Construction of Important Bridges on Rural Roads (2nd Revised)

CIBRR: Summary of the report: The project titled “Construction of Important Bridges on Rural Roads” for implementation under LGED with full funding from the Government of Bangladesh was approved by ECNEC on 10-01-2018 at a cost of Tk. 392676 Lac BDT. Subsequently, the project titled “Construction of Important Bridges on Rural Roads (1st Revised)” was ap   more...
Project Information Table
Implementing Agency : LGED
Project Code : ২২৪০৩৮২০০
Project Name : Construction of Important Bridges on Rural Roads (2nd Revised)
Name of PD : Md. Ziaul Islam Majumder
Date of Approval : 24/08/2026
Starting Date : Jan-2017
Completion Date : Jun-2028
Project Cost (Lac) : Total (Lac) GOB (Lac) PA (Lac)
645490 Lac 645490 Lac
Cumulative Expenditure : 135167.230 (In Lac Taka)
Physical Progress (%) : 24
Progress Reporting Date : 06/11/2022
Comments :

At a Glance
Short Title: CIBRR
Ministry: LGRD
Executing Agency: LGED
Approval Ref: 20.00.0000.347.14.102.19.(অংশ-৩)-284
Project Code: ২২৪০৩৮২০০
Sector: Rural
Status: Ongoing Investment Project
Funded By: GOB.
Budget (Lac): 645490 Lac
Start Date: Jan-2017
Completion Date: Jun-2028
Name of PD: Md. Ziaul Islam Majumder