
28/06/2017
|
100
|
|
|
|
|
371
|
RIDP(CBC)/C-W156 419314223
|
(A) Improvement of Vitorchar-Dumuria Purbapara-Hossainpur Bridge- Gajaria-Dharmapur road. Ch.1944 -2876m
|
RIDP-CBC
|
chouddagram
|
|
0.93
|
|
|
39.28
|
M/S S.S Corporation
|
41.23
|
|
24/05/2016
|
30/04/2017
|
100
|
|
|
|
|
372
|
RIDP(CBC)/C-W226 419314128
|
Const Of 2x4.50mx5.00m RCC Box Culvert on Dhaka Ctg highway (Dhailbari school)-Sufua bazar road ch.952mm
|
RIDP-CBC
|
chouddagram
|
|
|
|
|
25.29
|
M/S Poly Enterprise
|
26.55
|
|
14/05/2017
|
10/03/2018
|
100
|
|
|
|
|
373
|
RIDP(CBC)/C-SW47 419315094
|
Improvement Of Munshirhat high School-Mestala village ( Girls high school North) road ch.00-366m
|
RIDP-CBC
|
chouddagram
|
|
0.37
|
|
|
32.86
|
M/S ABC Construction
|
34.50
|
|
14/11/2017
|
20/05/2018
|
100
|
|
|
|
|
374
|
RIDP(CBC)/C-BW25 419314280
|
Construction of 48.06 Long RCC Girder Bridge on Boro Kachnai-Sreefoltala road via Reazul jannat Madrasha road at ch.750m
|
RIDP-CBC
|
chouddagram
|
|
|
|
|
273.09
|
M/S Poly Enterprise & Mazumder Traders (JV)
|
286.69
|
|
17/01/2018
|
23/01/2019
|
65
|
|
|
|
|
375
|
RIDP(CBC)/C-BW26 419315142
|
Construction of 36.06 Long RCC Girder Bridge on Vatora (Sreepur UP) village road at ch.550m
|
RIDP-CBC
|
chouddagram
|
|
|
|
|
182.04
|
M/S Mazumder Traders
|
190.88
|
|
11/03/2018
|
17/03/2019
|
65
|
|
|
|
|
376
|
RIDP(CBC)/C-W11 419313013
|
Improvement of Miabazar-Uzirpur UP Office-Shiberbazar-Chalklaxipur road at Ch. 4154-5170m
|
RIDP-CBC
|
chouddagram
|
|
1.02
|
|
|
55.23
|
M/S Hazi Enterprise
|
55.23
|
|
20/04/2015
|
31/05/2016
|
100
|
|
|
|
|
377
|
RIDP(CBC)/C-SW23 419314283
|
Improvement Of Khironshal High School-Shampur Bridge road Ch.00-1355m
|
RIDP-CBC
|
chouddagram
|
|
1.36
|
|
|
63.94
|
M/S Fatema Traders
|
67.12
|
|
21/07/2016
|
30/05/2018
|
100
|
|
|
|
|
378
|
RIDP(CBC)/C-W183 419315224
|
Improvement of Amangonda (Takia Amgash Koborastan) East Side Babuchi Village road at ch.2300-2940m
|
RIDP-CBC
|
chouddagram
|
|
0.64
|
|
|
31.97
|
M/S Poly Enterprise
|
33.57
|
|
05/10/2016
|
11/06/2017
|
100
|
|
|
|
|
379
|
RIDP(CBC)/C-M86 419673008
|
Periodic Maintenance (Rehabilition) Of Chowara - Bibir Bazar Via Bora Pukurpar (Sadar Part) road at Ch 2492- 5122m
|
RIDP-CBC
|
cumilla-s
|
|
2.63
|
|
|
46.42
|
M/S Hamim & Brothers
|
48.73
|
|
25/12/2016
|
04/12/2016
|
100
|
|
|
|
|
380
|
RIDP(CBC)/C-M130 419674011
|
Periodic Maintenance (Re-seal) of Ariora-Chittagong road at ch. 00-1800m.
|
RIDP-CBC
|
cumilla-s
|
|
1.80
|
|
|
24.90
|
M/S Nazmul Huda
|
26.14
|
|
02/03/2018
|
05/12/2017
|
100
|
|
|
|
|
381
|
RIDP(CBC)/C-W241 419673011
|
Improvement Of Chapapur RHD Dauderkhora-Nashrail Kotok Bazar (Kakaon road) road ch.2436-4157m
|
RIDP-CBC
|
cumilla-s
|
|
1.72
|
|
|
104.25
|
M/S Bhuiyan Enterprise
|
109.45
|
|
03/08/2017
|
09/08/2018
|
100
|
|
|
|
|
382
|
RIDP(CBC)/C-W62 419674034
|
Improvement of Kachiyatoli Bhuiyan bari-Banasua Bridge via Alekharchar, Durgapur road at ch. 00-1130m.
|
RIDP-CBC
|
cumilla-s
|
|
1.13
|
|
|
61.11
|
M/S Hamim & Brothers
|
64.15
|
|
08/06/2015
|
03/12/2015
|
100
|
|
|
|
|
383
|
RIDP(CBC)/C-W63 419674015
|
Improvement of Kamolapur-Krisnopur via Beltali road at ch. 00-1100m.
|
RIDP-CBC
|
cumilla-s
|
|
1.10
|
|
|
53.15
|
M/S Alamgir Hossain
|
55.80
|
|
10/06/2015
|
03/01/2016
|
100
|
|
|
|
|
384
|
RIDP(CBC)/C-W64 419675099
|
Improvement of Banasua bazar-Nez Banasua Griveyard road at ch. 00-580m.
|
RIDP-CBC
|
cumilla-s
|
|
0.58
|
|
|
25.04
|
M/S Hamim & Brothers
|
26.28
|
|
08/06/2015
|
27/12/2015
|
100
|
|
|
|
|
385
|
RIDP(CBC)/C-W65 419675194
|
Improvement of Tailkope Bhuvanghar-Barashar bazar pacca road to Katanesha road at ch. 00-532m.
|
RIDP-CBC
|
cumilla-s
|
|
0.53
|
|
|
24.90
|
M/S Taslima Enterprise
|
26.14
|
|
18/06/2015
|
23/02/2016
|
100
|
|
|
|
|
386
|
RIDP(CBC)/C-W66 419674017
|
Improvement of Munshirhat to Panddanagar road at ch. 440-1840m.
|
RIDP-CBC
|
cumilla-s
|
|
1.40
|
|
|
62.71
|
M/S. Masnun Enterprise
|
65.84
|
|
04/06/2015
|
10/11/2015
|
100
|
|
|
|
|
387
|
RIDP(CBC)/C-W108 419674042
|
(A) Improvement of Ratnabati(Erra) Prymary school to Banashoa bazar via H/Q Abdul Gaffar road ch. 00-500m. (B) Const. Of 1x1.00x1.00m Drain Culvert on same road at ch. 720m.
|
RIDP-CBC
|
cumilla-s
|
|
0.50
|
|
|
26.41
|
M/S Hamim & Brothers
|
27.72
|
|
29/02/2016
|
30/12/2016
|
100
|
|
|
|
|
388
|
RIDP(CBC)/C-W242 419675196
|
Improvement Of Karaninagor Bora Pukurper-Gomti Embankment road via Golabari Bhuiya Bari road ch.00-1265m
|
RIDP-CBC
|
cumilla-s
|
|
1.27
|
|
|
77.94
|
M/S Saiful Alam Rony
|
81.81
|
|
18/06/2017
|
05/09/2018
|
100
|
|
|
|
|
389
|
RIDP(CBC)/C-W290 419675086
419675088
|
Improvement Of (A) Taltala Chowmohani Rammohan road via Kamalapur Road ch.00-850m
(B) Taltala Chowmohani Rammohan road via Dhanuakhola Road ch.233-733m
|
RIDP-CBC
|
cumilla-s
|
|
1.35
|
|
|
94.01
|
M/S M.I Construction
|
98.70
|
|
13/05/2018
|
19/01/2019
|
70
|
|
|
|
|
390
|
RIDP(CBC)/C-W162 419674012
|
Improvement Of Amratoli- Shiber bazar road Ch.00-1520m
|
RIDP-CBC
|
cumilla-s
|
|
1.52
|
|
|
93.89
|
M/S Hamim & Brothers
|
98.52
|
|
26/05/2016
|
04/06/2017
|
100
|
|
|
|
|
391
|
RIDP(CBC)/C-W163 419674049
|
Improvement Of Pachim Majigasha-Joshpur road Ch.00-1890m
|
RIDP-CBC
|
cumilla-s
|
|
1.89
|
|
|
97.45
|
M/S Hamim & Brothers
|
102.69
|
|
26/05/2016
|
30/04/2018
|
60
|
|
|
|
|
392
|
RIDP(CBC)/C-W128 419912006
|
Improvement of Bagmara - Changahata-Pickpara road Ch.4352-4892m
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.54
|
|
|
38.05
|
M/S Farhana Builders
|
39.90
|
|
14/03/2016
|
30/12/2016
|
100
|
|
|
|
|
393
|
RIDP(CBC)/C-W47 419813034
|
Improvement of Soto Hargila-Char baria-Batara-Belghar road at ch. 2000-3000m & 3200-3900m
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.70
|
|
|
95.68
|
M/S. Zaman Traders
|
100.46
|
|
22/07/2015
|
28/11/2015
|
100
|
|
|
|
|
394
|
RIDP(CBC)/C-W48 419813031
|
Improvement of Alishwer-Atiti-Premnol road at ch. 2350-2650m & 2850-3300m
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.75
|
|
|
36.55
|
M/S. Pacific Inter.
|
37.65
|
|
04/06/2015
|
31/03/2016
|
100
|
|
|
|
|
395
|
RIDP(CBC)/C-W249 419913017
|
Improvement Of Chowara bazar-chashapara-Baishkhula-Joshpur road ch.2540-3388m
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.85
|
|
|
53.62
|
Md.Delowar hossain Babul
|
55.76
|
|
31/07/2017
|
06/08/2018
|
100
|
|
|
|
|
396
|
RIDP(CBC)/C-W49 419915049
|
Improvement of Sakera high school & Primary school to Kanoksree road Dr. Bodiul Alam bari road at ch. 00-910m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.91
|
|
|
45.82
|
M/S Abul Hasem
|
47.17
|
|
07/06/2015
|
30/08/2016
|
100
|
|
|
|
|
397
|
RIDP(CBC)/C-W50 419914006
|
Improvement of Dotiapur-Daulatpur road at ch. 00-228m & 3880-4225m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.57
|
|
|
25.95
|
M/S. Abul Kasham Bricks
|
24.36
|
|
01/06/2015
|
31/01/2016
|
100
|
|
|
|
|
398
|
RIDP(CBC)/C-W51 419915064
|
Improvement of Comilla-Laksham road to Bagmara-Bagadda road via Askamta road at ch. 1000-1600m & 1600-3100m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
2.04
|
|
|
98.08
|
M/S. Abul Kasham Bricks
|
92.10
|
|
01/06/2015
|
02/11/2015
|
100
|
|
|
|
|
399
|
RIDP(CBC)/C-W52 419914026
|
Improvement of Sindua Shispur-Chikutia-Gazaria road at ch. 1120-1910m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.79
|
|
|
37.48
|
M/S Abul Hasem
|
39.35
|
|
07/06/2015
|
30/12/2016
|
100
|
|
|
|
|
400
|
RIDP(CBC)/C-W53 419915105
|
Improvement of Chandgaon-Parul road at ch. 00-1060m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.06
|
|
|
52.17
|
M/S Hamim & Brothers
|
54.76
|
|
07/06/2015
|
30/10/2016
|
100
|
|
|
|
|
401
|
RIDP(CBC)/C-W129.a 419914010,
419915039
|
(A) Improvement of Jamua- Chotachalunda (AS+BC) road Ch.1000-1580m
(B) Atity- Shasonpar-Singoria road. Ch.1000-1600m
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.58
|
|
|
44.59
|
M/S Farhana Builders
|
46.80
|
|
14/03/2016
|
20/11/2016
|
100
|
|
|
|
|
402
|
RIDP(CBC)/C-W229 419914004
|
Improvement Of Barodarmapur-Lalmai road ch.1450-1922m
|
RIDP-CBC
|
cumilla-s daksin
|
|
0.48
|
|
|
22.75
|
M/S Montaha Construction
|
22.74
|
|
09/04/2017
|
26/11/2017
|
100
|
|
|
|
|
403
|
RIDP(CBC)/C-W289 419915047
419915110
|
Improvement Of (A) Dhaka CTg road-Sen bari road via Krishnapur road ch.00-1000m
(B) Horichar-Jagotpur road ch.00-690m
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.69
|
|
|
117.39
|
M/S Abul Kashem Bricks
|
123.32
|
|
05/04/2018
|
11/04/2019
|
60
|
|
|
|
|
404
|
RIDP(CBC)/C-W306 419915182
419914084
|
Improvement Of (A) Bagmara-Shodagar house to Topsil Office Road ch.00-670m
(B)Bijoypur Petrol Pump to Harespur road (ch.00-785m
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.46
|
|
|
114.24
|
M/S Shikder Construction
|
113.95
|
|
11/04/2018
|
17/04/2019
|
55
|
|
|
|
|
405
|
RIDP(CBC)/C-M12 419913006
|
Maintenance of Suagonj-Talpotti-Berahimpur-Komalpur road at ch. 1000-3200m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
2.20
|
|
|
39.65
|
M/S Raka Enterprise
|
41.55
|
|
14/11/2015
|
14/10/2015
|
100
|
|
|
|
|
406
|
RIDP(CBC)/C-M77 419913001
|
Maintenance of Misree Jame Mosque -Poroty- Via Palpara road at ch. 11720-13120m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.40
|
|
|
35.02
|
M/S Farhana Builders
|
36.76
|
|
20/11/2016
|
10/04/2016
|
100
|
|
|
|
|
407
|
RIDP(CBC)/C-M13 419913012
|
Maintenance of Siber bazar-Beltali road at ch. 875-2225m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.35
|
|
|
32.10
|
M/S Saboz & Brothers
|
30.60
|
|
02/07/2015
|
04/04/2015
|
100
|
|
|
|
|
408
|
RIDP(CBC)/C-M92 419913028
|
Periodic Maintenance (Rehabilition) Of Parul-Gazaria-Fazilpur-Singguria Shakra Bazar road at Ch 1600- 6880m
|
RIDP-CBC
|
cumilla-s daksin
|
|
5.28
|
|
|
97.99
|
M/S Arshad & Sons
|
97.49
|
|
14/02/2017
|
12/02/2017
|
100
|
|
|
|
|
409
|
RIDP(CBC)/C-M107 419913037
|
Periodic Maintenance of (Rehabilition) Bholin UP (Bucchi) Poroti Bazar-Jamuen-Modina Bazar road ch.4845-6345m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.50
|
|
|
33.64
|
M/S Pacific International
|
33.59
|
|
11/09/2017
|
30/06/2017
|
100
|
|
|
|
|
410
|
RIDP(CBC)/C-M9 419914104
|
Maintenance of Bamisa-Olir bazar road at ch. 00-2125m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
2.13
|
|
|
67.74
|
M/S Farhana Builders
|
71.11
|
|
24/05/2015
|
30/03/2015
|
100
|
|
|
|
|
411
|
RIDP(CBC)/C-M10 419915001
|
Maintenance of Lolbaria-Paranpur-Daulatpur road at ch. 00-1800m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.80
|
|
|
38.95
|
M/S Saboj & Brothers
|
40.51
|
|
26/07/2015
|
10/05/2015
|
100
|
|
|
|
|
412
|
RIDP(CBC)/C-M79 419914036
|
Maintenance of Hodgara - Bararulla road at ch. 1200-2423m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.22
|
|
|
21.23
|
M/S Saboj & Brothers
|
21.66
|
|
20/01/2017
|
20/01/2017
|
100
|
|
|
|
|
413
|
RIDP(CBC)/C-M80 419914027
|
Maintenance of Botogram Mojlispur -Joymongolpur road at ch. 1000-2100m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.10
|
|
|
29.08
|
M/S Razu Enterprise
|
28.62
|
|
19/10/2016
|
04/09/2016
|
100
|
|
|
|
|
414
|
RIDP(CBC)/C-M11 419914112
|
Maintenance of Suagonj-Rasulpur-Bhubanpur-Baishkhola-Alampur road at ch. 1000-3000m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
2.00
|
|
|
37.13
|
M/S. Abdur Razzak
|
35.72
|
|
29/06/2015
|
02/07/2015
|
100
|
|
|
|
|
415
|
RIDP(CBC)/C-M76 419914048
|
Maintenance of Goarbanga-Mitalla-Joktikhola road at ch. 00-2332m.
|
RIDP-CBC
|
cumilla-s daksin
|
|
2.33
|
|
|
52.02
|
M/S Muntaha Construction
|
51.69
|
|
28/10/2016
|
27/06/2016
|
100
|
|
|
|
|
416
|
RIDP(CBC)/C-M106 419914051
|
Periodic Maintenance (Rehabilition) of Doulatpur-Raypur Road at Ch. 00-14851m .
|
RIDP-CBC
|
cumilla-s daksin
|
|
1.49
|
|
|
40.16
|
M/S Farhana Builders
|
42.15
|
|
02/01/2018
|
20/08/2017
|
100
|
|
|
|
|
417
|
RIDP(CBC)/C-W14 419362008
|
Improvement of Goalmari GC-Kalibazar GC via Mollahkandi road at Ch 1580-3860m
|
RIDP-CBC
|
daudkandi
|
|
2.28
|
|
|
147.63
|
M/S Nero & Brothers
|
155.00
|
|
08/03/2016
|
30/07/2018
|
100
|
|
|
|
|
418
|
RIDP(CBC)/C-BW3 419362008
|
Construction of 14.00m Long RCC Girder Bridge On Goalmari GC-Kalirbazar GC via Mollahkandi road Ch. 900m
|
RIDP-CBC
|
daudkandi
|
|
|
|
|
92.13
|
M/S Azmin Construction
|
92.04
|
|
26/02/2017
|
30/06/2018
|
75
|
|
|
|
|
419
|
RIDP(CBC)/C-BW32 419362008
|
Construction of 18.00m Long RCC Girder Bridge On Goalmari GC-Kalirbazar GC via Mollahkandi road Ch. 3000m
|
RIDP-CBC
|
daudkandi
|
|
|
|
|
112.15
|
Md.Delowar hossain Babul
|
111.99
|
|
21/01/2018
|
27/01/2019
|
30
|
|
|
|
|
420
|
RIDP(CBC)/C-W307 419362008
|
Improvement of Goalmari GC-Kalibazar GC via Mollahkandi road at Ch 865-1580m
|
RIDP-CBC
|
daudkandi
|
|
0.72
|
|
|
50.37
|
M/S Mahin Enterprise
|
50.34
|
|
09/05/2018
|
15/01/2019
|
50
|
|
|
|
|
421
|
RIDP(CBC)/C-W13 419363005
|
Re-Construction of 3x3.7mx3.7m Triple vent RCC box Culvert on Dakshin (Elliotgonj GC)-Mohamadpur Natunbazar via Kalasona Bazar road at Ch 7661m
|
RIDP-CBC
|
daudkandi
|
|
|
|
|
25.32
|
M/S Golam Rabbani
|
25.22
|
|
29/06/2015
|
30/12/2016
|
100
|
|
|
|
|
422
|
RIDP(CBC)/C-W170 419363016
|
Improvement of Baynagar Bazar-Talersew Bazar Via Mohammadpur Purba Up Office road at ch.3675-4075m
|
RIDP-CBC
|
daudkandi
|
|
0.40
|
|
|
30.82
|
M/S Mizan Traders
|
29.25
|
|
09/01/2017
|
15/09/2017
|
100
|
|
|
|
|
423
|
RIDP(CBC)/C-W171 419363004
|
Improvement of Dhitpur Mowrabari-Baynagar Bazar (Jinglatoli UP Office Dhitpur NHW-Baynagar) road at ch.3190-4190m
|
RIDP-CBC
|
daudkandi
|
|
1.00
|
|
|
61.97
|
M/S Bhuiyan Traders
|
64.14
|
|
11/07/2016
|
28/02/2018
|
100
|
|
|
|
|
424
|
RIDP(CBC)/C-W168 419363014
|
Improvement of Pachgasia Bazar-Naiyer Bazar Via Maruka UP office road at ch.1850-2850m
|
RIDP-CBC
|
daudkandi
|
|
1.00
|
|
|
58.95
|
M/S Mahin Enterprise
|
61.87
|
|
25/09/2016
|
30/12/2018
|
100
|
|
|
|
|
425
|
RIDP(CBC)/C-W130 419363021
|
Improvement of Daudkandi Tolplaza- Daudkandi uttur UP office via Chengakandi golaperchar road Ch.900-2850m
|
RIDP-CBC
|
daudkandi
|
|
1.95
|
|
|
134.03
|
M/S Mahin Enterprise
|
133.53
|
|
13/03/2016
|
30/09/2018
|
85
|
|
|
|
|
426
|
RIDP(CBC)/C-W131 419363027
|
Improvement of Gouripur Bazar-Lalpur Bazar road Ch.00-1000m
|
RIDP-CBC
|
daudkandi
|
|
1.00
|
|
|
65.68
|
M/S Eshan Enterprise
|
65.40
|
|
09/05/2016
|
30/11/2018
|
80
|
|
|
|
|
427
|
RIDP(CBC)/C-W188 419363003
|
Improvement of Daulatpur UP Office (Paler Bazar )-Srirayarchar Bazar road at ch.2400-3400m
|
RIDP-CBC
|
daudkandi
|
|
1.00
|
|
|
70.30
|
M/S M.H Enterprise
|
73.80
|
|
27/10/2016
|
30/05/2018
|
40
|
|
|
|
|
428
|
RIDP(CBC)/C-W288 419363017
|
Improvement Of Chakratala baza-Naiyar bazar via Maruka UP office road ch.2790-3270m
|
RIDP-CBC
|
daudkandi
|
|
0.48
|
|
|
31.66
|
M/S Molla Enterprise
|
30.02
|
|
08/03/2018
|
13/11/2018
|
65
|
|
|
|
|
429
|
RIDP(CBC)/C-W60 419364033
|
Improvement of Goripur UP Office-Goliyarchar via Laxmipur road at ch. 1750-2550m.
|
RIDP-CBC
|
daudkandi
|
|
0.80
|
|
|
41.90
|
M/S Liverty Traders
|
38.13
|
|
20/09/2015
|
30/11/2016
|
100
|
|
|
|
|
430
|
RIDP(CBC)/C-W61 419364007
|
Improvement of Jinglatoli UP Office-Atipara(Jinglatoli UP Office-Kollanpur-Mohananda) road at ch. 00-500m.
|
RIDP-CBC
|
daudkandi
|
|
0.50
|
|
|
35.03
|
M/S Liverty Traders
|
35.02
|
|
23/06/2015
|
30/06/2017
|
100
|
|
|
|
|
431
|
RIDP(CBC)/C-W98 419365060
|
Improvement of Utter Baynagar-Shafiq Contractor bari road at ch. 00-500m.
|
RIDP-CBC
|
daudkandi
|
|
0.50
|
|
|
25.80
|
M/S Bhuiyan Traders
|
25.80
|
|
20/10/2015
|
30/12/2016
|
100
|
|
|
|
|
432
|
RIDP(CBC)/C-W124 419364016
|
Improvement of Kushiara Bazar -Kashipur road Ch.00-490m
|
RIDP-CBC
|
daudkandi
|
|
0.49
|
|
|
30.04
|
M/S Liverty Traders
|
31.50
|
|
17/05/2016
|
30/12/2017
|
100
|
|
|
|
|
433
|
RIDP(CBC)/C-W169 419364015
|
Improvement of Raipur Bazar-Hatkhola Bazar road at ch.2423- 3544m
|
RIDP-CBC
|
daudkandi
|
|
1.12
|
|
|
75.47
|
M/S Bhuiyan Traders
|
79.17
|
|
20/07/2016
|
28/02/2018
|
100
|
|
|
|
|
434
|
RIDP(CBC)/C-W99 419364018
|
Improvement of Dakhn Nagar Jamal mia bari-Udkhola madrasha (Nobagram-Udkhola) road at ch. 300-1100m.
|
RIDP-CBC
|
daudkandi
|
|
0.80
|
|
|
40.63
|
M/S Faruk Enterprise
|
40.62
|
|
02/11/2015
|
30/12/2017
|
60
|
|
|
|
|
435
|
RIDP(CBC)/C-SW22 419365113
|
Improvement Of (A) Dhaka-Chitagong (NHW)Gowripur Bazar Conecting road Ch.100-1275m (B) Protection Work 500.00m
|
RIDP-CBC
|
daudkandi
|
|
1.18
|
|
|
142.33
|
M/S Liverty Traders
|
134.50
|
|
02/11/2017
|
08/11/2018
|
85
|
|
|
|
|
436
|
RIDP(CBC)/C-BW6 419364040
|
Construction of 35.00m Long RCC Girder Bridge on Dhaka Chittagonj NHW to Hasanpur Doulatpur road ch.1750m
|
RIDP-CBC
|
daudkandi
|
|
|
|
|
156.74
|
M/S Ha-mim & Brothers
|
141.07
|
|
02/08/2017
|
03/12/2018
|
40
|
|
|
|
|
437
|
RIDP(CBC)/C-BW7 419364074
|
Construction of 30.00m Long RCC Girder Bridge on Daudkandi Bazar to Tujarbhanga-Baragaon-Krishnopur road ch.2500m
|
RIDP-CBC
|
daudkandi
|
|
|
|
|
148.55
|
M/S Ha-mim & Brothers
|
148.52
|
|
20/08/2017
|
03/12/2018
|
40
|
|
|
|
|
438
|
RIDP(CBC)/C-W312 419365044
419364009
|
(A) Improvement Of Mohammadpur-Hariala Road ch.00-458m
(B) Chadgaong Bazar-Mohammadpur Road Ch.1500-2096m
|
RIDP-CBC
|
daudkandi
|
|
1.05
|
|
|
77.41
|
M/S Nashashi Engineering & Construction
|
77.11
|
|
13/05/2018
|
19/11/2018
|
20
|
|
|
|
|
439
|
RIDP(CBC)/C-M104 419362002
|
Periodic Maintenance (Overlay) of Barokota GC-Joy Bangla Bazar RHD road at ch. 00-1300m.
|
RIDP-CBC
|
daudkandi
|
|
1.30
|
|
|
28.45
|
M/S M.H Enterprise
|
27.93
|
|
28/02/2018
|
20/01/2018
|
100
|
|
|
|
|
440
|
RIDP(CBC)/C-M151 419362006
|
Periodic Maintenance (Re-seal) of Daulatpur NHW Barkota GC road at ch. 00-1240m. Including emergency maintenance (Ch.1240-6250m)
|
RIDP-CBC
|
daudkandi
|
|
1.24
|
|
|
55.52
|
M/S Liverty Traders
|
57.14
|
|
17/08/2018
|
|
50
|
|
|
|
|
441
|
RIDP(CBC)/C-M103 419363022
|
Periodic Maintenance of (Re-Seal) Biteshar UP Office (Tinpara) Shibpur Road via Darigoali road at ch. 750-1750m.
|
RIDP-CBC
|
daudkandi
|
|
1.00
|
|
|
15.96
|
M/S M.H Enterprise
|
15.69
|
|
30/04/2018
|
25/04/2018
|
100
|
|
|
|
|
442
|
RIDP(CBC)/C-M152 419363004
|
Periodic Maintenance (Widening & Rehabilition) of Jhinglatoli Up office (Dhitpur NHW)-Baynagar Bazar road ch. 00-1286m.
|
RIDP-CBC
|
daudkandi
|
|
1.29
|
|
|
58.01
|
M/S Liverty Traders
|
60.10
|
|
17/08/2018
|
|
25
|
|
|
|
|
443
|
RIDP(CBC)/C-M81 419365021
419364009
|
Maintenance of (A) Chadgaon Bazar- Mohammadpur road at ch. 00-1500m.
(B) Baynagar Madrasha-Baynagar road Ch.00-200m
|
RIDP-CBC
|
daudkandi
|
|
1.70
|
|
|
37.62
|
M/S Nasashi Engineering
|
33.10
|
|
30/04/2017
|
30/04/2017
|
100
|
|
|
|
|
444
|
RIDP(CBC)/C-M66 419402002
|
Maintenance of Charbakar-Nabiabad Via Mohonpur GC road at ch. 00-4100m.
|
RIDP-CBC
|
debidwar
|
|
4.10
|
|
|
60.66
|
M/S Nero & Brothers
|
50.00
|
|
28/02/2017
|
26/02/2017
|
100
|
|
|
|
|
445
|
RIDP(CBC)/C-SM4 419402005
|
Maintenance of (Rehabilitation) of Pirgonj gc-Estagram RHD road at ch. 1500-3453m.
|
RIDP-CBC
|
debidwar
|
|
1.95
|
|
|
42.11
|
M/S E.F Trade International
|
41.11
|
|
20/08/2017
|
16/08/2017
|
100
|
|
|
|
|
446
|
RIDP(CBC)/C-M159 419402009
|
Periodic Maintenance (Widening & Rehabilition) of Jafargonj GC-Panchpukoria GC via Rajamehar road at ch. 3318-5410m.
|
RIDP-CBC
|
debidwar
|
|
2.09
|
|
|
97.48
|
M/S E.F Trade International
|
96.26
|
|
24/11/2018
|
|
100
|
|
|
|
|
447
|
RIDP(CBC)/C-M114 419403009
|
Periodic Maintenance of (Rehabilition & Widening) Mashikara Bazar-Madhomura road ch. 00-2025m.
|
RIDP-CBC
|
debidwar
|
|
2.03
|
|
|
75.12
|
M/S Saikat Construction
|
65.94
|
|
06/03/2017
|
30/10/2017
|
100
|
|
|
|
|
448
|
RIDP(CBC)/C-M158 419403001
|
Periodic Maintenance (Rehabilition & Widening) of C&B Bazar-Rasulpur UPC road ch. 00-2470m.
|
RIDP-CBC
|
debidwar
|
|
2.47
|
|
|
106.22
|
M/S E.F Trade International
|
104.90
|
|
29/11/2018
|
|
60
|
|
|
|
|
449
|
RIDP(CBC)/C-M161 419403021
|
Periodic Maintenance (Widening & Rehabilitation) of Kangshanagar GC-Alahabad UPC ( Simarkanda) road at ch. 4058-5074m.
|
RIDP-CBC
|
debidwar
|
|
1.02
|
|
|
36.08
|
M/S E.F Trade International
|
34.27
|
|
30/10/2018
|
|
60
|
|
|
|
|
450
|
RIDP(CBC)/C-W125 419402010
|
Improvement of Kongshanagar GC-Dhamti Hat GC road Ch. 5700-6700m
|
RIDP-CBC
|
debidwar
|
|
1.00
|
|
|
79.63
|
M/S Santa Enterprise
|
66.37
|
|
28/02/2016
|
05/03/2017
|
100
|
|
|
|
|
451
|
RIDP(CBC)/C-SBW29 419402005
|
Construction of 17.00m Long RCC Girder Bridge On Pirgonj GC-Estagram RHD road Ch. 1458m
|
RIDP-CBC
|
debidwar
|
|
|
|
|
108.47
|
M/S Mam Construction
|
87.10
|
|
09/10/2016
|
30/11/2018
|
90
|
|
|
|
|
452
|
RIDP(CBC)/C-W316 419402010
|
Improvement of Kongshanagar GC-Dhamti hat GC road (Debidwar Protion) at Ch 6700-7680m
|
RIDP-CBC
|
debidwar
|
|
0.98
|
|
|
79.10
|
E.F Trade International
|
78.11
|
|
25/04/2018
|
02/01/2019
|
70
|
|
|
|
|
453
|
RIDP(CBC)/C-W126 419403005
|
Improvement of Saharpar National Highway-Saitola road at ch.4320-5566m
|
RIDP-CBC
|
debidwar
|
|
1.24
|
|
|
85.22
|
M/S S.F International
|
74.18
|
|
16/02/2016
|
30/06/2017
|
100
|
|
|
|
|
454
|
RIDP(CBC)/C-W127 419403010
419403024
|
Improvement of (a) Dhamti Dhankhar-Cholash bazar road at ch.1087-1587m(B) Mohanpur Bazar-Tulagaon Bazar road Ch.691-1191m
|
RIDP-CBC
|
debidwar
|
|
1.00
|
|
|
58.49
|
M/S Mobin Traders
|
49.09
|
|
02/03/2016
|
08/03/2017
|
100
|
|
|
|
|
455
|
RIDP(CBC)/C-W165 419403017
|
Improvement of Masuabad Ferigat-Wahedpur Bazar road at ch.1210-1710m
|
RIDP-CBC
|
debidwar
|
|
0.50
|
|
|
27.71
|
M/S Saikat Construction
|
25.20
|
|
21/06/2016
|
27/02/2017
|
100
|
|
|
|
|
456
|
RIDP(CBC)/C-W223 419403008
|
Improvement Of Hossainpur R&H-Bakshar Bazar road ch.1225-2000m
|
RIDP-CBC
|
debidwar
|
|
0.78
|
|
|
50.42
|
M/S Sumi Enterprise
|
44.40
|
|
28/02/2017
|
06/03/2018
|
100
|
|
|
|
|
457
|
RIDP(CBC)/C-W224 419403003
|
Improvement Of Barkamta UPC (National H/W-Fagunda Bazar road ch.2000-2800m
|
RIDP-CBC
|
debidwar
|
|
0.80
|
|
|
48.24
|
M/S Faiza Construction
|
42.38
|
|
28/02/2017
|
30/06/2018
|
100
|
|
|
|
|
458
|
RIDP(CBC)/C-W222.a 419403013
419403009
|
Improvement Of (A) Debidwar R&H-Mashikara Bazar road ch.200-700m
(B) Mashikaea-Modomura road Ch.6450-7100m
|
RIDP-CBC
|
debidwar
|
|
1.15
|
|
|
75.02
|
M/S Eshan Enterprise
|
65.57
|
|
28/02/2017
|
30/06/2018
|
100
|
|
|
|
|
459
|
RIDP(CBC)/C-W133.a
419404079,
419404038
|
(A) Improvement of Rampur Madrasha - Dhami road Ch.744-1250m
(B) Mashikora Bazar-Pirozpur road. Ch.900-1400m
|
RIDP-CBC
|
debidwar
|
|
1.01
|
|
|
47.96
|
M/S Norjahan Enterprise
|
45.57
|
|
28/03/2016
|
02/07/2017
|
100
|
|
|
|
|
460
|
RIDP(CBC)/C-W149. 419404075,
419404087
|
(A) Improvement of Debidwar R&H - Mashikkara Bazar Via Arif bari road Ch.1000-1400m (B) Gomti Bridge-Shihnagar road. Ch.00-400m
|
RIDP-CBC
|
debidwar
|
|
1.80
|
|
|
39.41
|
M/S Norjahan Enterprise
|
34.41
|
|
13/06/2016
|
19/07/2017
|
100
|
|
|
|
|
461
|
RIDP(CBC)/C-SW36 419405020
|
Improvement Of Ujanijura-Kasarikhola Circular road ch.260-1833m
|
RIDP-CBC
|
debidwar
|
|
1.57
|
|
|
65.85
|
M/S Sumi Enterprise
|
64.10
|
|
07/08/2017
|
13/08/2018
|
100
|
|
|
|
|
462
|
RIDP(CBC)/C-SW37 419405110
|
Improvement Of Ujanijura-Hafurkhara via Baladmara road ch.414-1546m
|
RIDP-CBC
|
debidwar
|
|
1.13
|
|
|
47.48
|
M/S Sumi Enterprise
|
46.17
|
|
07/08/2017
|
13/04/2018
|
100
|
|
|
|
|
463
|
RIDP(CBC)/C-W295 419404002
419404019
|
Improvement Of (A) Chulassh bazar-Choumohoni bazar Road ch.00-400m
(B) Gopalnaghar-Nobipur via Gopalnaghar Pry.School road (ch.1400-2000m
|
RIDP-CBC
|
debidwar
|
|
1.00
|
|
|
65.73
|
M/S Saikot Construction
|
65.65
|
|
25/02/2018
|
03/11/2018
|
65
|
|
|
|
|
464
|
RIDP(CBC)/C-W296 419404004
419404011
|
Improvement Of (A) Barur-Kurakhal Road ch.00-400m
(B) Debidwar-dalahash road (ch.1230-2105m
|
RIDP-CBC
|
debidwar
|
|
1.28
|
|
|
78.34
|
M/S R.S Construction
|
66.54
|
|
07/03/2018
|
13/11/2018
|
60
|
|
|
|
|
465
|
RIDP(CBC)/C-W297 419404023
419404054
|
Improvement Of (A) Agaraghram Pry.School-B.para Road ch.600-1100m
(B) Barakamta-Mongata via Premu road (ch.2400-2964m
|
RIDP-CBC
|
debidwar
|
|
1.06
|
|
|
66.55
|
M/S Saikot Construction
|
66.54
|
|
25/02/2018
|
03/11/2018
|
60
|
|
|
|
|
466
|
RIDP(CBC)/C-W298 419404068
419404054
|
Improvement Of (A) Bagmara Islamia Madrasha-Brahmonkhara Road ch.00-400m
(B) Saichapara bazar-Gopalnagar road (ch.00-400m
|
RIDP-CBC
|
debidwar
|
|
0.80
|
|
|
50.98
|
M/S Sumi Enterprise
|
50.74
|
|
14/02/2018
|
20/10/2018
|
45
|
|
|
|
|
467
|
RIDP(CBC)/C-W315 419404025
|
Improvement Of Nurpur-Fatehabad Road ch.00-2197m
|
RIDP-CBC
|
debidwar
|
|
2.20
|
|
|
157.92
|
M/S Saikot Construction
|
165.55
|
|
14/05/2018
|
20/05/2019
|
60
|
|
|
|
|
468
|
RIDP(CBC)/C-W330 419405019
|
Improvement Of Bhaisherkot LGED Godown-Hazi Ali Akbar house Masjeed (Bhaisherkot Utturpara Jame mosjeed) road ch.00-480m
|
RIDP-CBC
|
debidwar
|
|
0.48
|
|
|
63.61
|
M/S Sumi Enterprise
|
66.63
|
|
24/09/2018
|
01/10/2019
|
30
|
|
|
|
|
469
|
RIDP(CBC)/C-W83 419404032
|
(a) Improvement of Taltala R&H-Khiraikandi road via Radanagar Primary School at ch. 00-400m (b) Const. Of 2x4.00x4.00m RCC Box culvert at ch. 2488m on Same road
|
RIDP-CBC
|
debidwar
|
|
0.40
|
|
|
34.25
|
M/S. Mobin Traders
|
26.45
|
|
22/07/2015
|
31/05/2016
|
100
|
|
|
|
|
470
|
RIDP(CBC)/C-W89 419405011
|
(a) Improvement of Hapurkhara to Panti road at ch. 2600-3200m (b) Const. Of 4.50x4.00m RCC Box culvert at ch. 3400m on Same road
|
RIDP-CBC
|
debidwar
|
|
0.60
|
|
|
41.68
|
M/S. S F International
|
34.18
|
|
21/09/2015
|
30/09/2016
|
100
|
|
|
|
|
471
|
RIDP(CBC)/C-W95 419404047
|
Improvement of Dhamta Bhuiyan market to Kurakhal road at ch. 00-800m
|
RIDP-CBC
|
debidwar
|
|
0.80
|
|
|
34.65
|
M/S. Faiza Construction
|
27.98
|
|
30/09/2015
|
16/04/2016
|
100
|
|
|
|
|
472
|
RIDP(CBC)/C-W139 419542002
|
Improvement of Homna-Dulalpur-Bancharampur road Ch.9040-10040m
|
RIDP-CBC
|
homna
|
|
1.00
|
|
|
60.52
|
M/S Shaki enterprise
|
57.23
|
|
25/05/2016
|
01/06/2017
|
100
|
|
|
|
|
473
|
RIDP(CBC)/C-W140 419542005
|
Improvement of Homna-Bagmara-Kalmina-Ganiarchar Bazar-Tebagia-Ramchandra pur road Ch.4600-5724m .7040-7508m
|
RIDP-CBC
|
homna
|
|
1.20
|
|
|
85.89
|
M/S Badsha Enterprise
|
90.18
|
|
15/05/2016
|
28/02/2018
|
100
|
|
|
|
|
474
|
RIDP(CBC)/C-W232 419544001
|
Improvement Of Dulalpur-Vitikalmina-Baherkalmina road ch.1500-3800m
|
RIDP-CBC
|
homna
|
|
2.30
|
|
|
123.02
|
M/S Badsha Enterprise
|
123.02
|
|
29/03/2017
|
30/09/2018
|
100
|
|
|
|
|
475
|
RIDP(CBC)/C-W233 419544027
|
Improvement Of Chanderchar-Baluakandi Ghat road ch.00-500m
|
RIDP-CBC
|
homna
|
|
0.50
|
|
|
29.16
|
M/S R.R Enterprise
|
28.38
|
|
16/07/2017
|
22/03/2018
|
60
|
|
|
|
|
476
|
RIDP(CBC)/C-SW44 419544047
|
Improvement Of North Horipur-Bijoynagar road ch.1510-2260m
|
RIDP-CBC
|
homna
|
|
0.75
|
|
|
47.99
|
M/S Harunor Rashid
|
50.38
|
|
11/02/2018
|
17/08/2018
|
60
|
|
|
|
|
477
|
RIDP(CBC)/C-M95 419542003
|
Maintenance ( Rehabilation) of Sreepur Bazar-Montala-Masimpur GC road at ch. 2500-3500m.
|
RIDP-CBC
|
homna
|
|
1.00
|
|
|
31.65
|
M/S E.F Trade International
|
28.97
|
|
05/08/2017
|
17/05/2017
|
100
|
|
|
|
|
478
|
RIDP(CBC)/C-M82 419544005
|
Maintenance of Masumpur-Vitivasania road at ch. 00-1500m.
|
RIDP-CBC
|
homna
|
|
1.50
|
|
|
39.62
|
M/S Rafik Traders
|
41.41
|
|
28/11/2017
|
25/11/2017
|
100
|
|
|
|
|
479
|
RIDP(CBC)/C-M156 419724001
|
Periodic Maintenance (Re-Seal) of Shatbaria-NagJatia road at ch. 1000-1807m.
|
RIDP-CBC
|
laksham
|
|
0.81
|
|
|
11.89
|
M/S Shobo Enterprise
|
12.48
|
|
28/10/2018
|
|
20
|
|
|
|
|
480
|
RIDP(CBC)/C-W29 419723001
|
Improvement of Kaliachow-Heshakhal road at ch.1020-2202m
|
RIDP-CBC
|
laksham
|
|
1.18
|
|
|
69.78
|
M/S Rina Enterprise
|
72.88
|
|
14/07/2015
|
10/03/2016
|
100
|
|
|
|
|
481
|
RIDP(CBC)/C-SW30 419723018
|
Improvement of Bagmara UPC Ashara Bazar via Joynagar Bhabukpara (Laksham part) road at ch.00-1610m
|
RIDP-CBC
|
laksham
|
|
1.61
|
|
|
96.46
|
M/S Hamim & Brothers
|
96.45
|
|
18/12/2016
|
24/04/2018
|
100
|
|
|
|
|
482
|
RIDP(CBC)/C-W204 419723015
|
Improvement Of Gazimura-Gonipur road ch.2530-3530m
|
RIDP-CBC
|
laksham
|
|
1.00
|
|
|
74.73
|
M/S Allahardan Store
|
74.63
|
|
17/04/2017
|
23/04/2018
|
70
|
|
|
|
|
483
|
RIDP(CBC)/C-W206 419723014
|
Improvement Of Khila UP office-Chandana Bazar road ch.1000-2000m
|
RIDP-CBC
|
laksham
|
|
1.00
|
|
|
73.93
|
M/S Allahardan Store
|
73.82
|
|
16/03/2017
|
30/04/2018
|
60
|
|
|
|
|
484
|
RIDP(CBC)/C-SW41 419723018
|
Improvement Of Bagmara UPC-Ashra Bazar via Joynagar-Babukpara road (Rasulpur-Hazipur via Mohonpur)ch.1610-2610m,3110-5610m
|
RIDP-CBC
|
laksham
|
|
3.50
|
|
|
206.84
|
MAZ & MAKB (JV)
|
206.63
|
|
26/09/2017
|
02/10/2018
|
80
|
|
|
|
|
485
|
RIDP(CBC)/C-W31 419724006
|
Improvement of Barobam-Cilion road at ch. 660-1160m.
|
RIDP-CBC
|
laksham
|
|
0.50
|
|
|
34.66
|
M/S Rina Enterprise
|
36.21
|
|
14/07/2015
|
17/03/2016
|
100
|
|
|
|
|
486
|
RIDP(CBC)/C-W32 419724009
|
Improvement of Batabaria R&H-Ghater road at ch. 00-500m.
|
RIDP-CBC
|
laksham
|
|
0.50
|
|
|
25.53
|
M/S Rina Enterprise
|
26.63
|
|
28/07/2015
|
31/03/2016
|
100
|
|
|
|
|
487
|
RIDP(CBC)/C-W33 419725053
|
Improvement of Daulatgonj-Sreeyang road-Kagoia GPS road at ch. 00-500m.
|
RIDP-CBC
|
laksham
|
|
0.50
|
|
|
26.00
|
M/S A G A Corporation
|
26.00
|
|
06/10/2015
|
30/11/2016
|
100
|
|
|
|
|
488
|
RIDP(CBC)/C-W107 419724024
|
Improvement of Charbaria-Poliya road at ch. 00-1100m.
|
RIDP-CBC
|
laksham
|
|
1.10
|
|
|
58.60
|
M/S Raka Enterprise
|
59.72
|
|
01/02/2016
|
07/02/2017
|
100
|
|
|
|
|
489
|
RIDP(CBC)/C-W194 419724007
|
Improvement of Azgora-Azgora road at ch.00-660m
|
RIDP-CBC
|
laksham
|
|
0.66
|
|
|
34.15
|
M/S Rina Enterprise
|
34.79
|
|
18/12/2016
|
24/08/2017
|
100
|
|
|
|
|
490
|
RIDP(CBC)/C-SW21 419725020
|
Improvement Of Noorpur-Shikaripara Road.Ch.00-2000m
|
RIDP-CBC
|
laksham
|
|
2.00
|
|
|
127.40
|
M/S Hamim & Brothers
|
127.26
|
|
31/05/2016
|
05/06/2017
|
100
|
|
|
|
|
491
|
RIDP(CBC)/C-SW42 419725014
|
Improvement Of Bakoi UP office-Komurpur R&H (Hajipur-Joyosri) road ch.1050-2500m
|
RIDP-CBC
|
laksham
|
|
1.45
|
|
|
93.09
|
M/S Aziz & Brothers
|
96.33
|
|
14/11/2017
|
20/11/2018
|
100
|
|
|
|
|
492
|
RIDP(CBC)/C-SW40 419724035
|
Improvement Of Nurpur Bazar R&H-Chengahata R&H road ch.60-2600m
|
RIDP-CBC
|
laksham
|
|
2.54
|
|
|
167.68
|
M/S Alam Enterprise
|
163.13
|
|
16/07/2017
|
30/11/2018
|
100
|
|
|
|
|
493
|
RIDP(CBC)/C-W203. 419725059
|
Improvement Of Chunati Bridge -Monoharpur GPS road Ch.00-930m
|
RIDP-CBC
|
laksham
|
|
0.93
|
|
|
53.46
|
M/S Shahparan Enterprise
|
53.23
|
|
06/04/2017
|
14/02/2018
|
35
|
|
|
|
|
494
|
RIDP(CBC)/C-SW39 419724022
|
Improvement Of Babukpara Bazar-Kapashtola R&H road ch.500-3605m
|
RIDP-CBC
|
laksham
|
|
3.11
|
|
|
185.26
|
M/S Confidance International
|
185.00
|
|
28/06/2017
|
30/11/2018
|
65
|
|
|
|
|
495
|
RIDP(CBC)/C-W157 419883001
|
Improvement of Kasimpur Bazar-Taltoli Bazar road Ch.00-1000m
|
RIDP-CBC
|
meghna
|
|
1.00
|
|
|
62.03
|
M/S Foysal & Fahim Enterprise
|
65.12
|
|
17/05/2016
|
30/06/2018
|
100
|
|
|
|
|
496
|
RIDP(CBC)/C-W39 419883003
|
Improvement of Chandanpur-Tulatoli road at ch. 1545-2400m
|
RIDP-CBC
|
meghna
|
|
0.86
|
|
|
55.85
|
M/S Foysal & Fahim Enterprise
|
55.85
|
|
15/09/2015
|
30/08/2018
|
60
|
|
|
|
|
497
|
RIDP(CBC)/C-W40 419883005
|
Improvement of Tulatoli Upazila connecting road at ch. 965-1466m
|
RIDP-CBC
|
meghna
|
|
0.50
|
|
|
33.57
|
M/S Foysal & Fahim Enterprise
|
35.25
|
|
29/12/2015
|
30/11/2017
|
60
|
|
|
|
|
498
|
RIDP(CBC)/C-W158 419883005
|
Improvement of Taltoli -Upazila Conecting road Ch.1466-2466m
|
RIDP-CBC
|
meghna
|
|
1.00
|
|
|
62.21
|
M/S Foysal & Fahim Enterprise
|
62.20
|
|
21/08/2016
|
27/08/2017
|
60
|
|
|
|
|
499
|
RIDP(CBC)/C-W191 419883002
|
Improvement of Manikarchar-Kasipur road via Karimabad Lostimalika road at ch.1388-2600m
|
RIDP-CBC
|
meghna
|
|
1.21
|
|
|
69.04
|
M/S Tufan traders
|
68.70
|
|
28/11/2016
|
06/12/2017
|
60
|
|
|
|
|
500
|
RIDP(CBC)/C-W41 419884008
|
Improvement of Tulatoli -Teterchar road at ch. 00-500m
|
RIDP-CBC
|
meghna
|
|
0.50
|
|
|
22.55
|
M/S Micro International
|
21.96
|
|
12/07/2015
|
06/05/2017
|
100
|
|
|
|
|
501
|
RIDP(CBC)/C-W42 419884010
|
Improvement of Tulatoli Bazar-Kandargaon Collage road at ch. 00-500m
|
RIDP-CBC
|
meghna
|
|
0.50
|
|
|
27.72
|
M/S Monia Enterprise
|
29.10
|
|
12/07/2015
|
30/06/2017
|
100
|
|
|
|
|
502
|
RIDP(CBC)/C-W105 419884031
|
Improvement of Chalibhanga Bazar-Islasmpur road at ch. 00-547m
|
RIDP-CBC
|
meghna
|
|
0.55
|
|
|
27.79
|
M/S Foysal & Fahim Enterprise
|
29.17
|
|
19/01/2016
|
30/12/2016
|
100
|
|
|
|
|
503
|
RIDP(CBC)/C-W106 419885003
|
Improvement of Chalibhanga-Nalsar via Farajikandi road at ch. 00-857m
|
RIDP-CBC
|
meghna
|
|
0.86
|
|
|
23.80
|
M/S Foysal & Fahim Enterprise
|
24.99
|
|
19/01/2016
|
30/12/2016
|
100
|
|
|
|
|
504
|
RIDP(CBC)/C-W153 419884007
|
Improvement of Rampur- Muzaffar Ali College-Baidanathpur Bazar BC road at ch. 3500- 4000m
|
RIDP-CBC
|
meghna
|
|
0.50
|
|
|
30.33
|
M/S Tisha Enterprise
|
31.70
|
|
24/04/2016
|
31/01/2018
|
100
|
|
|
|
|
505
|
RIDP(CBC)/C-W161 419884038
|
Improvement Of Ramnagar-Sayani-Mataberkandi (Rampur-Manikarchar Conective) Road.Ch.500-980m
|
RIDP-CBC
|
meghna
|
|
0.48
|
|
|
30.40
|
M/S Foysal & Fahim Enterprise
|
31.91
|
|
21/08/2016
|
30/09/2017
|
100
|
|
|
|
|
506
|
RIDP(CBC)/C-W166 419884006
|
Improvement of Manikarchar-Gobindapur road at ch. 00- 1020m
|
RIDP-CBC
|
meghna
|
|
1.20
|
|
|
55.35
|
M/S Azmin Construction
|
54.91
|
|
21/08/2016
|
08/11/2017
|
100
|
|
|
|
|
507
|
RIDP(CBC)/C-W167 419885010
|
Improvement of Hasnabad-Gobindapur-Sonarchar-Brammonchar road at ch. 1000- 2070m
|
RIDP-CBC
|
meghna
|
|
1.70
|
|
|
60.98
|
M/S Azmin Construction
|
60.50
|
|
21/08/2016
|
20/05/2018
|
100
|
|
|
|
|
508
|
RIDP(CBC)/C-W190 419884026
|
Improvement of Manikarchar-Bagaikandi via Jalarpar BC road at ch.00-1000m
|
RIDP-CBC
|
meghna
|
|
1.00
|
|
|
61.25
|
M/S Tufan traders
|
60.95
|
|
09/10/2016
|
30/06/2018
|
100
|
|
|
|
|
509
|
RIDP(CBC)/C-W192 419885060
|
Improvement of Loterchar Riverghat-Vaterchar-Omrakanda Connecting BC road at ch.00-1050m
|
RIDP-CBC
|
meghna
|
|
1.50
|
|
|
54.17
|
M/S Foysal & Fahim enterprise
|
50.35
|
|
28/12/2016
|
30/06/2018
|
100
|
|
|
|
|
510
|
RIDP(CBC)/C-W92 419884017
|
Improvement of Baharkhola-Meghna upazila BC road at ch. 650-1101m
|
RIDP-CBC
|
meghna
|
|
0.45
|
|
|
36.34
|
M/S Tisha Enterprise
|
34.32
|
|
24/05/2017
|
30/06/2018
|
60
|
|
|
|
|
511
|
RIDP(CBC)/C-W110 419885010
|
Improvement of Hasnabad-Gobindapur-Sonarchar-Brammanchar road at ch. 00-1000m
|
RIDP-CBC
|
meghna
|
|
1.00
|
|
|
47.84
|
M/S Azmin Construction
|
47.60
|
|
19/03/2017
|
30/04/2018
|
40
|
|
|
|
|
512
|
RIDP(CBC)/C-W201. 419885044
|
Improvement Of Boydhanathpur Baitun Nur jame Mosque-Shibnagar GPS vis Battola Bazar road at ch. 00-825m
|
RIDP-CBC
|
meghna
|
|
0.83
|
|
|
46.99
|
M/S Faysal & Fahim Enterprise
|
43.23
|
|
01/02/2017
|
20/10/2017
|
10
|
|
|
|
|
513
|
RIDP(CBC)/C-SW32 419874005
|
Improvement Of Sonarchar village Moulovi house -Dakhinkandi village via Haque mia Bapari house road ch.00-700m
|
RIDP-CBC
|
meghna
|
|
0.70
|
|
|
37.67
|
M/S Azmin Construction
|
37.55
|
|
11/06/2017
|
17/02/2018
|
40
|
|
|
|
|
514
|
RIDP(CBC)/C-W258 419885065
|
Improvement Of Sonakanda jabed Ali house-Dr.Nasir house road ch.00-600m
|
RIDP-CBC
|
meghna
|
|
0.60
|
|
|
38.41
|
M/S National Trade SystemS
|
36.10
|
|
28/06/2017
|
30/06/2018
|
40
|
|
|
|
|
515
|
RIDP(CBC)/C-W262 419884033
|
Improvement Of Maisharchar-Boroiakandi road ch.00-700m
|
RIDP-CBC
|
meghna
|
|
0.70
|
|
|
51.94
|
M/S Ma Enterprise
|
51.94
|
|
05/11/2017
|
11/11/2018
|
60
|
|
|
|
|
516
|
RIDP(CBC)/C-BW19 419884017
|
Construction of 30.00 Long RCC Girder Bridge on Baharkhola-Meghna Upzila Road at ch.1100m
|
RIDP-CBC
|
meghna
|
|
|
|
|
158.29
|
M/S R-TA Enterprise
|
142.46
|
|
19/11/2017
|
25/11/2018
|
50
|
|
|
|
|
517
|
RIDP(CBC)/C-BW31 419885057
|
Construction of 26.06 Long RCC Girder Bridge on Tulatoly village house of Shachib-UP Conection road at ch.500m
|
RIDP-CBC
|
meghna
|
|
|
|
|
165.57
|
M/S Niaz Traders
|
165.51
|
|
05/02/2018
|
01/01/2019
|
45
|
|
|
|
|
518
|
RIDP(CBC)/C-BW36 419884008
|
Construction of 45.06.00m Long RCC Girder Bridge On Tulatoli-Titirchar road Ch. 1000m
|
RIDP-CBC
|
meghna
|
|
|
|
|
256.55
|
M/S Hamim & Brothers-Tithi Enterprise
|
255.51
|
|
19/02/2018
|
25/02/2019
|
35
|
|
|
|
|
519
|
RIDP(CBC)/C-BW37 419884008
|
Construction of 36.00m Long RCC Girder Bridge On Tulatoli-Titirchar road Ch. 2850m
|
RIDP-CBC
|
meghna
|
|
|
|
|
255.67
|
M/S Niaz Traders
|
268.46
|
|
10/05/2018
|
16/05/2019
|
40
|
|
|
|
|
520
|
RIDP(CBC)/C-BW39 419884042
|
Construction of 33.00m Long RCC Girder Bridge On Joynagar Govt.Primary School road Ch. 650m
|
RIDP-CBC
|
meghna
|
|
|
|
|
223.96
|
M/S M.M Enterprise
|
209.28
|
|
08/03/2018
|
14/03/2019
|
50
|
|
|
|
|
521
|
RIDP(CBC)/C-W159 419884010
|
Improvement of Tolatoli Bazar-Kandergaon Collage road. Ch.500-1500m
|
RIDP-CBC
|
meghna
|
|
1.00
|
|
|
58.10
|
M/S Faysal & Fahim Enterprise
|
61.00
|
|
17/05/2016
|
22/05/2017
|
40
|
|
|
|
|
522
|
RIDP(CBC)/C-RM4
|
Improvement of Gobindapur Bazar
|
RIDP-CBC
|
meghna
|
|
|
|
|
28.84
|
M/S Babul Enterprise
|
26.25
|
|
24/02/2016
|
30/06/2018
|
90
|
|
|
|
|
523
|
RIDP(CBC)/C-M127 419882004
|
Periodic Maintenance (Rehabilition) of Manikarchar-Alipur Lanch Ghat road at ch. 1000-3000m.
|
RIDP-CBC
|
meghna
|
|
2.00
|
|
|
40.63
|
M/S National Trade System
|
38.98
|
|
30/04/2018
|
10/04/2018
|
100
|
|
|
|
|
524
|
RIDP(CBC)/C-M128 419882002
|
Periodic Maintenance (Rehabilition) of Rampur-Manikarchar road at ch. 00-2000m.
|
RIDP-CBC
|
meghna
|
|
2.00
|
|
|
59.85
|
M/S National Trade System
|
62.83
|
|
11/07/2018
|
19/03/2018
|
100
|
|
|
|
|
525
|
RIDP(CBC)/C-M94 419893002
|
Maintenance of (Overlay) Manikarchar-Kashimpur via Karimabad Lostimalika road at ch. 00-1388m.
|
RIDP-CBC
|
meghna
|
|
1.39
|
|
|
28.82
|
M/S Monia Enterprise
|
27.29
|
|
30/04/2018
|
28/03/2018
|
100
|
|
|
|
|
526
|
RIDP(CBC)/C-M83 419902004
|
Maintenance of (Rehabilitation) of Batabaria R&H - Monohargonj GC road at ch. 5230-8000m.
|
RIDP-CBC
|
monohorganj
|
|
2.77
|
|
|
82.06
|
M/S Zaman Traders
|
86.15
|
|
16/04/2017
|
11/07/2016
|
100
|
|
|
|
|
527
|
RIDP(CBC)/C-M88 419903011
|
Periodic Maintenance (Rehabilition) Of Bipulashar Up-Manikmura Bazar Via Bhogai Bazar road at Ch 2190-4660m
|
RIDP-CBC
|
monohorganj
|
|
2.47
|
|
|
88.61
|
M/S Homayun & Brathers
|
92.10
|
|
12/09/2017
|
15/03/2018
|
100
|
|
|
|
|
528
|
RIDP(CBC)/C-M60 419904040
|
Maintenance of Indri- Kashipur road at ch. 00-1100m.
|
RIDP-CBC
|
monohorganj
|
|
1.10
|
|
|
24.85
|
M/S Jaba Enterprise
|
26.09
|
|
30/12/2016
|
22/12/2016
|
100
|
|
|
|
|
529
|
RIDP(CBC)/C-M119 419904023
|
Periodic Maintenance (Overlay) of Compani Bazar-Baisgaon Bazar road at ch. 2900-3670m.
|
RIDP-CBC
|
monohorganj
|
|
0.77
|
|
|
21.59
|
M/S Hai & CO.
|
22.67
|
|
30/05/2018
|
28/02/2018
|
100
|
|
|
|
|
530
|
RIDP(CBC/C-W78 419903016
|
Improvement of Monohorgonj GC-Amtali bazar-Islampur-Chaitala-Ichapura bazar road at Ch. 2554-3560m
|
RIDP-CBC
|
monohorganj
|
|
1.01
|
|
|
54.55
|
M/S Emon Enterprise
|
57.14
|
|
15/09/2015
|
30/11/2017
|
100
|
|
|
|
|
531
|
RIDP(CBC)/C-W178 419904032
|
Improvement of Goaliara-Kashipur Bazar Via Taherpur Boranikhonda road) at ch.3575-5075m
|
RIDP-CBC
|
monohorganj
|
|
1.50
|
|
|
95.18
|
M/S MA Enterprise
|
95.12
|
|
01/08/2016
|
30/01/2018
|
100
|
|
|
|
|
532
|
RIDP(CBC)/C-W236 419904045
|
Improvement Of Natherpetua UP-Poranpur Primary School road ch.1090-1590m
|
RIDP-CBC
|
monohorganj
|
|
0.50
|
|
|
32.72
|
M/S Allahardan Store
|
32.65
|
|
20/02/2017
|
30/06/2018
|
100
|
|
|
|
|
533
|
RIDP(CBC)/C-W237 419905035
|
Improvement Of Ashirper Bazar-Maishatua UP office-Gazrapara-Ishapara road ch.00-500m
|
RIDP-CBC
|
monohorganj
|
|
0.50
|
|
|
33.41
|
M/S Zaman Traders
|
35.07
|
|
22/03/2017
|
28/11/2017
|
100
|
|
|
|
|
534
|
RIDP(CBC)/C-W268 419905038
|
Improvement Of (A) Durgapur-Khsrkharia road ch.00-640m (B) Construction of 1x3.00x3.00m RCC Box Culvert Same road At Ch.160 (C) Protection Work Ch.140m
|
RIDP-CBC
|
monohorganj
|
|
0.64
|
|
|
60.29
|
M/S Farhana Builders
|
65.72
|
|
19/02/2018
|
25/02/2019
|
100
|
|
|
|
|
535
|
RIDP(CBC)/C-W16 419903002
|
Improvement of Laksmanpur Bazar- Sorospur UP-Company Bazar road at Ch. 4000-5000m .
|
RIDP-CBC
|
monohorganj
|
|
1.00
|
|
|
61.58
|
M/S Emon Enterprise
|
64.66
|
|
10/06/2015
|
31/03/2016
|
100
|
|
|
|
|
536
|
RIDP(CBC)/C-W17 419903024
|
Improvement of Monohorgonj GC-Jolipur-Baishgaon UP-Burpist-Sathghoria-Hasnabad GC road at Ch. 7280-8130m
|
RIDP-CBC
|
monohorganj
|
|
0.85
|
|
|
53.29
|
M/S Alam Enterprise
|
55.95
|
|
23/07/2015
|
30/08/2017
|
100
|
|
|
|
|
537
|
RIDP(CBC)/C-W141 419903013
|
Improvement of Monohorgonj H/Q- Betiapara-Vatcor-Shapur-Sorospur UP road Ch.5000-5625m
|
RIDP-CBC
|
monohorganj
|
|
0.63
|
|
|
41.22
|
M/S Bhuiyan Traders
|
40.77
|
|
05/04/2016
|
30/01/2018
|
100
|
|
|
|
|
538
|
RIDP(CBC)/C-W195 419903009
419903014
419903020
|
Improvement of (A) Bipulashar-Compani Bazar road at ch.2582-3082m
(B) Laksmanpur Bazar-Vaupur-Rudrapur-Nadana Bazar road.Ch.1580-2080m
© Monohorgonj H/Q-Disabondho-Boronikhonda-Thangerbam- Uttur Hawla UP road.Ch.00-670m
|
RIDP-CBC
|
monohorganj
|
|
1.67
|
|
|
92.94
|
M/S Allahardan Store
|
92.80
|
|
20/02/2017
|
30/12/2018
|
100
|
|
|
|
|
539
|
RIDP(CBC)/C-W18 419905036
|
Improvement of Monohorgonj GC-Chikutia-Amtoli Bazar road at Ch.00-600m
|
RIDP-CBC
|
monohorganj
|
|
0.60
|
|
|
32.60
|
M/S Emon Enterprise
|
34.23
|
|
24/06/2015
|
31/12/2016
|
100
|
|
|
|
|
540
|
RIDP(CBC)/C-W19 419904018
|
Improvement of Marah-Batkor-Kharkharia road at Ch. 1200-1885m Under Monohargonj Upazila
|
RIDP-CBC
|
monohorganj
|
|
0.69
|
|
|
35.26
|
M/S MA Enterprise
|
35.25
|
|
01/08/2016
|
07/04/2017
|
100
|
|
|
|
|
541
|
RIDP(CBC)/C-W15 419904039
|
Improvement of Munshirhat-Shingguri road at Ch. 3500-4500m Under Monohargonj Upazila
|
RIDP-CBC
|
monohorganj
|
|
1.00
|
|
|
57.60
|
M/S Emon Enterprise
|
60.47
|
|
22/07/2015
|
24/02/2016
|
100
|
|
|
|
|
542
|
RIDP(CBC)/C-W84 419905042
|
Improvement of Latshor-Kashipur bazar road at Ch. 00-410m
|
RIDP-CBC
|
monohorganj
|
|
0.41
|
|
|
28.54
|
M/S Islam Trading
|
29.96
|
|
13/09/2015
|
30/05/2016
|
100
|
|
|
|
|
543
|
RIDP(CBC)/C-W137 419904085
|
(A) Improvement of Baihgaon UP office - Baishgaon Bazar -Via Saktola road. Ch.3600-4600m
|
RIDP-CBC
|
monohorganj
|
|
1.00
|
|
|
64.91
|
M/S Lucky Prokowsali
|
58.71
|
|
04/04/2016
|
28/02/2018
|
100
|
|
|
|
|
544
|
RIDP(CBC)/C-W269 419905039
|
Improvement Of Mahar-Ganjiapara-Keyere road ch.00-1000m
|
RIDP-CBC
|
monohorganj
|
|
1.00
|
|
|
61.05
|
M/S Zaman Traders
|
67.09
|
|
26/04/2018
|
02/01/2019
|
100
|
|
|
|
|
545
|
RIDP(CBC/C-W142 419904075
|
Improvement of Borolla Bazar-Munshirhat GC Road Ch.1000-1500m
|
RIDP-CBC
|
monohorganj
|
|
0.50
|
|
|
29.16
|
M/S Hamim & Brothers
|
29.16
|
|
19/04/2016
|
16/04/2017
|
10
|
|
|
|
|
546
|
RIDP(CBC)/C-W138 419904066
419904008
|
Improvement of (A) Bachor Bazar- Jadubpur Bazar Road Ch.00-580m
(B) Bihora - Sakchail Road Ch.00-600m
|
RIDP-CBC
|
monohorganj
|
|
1.18
|
|
|
74.30
|
M/S Hamim & Brothers
|
72.20
|
|
17/05/2016
|
30/04/2018
|
100
|
|
|
|
|
547
|
RIDP(CBC)/C-W221 419904087
|
Improvement Of Mannara road-Burpist road ch.00-500m
|
RIDP-CBC
|
monohorganj
|
|
0.50
|
|
|
30.64
|
M/S Allahardan Store
|
30.58
|
|
16/03/2017
|
30/08/2018
|
60
|
|
|
|
|
548
|
RIDP(CBC)/C-W235 419904077
|
Improvement Of Kestola Bazar-Abul Market-Mirzapur Bazar road ch.00-800m
|
RIDP-CBC
|
monohorganj
|
|
0.80
|
|
|
54.03
|
M/S MA Enterprise
|
54.03
|
|
05/04/2017
|
28/02/2019
|
65
|
|
|
|
|
549
|
RIDP(CBC)/C-W243 419812007
|
Improvement of Chandla GC-Sonarampur road via Madabpur-Jangar-Dalfa-Hatbalibari road Ch.2330-3630m
|
RIDP-CBC
|
muradnagar
|
|
1.30
|
|
|
119.78
|
M/S Haque International
|
107.80
|
|
24/05/2017
|
30/11/2018
|
70
|
|
|
|
|
550
|
RIDP(CBC)/C-W36 419813036
|
Improvement of Companigonj Bazar C&B Bazar via Gonjar-Beltali Bazar road at ch. 51-1051m
|
RIDP-CBC
|
muradnagar
|
|
1.00
|
|
|
53.63
|
M/S Santa Enterprise
|
46.66
|
|
23/06/2015
|
30/12/2015
|
100
|
|
|
|
|
551
|
RIDP(CBC)/C-W37 419813018
|
Improvement of Khoroel-Siddeyshori bazar-Darora union-Darora bazar-Raytala road at ch. 4300-4800m
|
RIDP-CBC
|
muradnagar
|
|
0.50
|
|
|
31.18
|
M/S Nero & Brothers
|
27.00
|
|
03/02/2016
|
03/01/2016
|
100
|
|
|
|
|
552
|
RIDP(CBC)/C-W96 419813029
|
Improvement of Palasuta-Subelarchar(Borarchar bazar) road at ch. 739-1439m
|
RIDP-CBC
|
muradnagar
|
|
0.70
|
|
|
37.31
|
M/S Rafiqe Traders
|
33.35
|
|
26/10/2015
|
30/11/2016
|
100
|
|
|
|
|
553
|
RIDP(CBC)/C-W109 419813032
|
Improvement of Muradnagar-Eliotgonj road(Suranandi) to Nayamatkandi RHD road at ch. 790-1290m
|
RIDP-CBC
|
muradnagar
|
|
0.50
|
|
|
29.84
|
M/S Abdus Samad
|
25.34
|
|
24/02/2016
|
30/12/2017
|
100
|
|
|
|
|
554
|
RIDP(CBC)/C-W216 419813012
|
Improvement Of Phirkashimpur-Horerpar road ch.00-1000m
|
RIDP-CBC
|
muradnagar
|
|
1.00
|
|
|
63.76
|
M/S Nero & Brothers
|
63.74
|
|
20/02/2017
|
26/02/2018
|
30
|
|
|
|
|
555
|
RIDP(CBC)/C-W217 419813026
|
Improvement Of Estagram RHD road Korbanpur road via Nabiabad road ch.3200-4390m
|
RIDP-CBC
|
muradnagar
|
|
1.19
|
|
|
70.91
|
M/S Nero & Brothers
|
70.87
|
|
20/02/2017
|
30/12/2018
|
70
|
|
|
|
|
556
|
RIDP(CBC)/C-W218 419813013
|
Improvement Of Jahapur-Ranimohuri road ch.1850-2620m
|
RIDP-CBC
|
muradnagar
|
|
0.77
|
|
|
51.25
|
M/S Saikot Construction
|
51.00
|
|
05/06/2017
|
10/06/2018
|
70
|
|
|
|
|
557
|
RIDP(CBC)/C-W219 419813020
419813034
|
Improvement Of (A) Chandanail-Salpa-Pennai road via Peporiakanda bazar road ch.00-500m
(B) Pepolia Roachala-Dhanpotikhola road Ch.1000-1500m
|
RIDP-CBC
|
muradnagar
|
|
1.00
|
|
|
61.98
|
M/S Nero & Brothers
|
61.96
|
|
26/02/2017
|
04/03/2018
|
60
|
|
|
|
|
558
|
RIDP(CBC)/C-W270 419813012
|
Improvement Of Phirkashimpur-Horerpar road ch.1000-2050m
|
RIDP-CBC
|
muradnagar
|
|
1.05
|
|
|
72.33
|
M/S Nero & Brothers
|
69.94
|
|
18/10/2017
|
24/10/2018
|
20
|
|
|
|
|
559
|
RIDP(CBC)/C-W271 419813020
|
Improvement Of Chandanail-Salpa-Pannai road via Pipuriakanda bazar road ch.500-1600m
|
RIDP-CBC
|
muradnagar
|
|
1.10
|
|
|
76.31
|
M/S Nero & Brothers
|
70.00
|
|
18/10/2017
|
24/10/2018
|
60
|
|
|
|
|
560
|
RIDP(CBC)/C-W5 419815127
|
Construction of 2x4.50x5.00m RCC Box culvert on Gazipur(Gazirhat)-Kaligonj road Jaj Faruk shahed bari road at ch. 623m.
|
RIDP-CBC
|
muradnagar
|
|
|
|
|
20.40
|
M/S Abdus Samad
|
17.42
|
|
29/03/2015
|
05/07/2015
|
100
|
|
|
|
|
561
|
RIDP(CBC)/C-W116 419814003
|
Improvement of Babutipara-Paharpur Via GDB School road at ch. 00-500m
|
RIDP-CBC
|
muradnagar
|
|
0.50
|
|
|
29.45
|
M/S S.F International
|
24.49
|
|
19/01/2016
|
25/09/2016
|
100
|
|
|
|
|
562
|
RIDP(CBC)/C-W38 419814087
|
Improvement of Korerpar R&H road to Woman Collage road at ch. 00-1350m
|
RIDP-CBC
|
muradnagar
|
|
1.35
|
|
|
66.69
|
M/S Pioneer construction
|
55.50
|
|
16/07/2015
|
30/07/2016
|
100
|
|
|
|
|
563
|
RIDP(CBC)/C-W54 419814037
|
Improvement of Ranimohure to Darikandi road at ch. 3600-5400m
|
RIDP-CBC
|
muradnagar
|
|
1.80
|
|
|
107.55
|
M/S. Eashan Enterprise
|
98.11
|
|
26/05/2015
|
31/12/2016
|
100
|
|
|
|
|
564
|
RIDP(CBC)/C-W55 419814093
|
Improvement of Danopati R&H-Royasala road at ch. 00-1000m
|
RIDP-CBC
|
muradnagar
|
|
1.00
|
|
|
52.36
|
M/S Nero & Brothers
|
52.34
|
|
26/05/2015
|
30/03/2016
|
100
|
|
|
|
|
565
|
RIDP(CBC)/C-W90 419814055
|
Improvement of Kawotgram Mosque-Shusunda Baribandha Primary School road at ch. 750-1000m
|
RIDP-CBC
|
muradnagar
|
|
0.25
|
|
|
15.14
|
M/S Golam Rabbani
|
12.50
|
|
06/09/2015
|
28/02/2016
|
100
|
|
|
|
|
566
|
RIDP(CBC)/C-W85 419814038
|
Improvement of Khapura-Ulumuria-Chapitala road at ch. 00-400m
|
RIDP-CBC
|
muradnagar
|
|
0.40
|
|
|
19.01
|
M/S Golam Rabbani
|
16.15
|
|
06/09/2015
|
30/03/2016
|
100
|
|
|
|
|
567
|
RIDP(CBC)/C-W86 419815061
|
Improvement of Chapitala RHD road to Kazi Serajuddin Chati road via Darbar bhuiyan house (Chapitala-Baira road on Badar Uddin house to Kazi bari road at Ch. 00-400mm
|
RIDP-CBC
|
muradnagar
|
|
0.40
|
|
|
17.70
|
M/S Golam Rabbani
|
15.50
|
|
29/09/2015
|
23/02/2016
|
100
|
|
|
|
|
568
|
RIDP(CBC)/C-W94 419815127
|
Improvement of Gazirhat-Kaligonj to Gazipur Justice Md. Faruk Bari road at Ch. 00-648m
|
RIDP-CBC
|
muradnagar
|
|
0.65
|
|
|
31.49
|
M/S Rashid $ Brothers
|
29.90
|
|
26/10/2015
|
02/04/2016
|
100
|
|
|
|
|
569
|
RIDP(CBC)/C-W114
|
Improvement of Muradnagar RHD road (West Side of Food Godown to Nimaikandi road Ch.00-500m
|
RIDP-CBC
|
muradnagar
|
|
0.50
|
|
|
24.32
|
M/S Rashid & Brothers
|
20.40
|
|
24/01/2016
|
30/05/2017
|
100
|
|
|
|
|
570
|
RIDP(CBC)/C-SW25 419815024
|
Improvement of Babutipara Neya Puskuronipar road) at ch.00-1200m
|
RIDP-CBC
|
muradnagar
|
|
1.20
|
|
|
61.73
|
M/S Kamal uddin
|
64.81
|
|
11/07/2016
|
30/11/2018
|
100
|
|
|
|
|
571
|
RIDP(CBC)/C-W121 419814122
|
Improvement of Shaliakandi Market-kaziatol Hasan Market Bridge road Ch.00-720m
|
RIDP-CBC
|
muradnagar
|
|
0.72
|
|
|
47.68
|
M/S Nero & Brothers
|
41.01
|
|
16/02/2016
|
22/07/2016
|
85
|
|
|
|
|
572
|
RIDP(CBC)/C-W212. 419814008
|
Improvement Of Gazirhat-Srekail road Ch.850-2350m
|
RIDP-CBC
|
muradnagar
|
|
1.50
|
|
|
99.03
|
M/S Kamal uddin
|
97.96
|
|
14/02/2017
|
20/02/2018
|
75
|
|
|
|
|
573
|
RIDP(CBC)/C-W228 419814120
|
Improvement Of Chandranail -Baraia Chara bazar road ch.366-866m
|
RIDP-CBC
|
muradnagar
|
|
0.50
|
|
|
32.66
|
M/S Nero & Brothers
|
32.62
|
|
26/02/2017
|
04/11/2017
|
30
|
|
|
|
|
574
|
RIDP(CBC)/C-W250 419815096
|
Improvement Of Gazipur-Nabinagar road to kaligonj road near grave-yard ch.00-500m
|
RIDP-CBC
|
muradnagar
|
|
0.50
|
|
|
34.89
|
M/S Nero & Brothers
|
34.82
|
|
05/06/2017
|
11/02/2018
|
30
|
|
|
|
|
575
|
RIDP(CBC)/C-BW14 419814038
|
Construction of 20m Long RCC Girder Bridge Over khapura-Ulumuria-Chapitola road.(Muktijoddah Mohosin Bhuiyan sarkar)at Ch-3190m
|
RIDP-CBC
|
muradnagar
|
|
|
|
|
94.49
|
Md.Delowar Hossain Babul
|
85.04
|
|
30/10/2017
|
05/11/2018
|
30
|
|
|
|
|
576
|
RIDP(CBC)/C-W286 419814039
419814048
|
Improvement Of (A) Gazipur-Kaligonj road ch.1000-1500m
(B) Dhamgar-Aralia road ch.100-660m
|
RIDP-CBC
|
muradnagar
|
|
1.06
|
|
|
62.92
|
M/S Naium Enterprise
|
62.88
|
|
05/03/2018
|
11/11/2018
|
60
|
|
|
|
|
577
|
RIDP(CBC)/C-W320 41981463
|
(A) Improvement Of Muchagara Bazar-Bhabanipur road ch.00-1010m
(B) Improvement Of Nemikandi RHd-Embakment (Ramdhonomor)road ch.00-263m
(C) Improvement Of Burarchar Safor Ali Bhuyan house-Palasuta via Primary School link road ch.00-540m
(D) Construction O
|
RIDP-CBC
|
muradnagar
|
|
1.81
|
|
|
144.51
|
M/S Hazi Construction
|
150.94
|
|
05/07/2018
|
11/07/2019
|
50
|
|
|
|
|
578
|
RIDP(CBC)/C-RM14
|
Improvement of Muradnagar Bazar
|
RIDP-CBC
|
muradnagar
|
|
|
|
|
29.86
|
M/S E.F Trade Int.
|
26.87
|
|
01/02/2018
|
07/10/2018
|
65
|
|
|
|
|
579
|
RIDP(CBC)/C-M16 419812004
|
Maintenance of Muradnagar (Pannarpur)-Eliotgonj road at ch. 10100-13300m.
|
RIDP-CBC
|
muradnagar
|
|
3.20
|
|
|
46.94
|
M/S Nero & Brothers
|
39.80
|
|
30/06/2015
|
25/05/2015
|
100
|
|
|
|
|
580
|
RIDP(CBC)/C-M125 419812003
|
Periodic Maintenance (Rehabilition) of Jafargonj GC-Pabchpukuria road at ch. 818-1818m.
|
RIDP-CBC
|
muradnagar
|
|
1.00
|
|
|
31.50
|
M/S S.F International
|
31.34
|
|
30/01/2018
|
24/12/2017
|
100
|
|
|
|
|
581
|
RIDP(CBC)/C-M129 419812004
|
Re-Construction of 4.50x4.50m Rcc Culvert on Muradnagar-Eliotgonj road at Ch.19128m
|
RIDP-CBC
|
muradnagar
|
|
|
|
|
16.74
|
M/S Nero & Brothers
|
15.07
|
|
31/03/2018
|
11/02/2018
|
100
|
|
|
|
|
582
|
RIDP(CBC)/C-M15 419813003
|
Maintenance of Saypara-Paramtala road at ch. 00-1170m.
|
RIDP-CBC
|
muradnagar
|
|
1.17
|
|
|
21.21
|
M/S Rashid & Brothers
|
18.52
|
|
10/07/2015
|
21/06/2015
|
100
|
|
|
|
|
583
|
RIDP(CBC)/C-M14 419813022
|
Maintenance of Jahapur UP Office-Gomti embackment via Jahapur madrasha road at ch. 00-780m.
|
RIDP-CBC
|
muradnagar
|
|
0.78
|
|
|
12.90
|
M/S Abdus Samad
|
11.10
|
|
30/03/2016
|
25/01/2016
|
100
|
|
|
|
|
584
|
RIDP(CBC)/C-M41 419813014
|
Maintenance (overly) of Lazure-Babutypara UP Office road at ch. 00-1000m.
|
RIDP-CBC
|
muradnagar
|
|
1.00
|
|
|
11.00
|
M/S Abdus Samad
|
11.54
|
|
31/05/2017
|
25/05/2017
|
100
|
|
|
|
|
585
|
RIDP(CBC)/C-M124 419813007
|
Periodic Maintenance (Rehabili tion) of Chapitala-Mohesper road ch. 00-1100m.
|
RIDP-CBC
|
muradnagar
|
|
1.10
|
|
|
24.69
|
M/S Abdus Samad
|
24.68
|
|
31/03/2018
|
25/03/2018
|
100
|
|
|
|
|
586
|
RIDP(CBC)/C-M91 419813015
|
Periodic Maintenance (Rehabilition) Of Raytola-Kaziatol road at Ch 00- 2545m
|
RIDP-CBC
|
muradnagar
|
|
2.55
|
|
|
74.39
|
M/S Rafik Traders
|
67.53
|
|
30/10/2017
|
21/10/2017
|
100
|
|
|
|
|
587
|
RIDP(CBC)/C-M18 419872007
|
Maintenance of Nangalkot-Toguria road at ch. 3800-6690m.
|
RIDP-CBC
|
nangalkot
|
|
2.89
|
|
|
62.09
|
M/S Arsad & Sons
|
58.64
|
|
06/07/2015
|
09/06/2015
|
100
|
|
|
|
|
588
|
RIDP(CBC)/C-M17 419873019
|
Maintenance of Dalua-Bisnopur-Chandghara-Nowapara-Chodia bazar road at ch. 1960-2960m.
|
RIDP-CBC
|
nangalkot
|
|
1.00
|
|
|
28.09
|
M/S Banu Enterprise
|
26.65
|
|
02/07/2015
|
12/05/2015
|
100
|
|
|
|
|
589
|
RIDP(CBC)/C-M19 419873025
|
Maintenance of Satbaria-Chowkure-Mannara-Bayra-Sarfatali-Sejeyara-Shehar bazar road at ch. 8600-9780m.
|
RIDP-CBC
|
nangalkot
|
|
1.18
|
|
|
25.89
|
M/S Modina Construction
|
23.74
|
|
01/07/2015
|
17/05/2015
|
100
|
|
|
|
|
590
|
RIDP(CBC)/C-SM2 419873012
|
Maintenance of Sreefolia Dr. Jobeda Hannan Road at Ch. 00-2555m Under Nangalkot Upazila
|
RIDP-CBC
|
nangalkot
|
|
2.56
|
|
|
76.29
|
M/S Halima Enterprise
|
72.21
|
|
21/02/2016
|
21/02/2016
|
100
|
|
|
|
|
591
|
RIDP(CBC)/C-M34 419873008
|
Maintenance of Adra-Volain bazar-Chatitola-Goramoidan-Manikmora Road at Ch. 00-4000m Under Nangalkot Upazila
|
RIDP-CBC
|
nangalkot
|
|
4.00
|
|
|
115.73
|
M/S Banu Enterprise
|
115.62
|
|
24/08/2016
|
20/08/2016
|
100
|
|
|
|
|
592
|
RIDP(CBC)/C-M69 419873010
|
Maintenance of Baiara-Mandra-Deovandar Road at Ch.3450-7398m
|
RIDP-CBC
|
nangalkot
|
|
3.95
|
|
|
112.38
|
M/S Rehana Construction
|
107.33
|
|
31/12/2017
|
29/12/2017
|
100
|
|
|
|
|
593
|
RIDP(CBC)/C-M67 419873027
|
Maintenance of Montala-Olipur-Samirkhil-Kestala-Tilip-Mowara-Gomkot Road.Ch. 00-349,1337-2022m
|
RIDP-CBC
|
nangalkot
|
|
1.03
|
|
|
37.53
|
M/S Rehana Construction
|
35.79
|
|
30/08/2017
|
16/08/2017
|
100
|
|
|
|
|
594
|
RIDP(CBC)/C-M75 419873011
|
Maintenance of Nangolkot-Merkot-Ludua road.Ch. 00-1730m
|
RIDP-CBC
|
nangalkot
|
|
1.73
|
|
|
50.53
|
M/S Ar-Ta Enterprise
|
46.18
|
|
17/04/2017
|
15/04/2017
|
100
|
|
|
|
|
595
|
RIDP(CBC)/C-M98 419873014
|
Maintenance of (Rehabilition) Boxgonj-Batabaria-Dubai Bazar-Bam-Pirmohammad-Kandail-Sondail road ch.00-3375m.
|
RIDP-CBC
|
nangalkot
|
|
3.38
|
|
|
93.08
|
M/S Modina Construction
|
92.99
|
|
10/12/2017
|
03/06/2017
|
100
|
|
|
|
|
596
|
RIDP(CBC)/C-M99 419873026
|
Maintenance of (Rehabilition) Boxgonj-Barokali-Suvapur-Kabilakhali-Satbaria road ch.00-1000m.
|
RIDP-CBC
|
nangalkot
|
|
1.00
|
|
|
31.76
|
M/S Ma-Moni Enterprise
|
31.76
|
|
17/08/2017
|
10/06/2017
|
100
|
|
|
|
|
597
|
RIDP(CBC)/C-M115 419873019
|
Periodic Maintenance (Overlay) of Noapara-Chadia Bazar via Atiabari road (Dhalua Bisnapur Chagara Noapara Chadia Bazar road ch. 00-1200m.
|
RIDP-CBC
|
nangalkot
|
|
1.20
|
|
|
53.11
|
M/S Meazi Enterprize
|
52.94
|
|
06/03/2018
|
04/03/2018
|
100
|
|
|
|
|
598
|
RIDP(CBC)/C-M68 419874125
|
Maintenance of Kandra-Tetoia-Jhatiapara-Purba Bampara road at ch. 1622-1981m.2392-2628m.2628-3260m
|
RIDP-CBC
|
nangalkot
|
|
1.23
|
|
|
40.41
|
M/S Rehana Construction
|
38.54
|
|
02/10/2016
|
01/10/2016
|
100
|
|
|
|
|
599
|
RIDP(CBC)/C-W7 419873011
|
Improvement of Nangalkot-Merkot-Lodua road at ch. 5500-8222m.
|
RIDP-CBC
|
nangalkot
|
|
2.72
|
|
|
143.17
|
M/S Zaman Traders
|
150.33
|
|
18/02/2015
|
24/06/2015
|
100
|
|
|
|
|
600
|
RIDP(CBC)/C-W8 419873028
|
Improvement of Mokrabpur bazar-Zorepokuria-Utter Mahini-Sharifpur road at ch. 1906-3174m.
|
RIDP-CBC
|
nangalkot
|
|
1.27
|
|
|
64.30
|
M/S Farhana Builders
|
67.51
|
|
18/02/2015
|
24/06/2015
|
100
|
|
|
|
|
601
|
RIDP(CBC)/C-W9 419873027
|
Improvement of Montali-Alipur Shamirkhil-Keshtala-Tilip-Mayora-Gomkot road at ch. 347-1384m.
|
RIDP-CBC
|
nangalkot
|
|
1.04
|
|
|
52.15
|
M/S Banu Enterprise
|
52.15
|
|
25/03/2015
|
31/12/2015
|
100
|
|
|
|
|
602
|
RIDP(CBC)/C-W4 419873001
|
Construction of 3x4.50x3.50m RCC Box culvert on Baiyara-Manikmura road at ch. 5980m.
|
RIDP-CBC
|
nangalkot
|
|
|
|
|
20.08
|
M/S Banu Enterprise
|
18.86
|
|
25/03/2015
|
02/07/2015
|
100
|
|
|
|
|
603
|
RIDP(CBC)/C-W68 419873020
|
Improvement of Gomkot-Dipjol Market-Khatachow-Patwar-Omargonj Bazar Road at Ch. 3288-4890m
|
RIDP-CBC
|
nangalkot
|
|
1.60
|
|
|
65.78
|
M/S Halima Enterprise
|
64.63
|
|
16/07/2015
|
31/12/2016
|
100
|
|
|
|
|
604
|
RIDP(CBC)/C-W69 419873016
|
Improvement of Baiara-Jodda-Kashipur Road at Ch. 1310-2100m & 3870-4960m
|
RIDP-CBC
|
nangalkot
|
|
1.89
|
|
|
86.56
|
M/S Halima Enterprise
|
86.14
|
|
16/07/2015
|
15/01/2017
|
100
|
|
|
|
|
605
|
RIDP(CBC)/C-W70 419873020
|
Improvement of Satbaria-Chowkori-Mannara-Bayra-Sarfatuli-Sejiara-Shehar Bazar Road at Ch. 7200-7420m
|
RIDP-CBC
|
nangalkot
|
|
0.22
|
|
|
9.97
|
M/S Raju Enterprise
|
9.16
|
|
15/09/2015
|
15/02/2016
|
100
|
|
|
|
|
606
|
RIDP(CBC)/C-W67 419873028
|
Improvement of Mokrabpur bazar-Zorepokuria-Utter Mahini-Sharifpur road at ch. 4174-4674m & 4674-5656m.
|
RIDP-CBC
|
nangalkot
|
|
1.48
|
|
|
76.16
|
M/S Arshad & Sons
|
79.95
|
|
07/12/2015
|
20/01/2017
|
100
|
|
|
|
|
607
|
RIDP(CBC)/C-W196 419873014
|
Improvement of Boxgonj-Batabaria-Dubai Bazar-Bam-Pirmohammad-kandal-Sondail road at ch.8400-9240m
|
RIDP-CBC
|
nangalkot
|
|
0.84
|
|
|
60.39
|
M/S Modina Construction
|
60.32
|
|
04/12/2016
|
10/12/2017
|
100
|
|
|
|
|
608
|
RIDP(CBC)/C-W197 419873019
|
Improvement of Dhalua-Bishnapur-Changara-Noapara-Chadia Bazar road at ch.3000-4600m
|
RIDP-CBC
|
nangalkot
|
|
1.60
|
|
|
100.07
|
M/S Modina Construction
|
100.01
|
|
04/12/2016
|
10/12/2017
|
100
|
|
|
|
|
609
|
RIDP(CBC)/C-W264 419873025
|
(A) Improvement of Satbaria-Chowkori-Mannara-Bayra-Sarfatuli-SejiaraShehor bazar road at ch.1635-3035m (B) protectionWorks at Ch.185m
|
RIDP-CBC
|
nangalkot
|
|
1.40
|
|
|
103.87
|
M/S Ma-Moni Enterprise
|
102.72
|
|
22/10/2017
|
28/10/2018
|
55
|
|
|
|
|
610
|
RIDP(CBC)/C-W265 419873026
|
(A) Improvement of Boxgonj-Barokali-Suvapur-Kabilakhali-Satbaria road at ch.5110-7345m (B) protectionWorks at Ch.635m
|
RIDP-CBC
|
nangalkot
|
|
2.24
|
|
|
181.33
|
M.M. Builders
|
166.55
|
|
03/10/2017
|
09/10/2018
|
10
|
|
|
|
|
611
|
RIDP(CBC)/C-W6 419874081
|
Improvement of Jeneyara-Masimpur road at ch. 1600-3249m.
|
RIDP-CBC
|
nangalkot
|
|
1.65
|
|
|
82.89
|
M/S Ma Moni Enterprise
|
81.72
|
|
09/04/2015
|
31/12/2015
|
100
|
|
|
|
|
612
|
RIDP(CBC)/C-SW12 419874204
|
Improvement of Kazi Jorpokuria-South para Mosque to North para Graveyard (Hazi Abdul Latif) Road at Ch. 00-600m
|
RIDP-CBC
|
nangalkot
|
|
0.60
|
|
|
29.06
|
M/S Meazi Enterprise
|
30.22
|
|
15/04/2015
|
31/12/2015
|
100
|
|
|
|
|
613
|
RIDP(CBC)/C-W71 419874028
|
Improvement of Nurpur-Kadoba Road at Ch. 00-1902m
|
RIDP-CBC
|
nangalkot
|
|
1.90
|
|
|
99.03
|
M/S Meksa & Co
|
96.94
|
|
27/07/2015
|
30/11/2016
|
100
|
|
|
|
|
614
|
RIDP(CBC)/C-W72 419874079
|
Improvement of Satbaria-Meherbagh via Topoban Road at Ch. 00-532m
|
RIDP-CBC
|
nangalkot
|
|
0.53
|
|
|
42.63
|
M/S Fatema Traders
|
38.38
|
|
21/07/2016
|
30/01/2018
|
100
|
|
|
|
|
615
|
RIDP(CBC)/C-W73 419874136
|
Improvement of Kharghar Primary School-Raykot Nutan Bazar Road at Ch. 00-1000m
|
RIDP-CBC
|
nangalkot
|
|
1.00
|
|
|
49.43
|
M/S Modina Construction
|
51.82
|
|
14/07/2015
|
30/06/2016
|
100
|
|
|
|
|
616
|
RIDP(CBC)/C-SW14 419874217
|
Improvement of Daulatpur-Laxmipadua Primary School Road at ch. 00-1650m
|
RIDP-CBC
|
nangalkot
|
|
1.65
|
|
|
79.89
|
M/S Rocky Auto House
|
78.06
|
|
13/09/2015
|
30/12/2016
|
100
|
|
|
|
|
617
|
RIDP(CBC)/C-W93 419874166
|
Improvement of Dhalua-Badarpur-Mannara-Kadamtali-Machimpur Matiagoda road at ch. 3010-4010m
|
RIDP-CBC
|
nangalkot
|
|
1.00
|
|
|
46.12
|
M/S Fatema Traders
|
40.31
|
|
04/11/2015
|
30/11/2016
|
100
|
|
|
|
|
618
|
RIDP(CBC)/C-W123 419874092
|
Improvement of Binoyghar-Chandia Bazar road Ch.3170-4270m
|
RIDP-CBC
|
nangalkot
|
|
1.10
|
|
|
50.89
|
M/S Arshad & Sons
|
50.13
|
|
28/02/2016
|
05/03/2017
|
100
|
|
|
|
|
619
|
RIDP(CBC)/C-W180 419874198
|
Improvement of Gopdua GC(Zame Mosque)-Baira Via Sarfatuli Prymary School road) at ch.00-1465m
|
RIDP-CBC
|
nangalkot
|
|
1.47
|
|
|
83.34
|
M/S Modina Construction
|
87.39
|
|
06/10/2016
|
12/10/2017
|
100
|
|
|
|
|
620
|
RIDP(CBC)/C-W198 419874093
|
Cnstruction of 2x4.00m RCC Box Culvert at ch.2050m.Over the canel on Puzkora-Tuguria road.
|
RIDP-CBC
|
nangalkot
|
|
|
|
|
15.73
|
M/S Arshad & sons
|
15.71
|
|
14/12/2016
|
20/08/2017
|
100
|
|
|
|
|
621
|
RIDP(CBC)/C-SW31. 419875033
|
Improvement Of Noapara Kashembari-Edrish bari road Ch.00-377m
|
RIDP-CBC
|
nangalkot
|
|
0.38
|
|
|
31.10
|
M/S Meazi Enterprise
|
31.04
|
|
15/02/2017
|
28/02/2018
|
100
|
|
|
|
|
622
|
RIDP(CBC)/C-W281 419874078
|
Re-Construction of 2x3.00x3.60m RCC Culvert on Shaktali-Chadia Bazar road ch.1350m
|
RIDP-CBC
|
nangalkot
|
|
|
|
|
29.08
|
M/S A.K Traders
|
29.07
|
|
14/01/2017
|
20/07/2018
|
100
|
|
|
|
|
623
|
RIDP(CBC)/C-W182 419874099
|
Improvement of Tulagaon- Baro Fulgaon road) at ch.600-1795m
|
RIDP-CBC
|
nangalkot
|
|
1.20
|
|
|
65.16
|
M/S Chowdory Trade Corporation
|
59.36
|
|
21/08/2016
|
30/06/2018
|
100
|
|
|
|
|
624
|
RIDP(CBC)/C-W172 419874011
|
Improvement of Razapara-Shaktili road at ch.00- 700m
|
RIDP-CBC
|
nangalkot
|
|
0.70
|
|
|
35.16
|
M/S Chowdory trade Corporation
|
31.99
|
|
11/07/2016
|
30/10/2017
|
70
|
|
|
|
|
625
|
RIDP(CBC)/C-W181 419874023
419875016
|
Improvement of (A) Mannara-Mokimpur (Mokimpur-Mannara-bashudai) road ch.00-500m
(B) Narayankot Rahim Mollah bari to Narayankot Govt.pry. School Road at Ch.00-750m
|
RIDP-CBC
|
nangalkot
|
|
1.25
|
|
|
71.84
|
M/S Chowdory Trade Corporation
|
65.44
|
|
21/08/2016
|
30/05/2018
|
70
|
|
|
|
|
626
|
RIDP(CBC)/C-W207 419874166
|
Improvement Of Dhalua-Badarpur-Mannara-Kadamtali-Machimpur Matiagoda road at ch. 4010-4925m
|
RIDP-CBC
|
nangalkot
|
|
0.92
|
|
|
48.01
|
M/S Razu Enterprise
|
47.96
|
|
20/02/2017
|
20/08/2018
|
60
|
|
|
|
|
627
|
RIDP(CBC)/C-W215 419874005
|
(A) Improvement Of Shahpur-Tua-Heshakhal road ch.1070-1870m
(B) Improvement Of Makrabpur-Heshakhal road Ch.00-500m
|
RIDP-CBC
|
nangalkot
|
|
1.30
|
|
|
72.67
|
M/S Meazi Enterprise
|
72.50
|
|
28/02/2017
|
06/03/2018
|
60
|
|
|
|
|
628
|
RIDP(CBC)/C-W263 419874079
|
Improvement Of Satbaria-Meherbag via Tapoban road ch.532-1657m
|
RIDP-CBC
|
nangalkot
|
|
1.13
|
|
|
66.85
|
M/S Alvee trading Corporation
|
69.79
|
|
31/07/2017
|
06/08/2018
|
10
|
|
|
|
|
629
|
RIDP(CBC)/C-RM15
|
Improvement of Chadia Bazar
|
RIDP-CBC
|
nangalkot
|
|
|
|
|
28.21
|
M/S A.K Traders
|
29.62
|
|
20/02/2018
|
26/10/2018
|
85
|
|
|
|
|
630
|
RIDP(CBC)/C-M20 419892003
|
Maintenance of Goripur-Ziarkandi-Bakrabad(Muradnagar) road at ch. 00-1200m.
|
RIDP-CBC
|
titas
|
|
1.20
|
|
|
21.79
|
M/S Labonna Construction
|
20.37
|
|
01/07/2015
|
07/06/2015
|
100
|
|
|
|
|
631
|
RIDP(CBC)/C-SM3 419893006
|
Maintenance of Shibpur-Shahpur Lalpur bazar road at Ch 2429-3900m
|
RIDP-CBC
|
titas
|
|
1.47
|
|
|
42.31
|
M/S Badsha Enterprise
|
40.10
|
|
20/06/2016
|
16/06/2016
|
100
|
|
|
|
|
632
|
RIDP(CBC)/C-M63 419893018
|
Maintenance of Darikandi-Naraondia UP Office (Asmania) Via Gopalpur Bazar-Bagairampur road at Ch 1700-3053m
|
RIDP-CBC
|
titas
|
|
1.35
|
|
|
29.40
|
M/S E.F Trade International
|
27.05
|
|
27/08/2016
|
08/05/2016
|
100
|
|
|
|
|
633
|
RIDP(CBC)/C-M64 419893003
|
Maintenance of Ziarkandi-Solakandi -Lalpur road at Ch 00-1500m
|
RIDP-CBC
|
titas
|
|
1.50
|
|
|
41.78
|
M/S Azmin Construction
|
37.92
|
|
30/12/2016
|
26/12/2016
|
100
|
|
|
|
|
634
|
RIDP(CBC)/C-M90 419894014
|
Maintenance (Rehabilition) of Machimpur GC- Basania Bazar Road at Ch. 00-1281m .
|
RIDP-CBC
|
titas
|
|
1.28
|
|
|
39.54
|
M/S Jobaid Enterprise
|
39.34
|
|
20/05/2017
|
04/05/2017
|
100
|
|
|
|
|
635
|
RIDP(CBC)/C-W80 419893007
|
Improvement of Korikandi UP(Bandarampur)-Narandia UP (Asmania Bazar) road at Ch. 1340-2300m
|
RIDP-CBC
|
titas
|
|
0.96
|
|
|
56.77
|
M/S Islam Trading
|
53.38
|
|
16/09/2015
|
30/05/2017
|
100
|
|
|
|
|
636
|
RIDP(CBC)/C-W87 419893012
|
Improvement of Salikandi bazar-Raghunathpur-Khalilabad-Asmania road at ch. 1100-1800m under Titas upazila, Comilla.
|
RIDP-CBC
|
titas
|
|
0.70
|
|
|
40.14
|
M/S Badon Traders
|
36.63
|
|
02/11/2015
|
30/04/2018
|
100
|
|
|
|
|
637
|
RIDP(CBC)/C-W231 419893013
|
Improvement Of Batakandi-Raipur GCCR-Kadamtoli-Bhitikandi UP Office road ch.300-1300m
|
RIDP-CBC
|
titas
|
|
1.00
|
|
|
61.53
|
M/S Bites & Bites
|
61.50
|
|
25/04/2017
|
31/12/2018
|
60
|
|
|
|
|
638
|
RIDP(CBC)/C-BW11 419893002
|
Construction of 51m Girder Bridge Bhitikandi UP office (Dularampur Bazar) Panchpukuria GC road.at Ch-6000m
|
RIDP-CBC
|
titas
|
|
|
|
|
269.15
|
M/S Hamim & Brothers
|
269.09
|
|
17/09/2017
|
03/12/2018
|
40
|
|
|
|
|
639
|
RIDP(CBC)/C-W79 419894001
|
Improvement of Karikandi-Monairkandi road at ch. 00-1200m
|
RIDP-CBC
|
titas
|
|
1.20
|
|
|
71.49
|
M/S. Rafiq Traders
|
74.68
|
|
17/09/2015
|
30/03/2017
|
100
|
|
|
|
|
640
|
RIDP(CBC)/C-W81 419894027
|
Improvement of Karikandi-Shahabuddin-Mojidpur road at ch. 00-400m
|
RIDP-CBC
|
titas
|
|
0.40
|
|
|
23.76
|
M/s Labanna constraction
|
21.69
|
|
09/09/2015
|
15/03/2016
|
100
|
|
|
|
|
641
|
RIDP(CBC)/C-SW17 419895016
|
Improvement of Lalkpur Eidgha-Baharchar (Lalpur bazar Eidgha math of Baterchar Gudaraghat Daudkandi via Choker bari road) road at ch. 00-1000m
|
RIDP-CBC
|
titas
|
|
1.00
|
|
|
40.18
|
M/S Meer Rafikul Islam
|
40.18
|
|
14/10/2015
|
30/05/2017
|
100
|
|
|
|
|
642
|
RIDP(CBC)/C-W88 419895035
|
Improvement of Batakandi-Raypur road to Naranpur Masjid-Morsheda Bari via Karim Sarker Bari road at ch. 00-400m
|
RIDP-CBC
|
titas
|
|
0.40
|
|
|
21.33
|
M/S. Labonna Construction
|
19.41
|
|
09/09/2015
|
30/05/2016
|
100
|
|
|
|
|
643
|
RIDP(CBC)/C-W152 419895031
|
Improvement of Batakandi-Raypur road road at Beparibari-Ratonpur Eidgah field Via Ratonpur Bhuyan bari Govt.Pry.School & 6No Vitikandi Uninon health Complex road ch. 00-425m
|
RIDP-CBC
|
titas
|
|
0.43
|
|
|
33.74
|
M/S Munshi Enterprise
|
33.15
|
|
08/05/2016
|
30/06/2017
|
100
|
|
|
|
|
644
|
RIDP(CBC)/C-W257 419894005
|
Improvement Of Moutupi-Yousufpur road ch.1600-1950m
|
RIDP-CBC
|
titas
|
|
0.35
|
|
|
26.12
|
M/S Shakil Enterprise
|
26.12
|
|
04/06/2017
|
10/02/2018
|
100
|
|
|
|
|
645
|
RIDP(CBC)/C-W179 419895017
|
Improvement of Karikandi Engineer Md. Abul Kashem Bhuiyan (Gowripur-Homna road -Karikandi Govt.Pry.School road) by BC at ch.00-715m
|
RIDP-CBC
|
titas
|
|
0.72
|
|
|
55.54
|
M/S Shahin Enterprise
|
53.60
|
|
09/10/2016
|
30/11/2018
|
100
|
|
|
|
|
646
|
RIDP(CBC)/C-BW10 419894003
|
Construction of 22m Girder Bridge Ziarkandi-Solakandi-Lalpur road.at Ch-2500m
|
RIDP-CBC
|
titas
|
|
|
|
|
138.87
|
M/S Priyanka Enterprise
|
138.78
|
|
20/09/2017
|
03/12/2018
|
40
|
|
|
|
|
647
|
RIDP(MU)/W 1 ID 419813023
|
Improvement of Companigong-Jahapur-Dailarchar Hizbullah Complex Road at ch.9615-15615m.(Tender ID No: 117196)
|
RIDPMUCD
|
muradnagar
|
|
6.00
|
|
|
364.51
|
M/s Noona Traders
|
362.00
|
|
19/12/2017
|
25/12/2018
|
40
|
|
|
|
|
648
|
RIDP(MU)/W 5 ID 419813018
|
Improvement of Khurril Bazar Shidiswary Bazar Darora UP Darora Bazar Raitola Road at ch.4800-7800m.(Tender ID No:121615)
|
RIDPMUCD
|
muradnagar
|
|
3.00
|
|
|
182.07
|
M/s Kamal Uddin
|
187.34
|
|
11/02/2018
|
17/02/2019
|
70
|
|
|
|
|
649
|
RIDP(MU)/W 18 ID 419813030
|
Construction of Karimpur R&H- Gash Fild Road via Domoria-Alirchar Collage Road 4814mChainge 42.00m Long RCC Girder Bridge (Tender ID No: 179343)
|
RIDPMUCD
|
muradnagar
|
|
|
|
|
217.68
|
M/s Zaima Enterprise
|
226.39
|
|
17/05/2018
|
23/05/2019
|
0
|
|
|
|
|
650
|
RIDP(MU)/W 2 ID 419814039
|
Improvement of Gazipur-Kaligong Road at ch.1500-2500m. (Tender ID No: 117197)
|
RIDPMUCD
|
muradnagar
|
|
1.00
|
|
|
57.59
|
M/s Nero & Brothers
|
60.41
|
|
06/11/2017
|
12/11/2018
|
70
|
|
|
|
|
651
|
RIDP(MU)/W 3 ID 419815144
|
Improvement of Paiyapathar Jiban Miah via Kamal Chairman house Road at ch.38-895m. (Tender ID No: 117198)
|
RIDPMUCD
|
muradnagar
|
|
0.86
|
|
|
52.14
|
M/s Kamal Uddin
|
54.26
|
|
30/10/2017
|
05/11/2018
|
70
|
|
|
|
|
652
|
RIDP(MU)/W 4 ID 419815132
|
Improvement of Songchail LGED Steel Bridge to Joynagar village Road at ch.00-750m. (Tender ID No: 117199)
|
RIDPMUCD
|
muradnagar
|
|
0.75
|
|
|
44.71
|
M/s Bhuiyan & Brothers
|
46.60
|
|
02/11/2017
|
08/07/2018
|
70
|
|
|
|
|
653
|
RIDP(MU)/W6 ID 419814046
|
Improvement of Jatrapur-Algi Road at ch.400-1400m. (Tender ID No: 121616)
|
RIDPMUCD
|
muradnagar
|
|
1.00
|
|
|
66.60
|
Md Delwar Hossan Babol
|
64.59
|
|
26/12/2017
|
01/01/2019
|
70
|
|
|
|
|
654
|
RIDP(MU)/W 7 ID 419814117
|
Improvement of Kagatua Bazar Choumuhoni Graveyard via Kagatua Mosque & Pry School Road at ch.00-1100m. (Tender ID No: 121617)
|
RIDPMUCD
|
muradnagar
|
|
1.10
|
|
|
71.09
|
Md Delwar Hossan Babol
|
68.94
|
|
28/12/2017
|
03/01/2019
|
70
|
|
|
|
|
655
|
RIDP(MU)/W 8 ID 419815158
|
Improvement of Jatrapur-Ragurampur Road at ch.00-1000m. (Tender ID No: 121618)
|
RIDPMUCD
|
muradnagar
|
|
1.00
|
|
|
63.81
|
M/s Bhuiyan & Brothers
|
63.73
|
|
20/12/2017
|
26/12/2018
|
15
|
|
|
|
|
656
|
RIDP(MU)/W 9 ID 419814024
|
Improvement of Burarchar Putiazuri Road at ch.100-1000m. (Tender ID No: 121619)
|
RIDPMUCD
|
muradnagar
|
|
0.90
|
|
|
64.66
|
M/s Rafiq Traders
|
63.45
|
|
04/01/2018
|
10/01/2019
|
100
|
|
|
|
|
657
|
RIDP(MU)/W 10 ID 419815138
|
Improvement of Chapitola RHD Road to Farid Uddin Degree College road via Chapitola Fishery & Hatchery LTD. Road at ch.00-1000m. (Tender ID No: 169255)
|
RIDPMUCD
|
muradnagar
|
|
1.00
|
|
|
68.67
|
M/s Nero & Brothers
|
67.86
|
|
24/04/2018
|
01/01/2019
|
30
|
|
|
|
|
658
|
RIDP(MU)/W 12 ID 419814001
|
Improvement of Nayamatkandi-Melamchar Sublarchar Road at ch.00-1000m. (Tender ID No: 133825)
|
RIDPMUCD
|
muradnagar
|
|
1.00
|
|
|
74.61
|
M/s Rafiq Traders
|
70.43
|
|
01/02/2018
|
31/01/2019
|
100
|
|
|
|
|
659
|
RIDP(MU)/W 13 ID 419814053
|
Improvement of Companigonj Bazar to Alirchar Gumati Embankbent cum Road at ch.00-4000m. (Tender ID No: 133822)
|
RIDPMUCD
|
muradnagar
|
|
4.00
|
|
|
254.90
|
M/s Kamal Uddin
|
236.87
|
|
28/01/2018
|
03/02/2019
|
70
|
|
|
|
|
660
|
RIDP(MU)/W 14 ID 419814122
|
Improvement of Chaliakandi Bazar-Kaziatala Hassan Market Road at ch.700-1715m. (Tender ID No: 133824)
|
RIDPMUCD
|
muradnagar
|
|
1.02
|
|
|
74.39
|
M/s Rafiq Traders
|
70.21
|
|
01/02/2018
|
31/01/2019
|
100
|
|
|
|
|
661
|
RIDP(MU)/W 15 ID 419814031
|
Improvement of Bakharnagar C&B Charubari Road at ch.00-1000m. (Tender ID No: 133825 )
|
RIDPMUCD
|
muradnagar
|
|
1.00
|
|
|
78.22
|
M/s Priyanka Enterprise
|
73.84
|
|
01/02/2018
|
07/02/2019
|
70
|
|
|
|
|
662
|
RIDP(MU)/W 16 ID 419814084
|
Rehabilitation of Bhutail Hatkhola Bazar Road (west side) at ch.00-1110m. (Tender ID No: 149603)
|
RIDPMUCD
|
muradnagar
|
|
1.11
|
|
|
57.90
|
M/s Naium Enterprise
|
60.75
|
|
21/03/2018
|
27/11/2018
|
0
|
|
|
|
|
663
|
RIDP(MU)/W 17 ID 419814093
|
Improvement of Dhanapatikhola RHD-Roachala Road at ch.1060-4200m. (Tender ID No: 133825 )
|
RIDPMUCD
|
muradnagar
|
|
3.14
|
|
|
174.42
|
M/s Kamal Uddin
|
190.95
|
|
14/08/2018
|
20/08/2019
|
0
|
|
|
|
|
664
|
RIDP(MU)/W 19 ID 419814093
|
Construction of Dhanapatikhola RHD-Roachala Road 4120m Chainage 39.00m Long RCC Girder Bridge (Tender ID No:155660)
|
RIDPMUCD
|
muradnagar
|
|
|
|
|
151.57
|
M/s Kamal Uddin
|
151.30
|
|
27/03/2018
|
02/04/2019
|
0
|
|
|
|
|
665
|
RTIP-II/COM/UNR-6
|
b) Paranpur Bazar[ R&H]-Payelgacha UP office Road
|
RTIP-2
|
barura
|
|
5.77
|
|
|
381.17
|
|
0.00
|
|
22/07/2014
|
20/03/2016
|
100
|
|
|
|
|
666
|
RTIP-II/COM/RPM-133
|
Chitoshiy Rly. Station-Barura via Janora road
|
RTIP-2
|
barura
|
|
20.75
|
|
|
415.40
|
M/S. Ananta Enterprise
|
463.44
|
|
30/03/2014
|
18/05/2015
|
100
|
|
|
|
|
667
|
RTIP-II/COM/RPM-193
|
a) Barura (Talagram)-Adda GC Road.
|
RTIP-2
|
barura
|
|
3.50
|
|
|
157.83
|
M/S. R-TA Enterprise
|
136.61
|
|
15/07/2015
|
28/02/2017
|
100
|
|
|
|
|
668
|
RTIP-II/COM/RPM-281
|
Barura-Singur road via Mohitpur.
|
RTIP-2
|
barura
|
|
6.71
|
|
|
321.13
|
M/S. Zaman Traders
|
321.11
|
|
13/09/2017
|
30/01/2018
|
100
|
|
|
|
|
669
|
RTIP-II/COM/RPM-390
|
Baichapukuria-Adda Bazar-Kachua Road
|
RTIP-2
|
barura
|
|
17.92
|
|
|
981.57
|
M/S. Zaman Traders
|
1028.90
|
|
06/02/2017
|
30/07/2017
|
100
|
|
|
|
|
670
|
RTIP-II/COM/RPM-50.1
|
Comilla-Fakir bazar-Salda Nodi
|
RTIP-2
|
brahmanpara
|
|
6.40
|
|
|
261.88
|
M/S. MA Zaher
|
248.26
|
|
12/08/2013
|
28/12/2014
|
100
|
|
|
|
|
671
|
RTIP-II/COM/RPM-156
|
b) Brahmanpara-Dulalpur GC road
|
RTIP-2
|
brahmanpara
|
|
5.07
|
|
|
110.79
|
|
0.00
|
|
18/01/2014
|
05/05/2016
|
100
|
|
|
|
|
672
|
RTIP-II/COM/RPM-188
|
a) Shahebabad UP Office [R&H]-Ramnagar bazar road
|
RTIP-2
|
brahmanpara
|
|
6.29
|
|
|
231.61
|
Pioneer Construction
|
513.46
|
|
13/07/2015
|
28/02/2017
|
100
|
|
|
|
|
673
|
RTIP-II/COM/UZR-53
|
Abidpur GC-Debpur bazar (Gakkhur) RHW Road.
|
RTIP-2
|
burichong
|
|
2.44
|
|
|
264.77
|
Pioneer Construction & M/S Ha-Mim & Brothers JV, [(PC & HB (JV)]
|
281.80
|
|
24/02/2016
|
30/06/2018
|
100
|
|
|
|
|
674
|
RTIP-II/COM/UNR-7
|
a) Mokam UP Office-Abidpur Bazar via Mitholma road
|
RTIP-2
|
burichong
|
|
3.70
|
|
|
266.71
|
M/S. R-TA Enterprise & M/S. Air Ahamed Salim [R-TA Enterprise & AAS (JV)]
|
706.62
|
|
21/05/2014
|
28/03/2016
|
100
|
|
|
|
|
675
|
RTIP-II/COM/RPM-50.2
|
Burichang UP office -Anandapur via Bakshimul UP Office
|
RTIP-2
|
burichong
|
|
7.10
|
|
|
75.43
|
M/S Islam Brothers
|
87.43
|
|
07/09/2013
|
13/11/2014
|
100
|
|
|
|
|
676
|
RTIP-II/COM/RPM-156
|
a) Burichang GC- Kangshanagar bazar GC road
|
RTIP-2
|
burichong
|
|
4.12
|
|
|
178.95
|
M/S. Tanvir Traders
|
182.47
|
|
18/01/2014
|
05/05/2016
|
100
|
|
|
|
|
677
|
RTIP-II/COM/RPM-189
|
Comilla-Fakir Bazar-Saldanadi Rd
|
RTIP-2
|
burichong
|
|
11.04
|
|
|
717.74
|
Pioneer Construction & M/S. R-TA Enterprise JV, [(R-TA Enterprise & PC (JV)]
|
760.46
|
|
15/06/2016
|
30/06/2018
|
77
|
|
|
|
|
678
|
RTIP-II/COM/RPM-282
|
Rajapur UP Office-Pachara BazarCharanal Road.
|
RTIP-2
|
burichong
|
|
3.20
|
|
|
86.67
|
M/S. Rasal Ahamed Mozumder
|
87.19
|
|
28/08/2016
|
23/01/2017
|
100
|
|
|
|
|
679
|
RTIP-II/COM/RPM-52
|
Kutumbapur-Kaliarchar Bazar
|
RTIP-2
|
chandina
|
|
11.44
|
|
|
317.30
|
Joint Venture of M/S. Mynamoti Builders & M/S. R-TA Enterprise
{MMB & MRE (JV)}
|
345.79
|
|
31/03/2013
|
15/11/2014
|
100
|
|
|
|
|
680
|
RTIP-II/COM/RPM-128
|
Madhaiya-Dollai Nowabpur-Rahimanagar road
|
RTIP-2
|
chandina
|
|
20.70
|
|
|
663.64
|
JV of M/S. Dhiman Construction & M/S. Islam Traders (MDC-MIT JV)
|
697.96
|
|
30/04/2014
|
30/12/2016
|
100
|
|
|
|
|
681
|
RTIP-II/COM/GCM-4
|
a) Improvement of Badarpur GCM
|
RTIP-2
|
chandina
|
|
2.00
|
|
|
84.82
|
M/S. M. M. Enterprise
|
160.31
|
|
14/01/2015
|
29/06/2016
|
100
|
|
|
|
|
682
|
RTIP-II/COM/UZR-6
|
Upazila H/Q (Nabagram)-Munshirhat-Kashinagar UP-Suagonj(Isshor Mazumder) Road (Bir Muktizhodha Md. Mujibul Haque Road)
|
RTIP-2
|
chouddagram
|
|
5.02
|
|
|
1232.96
|
M/S. Noona Traders & M/S. Air Ahamed Salim [(NT & AAS(JV)]
|
1294.14
|
|
30/11/2016
|
29/03/2018
|
44
|
|
|
|
|
683
|
RTIP-II/COM/UNR-7
|
c) Gunabati UP Office (bazar)-Choudhuri bazar (Sukshail) road.
|
RTIP-2
|
chouddagram
|
|
4.65
|
|
|
332.15
|
|
0.00
|
|
21/05/2014
|
28/03/2016
|
100
|
|
|
|
|
684
|
RTIP-II/COM/RPM-129
|
b) Atogram-Sharifpur (Bibir) road
|
RTIP-2
|
chouddagram
|
|
6.06
|
|
|
208.55
|
|
0.00
|
|
26/01/2014
|
28/03/2015
|
100
|
|
|
|
|
685
|
RTIP-II/COM/PBMC-2.1
|
Rajabazar-Alkara (Shah Fakruddin Road)
|
RTIP-2
|
chouddagram
|
|
33.72
|
|
|
772.83
|
M/S Abul Hasem
|
942.81
|
|
21/05/2014
|
14/05/2019
|
100
|
|
|
|
|
686
|
RTIP-II/COM/PBMC-2.2
|
Upazila H/Q (Nabagram)-Munshirhat-Kashinagar UP-Suagonj (Isshor Mazumder) Road
|
RTIP-2
|
chouddagram
|
|
16.49
|
|
|
460.78
|
M/S Mazumder Traders
|
557.41
|
|
11/05/2014
|
11/05/2019
|
100
|
|
|
|
|
687
|
RTIP-II/COM/RPM-190
|
Safua NHW- Nalgar Bazar-Chowmuhany Madina bazar via Sreepur UP Office (Padua) Road
|
RTIP-2
|
chouddagram
|
|
9.45
|
|
|
366.31
|
M/S Mazumder Traders
|
376.10
|
|
23/07/2015
|
20/07/2016
|
100
|
|
|
|
|
688
|
RTIP-II/COM/RPM-131
|
Shahapur Mazar sharif (Golabari Zero point)-Chandpur bridge-Palpara road (WDB embankment)
|
RTIP-2
|
cumilla-s
|
|
12.00
|
|
|
160.99
|
R-TA & MME (JV)
|
183.59
|
|
02/02/2014
|
10/02/2015
|
100
|
|
|
|
|
689
|
RTIP-II/COM/GCM-4
|
b) Improvement of Kalir Bazar GCM
|
RTIP-2
|
cumilla-s
|
|
2.00
|
|
|
56.00
|
|
0.00
|
|
14/01/2015
|
29/06/2016
|
100
|
|
|
|
|
690
|
RTIP-II/COM/RPM-188
|
b) Comilla (Chandpur Bridge)-Fakir Bazar-Saldanadinadi-Bagra bazar sadar part (B.Para)Rd.
|
RTIP-2
|
cumilla-s
|
|
6.45
|
|
|
333.47
|
|
0.00
|
|
13/07/2015
|
28/02/2017
|
100
|
|
|
|
|
691
|
RTIP-II/COM/RPM-283
|
Balutupa-Khaish GC-Suagonj-Pipulia-Dakhin Bijoypur-Adinamura-Bataichari (Barura) Road. (Sadar Part)
|
RTIP-2
|
cumilla-s
|
|
4.65
|
|
|
156.65
|
M/S. Ha-Mim & Brothers
|
165.10
|
|
28/08/2016
|
27/08/2017
|
100
|
|
|
|
|
692
|
RTIP-II/COM/RPM-132
|
Gonti-Metalla road
|
RTIP-2
|
cumilla-s daksin
|
|
8.73
|
|
|
192.86
|
M/S. Zaman Traders
|
217.58
|
|
26/02/2014
|
22/11/2014
|
100
|
|
|
|
|
693
|
RTIP-II/COM/RPM-191
|
a) Pipulia-Hazatkhala-Bagmara Rd
|
RTIP-2
|
cumilla-s daksin
|
|
8.05
|
|
|
317.22
|
M/S. Zaman Traders
|
477.38
|
|
19/05/2015
|
15/11/2015
|
100
|
|
|
|
|
694
|
RTIP-II/COM/RPM-284
|
Balutupa-Khaish GC-Suagonj-Pipulia-Dakhin Bijoypur-Adinamura-Bataichari (Barura) Road.
|
RTIP-2
|
cumilla-s daksin
|
|
6.80
|
|
|
498.33
|
M/S. Zaman Traders
|
507.27
|
|
14/06/2016
|
17/07/2016
|
100
|
|
|
|
|
695
|
RTIP-II/COM/UNR-8
|
Dakshin Elliotganj UP Office (Elliotganj GC)-Mohamadpur Natunbazar via Kalasona bazar Road
|
RTIP-2
|
daudkandi
|
|
6.63
|
|
|
739.29
|
M/S. Jahan & Sons
|
838.82
|
|
09/02/2015
|
30/03/2018
|
100
|
|
|
|
|
696
|
RTIP-II/COM/UNR-8-STR-43
|
Construction of 18.00 m RCC Girder Bridge on Dakshin Elliotganj UP Office (Elliotganj GC)-Mohamadpur Natunbazar via Kalasona bazar Road at Ch. 2+300km
|
RTIP-2
|
daudkandi
|
|
|
|
|
261.94
|
M/S. Pioneer Construction & SF International, [(SF International (JVCA)]
|
242.82
|
|
24/04/2017
|
09/02/2018
|
24
|
|
|
|
|
697
|
RTIP-II/CUM/UNR-8-STR-43A
|
Remaining work of Construction of 18.00 m RCC Girder Bridge on Dakshin Elliotganj UP Office (Elliotganj GC)-Mohamadpur Natunbazar via Kalasona bazar Road at Ch. 2+300km
|
RTIP-2
|
daudkandi
|
|
18.00
|
|
|
244.40
|
M/S. Mazumder Traders
|
255.25
|
|
|
|
0
|
|
|
|
|
698
|
RTIP-II/COM/RPM-192
|
Barkota G.C.-Nayergaon bazar via Pitambardi bazar Road
|
RTIP-2
|
daudkandi
|
|
6.49
|
|
|
234.93
|
M/S. R-TA Enterprise
|
207.10
|
|
19/05/2015
|
30/01/2017
|
100
|
|
|
|
|
699
|
RTIP-II/COM/RPM-134
|
Madhaiya G.C.to Punchpokoria G.C (Debidwar Portion) road
|
RTIP-2
|
debidwar
|
|
8.30
|
|
|
187.30
|
M/S. R-TA Enterprise
|
211.98
|
|
19/02/2014
|
31/12/2015
|
100
|
|
|
|
|
700
|
RTIP-II/COM/RPM-129
|
a) Kararkandi-Asadpur-Chanderchar bazar road
|
RTIP-2
|
homna
|
|
3.67
|
|
|
90.71
|
MMB & AAS (JV)
|
316.58
|
|
26/01/2014
|
28/03/2015
|
100
|
|
|
|
|
701
|
RTIP-II/COM/RPM-191
|
b) Homna-Sreemoddi Road.
|
RTIP-2
|
homna
|
|
4.55
|
|
|
147.11
|
|
0.00
|
|
19/05/2015
|
15/11/2015
|
100
|
|
|
|
|
702
|
RTIP-II/COM/UNR-6
|
a) Bizra-Laksam Rd.
|
RTIP-2
|
laksham
|
|
2.69
|
|
|
184.08
|
Pioneer Construction & M/S. Air Ahamed Salim JVCA (Pioneer & Air Ahamed Salim JV)
|
899.98
|
|
22/07/2014
|
20/03/2016
|
100
|
|
|
|
|
703
|
RTIP-II/COM/RPM-51
|
Laksam-Monohargonj
|
RTIP-2
|
laksham
|
|
6.40
|
|
|
160.83
|
M/S. R-TA Enterprise
|
174.40
|
|
31/03/2013
|
29/05/2014
|
100
|
|
|
|
|
704
|
RTIP-II/COM/RPM-285
|
Laksam-Modaffergonj
|
RTIP-2
|
laksham
|
|
5.28
|
|
|
212.23
|
M/S. Zaman Traders
|
219.76
|
|
27/07/2016
|
29/12/2016
|
100
|
|
|
|
|
705
|
RTIP-II/COM/UZR-57
|
Monohorgonj GC -Laksmanpur- Bipulasar R&H Rd.
|
RTIP-2
|
monohorganj
|
|
6.41
|
|
|
946.16
|
Mohammed Eunus & Brothers (Pvt.) Ltd.,
|
946.30
|
|
06/03/2016
|
14/01/2019
|
90
|
|
|
|
|
706
|
RTIP-II/COM/RPM-127
|
a) Monohorgonj - Laksam road
|
RTIP-2
|
monohorganj
|
|
4.75
|
|
|
112.93
|
M/S. Zaman Traders
|
374.52
|
|
09/02/2014
|
26/03/2015
|
100
|
|
|
|
|
707
|
RTIP-II/COM/RPM-151
|
Natherpetua-Hasnabad road
|
RTIP-2
|
monohorganj
|
|
17.31
|
|
|
489.59
|
M/S. Zaman Traders
|
528.97
|
|
07/12/2013
|
24/08/2014
|
100
|
|
|
|
|
708
|
RTIP-II/COM/UNR-9
|
Kurbanpur-Kaligonj Rd.
|
RTIP-2
|
muradnagar
|
|
8.00
|
|
|
965.97
|
Rana Builders (Pvt.) Ltd. & M/S. Kamal Uddin [RBL-KU (JV)]
|
1146.22
|
|
07/01/2015
|
30/06/2017
|
100
|
|
|
|
|
709
|
RTIP-II/COM/UNR-6
|
c) Adra-Volainbazar-Chatitala-Ghoramaidan-Manikmura Road.
|
RTIP-2
|
nangalkot
|
|
1.95
|
|
|
196.02
|
|
0.00
|
|
22/07/2014
|
20/03/2016
|
100
|
|
|
|
|
710
|
RTIP-II/COM/RPM-127
|
b) Boxganj-Satbaria-Gunbati road
|
RTIP-2
|
nangalkot
|
|
5.61
|
|
|
231.09
|
|
0.00
|
|
09/02/2014
|
26/03/2015
|
100
|
|
|
|
|
711
|
RTIP-II/COM/RPM-194
|
Nangalkot-Doulkhar-Boxganj Rd.
|
RTIP-2
|
nangalkot
|
|
14.21
|
|
|
589.39
|
Pioneer Construction & M/S. R-TA Enterprise (R-TA Enterprise & PC (JV)
|
602.96
|
|
19/05/2015
|
12/07/2016
|
100
|
|
|
|
|
712
|
RTIP-II/COM/RPM-286
|
Mahini-Boxganj Rd.
|
RTIP-2
|
nangalkot
|
|
13.50
|
|
|
1025.81
|
R-TA Enterprise & BB (JV)
|
1076.75
|
|
23/07/2016
|
30/12/2017
|
100
|
|
|
|
|
713
|
RTIP-II/COM/RJ-6
|
Batikandi Ghat
|
RTIP-2
|
titas
|
|
1.00
|
|
|
170.17
|
M/S. Noona Traders
|
168.66
|
|
21/08/2016
|
30/03/2018
|
91
|
|
|
|
|
714
|
RTIP-II/COM/RJ-16
|
Puran Batakandi Ghat
|
RTIP-2
|
titas
|
|
1.00
|
|
|
166.52
|
M/S. Mazumder Traders
|
174.56
|
|
19/06/2016
|
30/12/2018
|
95
|
|
|
|
|
715
|
RTIP-II/COM/RWT-01
|
Dredging work and installation of navigational aid in Titas river from Kathalia to Machimpur via Batakandi
|
RTIP-2
|
titas
|
|
11.30
|
|
|
1385.11
|
JV of Asian Dredgers Limited & M/S. Liberty Traders [ADL-MLT (JV)]
|
875.01
|
|
03/03/2015
|
30/10/2016
|
100
|
|
|
|
|
716
|
RIDP (SD NK-2) SD-W-03
|
Improvement of Durlabpur -Sreekamta-Lulbaria-Paran pur Road at Ch- 1000-2300m. (Road ID 419914080) (Tender ID No: 74051 & 79778)
|
SDNK-2
|
cumilla-s daksin
|
|
1.30
|
|
|
65.46
|
M/S Shobuj & Brothers
|
68.07
|
|
|
|
100
|
|
|
|
|
717
|
RIDP (SD NK-2) SD-W-04
|
Improvement of Perul-Hapaniea Road at Ch- 00-1250m. (Road ID 419914032) (Tender ID No: 74052 & 79779
|
SDNK-2
|
cumilla-s daksin
|
|
1.25
|
|
|
62.58
|
M/S Zamam Traders
|
64.89
|
|
03/02/2017
|
|
100
|
|
|
|
|
718
|
RIDP (SD NK-2) SD-W-05
|
Improvement of (A) B . Baria -Mohammadpur-Olir Bazar Road at Ch- 700 -1005m. (Road ID 419914073) (B) Dalatpur -Rahman Bari to Katalia Via Halodia Madrasha Road at Ch 615-1650m (Tender ID No: 74053 & 79780)
|
SDNK-2
|
cumilla-s daksin
|
|
1.34
|
|
|
69.94
|
M/S Zamam Traders
|
73.44
|
|
03/02/2017
|
|
100
|
|
|
|
|
719
|
RIDP (SD NK-2) SD-W-16
|
Improvement of (A) Hadgora-Borotul Road at Ch 4200-4490m (ID-419914036) (B) Bijoypur Mahila Collage-Gangkul-Rangamura Road at Ch: 00-1000m. (ID No-419915031) (Tender ID No: 81490 & 92382)
|
SDNK-2
|
cumilla-s daksin
|
|
1.29
|
|
|
79.53
|
M/S Muntaha Construction
|
73.68
|
|
|
30/05/2018
|
100
|
|
|
|
|
720
|
RIDP (SD NK-2) SD-W-23
|
Construction of 36.00m Long RCC Girder Bridge on Jaynagar-Vabokpara Road Over Dakatia River at Ch 1950m (ID-419915071) (Tender ID No: 99551)
|
SDNK-2
|
cumilla-s daksin
|
|
|
|
|
215.28
|
Hassan - Zaman Traders (JV)
|
215.00
|
|
08/03/2017
|
|
80
|
|
|
|
|
721
|
RIDP (SD NK-2) SD-W-24
|
Construction of 40.00m Long RCC Girder Bridge on Sanecho-Nurpur Road Over Dakatia River at Ch 1100m (ID-419914038) (Tender ID No: 99552)
|
SDNK-2
|
cumilla-s daksin
|
|
|
|
|
221.81
|
M/S Chowdhury Traders
|
209.62
|
|
|
27/11/2018
|
14
|
|
|
|
|
722
|
RIDP (SD NK-2) SD-W-25
|
Construction of 48.00m Long RCC Girder Bridge on Bagmara-Raipur-Hazatkhola Road Over Dakatia River at Ch 3100m (ID-41994009) (Tender ID No: 99553)
|
SDNK-2
|
cumilla-s daksin
|
|
|
|
|
237.27
|
MAS & PC (JV)
|
237.23
|
|
|
|
18
|
|
|
|
|
723
|
RIDP (SD NK-2) SD-W-26
|
Improvement of Comilla -Chandpur RHD Road - Boro Durgapur Road at Ch : 00-950m (ID-419914070) (Tender ID No: 117200)
|
SDNK-2
|
cumilla-s daksin
|
|
0.95
|
|
|
52.45
|
M/S Farhana Builders
|
54.99
|
|
|
|
100
|
|
|
|
|
724
|
RIDP (SD NK-2) SD-W-27
|
Improvement of Bhagolpur- Jolai-Banipur Road (Old Dhaka Chittagong Road -Dhulipara-Bagalpur) Road at Ch 00-1545m (ID-419914034) (Tender ID No: 117201)
|
SDNK-2
|
cumilla-s daksin
|
|
1.55
|
|
|
97.73
|
M/S M. H. Bablu
|
97.25
|
|
11/12/2017
|
18/11/2018
|
90
|
|
|
|
|
725
|
RIDP (SD NK-2) SD-W-28
|
Improvement of Hossainpur-Sananda-Army Road at Ch 1200-1470m & 1570-2320m (ID-419914096)
Improvement of Mathurapur-Goalgaon-Himmatpur Road at Ch 00-2225m (ID-419914096) (Tender ID : 178948 & 188279
|
SDNK-2
|
cumilla-s daksin
|
|
4.18
|
|
|
195.00
|
M/S Shikder Construction
|
204.75
|
|
06/04/2018
|
|
30
|
|
|
|
|
726
|
RIDP (SD NK-2) SD-W-29
|
Improvement of Kolomiah m(RHD) Jadobpur Amin Master house-Matainkot Road at Ch. 00-2115m. ID 419915175. (Tender ID : 178949, 188281 & 198133)
|
SDNK-2
|
cumilla-s daksin
|
|
2.12
|
|
|
146.86
|
M/S Shikder Construction
|
154.20
|
|
|
|
0
|
|
|
|
|
727
|
RIDP (SD NK-2) SD-W-30
|
Improvement of Kodalia-Sispur-Sinduya Road at Ch. 00-1115m & 1315-2185m. ID 419915175. (Tender ID : 178950)
|
SDNK-2
|
cumilla-s daksin
|
|
1.99
|
|
|
143.50
|
M/S Farhana Builders
|
143.50
|
|
|
26/05/2019
|
40
|
|
|
|
|
728
|
RIDP (SDNK-2) SD-R15
|
Maintenance of Gondhamoti-Gabtoli-Maddam Bijoy Road at Ch 1800 -6275m (Road ID 419912013) (Tender ID No: 123320 & 144309)
|
SDNK-2
|
cumilla-s daksin
|
|
4.48
|
|
|
140.20
|
M/S Zaman Traders
|
151.26
|
|
02/02/2018
|
|
100
|
|
|
|
|
729
|
RIDP (SDNK-2) SD-R17
|
Maintenance of Khaish GC-Suagonj-Pipulia-Daksin Bijoypur -Adinamura-Bataichari (Barura) Road at Ch 26000m-29000m (Road ID 419912002) (Tender ID No: 143156)
|
SDNK-2
|
cumilla-s daksin
|
|
3.00
|
|
|
148.36
|
M/S Zaman Traders
|
158.82
|
|
|
25/10/2018
|
35
|
|
|
|
|
730
|
RIDP (SDNK-2) SD-M3
|
Maintenance of Suagon Bazar - Subarnapur - Banipur Dholipara - Kalir Bazar Road at Ch 00 - 2450m (Road ID 4419813019) (Tender ID No: 80130)
|
SDNK-2
|
cumilla-s daksin
|
|
2.45
|
|
|
42.26
|
M/S Motaher Traders
|
41.43
|
|
|
|
100
|
|
|
|
|
731
|
RIDP (SDNK-2) SD-R7
|
Re-Construction & Maintenance of Moinamoti Museum-Beltoli Bazar-Balarampur Road at ch 2500 - 3650m (Road ID 419913013) (Tender ID No : 81497)
|
SDNK-2
|
cumilla-s daksin
|
|
1.15
|
|
|
28.69
|
Md. Alamgir Hossain
|
28.36
|
|
|
|
100
|
|
|
|
|
732
|
RIDP (SDNK-2) SD-M 7
|
Maintenance of Biyoypur-Kashkhamar-Tangirper-Pipulia Road at ch 1400-6100m. (Road ID 419913005) (Tender ID No : 91109)
|
SDNK-2
|
cumilla-s daksin
|
|
4.70
|
|
|
114.51
|
M/S Shikider Constraction
|
114.79
|
|
|
28/02/2018
|
100
|
|
|
|
|
733
|
RIDP (SDNK-2) -SD-R18
|
Maintenance of Suagong-Kalikapur-Talikhona Road at ch 00m- 975m & 1775m-2575m. (Road ID 419913007) (Tender ID No : 143157
|
SDNK-2
|
cumilla-s daksin
|
|
1.78
|
|
|
50.91
|
M/S Motaher Traders
|
50.36
|
|
|
24/06/2018
|
100
|
|
|
|
|
734
|
RIDP (SDNK-2) SD-M1
|
Maintenance of Laxmipur - Jongalpur - Kalikapur - Chouara Road at Ch 00-3105m (ID-419914035) (Tender ID No: 80128)
|
SDNK-2
|
cumilla-s daksin
|
|
3.11
|
|
|
67.58
|
M/S Ananta Enterprise
|
67.55
|
|
|
|
100
|
|
|
|
|
735
|
RIDP (SDNK-2) SD-M2
|
Maintenance of Suarkhal Chowmohani - Sultanpur - Neaibag - Molishpur Road at ch-00-1200m (Road ID 419914097) (Tender ID No: 80129)
|
SDNK-2
|
cumilla-s daksin
|
|
1.20
|
|
|
27.72
|
M/S Motaher Traders
|
27.17
|
|
|
|
100
|
|
|
|
|
736
|
RIDP (SDNK-2) SD-R1
|
Re-Construction & Maintenance of Bishnapur - Lampur Firingirhat Road at ch 00 - 1855m (Road ID 419915003) (Tender ID No : 80123)
|
SDNK-2
|
cumilla-s daksin
|
|
1.86
|
|
|
46.75
|
M/S Shah Poran Enterprise
|
46.40
|
|
03/02/2017
|
|
100
|
|
|
|
|
737
|
RIDP (SDNK-2) SD-R6
|
Re-Construction & Maintenance of Lampur-Komoipur Road at Ch 00 - 1742m (Road ID 4419915114) (Tender ID No: 81496)
|
SDNK-2
|
cumilla-s daksin
|
|
1.74
|
|
|
44.06
|
M/S Shah Poran Enterprise
|
43.77
|
|
|
25/11/2017
|
100
|
|
|
|
|
738
|
RIDP (SDNK-2) SD-R14
|
Re-Construction of Suagonj Bazar -Boishkhola-Bhobonpur-BorrowBamisha Road at Ch 2000-5285m (Road ID 419914112) (Tender ID No: 91108)
|
SDNK-2
|
cumilla-s daksin
|
|
3.29
|
|
|
87.01
|
M/S Zaman Traders
|
91.35
|
|
06/07/2017
|
13/02/2018
|
100
|
|
|
|
|
739
|
RIDP (SDNK-2) SD-M8
|
Maintenance of Ratanpur -Horeshpur-Rangamura-Maddam Bijoypur Road at Ch 00-1310m (Road ID 419914100) (Tender ID No: 91110)
|
SDNK-2
|
cumilla-s daksin
|
|
1.31
|
|
|
28.99
|
M/S Shobus & Brothers
|
28.70
|
|
06/04/2017
|
|
100
|
|
|
|
|
740
|
RIDP (SDNK-2) SD-R16
|
Maintenance of Daksin Sindua-Mangalpur-Olir Bazar Road at Ch 1000-2335m (Road ID 419914109) (Tender ID No: 123321 & 144311)
|
SDNK-2
|
cumilla-s daksin
|
|
1.34
|
|
|
38.57
|
M/S R-Ta Enterprise
|
38.12
|
|
|
24/06/2018
|
100
|
|
|
|
|
741
|
RIDP (SDNK-2) SD-R20
|
Maintenance of Suagonj -Kalikapur -Shibpur Road at Ch 00-1225m (Road ID 419915173) (Tender ID No: 178945 & 188266
|
SDNK-2
|
cumilla-s daksin
|
|
1.23
|
|
|
80.45
|
M/S Motaher Traders
|
80.46
|
|
|
|
30
|
|
|
|
|
742
|
RIDP (SDNK-2) SD-M9
|
Maintenance of Golachu-Kachiapukuria Road at Ch 1000-2325m (Road ID 419914011) (Tender ID No: 123322)
|
SDNK-2
|
cumilla-s daksin
|
|
1.33
|
|
|
30.56
|
M/S Farhana Builders
|
32.09
|
|
12/04/2017
|
|
100
|
|
|
|
|
743
|
RIDP (SDNK-2) SD-M10
|
Maintenance of Juktikhola-Kalora-Choulbander Road at Ch 1000-2450m (Road ID 419914049) (Tender ID No: 123323)
|
SDNK-2
|
cumilla-s daksin
|
|
1.45
|
|
|
43.00
|
M/S Meksha Co
|
45.14
|
|
|
15/06/2018
|
85
|
|
|
|
|
744
|
RIDP (SDNK-2) SD-M11
|
Maintenance of Shiber Bazar -Beltoli Bazar (Hossainpur End) Road at Ch 00-945m (Road ID 419913012)
Maintenance of Comilla Laksam-RHD-Perul Daksin GPS Road at Ch 00-1500m (Road ID 419915185)
Maintenance of Hadgara-Baratula Road at Ch 00-1195m (Road ID 419
|
SDNK-2
|
cumilla-s daksin
|
|
5.22
|
|
|
137.96
|
M/S Arsad & Sons
|
144.09
|
|
|
27/08/2018
|
60
|
|
|
|
|
745
|
RIDP (SD NK-2) NK-W-01
|
Improvement of Peria -Tulagaon-Makrobpur Bazar Road at Ch-00-1500m (Road ID 419873013) (Tender ID No: 74049 & 77487)
|
SDNK-2
|
nangalkot
|
|
1.50
|
|
|
89.39
|
M/S Ma-Moni Enterprise
|
89.37
|
|
|
30/04/2018
|
100
|
|
|
|
|
746
|
RIDP (SD NK-2) NK-W-02
|
Improvement of Makrabpur Batora Bannagar Heshakhal Bazar Road at Ch-00-1440m (Road ID 419873017) (Tender ID No: 74050, 77488 & 82036
|
SDNK-2
|
nangalkot
|
|
1.44
|
|
|
96.77
|
M/S A K Traders
|
96.74
|
|
|
25/03/2018
|
100
|
|
|
|
|
747
|
RIDP (SD NK-2) NK-W-22
|
Improvement of Satbaria Chowkori Mannara Bayra Sarfatuli Sejiara Shehar Bazar Road at Ch-00-1635 (Road ID 419873025) (Tender ID No: 86220)
|
SDNK-2
|
nangalkot
|
|
1.64
|
|
|
154.43
|
M/S Madina Construction
|
154.43
|
|
05/09/2017
|
27/07/2018
|
60
|
|
|
|
|
748
|
RIDP (SD NK-2) NK-W-06
|
Improvement of Magua-Makimpur Kala Miah Hazi Bari Road at ch- 00-1500m. (Road ID 419874221) (Tender ID No: 74054)
|
SDNK-2
|
nangalkot
|
|
1.50
|
|
|
82.30
|
M/S Arsad & Sons
|
82.27
|
|
01/12/2017
|
18/01/2018
|
100
|
|
|
|
|
749
|
RIDP (SD NK-2) NK-W-07
|
Improvement of Dhalua- Mogra Road at Ch 00-715m (Road ID-419874210 ) (Tender ID No: 74055)
|
SDNK-2
|
nangalkot
|
|
0.72
|
|
|
35.37
|
M/S Arsad & Sons
|
35.35
|
|
01/12/2017
|
18/09/2017
|
100
|
|
|
|
|
750
|
RIDP (SD NK-2) NK-W-08
|
Improvement of Boxgonj Main Road Manikgonga Road at Ch 00-750m (ID-419874237) (Tender ID No: 74057 & 77490)
|
SDNK-2
|
nangalkot
|
|
0.75
|
|
|
39.75
|
M/S Ma-Moni Enterprise
|
39.72
|
|
|
30/03/2018
|
100
|
|
|
|
|
751
|
RIDP (SD NK-2) NK-W-09
|
Improvement of Gopadua GC Road (Zame Mosque) - Baira Road Via Sarfatuli Primary School Road at Ch 1465-2315m (ID-419874198) (Tender ID No: 74059)
|
SDNK-2
|
nangalkot
|
|
0.85
|
|
|
40.56
|
M/S Madina Construction
|
40.55
|
|
01/12/2017
|
18/09/2017
|
100
|
|
|
|
|
752
|
RIDP (SD NK-2) NK-W-10
|
Improvement of Aliara -Verali Road at Ch 00-1950m (ID-419874202) (Tender ID No: 74060)
|
SDNK-2
|
nangalkot
|
|
1.95
|
|
|
101.46
|
M/S Arsad & Sons
|
101.44
|
|
|
25/06/2018
|
100
|
|
|
|
|
753
|
RIDP (SD NK-2) NK-W-11
|
Improvement of Porikot-Joggashal-Raikot Road at Ch 00-920m (ID-419874035) (Tender ID No: 74061)
|
SDNK-2
|
nangalkot
|
|
0.92
|
|
|
50.81
|
M/S Latif Builders
|
50.77
|
|
|
07/04/2018
|
100
|
|
|
|
|
754
|
RIDP (SD NK-2) NK-W-12
|
Improvement of Mahini School North Side -KukirKhil Sayed Ahmed Bari Road at Ch00-1205m (ID-419874236) (Tender ID No: 74056, 77489 & 82025
|
SDNK-2
|
nangalkot
|
|
1.21
|
|
|
62.16
|
M/S Madina Construction
|
62.13
|
|
|
|
100
|
|
|
|
|
755
|
RIDP (SD NK-2) NK-W-13
|
Improvement of Baro Fatepur -Keshtala Road at Ch00-1000m (ID-419874046) (Tender ID No: 74062)
|
SDNK-2
|
nangalkot
|
|
1.00
|
|
|
63.33
|
M/S Ma-Moni Enterprise
|
63.24
|
|
|
07/04/2018
|
100
|
|
|
|
|
756
|
RIDP (SD NK-2) NK-W-14
|
Improvement of Porikot - Shampur Road at Ch 00-1500m (ID-419874024) (Tender ID No: 74063)
|
SDNK-2
|
nangalkot
|
|
1.50
|
|
|
82.93
|
M/S Halima Enterprise
|
82.91
|
|
01/12/2017
|
15/06/2018
|
100
|
|
|
|
|
757
|
RIDP (SD NK-2) NK-W-15
|
Improvement of Batupara-Mia Bazar Road at Ch 00-1500m (ID-419874045) (Tender ID No: 74058)
|
SDNK-2
|
nangalkot
|
|
1.50
|
|
|
85.80
|
M/S Arsad & Sons
|
85.76
|
|
|
25/06/2018
|
100
|
|
|
|
|
758
|
RIDP (SD NK-2) NK-W-19
|
Improvement of Boroyapara Pucca Road Gorkata-Kalachow Pandit Bari Road at Ch : 00-1800m (ID-419874089) (Tender ID No: 81493)
|
SDNK-2
|
nangalkot
|
|
1.00
|
|
|
107.66
|
M/S Razu Enterprise
|
107.77
|
|
|
17/06/2018
|
70
|
|
|
|
|
759
|
RIDP (SD NK-2) NK-W-20
|
Improvement of Patwar Madrasha-Chowguri Road at Ch : 00-1075m (ID-419874016) (Tender ID No: 81494)
|
SDNK-2
|
nangalkot
|
|
1.08
|
|
|
59.79
|
M/S Meazi Enterprise
|
59.78
|
|
|
|
100
|
|
|
|
|
760
|
RIDP (SD NK-2) NK-W-21
|
Improvement of Bangodda-Gandachi-ShampurRoad at Ch : 1250-2630m (ID-419874034) (Tender ID No: 81495)
|
SDNK-2
|
nangalkot
|
|
1.38
|
|
|
84.00
|
M/S Madina Construction
|
83.97
|
|
|
|
100
|
|
|
|
|
761
|
RIDP (SD NK-2) NK-W-31
|
Improvement of Malangahar-Tetoia Road at Ch. 1260-2300m. Road ID No: 4198755003. (Tender ID : 178951)
|
SDNK-2
|
nangalkot
|
|
1.40
|
|
|
70.87
|
Alvee Trading Poration
|
74.38
|
|
|
27/01/2019
|
60
|
|
|
|
|
762
|
RIDP (SD NK-2) NK-W-32
|
A (1) Improvement of Kashipur Jodda -Bhabanipur Road at Ch. 2300-3620m. Road. B (2) Construction of 4.50 X 3.00m Box Culvert . ID No: 419874184. (Tender ID : 19324)
Improvement of Munshikalamia-Kedarduar Road at Ch. 00-830m. Road ID No: 419874180.
|
SDNK-2
|
nangalkot
|
|
2.15
|
|
|
158.55
|
M/S Nur Ayasha Traders
|
164.73
|
|
|
|
0
|
|
|
|
|
763
|
RIDP (SDNK-2) NK-R2
|
Re-Construction & Maintenance of Nangakot (Omarganj Bazar) - Tuguria RHD Road at ch 6690 - 10760m (Road ID 419812002) (Tender ID No : 80124)
|
SDNK-2
|
nangalkot
|
|
4.07
|
|
|
130.65
|
M/S Madina Construction
|
130.59
|
|
03/02/2017
|
|
100
|
|
|
|
|
764
|
RIDP (SDNK-2) NK-R19
|
Re-Construction of Nangakot -Khila Road at ch 00-3000m (Road ID 419872002) (Tender ID No : 143158
|
SDNK-2
|
nangalkot
|
|
3.00
|
|
|
273.34
|
M/S Zaman Traders
|
292.94
|
|
|
25/10/2018
|
100
|
|
|
|
|
765
|
RIDP (SDNK-2) NK-R9
|
Re-Construction of Nangalkot GC -Ludua RHD Via Merkot Bazar Road at ch 1730-5500m (Road ID 419873011) (Tender ID No : 85470)
|
SDNK-2
|
nangalkot
|
|
3.77
|
|
|
112.58
|
M/S Halima Enterprise
|
110.31
|
|
|
|
100
|
|
|
|
|
766
|
RIDP (SDNK-2) NK-R10
|
Re-Construction of Baiara Bazar UP-Sondail Bazar Road Via Vobanipur at ch 00-1850m (Road ID 419873001) (Tender ID No : 85471)
|
SDNK-2
|
nangalkot
|
|
1.85
|
|
|
62.50
|
M/S Razu Enterprise
|
62.35
|
|
|
|
40
|
|
|
|
|
767
|
RIDP (SDNK-2) NK-R12
|
Re-Construction of Gomkot-Aliara Road at ch 00-1470m (Road ID 419873007) (Tender ID No : 85473)
|
SDNK-2
|
nangalkot
|
|
1.47
|
|
|
37.08
|
M/S Arsad & Sons
|
37.07
|
|
|
|
100
|
|
|
|
|
768
|
RIDP (SDNK-2) NK-R13
|
Re-Construction of Boxgonj-Barokali Suvapur-Kabilakhali-Satbaria Road at ch 00-3411m & 4032-5110m (Road ID 419873026) (Tender ID No : 85474)
|
SDNK-2
|
nangalkot
|
|
4.49
|
|
|
88.87
|
M/S Ma-moni Enterprise
|
88.68
|
|
|
20/05/2018
|
100
|
|
|
|
|
769
|
RIDP (SDNK-2) NK-M4
|
Rehabilitation & Maintenance of Mahini - Kukirkhil Road at ch 00 - 900m (Road ID 419874137) (Tender ID No : 80131)
|
SDNK-2
|
nangalkot
|
|
0.90
|
|
|
22.82
|
M/S Madina Construction
|
22.80
|
|
03/02/2017
|
|
100
|
|
|
|
|
770
|
RIDP (SDNK-2) SD-M6
|
Rehabilitation & Maintenance of Kashipur Purbapara Road at ch 00-762m (Road ID 419874156) (Tender ID No : 85475)
|
SDNK-2
|
nangalkot
|
|
0.76
|
|
|
19.80
|
M/S Razu Enterprise
|
19.80
|
|
|
29/12/2017
|
100
|
|
|
|
|
771
|
RIDP (SDNK-2) NK-R3
|
Re-Construction & Maintenance of Shantir Bazar - Pipodda Road at ch 00 - 1720m (Road ID 419874130) (Tender ID No : 80125)
|
SDNK-2
|
nangalkot
|
|
1.72
|
|
|
54.65
|
M/S Madina Construction
|
54.56
|
|
03/02/2017
|
|
100
|
|
|
|
|
772
|
RIDP (SDNK-2) NK-R4
|
Re-Construction & Maintenance of Binaygar - Chadia Bazar -Omargonj Road at ch 5870 - 6700m (Road ID 419874092) (Tender ID No : 80126)
|
SDNK-2
|
nangalkot
|
|
0.83
|
|
|
21.92
|
M/S Arsad & Sons
|
21.90
|
|
|
22/10/2017
|
100
|
|
|
|
|
773
|
RIDP (SDNK-2) NK-R11
|
Re-Construction of Nangalkot-Makrabpur By Pass Road at Ch 00 - 1800m (Road ID 4419874002) (Tender ID No: 85472)
|
SDNK-2
|
nangalkot
|
|
1.80
|
|
|
48.51
|
M/S Halima Enterprise
|
48.22
|
|
|
|
100
|
|
|
|
|
774
|
RIDP (SDNK-2) SD-M12
|
Maintenance of Malangshar-Tetoia Road at Ch 00-480m (Road ID 419875003)
Maintenance of Boxgonj GC Road AziaraRoad via Bhuyain Bari at Ch 00-612m (Road ID 419874193)
Maintenance of Peria -Tulagaon Makrabpur Bazar Road at Ch 2930-3430m (Road ID 419874193)
|
SDNK-2
|
nangalkot
|
|
1.59
|
|
|
12.21
|
M/S Hamdan Enterprise
|
35.36
|
|
|
28/09/2018
|
100
|
|
|
|
|
775
|
w.280
|
Construction of chitada UP Complex
|
UCCP-2
|
barura
|
|
|
|
100
|
88.61
|
|
81.00
|
11/02/2016
|
|
01/02/2017
|
100
|
80.88
|
100
|
17/08/2020
|
|
776
|
w.453
|
Construction of 4 nogalimpur UP Complex
|
UCCP-2
|
barura
|
|
|
|
100
|
95.80
|
|
90.05
|
24/05/2016
|
|
25/02/2017
|
100
|
90.04
|
100
|
17/08/2020
|
|
777
|
w.622
|
Construction of13 no adraUP Complex
|
UCCP-2
|
barura
|
|
|
|
|
128.76
|
|
122.32
|
21/01/2019
|
|
20/10/2019
|
100
|
45.00
|
|
17/03/2020
|
|
778
|
w.461
|
Construction of pirjatpur UP Complex
|
UCCP-2
|
burichong
|
|
|
|
100
|
96.49
|
|
86.52
|
19/04/2017
|
|
30/11/2018
|
100
|
86.37
|
100
|
17/08/2020
|
|
779
|
209/246
|
construction of burichong up
|
UCCP-2
|
burichong
|
|
|
|
|
35.00
|
|
35.00
|
26/04/2006
|
|
|
0
|
|
|
15/07/2020
|
|
780
|
w.467
|
Construction of suhilpur UP Complex
|
UCCP-2
|
chandina
|
|
|
|
100
|
113.07
|
|
98.73
|
28/09/2016
|
|
31/12/2018
|
100
|
98.30
|
100
|
17/08/2020
|
|
781
|
208/246
|
construction of batagasi up
|
UCCP-2
|
chandina
|
|
|
|
100
|
59.00
|
|
69.02
|
28/12/2010
|
|
29/11/2014
|
100
|
68.90
|
100
|
15/07/2020
|
|
782
|
207/246
|
construction of maizekhar up
|
UCCP-2
|
chandina
|
|
|
|
100
|
59.00
|
|
66.94
|
20/05/2011
|
|
31/05/2015
|
100
|
66.90
|
100
|
15/07/2020
|
|
783
|
w-34
|
Construction of borkoroi UP Complex
|
UCCP-2
|
chandina
|
|
|
|
0
|
126.63
|
|
125.74
|
25/09/2019
|
|
25/06/2020
|
15
|
0.00
|
0
|
17/03/2020
|
|
784
|
137/176
|
Construction of chewra UP Complex
|
UCCP-2
|
chouddagram
|
|
|
|
50
|
139.91
|
|
146.84
|
06/06/2018
|
|
31/01/2020
|
95
|
|
50
|
03/09/2020
|
|
785
|
w.050
|
Construction of gunoboti UP Complex
|
UCCP-2
|
chouddagram
|
|
|
|
100
|
88.69
|
|
92.99
|
07/11/2012
|
|
25/02/2016
|
100
|
91.75
|
100
|
17/08/2020
|
|
786
|
w.663
|
Construction of kalikapur UP Complex
|
UCCP-2
|
chouddagram
|
|
|
|
0
|
178.16
|
|
181.63
|
05/12/2018
|
|
27/04/2020
|
40
|
0.00
|
0
|
17/03/2020
|
|
787
|
w.158
|
Construction of kalir bazar UP Complex
|
UCCP-2
|
cumilla-s
|
|
|
|
100
|
92.32
|
|
96.92
|
07/10/2016
|
|
04/10/2017
|
100
|
96.14
|
100
|
17/08/2020
|
|
788
|
perul (n)
|
construction of sadar dakkhin up
|
UCCP-2
|
cumilla-s
|
|
|
|
100
|
41.97
|
|
41.97
|
23/10/2007
|
|
22/10/2008
|
100
|
41.57
|
100
|
15/07/2020
|
|
789
|
w.338
|
Construction of belghar (s) UP Complex
|
UCCP-2
|
cumilla-s daksin
|
|
|
|
100
|
29.67
|
|
29.67
|
04/08/2003
|
|
27/09/2017
|
100
|
27.83
|
100
|
17/08/2020
|
|
790
|
199/246
|
construction of perul( s) remaining up
|
UCCP-2
|
cumilla-s daksin
|
|
|
|
100
|
21.63
|
|
16.18
|
20/02/2017
|
|
31/01/2018
|
100
|
16.18
|
100
|
15/07/2020
|
|
791
|
132/176
|
Construction of gouripur UP Complex
|
UCCP-2
|
daudkandi
|
|
|
|
100
|
84.84
|
|
84.84
|
13/12/2012
|
|
30/06/2015
|
100
|
84.11
|
100
|
03/09/2020
|
|
792
|
w.148
|
Construction of maligaon UP Complex
|
UCCP-2
|
daudkandi
|
|
|
|
100
|
92.92
|
|
95.50
|
30/11/2014
|
|
30/03/2016
|
100
|
93.74
|
100
|
17/08/2020
|
|
793
|
w.380
|
Construction of maruka UP Complex
|
UCCP-2
|
daudkandi
|
|
|
|
100
|
88.49
|
|
92.91
|
27/04/2014
|
|
30/08/2015
|
100
|
88.39
|
100
|
17/08/2020
|
|
794
|
w.049
|
Construction of 7 no alehabad UP Complex
|
UCCP-2
|
debidwar
|
|
|
|
100
|
84.04
|
|
84.63
|
02/09/2013
|
|
23/12/2014
|
100
|
84.62
|
100
|
17/08/2020
|
|
795
|
206/246
|
construction of borosalgar up
|
UCCP-2
|
debidwar
|
|
|
|
100
|
61.88
|
|
61.88
|
28/11/2010
|
|
20/04/2011
|
100
|
61.71
|
100
|
15/07/2020
|
|
796
|
w.339
|
Construction of chanderchar UP Complex
|
UCCP-2
|
homna
|
|
|
|
100
|
87.46
|
|
99.93
|
04/09/2013
|
|
31/03/2016
|
100
|
99.90
|
100
|
17/08/2020
|
|
797
|
w.423
|
Construction of 1 no bakai UP Complex
|
UCCP-2
|
laksham
|
|
|
|
100
|
85.86
|
|
89.94
|
24/04/2014
|
|
15/10/2015
|
100
|
89.79
|
100
|
17/08/2020
|
|
798
|
w.217
|
Construction of 5 no uttarda UP Complex
|
UCCP-2
|
laksham
|
|
|
|
100
|
90.13
|
|
88.81
|
06/06/2016
|
|
10/12/2016
|
100
|
87.37
|
100
|
17/08/2020
|
|
799
|
130/176
|
Construction of radhanagar UP Complex
|
UCCP-2
|
meghna
|
|
|
|
100
|
71.90
|
|
75.50
|
14/11/2012
|
|
20/06/2017
|
100
|
75.49
|
100
|
03/09/2020
|
|
800
|
131/176
|
Construction of bhaorkhola UP Complex
|
UCCP-2
|
meghna
|
|
|
|
100
|
59.00
|
|
67.57
|
17/04/2012
|
|
30/06/2015
|
100
|
67.06
|
100
|
03/09/2020
|
|
801
|
w.051
|
Construction of barkanda UP Complex
|
UCCP-2
|
meghna
|
|
|
|
100
|
68.70
|
|
71.79
|
10/10/2012
|
|
30/06/2015
|
100
|
71.67
|
100
|
17/08/2020
|
|
802
|
205/246
|
construction of loterchar up
|
UCCP-2
|
meghna
|
|
|
|
100
|
59.00
|
|
68.02
|
26/10/2010
|
|
23/04/2011
|
100
|
68.02
|
100
|
15/07/2020
|
|
803
|
w.052
|
Construction ofbabutipara UP Complex
|
UCCP-2
|
muradnagar
|
|
|
|
100
|
84.26
|
|
88.47
|
16/04/2014
|
|
30/10/2015
|
100
|
88.40
|
100
|
17/08/2020
|
|
804
|
w.086
|
Construction of chapitola UP Complex
|
UCCP-2
|
muradnagar
|
|
|
|
100
|
84.19
|
|
84.19
|
05/06/2013
|
|
31/12/2015
|
100
|
83.96
|
100
|
17/08/2020
|
|
805
|
204/246
|
construction of bhangora(e) up
|
UCCP-2
|
muradnagar
|
|
|
|
100
|
69.00
|
|
72.44
|
10/11/2013
|
|
27/04/2015
|
100
|
72.27
|
100
|
15/07/2020
|
|
806
|
203/246
|
construction of dhamgar up
|
UCCP-2
|
muradnagar
|
|
|
|
100
|
29.56
|
|
29.00
|
25/08/2011
|
|
30/11/2013
|
100
|
29.00
|
100
|
15/07/2020
|
|
807
|
136/176
|
Construction of satbaria UP Complex
|
UCCP-2
|
nangalkot
|
|
|
|
100
|
59.00
|
|
67.21
|
09/05/2010
|
|
01/10/2011
|
100
|
61.96
|
100
|
03/09/2020
|
|
808
|
135/176
|
Construction of bangodda UP Complex
|
UCCP-2
|
nangalkot
|
|
|
|
100
|
114.53
|
|
108.80
|
09/09/2018
|
|
26/05/2019
|
100
|
80.26
|
100
|
03/09/2020
|
|
809
|
w.080
|
Construction of bakshagonj UP Complex
|
UCCP-2
|
nangalkot
|
|
|
|
100
|
93.44
|
|
93.43
|
22/12/2015
|
|
15/05/2017
|
100
|
92.99
|
100
|
17/08/2020
|
|
810
|
202/246
|
construction of doulkhar up
|
UCCP-2
|
nangalkot
|
|
|
|
100
|
62.38
|
|
52.41
|
15/08/2016
|
|
15/02/2017
|
100
|
52.33
|
100
|
15/07/2020
|
|
811
|
201/246
|
construction of mokrabpur up
|
UCCP-2
|
nangalkot
|
|
|
|
100
|
59.00
|
|
58.99
|
09/05/2010
|
|
09/01/2011
|
100
|
58.86
|
100
|
15/07/2020
|
|
812
|
w.616
|
Construction of dalua UP Complex
|
UCCP-2
|
nangalkot
|
|
|
|
|
116.55
|
|
110.72
|
18/10/2018
|
|
27/06/2019
|
50
|
10.00
|
|
17/03/2020
|
|
813
|
198/246
|
construction of satani up
|
UCCP-2
|
titas
|
|
|
|
0
|
59.00
|
|
59.00
|
|
|
|
0
|
0.00
|
0
|
15/07/2020
|
|
814
|
CBU-100/ Purto-256
|
কুমিল্লা জেলার চৌদ্দগ্রাম উপজেলাধীন গুনবতী জিসি - আকদিয়া - বান্দেরজলা সড়কে ২৮৫০ মিটার চেইনেজে PSC ব্রিজ নির্মাণ (রোড আইডিঃ ৪১৯৩১২০০৭)
|
UHBP
|
chouddagram
|
419312007
|
|
0.00
|
0
|
835.81
|
M/S. Kashem Traders- M/S. Poly Enterprise (JV)
Vill-Bashuara, Post- Utter Padua, P.S-Chuddagram, Dist- Cumilla.
|
232.07
|
11/03/2020
|
11/03/2020
|
30/06/2023
|
100
|
175.50
|
0
|
28/09/2024
|
|
815
|
CBU-100/ Purto-256(A)
|
কুমিল্লা জেলার চৌদ্দগ্রাম উপজেলাধীন গুনবতী জিসি-আকদিয়া-বান্দেরজলা সড়কে ২৮৫০ মিটার চেইনেজে অসমাপ্ত সেতু নির্মাণ (রোড আইডিঃ ৪১৯৩১২০০৭)
|
UHBP
|
chouddagram
|
419312007
|
|
81.00
|
0
|
699.92
|
M/S Amin International
|
766.41
|
01/01/1900
|
|
|
0
|
0.00
|
0
|
28/09/2024
|
|
816
|
CBU-100/ Purto-257
|
কুমিল্লা জেলার চৌদ্দগ্রাম উপজেলাধীন রাজেন্দ্রপুর-চরলক্ষ্মীপুর ভায় ফজলু মেম্বারের বাড়ি সড়কে কাঁকড়ি খালের উপর ০৫ মিটার চেইনেজে RCC সেতু নির্মাণ (রোড আইডিঃ ৪১৯৩১৪১৮১)
|
UHBP
|
chouddagram
|
419314181
|
|
48.00
|
0
|
331.44
|
M/S. Kashem Traders- M/S. Poly Enterprise (JV)
Vill-Bashuara, Post- Utter Padua, P.S-Chuddagram, Dist- Cumilla.
|
331.43
|
10/03/2020
|
10/03/2020
|
30/04/2023
|
100
|
322.38
|
0
|
28/09/2024
|
|
817
|
CBU-100/ Purto-258
|
কুমিল্লা জেলার দাউদকান্দি উপজেলাধীন দাউদকান্দি-জিসি পাঁকা রাস্তা হতে বাতাকান্দি জিসি রোড মোহনপুর লঞ্চঘান সড়কে ৪৫০ মিটার চেইনেজে সতানন্দী খালের উপর PSC ব্রিজ নির্মাণ। (রোড আইডিঃ ৪১৯৩৬২০০৫)
|
UHBP
|
daudkandi
|
419362005
|
|
96.00
|
0
|
1727.01
|
MAE & DCL (JV)
|
2169.53
|
26/07/2020
|
26/07/2020
|
12/09/2022
|
65
|
1260.08
|
0
|
28/09/2024
|
|
818
|
CBU-100/ Purto-435
|
কুমিল্লা জেলার দাউদকান্দি উপজেলাধীন মোল্লাকান্দি - শ্রীরায়েরচর সড়ক ভায়া বনুয়াকান্দি সড়কে ৩০৫০মিটার চেইনেজে (রোড আইডি-৪১৯৩৬৪০৪৩) ব্রিজ নির্মাণ।
|
UHBP
|
daudkandi
|
419364043
|
|
66.00
|
0
|
504.83
|
PC & MIIR & MST (JV), Kawtoli, B.baria.
|
544.25
|
24/10/2021
|
24/10/2021
|
30/10/2023
|
65
|
300.33
|
0
|
28/09/2024
|
|
819
|
CBU-100/ Purto-260
|
কুমিল্লা জেলার লাকসাম উপজেলাধীন শিয়াং রাস্তার কালিয়াপুর বাজার সংলগ্ন কার্জন খালের উপর সেতু নির্মাণ (রোড আইডিঃ ৪১৯৭২৪০১৯)
|
UHBP
|
laksham
|
419724019
|
|
50.00
|
0
|
575.80
|
Kasfem Traders And The New Trade Link(JV
|
603.85
|
25/02/2021
|
25/02/2021
|
15/05/2022
|
60
|
332.41
|
0
|
28/09/2024
|
|
820
|
CBU-100/ Purto-437
|
কুমিল্লা জেলার লাকসাম উপজেলাধীন লাকসাম জংশন(নরুল হক নেভি সড়ক)-বাউরতলা মজিদ মিয়া বাড়ি সড়কে ৬০০মিটার চেইনেজে (রোড আইডি-৪১৯৭২৫১৫১) সেতু নির্মাণ।
|
UHBP
|
laksham
|
419725151
|
|
43.00
|
0
|
593.47
|
|
0.00
|
01/01/1900
|
|
|
0
|
0.00
|
0
|
28/09/2024
|
|
821
|
CBU-100/ Purto-261
|
(ক) কুমিল্লা জেলার মনোহরগঞ্জ উপজেলাধীন জাওড়া-নদনা সড়কে ১২০০ মিটার চেইনেজে সেতু নির্মাণ। (রোড আইডি-৪১৯৯০৪১০২)
|
UHBP
|
monohorganj
|
419904102
|
|
26.00
|
0
|
229.51
|
Max Infrastructure Ltd.
|
454.62
|
28/08/2022
|
28/08/2022
|
02/02/2024
|
50
|
209.32
|
0
|
28/09/2024
|
|
822
|
|
(খ) কুমিল্লা জেলার মনোহরগঞ্জ উপজেলাধীন সাতঘরিয়া আরএন্ড এইচ-সাতঘরিয়া অহিদুল আলম সড়কে ৪৫০মিঃ চেইনেজে সেতু নির্মাণ। (রোড আইডি-৪১৯৯০৫০৮৮)
|
UHBP
|
monohorganj
|
419905088
|
|
16.00
|
0
|
185.66
|
|
0.00
|
01/01/1900
|
|
|
35
|
0.00
|
0
|
28/09/2024
|
|
823
|
CBU-100/ Purto-259
|
কুমিল্লা জেলার নাঙ্গলকোট উপজেলাধীন নাঙ্গলকোর্টের মৌকারা ইউনিয়নের চারিতুপা গ্রামে পান্নারা সড়কে গুরুত্বপূর্ন ডাকাতিয়া নদীর উপর PSC ব্র্রীজ ব্রিজ নির্মাণ। (রোড আইডিঃ ৪১৯৮৭৪২৫৩)
|
UHBP
|
nangalkot
|
419874253
|
|
75.00
|
0
|
624.14
|
Toma Construction & Co. Limited-M/S. MA Zaher (JV)
|
622.07
|
11/06/2020
|
18/06/2020
|
30/06/2023
|
50
|
290.66
|
0
|
28/09/2024
|
|
824
|
CBU-100/ Purto-436
|
কুমিল্লা জেলার তিতাস উপজেলাধীন দড়িমাছিমপুর-আফজলকান্দি ওয়াপদা ভায়া কলাকান্দি উত্তর পাড়া-উত্তর মানিকনগর সড়কে ৪২৫মিটার চেইনেজে (রোড আইডি-৪১৯৮৯৪০৪৩) ব্রিজ নির্মাণ।
|
UHBP
|
titas
|
419894043
|
|
60.00
|
0
|
535.29
|
PC & MIIR & MST (JV), Kawtoli, B.baria.
|
587.10
|
13/10/2021
|
13/10/2021
|
02/06/2024
|
85
|
473.33
|
0
|
28/09/2024
|
|
825
|
UIIP-BC/PCO/W-263
|
(1) (ROAD) Improvement of a Road at Panchr House of Kader Mmember to House of Saiful Counselor under Chouddagram Pourashava,Cumilla (Ch.235.500m)(1) (CROSS DRAIN) Improvement of a Road at Panchr House of Kader Mmember to House of Saiful Counselor under Chouddagram Pourashava,Cumilla (Ch.235.500m)(3) (ROAD) Constructionof RCC Road for Chouddagram Upazila Porishod Under Chouddagram Pourashava,Cumilla.( Ch.00-80.00m)( 4) ( Rataining Wall) Construction of RCC Retaining wall at nearest in front of Chouddagaram Upazila Porishod Road Side Under Chouddagram Pourashava ,Cumilla( Ch.0.00-80.00m)( 5) ROAD-BC) Improvement of a Road From Dhaka-Chittagong Highway to Falgunkara Chowdhury Bari Road under Chouddagram Pourashava,Cumilla( Ch.00-510.00m)( 6) ( Road-R.C.C) Construction of R.C.C Road at South Falgunkara Road to house of Chowdhury Bari under Chouddagaram Pourashava,Cumilla( ch.00-96.00m)(7) Construction of RCC road at Chandishkara Laksum Road to Towards north side house of Shekh of Abdur Rahman under Chouddagram Pourashava Cumilla (Ch: 00-262.00m
|
UIIP
|
chouddagram
|
|
1.26
|
0.00
|
79
|
109.72
|
M/S. Tuhin Brothers
|
102.05
|
27/09/2021
|
04/10/2021
|
08/05/2022
|
100
|
62.55
|
79
|
14/10/2024
|
|
826
|
UIIP-BC/PCO/W-264
|
(A)(ROAD -BC) Rehabilitation of Road by BC of Chouddagram H.J gov.High School Main Road Under Chouddagram Pourashava,Comilla.( Ch.00-150.00m)( B) ( Retaining wall ) Rehabilitation of Chouddagram H.J Gov.High School Main Road Under Chouddagram Pourashava,Comilla.( Ch.00-150.00m)( c) Construction of RCC Drain at H.J High School Road Side Under Chouddagram Pourashava,Comilla.( Ch.00-130.00m)( D) Construction of RCC Main Drain from H.J Gov.High School Play Ground to South Side Shorpolona Canel Under Chouddagram Pourashava,Comilla.( Ch.00-25.00m)( D) Construction of RCC Main Drain from H.J Gov.High School Play Ground to South Side Shorpolona Canel Under Chouddagram Pourashava,Comilla.( Ch.00-25.00m)( E) (Road-RCC)Construction of RCC Road at Chouddagram H.J Gov.High School Road Under Chouddagram Pourashava,Comilla.( Ch.00-520.00m)
|
UIIP
|
chouddagram
|
|
0.82
|
0.00
|
100
|
149.31
|
M/S. Tuhin Brothers
|
133.38
|
18/07/2021
|
25/07/2021
|
30/06/2022
|
100
|
132.43
|
100
|
14/10/2024
|
|
827
|
UIIP-BC/PCO/W-509
|
A) Constraction of RCC Road at Pachra Monshibari road under Chouddagram PourashavaCumilla (Ch.0.00-305.00m) B) Construction of Retaining wall at Pachra Monshibari Road under Chouddagram Pourashava(Ch.230.00- 300=70.00m))C) Construction of RCC Road at Natapara(East) H/O Kala Mia to Hoddar Pond under Chouddagram PourashavaCumilla (Ch.0.00-242.00m)D) Construction of RCC Road at Chandishkara Laksham Road to North Side of H/O Hazi Yousuf & Md. Ismail under Chouddagram Pourashava Cumilla (Ch.0.00-165.00m)E) Construction of RCC Drain at King Sreeour Kacha Bazer to Asho shah Fakir Mazer under Chouddagram PourashavaCumilla (Ch.0.00-263.00m)F) Construction of RCC Drain at Falgunkhara H/O Arob Mulla to North Side Canal under Chouddagram Pourashava Cumilla (Ch.508.00-577.00m=69.00m
|
UIIP
|
chouddagram
|
|
0.78
|
0.00
|
41
|
142.18
|
M/s Rafiq Traders
|
127.84
|
07/07/2022
|
11/07/2012
|
10/07/2023
|
52
|
52.98
|
41
|
14/10/2024
|
|
828
|
UIIP-BC/PCO/W-510
|
A) Construction of RCC Road at Chondipur Bypass Road to Graveyard under Chouddagram PourashavaCumilla (Ch.0.00-275.00m)B) Construction of RCC Road at Laxmipur Jame Mosque Road to Ramrygram H/O NSI Kazi Kamal under Chouddagram Pourashava Cumilla (Ch.0.00-295.00m)C) Construction of Protection wall at Laxmipur Jame Mosque Road to Ramrygram H/O NSI Kamal under Chouddagram PourashavaCumilla (Ch.0.00-295.00m) D) Construction of RCC Road at Jayantinagar BC Road to H/O CEO shab under Chouddagram Pourashava Cumilla (Ch. 0.00-130.00m)E) Construction of RCC Drain at Jayantinagar BC Road to H/O CEO shab under Chouddagram Pourashava Cumilla (Ch. 0.00-130.00m)F) Construction of RCC Drain at Laximipur Eidga to H/O khalill Miha under Chouddagram Pourashava Cumilla (Ch.0.00-107.00m)G) Construction of RCC Box Culvert (2.00x2.00m) at Joyantynagar GPS Road Nearest Highway at Ch.10.00m under Chouddagram Pourashava Cumilla.
|
UIIP
|
chouddagram
|
|
1.00
|
2.50
|
76
|
113.23
|
M/s Patwary Enterprise
|
100.87
|
07/07/2022
|
11/07/2022
|
10/07/2023
|
97
|
76.83
|
76
|
14/10/2024
|
|
829
|
UIIP-BC/PCO/W-511
|
A) Rehabilitation of RCC Road from Chouddagram Highway Connecting Road in front of Girls School Including Foothpath under Chouddagram PourashavaCumilla (Ch.0.00-25.00m)
B) Construction of Top Slab of Drain at Chandishkara Laksham Road to South side Gazi Bari Road under Chouddagram Pourashava Cumilla (Ch.00-125.00m)
C) Construction of RCC Box Culvert (4.00x3.00m) at Chandishkar on Shorpolona Canel Nearest H/O Journalist Mahbobur Rahman Miazil under Chouddagram PourashavaCumilla. (dropped)
D) Construction of RCC Box Culvert (4.00x3.00m ) at on Kisnochora Canel at Falgunkara West-South side H/O Mano Masterl under Chouddagram PourashavaCumilla.
E) Construction of RCC Box Culvert (4.00x4.00m) at Highwayl Connecting Road in front of Girls School at Ch.15.00m Under Chouddagram PourashavaCumilla.
|
UIIP
|
chouddagram
|
|
0.25
|
9.55
|
28
|
109.33
|
M/S Patwary Enterprise
|
74.62
|
14/08/2022
|
21/08/2022
|
27/05/2024
|
46
|
21.25
|
28
|
14/10/2024
|
|
830
|
UIIP-BC/PCO/W-573
|
(A) Improvement of RCC Road work at Dhaka Chittagong Highway to West Bypass Tower West Corner ( Ch.00-375.00m) Link Judge Kaushik Khandikar & Azad Home ( Ch. 00-100.00+00-40)=140.00m Ward no-06. Under Chouddagram PourashavaCumilla
(B) Improvement of RCC Road & RCC Retaining wall at Falgunkora Bhuiyan Jame Mosque Road to H/O Mafigur Rahman Councilor ( Ch.00-199.00m) Ward no-06. Under Chouddagram PourashavaCumilla
(C) Improvement of RCC Road at Ramchandrapur Siddikur Rahman Shop to Dhaka Chittagong Highway Deputy Tax Calculator Office( Ch.00-510.00m) With on Cross Drain at (Ch. 00-m) Ward no-08 & 09 Under Chouddagram PourashavaCumilla
(D) Improvement of RCC Road Baiderkhil Jame Mosque Road to H/O Mahabudul Haque ( Ch.00-95.00m) Ward no-07. Under Chouddagram PourashavaCumilla
|
UIIP
|
chouddagram
|
|
1.32
|
|
55
|
196.91
|
Aristocratic Construction Firm
|
196.39
|
05/06/2023
|
11/06/2023
|
10/06/2024
|
68
|
107.59
|
55
|
14/10/2024
|
|
831
|
UIIP/PCO/G-44
|
Implementation & Supply 781 nos Waste Basket (120 ltr) & 9 nos Non-motorized vehicle (van) under Chouddagram Pourashava District: Cumilla.
|
UIIP
|
chouddagram
|
|
|
|
0
|
39.96
|
RFL Plastrics Limited
|
25.57
|
02/02/2024
|
11/02/2024
|
10/02/2025
|
20
|
0.00
|
0
|
14/10/2024
|
|
832
|
UIIP-BC/PCO/W-81
|
(A) A-1( Road) Construction of R.C.C Road at Chandishkara Laksum Road to Towards north West side house of Mizan Moulana under Chouddagram Pourashava,Cumilla . ( Ch.00-270.00 m) ( B).A2-(Retaining wall) Construction of Retaining wall Road Side at Chandishkara Laksum Road to Towards north West side of Mizan Moulana under Chouddagram Pourashava,Cumilla. ( Ch.200-234=34.00 m) ( B).A2-(Retaining wall) Construction of Retaining wall Road Side at Chandishkara Laksum Road to Towards north West side of Mizan Moulana under Chouddagram Pourashava,Cumilla. ( Ch.200-234=34.00 m)(C ) B1-( Road) Construction of R.C.C Road at Chandishkara Shiraz Patowary Bari RCC Road to South side New Mosque Nearest house of Ali Hossain under Chouddagram Pourashava,Cumilla ( Ch.0.00-300.00m)( D) B2-(Drain-1) Construction of Drain at Chandishkara Shiraz Patwory Bari R.C.C Road to south side New Mosque Nearest house of Ali Hossain under Chouddagram Pourashava,Cumilla. ( Ch.0.00-128.00m)( E) B3-(Drain-2) Construction of Drain at Chandishkara Shiraz Patwary Bari RCC Road to south side New Mosque Nearest house of Ali Hossain under Chouddagram Pourashava,Cumilla. ( Ch.0.00-45.00m) ( G) A2- ( Drain)Construction of Drain at Noapara East bypass Road to house of Driver Ali Hossain underChouddagram Pourashava,Cumilla. ( Ch.00-254.00m)( H) B1-( Road) Construction of HBB Road at Highway Side from Ramchandrapur BICIS Road to South Side Shop of Nurul Amin under Chouddagram Pourashava,Cumilla. ( Ch.2320.00-2950.00m) ( I) B2-Construction of 4.00m x3.00m RCC Box Culvert in on Mitalla Cannel under Chouddagram Pourashava,Cumilla ( Ch.2550.00 m)
|
UIIP
|
chouddagram
|
|
1.48
|
4.00
|
81
|
182.73
|
M/S.Hoque Traders
|
182.22
|
28/09/2020
|
05/10/2020
|
05/10/2021
|
100
|
147.16
|
81
|
29/09/2022
|
|
833
|
UIIP-BC/PCO/W-82
|
(A)B1-( Drain) Construction of R.C.C Drain From Baidderkhi house of Habu Miah to North Side Canel under Chouddagram Pourashava,Cumilla. ( Ch.0.00-280.00 M )( B) C1-(Road -BC) Improvement of a Road from Dhaka-Chittagong Highway to East Dhonmuri BC Road under Chouddagram Pourashava,Cumilla. ( Ch.600-1310.00m)(C) E1-Construction of 2.00m x 2.00m RCC Box Culvert at Pachra Balujuri Road under Chouddagram Pourashava,Cumilla. ( Ch.1050.00M) ( D) E2-Contruction of 2.00m x 2.00 m RCC Box Culvert at Pachra Nearest House of Shamsu Bsc under Chouddagram Pourashava,Cumilla. ( Ch.750.0 M)
|
UIIP
|
chouddagram
|
|
0.71
|
2.00
|
100
|
81.06
|
M/S. Kamrul Enterprise
|
83.37
|
28/09/2020
|
05/10/2020
|
05/10/2021
|
100
|
82.99
|
100
|
29/09/2022
|
|
834
|
UIIP-BC/PCO/W-265
|
( A) Construction of RCC Drain at King Sreepur High School Road from house of Abdul Mannan to west side Culvert Under Chouddagram Pourashava,Comilla.( Ch.694-904.00m)( B) Construction of RCC Road at Sreepur West Bypass Road to West Side House of Chan Miah Under Chouddagram Pourashava,Comilla.( Ch.00-320.00m)( c) Construction of RCC Drain at Sreepur West Bypass Road to West Side House of Chan Miah & Jamal Under Chouddagram Pourashava,Comilla.( Ch.30-230.00m)( D) Improvement of West Dhonmuri Road to House of Advocat Shiraz Nearest Chatitola Road at Sreepur West Bypass Road to West Side House of Chan Miah Under Chouddagram Pourashava,Comilla.( Ch.00-300.00m)
|
UIIP
|
chouddagram
|
|
|
0.00
|
51
|
100.49
|
M/S. Tuhin Brothers
|
93.34
|
18/07/2021
|
25/07/2021
|
30/06/2022
|
100
|
47.88
|
51
|
29/09/2022
|
|
835
|
UIIP-BC/PCO/W-74
|
( a)Rehabilitation & Widening of BC road starting from Homna Post Office moar to Raj gat in ward No-04 ( Ch.00-700m) ( b) Construction of RCC Road starting from Rehana Mojid Mohila Collage to Motin Shop via Mostafa bari Graveyard in Ward No-03 & 04 ( Ch.00-470) ( c) Rehabilitation of BC Road starting from Homna Adrashapara Ghatla to Homna-Kashipur road in ward No-03 ( Ch. 800-1+820m)
|
UIIP
|
homna
|
|
2.17
|
0.00
|
100
|
152.93
|
M/S Modina Construction
|
152.89
|
02/11/2020
|
09/11/2020
|
25/05/2022
|
100
|
151.03
|
100
|
14/10/2024
|
|
836
|
UIIP-BC/PCO/W-229
|
Construction of RCC Road starting from A) Homna Post Office Mour to Old Bus Stand Bridge approach via Homna Bazar ( Ch.00-712m). B) A 1 Rashid Plaza corner to Homna Thana Gate in ward no 04 & 05 under Homna Pourashava ( ch.00-48m)
|
UIIP
|
homna
|
|
0.76
|
0.00
|
100
|
153.23
|
M/S. Zaman Traders
|
71.57
|
15/06/2021
|
22/06/2021
|
21/12/2021
|
100
|
145.48
|
100
|
14/10/2024
|
|
837
|
UIIP-BC/PCO/W-421
|
Construction of RCC Road starting from Bagmara Madrasha to Homna-Kashipur Road in ward No-02 under Homna Pourashava (Ch.0.00-850m).
|
UIIP
|
homna
|
|
0.85
|
0.00
|
100
|
96.18
|
M/S. Lockman Hossain
|
96.18
|
29/05/2022
|
06/05/2022
|
06/04/2023
|
100
|
96.10
|
100
|
14/10/2024
|
|
838
|
UIIP-BC/PCO/W-497
|
A) Construction of RCC Road starting from Bagmara-Kalmina Road to Graveyard existing pacca Road (Ch.0.00-155m) ward No.09 under Homna Pourashava. B) Construction of RCC Drain starting from REB Mosjid Road Hazrat Ali Bari moar to REB Office existing Drain (Ch.0.00-180m) ward No.04 under Homna Pourashava.C) Construction of 03 (Three) No. Box Culvert ( Size:3.0m x 3.5m x 6.20m) from Bus Stand to Latia Road at Chainage 650m 1600 & 2750m) Under under Homna Pourashava.
|
UIIP
|
homna
|
|
0.16
|
9.00
|
58
|
138.97
|
MAM Construction Ltd.
|
132.56
|
29/05/2022
|
06/05/2022
|
06/04/2023
|
80
|
77.41
|
58
|
14/10/2024
|
|
839
|
UIIP-BC/PCO/W-420
|
Rehabilitation of BC Road by RCC Road starting from Homna Old Bus Stand Over Bridge to East Srimoddi Eidgah in ward No-05 & 06 under Homna Pourashava (Ch.820-2000m).
|
UIIP
|
homna
|
|
1.18
|
|
100
|
152.48
|
M/S Modina Construction
|
152.47
|
30/06/2022
|
07/07/2022
|
06/07/2023
|
100
|
151.76
|
100
|
14/10/2024
|
|
840
|
UIIP-BC/PCO/W-576
|
Improvement of BC road from starting from Srimoddi Bazar Mosjid moar to Latia road Anu Miahbari existing RCC road (Ch.00-795.00m) under Homna Pourasha,Cumilla.
|
UIIP
|
homna
|
|
0.80
|
|
0
|
32.98
|
M/S Modina Construction
|
32.37
|
16/05/2023
|
23/05/2023
|
22/05/2024
|
50
|
0.00
|
0
|
14/10/2024
|
|
841
|
UIIP-BC/PCO/W-630
|
Construction Of single Storied Vegetables and Agricultural products Market on 5 storied Foundation At Homna Pourashava,Cumilla.(Floor Area=314 sqm)
|
UIIP
|
homna
|
|
|
|
48
|
99.56
|
M/S Shahid Traders
|
104.54
|
24/07/2023
|
31/07/2023
|
30/07/2024
|
76
|
49.67
|
48
|
14/10/2024
|
|
842
|
UIIP/PCO/G-45
|
Implementation & Supply 765 nos Waste Basket (120 ltr) & 10 nos Non-motorized vehicle (van) under Homna Pourashava District: Cumilla.
|
UIIP
|
homna
|
|
|
|
55
|
39.97
|
RFL Plastrics Limited
|
27.22
|
11/01/2024
|
15/01/2024
|
17/04/2024
|
95
|
15.00
|
55
|
14/10/2024
|
|
843
|
UIIP-BC/PCO/W-75
|
(a)Construction of RCC Road starting from Pourashava Office road to Existing Horipur via Homna Kanda Eidgah in ward No-03( Ch.00.00-891.00m) ( b) Rehabilitation of BC Road starting from Homna East Srimoddi Eidgag to Srimoddi Lanchgat in ward No-06,07 & 08( Ch.2+000-4+550 m).
|
UIIP
|
homna
|
|
2.89
|
0.00
|
100
|
147.57
|
MAM Construction Ltd.
|
143.14
|
03/08/2020
|
10/08/2020
|
09/08/2021
|
100
|
143.01
|
100
|
29/09/2022
|
|
844
|
UIIP-BC/PCO/W-230
|
(a)Construction of RCC Drain starting from Homna Degree College Bridge East Side to Titas River via BRDB Godown ( L-410.00 m) under Homna Pourashava & Link Goal Bari Bridge ( L-108.00 m) in ward No-05, under Homna Pourashava. ( b)Construction of RCC Drain Starting from Bagmara Bazer to Alipur Canal via Bagmara Madrasha ( L-705.00 m) in ward No-02 ,under Homna Pourashava. ( c) Construction of RCC Drain Starting from Homna Sadar from Homna Sadar Hospital Gate to Post Office moar existing drain ( L-170.00 m) in ward No-04, under Homna Pourashava.
|
UIIP
|
homna
|
|
|
0.00
|
72
|
210.83
|
M/S. Zaman Traders
|
200.08
|
15/06/2021
|
22/06/2021
|
21/12/2021
|
100
|
143.11
|
72
|
29/09/2022
|
|
845
|
UIIP-BC/PCO/BCO/W-513
|
Construction of RCC drain front of Nangalkot Poura Bhaban (Ch.0.00-875.00m) under Nangalkot Pourashava Cumilla.
|
UIIP
|
nangalkot
|
|
|
0.00
|
60
|
119.02
|
M/S Modina Construction
|
130.85
|
24/07/2022
|
31/07/2022
|
30/07/2023
|
77
|
78.35
|
60
|
15/10/2024
|
|
846
|
UIIP-BC/PCO/BCO/W-546
|
(A) Construction of One Storied Vegetable & Agricultural Product Market (Floor Area=145.00 sqm) under Nangalkot Bazar
(B) Construction of One Storied Public Toilet Building (Type A=56 sqm) Under Nangalkot Bazar
(C) Construction of Shed For Public Transport Passenger (28.00 sqm) Nangalkot Bus Stant
|
UIIP
|
nangalkot
|
|
|
|
29
|
115.36
|
MMC-MST (JV)
|
125.97
|
31/05/2023
|
07/06/2023
|
06/06/2024
|
51
|
37.16
|
29
|
15/10/2024
|
|
847
|
UIIP/PCO/G-46
|
Implementation & Supply 765 nos Waste Basket (120 ltr) & 10 nos Non-motorized vehicle (van) under Nangolkot Pourashava District: Cumilla.
|
UIIP
|
nangalkot
|
|
|
|
50
|
39.97
|
RFL Plastrics Limited
|
29.98
|
10/03/2024
|
10/03/2024
|
09/06/2024
|
60
|
15.00
|
50
|
15/10/2024
|
|
848
|
UIIP-BC/PCO/BCO/W-498
|
Improvement of road from bypass road to Rail Station road & Police Station via B.B Chattar (Ch.00-470.00m) under Nangalkot Pourashava.
|
UIIP
|
nangalkot
|
|
0.47
|
0.00
|
100
|
118.48
|
M/S Azam & Saiham Traders
|
128.85
|
24/06/2022
|
01/07/2022
|
30/06/2023
|
100
|
128.15
|
100
|
14/10/2024
|
|
849
|
UIIP-BC/PCO/BCO/W-499
|
Improvement of road from Mahini and Bazar Road to Anwar Kausar AC Land office Teacher Training Center Road (Ch.00-481.00m) by RCC under Nangalkot Pourashava.
|
UIIP
|
nangalkot
|
|
0.48
|
0.00
|
83
|
63.57
|
M/S Shalaha Traders
|
69.25
|
24/06/2022
|
07/01/1900
|
30/06/2023
|
85
|
57.14
|
83
|
14/10/2024
|
|
850
|
UIIP-BC/PCO/W-57
|
Improvement of road at Bot tola (Laksam rd. Mahin rd. Sreefolia rd. & Hospital road) (L-635.00m) by RCC
|
UIIP
|
nangalkot
|
|
0.64
|
0.00
|
100
|
270.41
|
MMC-MST (JV) Nagalkot Bazar
|
270.43
|
10/01/2020
|
10/04/2020
|
30/09/2021
|
100
|
270.41
|
100
|
29/09/2022
|
|
851
|
UIIP-BC/PCO/BCO/W-188
|
Improvement of Road from Sreekamta pucca road to Poura boundary via Lucky's house (Ch. 0.11-0.900m) under Nangalkot Porosava
|
UIIP
|
nangalkot
|
|
0.90
|
1.00
|
99
|
118.28
|
M/S Saidul Enterprise
|
118.21
|
17/01/2021
|
24/01/2021
|
23/01/2022
|
100
|
117.19
|
99
|
29/09/2022
|
|
852
|
UIIP-BC/PCO/BCO/W-189
|
1. Improvement of Road from Dayemchati Bazar to Ludua Road (Ch. 0.000-0+790m) by BC under Nangalkot Porosava2. Construction of X Drain 6.00mx 1.00x1.00m on Dayemchati bazar to Ludia road3. Construction of 1x3.0x3.0m RCC Culkvert on Asawdia road (road way 5.00m)
|
UIIP
|
nangalkot
|
|
0.79
|
1.00
|
100
|
77.55
|
M/S Modina Construction
|
77.54
|
13/01/2021
|
|
19/01/2021
|
100
|
77.35
|
100
|
29/09/2022
|
|
853
|
UIIP-BC/PCO/BCO/W-190
|
Improvement of Road from Betagaon-Atakora Road to Sreehashya road (Ch. 0.00-1+490Km) under Nangolkot Pourosava.
|
UIIP
|
nangalkot
|
|
1.49
|
0.00
|
76
|
142.75
|
M/S Nur Ayesha Traders
|
142.72
|
17/01/2021
|
|
23/01/2021
|
100
|
108.83
|
76
|
29/09/2022
|
|
854
|
UIIP-BC/PCO/BCO/W-512
|
A) Construction of RCC drain beside Nangalkot to Dhalua Road (Ch.0.00-627.00m) under Nangalkot Pourashava Cumilla.B) Construction of RCC drain beside Sreekamta Pucca Road (Ch.0.00-51.00m) under Nangalkot Pourashava Cumilla.
|
UIIP
|
nangalkot
|
|
|
0.00
|
0
|
95.88
|
M/S Modina Construction
|
105.41
|
24/07/2022
|
31/07/2022
|
30/07/2023
|
0
|
0.00
|
0
|
29/09/2022
|
|
855
|
UTMIDP- MONO/ COM/ WR-7
|
Improvement of Batabaria-Monohorjonj Road, at(Ch.3600m-5200m) under Monohorganj Upazila.
|
UTMIDP
|
monohorganj
|
419902004
|
1.60
|
|
31
|
95.85
|
M/S Master Enterprise
|
95.84
|
30/05/2019
|
|
05/02/2020
|
100
|
30.00
|
31
|
04/09/2019
|
|