Construction of Bridge over Feni River on Sonagazi & Mirsharai Economic Zones Connecting Road Project (1st Revise). (BEZA-Bridge)

BEZA-Bridge:

Development of Dhaka-Chittagon   more...

Project Information Table
Implementing Agency : LGED
Project Code : 224280700
Project Name : Construction of Bridge over Feni River on Sonagazi & Mirsharai Economic Zones Connecting Road Project (1st Revise).
Name of PD : MD SHARIFUL ISLAM
Date of Approval : 30/06/2019
Starting Date : Feb-2019
Completion Date : Jun-2023
Project Cost (Lac) : Total (Lac) GOB (Lac) PA (Lac)
66288.00 (1st Revise 69865.00 lac) 66288.00 (1st Revise 69865.00 lac)
Cumulative Expenditure : 66288.000 (In Lac Taka)
Physical Progress (%) : 22
Progress Reporting Date : 20/08/2020
Comments : Project progress is ongoing

At a Glance
Short Title: BEZA-Bridge
Ministry: LGRD
Executing Agency: LGED
Approval Ref: 46.093.014.01.00.415.2018-383
Project Code: 224280700
Sector: Rural
Status: Ongoing Investment Project
Funded By: GOB.
Budget (Lac): 66288.00 (1st Revise 69865.00 lac)
Start Date: Feb-2019
Completion Date: Jun-2023
Name of PD: MD SHARIFUL ISLAM