Development of Rural Infrastructure of Jamalpur & Sherpur District (JSP)

Project Implementation Strategy

Executive Engineers of the concerned Districts are instructed to prepare estimate as per actual field condition.  Then estimates are checked by the HQ officials and sent to Chief Engineer for approval. After getting approval, concerned Executive Engineer implements the schemes through local competitive bidding.
At a Glance
Short Title: JSP
Ministry: LGRD
Executing Agency: LGED
Approval Ref:
Project Code: 224037600
Sector: Rural
Status: Completed Investment Project
Funded By: GOB.
Budget (Lac): 50005.00 Lac Taka
Start Date: Jul-2016
Completion Date: Dec-2021
Name of PD: Mollah Mohammad Shahnawaz