Project Implementation Strategy

Local Government Engineering Department under Local Government Division will implement the project through a Project Implementation Unit (PIU) with the officers/employees appointed from a regular setup of LGED (Deputation/Outsourcing) under the leadership and responsibility of a full time Project Director. The Executive Engineer/Upazila Engineer of the project area along with technical staffs will execute the schemes as per design & specification. The Additional Chief Engineer (Division) and the Superintending Engineer (Region) will co-ordinate the project works with the concerned Executive Engineers. Chief Engineer, LGED, will oversee the project activities as a whole. 


The Consultant Firm will be engaged for design and supervision of the project work.

At a Glance
Short Title: FDRIRP2022
Ministry: LGRD
Executing Agency: LGED
Approval Ref: 46.00.0000.093.14.029.22-741
Project Code: 224373900
Sector: Rural
Status: Ongoing Investment Project
Funded By: ADB, GOB.
Budget (Lac): 113775.24 Lac
Start Date: Apr-2023
Completion Date: Jun-2027
Name of PD: Khandaker Asaduzzaman