Rural Employment and Road Maintenance Programme-3 (RERMP-3)

Project Implementation Strategy

Project Implementation Strategies are-

 

  •    Improving socio-economic status of the project area and alleviating poverty through BBS Report, Planning Commission (GED) Report and Impact Study

  •     Raising the standard of living of the poorest beneficiaries by conducting immediate interviews with the beneficiaries at the end of the project.

  •    Submission of Project Progress Report and Project Completion Report through Project Manager Record & Audit Report

At a Glance
Short Title: RERMP-3
Ministry: LGRD
Executing Agency: LGED
Approval Ref: 20.00.0000.411.14. 106.19-366, Date:27.11.2019
Project Code: 224300300
Sector: Rural
Status: Ongoing Investment Project
Funded By:
Budget: 172315.00 Lakh
Start Date: Jul-2019
Completion Date: Jun-2023
Name of PD: Salma Shahid