Urban Development and City Governance Project (UDCGP)

Serial District Name District Code/ID Upazila Name Upazila Code/ID Project ID Package No Scheme Name Road ID Length of Scheme(Km) - Road Length of Scheme(m) - Bridge/Culverts Building Quantity Estimated Amount(LAC) Contractor Name Contract Amount(LAC) Date of Contract (DD/MM/YYYY) Date of commencement (DD/MM/YYYY) Date of Completion (DD/MM/YYYY) Physical Progress(%) Financial Progress (Amount) (LAC) Financial Progress(%) Date of Progress Update (DD/MM/YYYY) Remarks
1 Cox's bazar 13 cox's bazar-s 100 1032 CBP-RB-1 Construction of Road from Kasturaghat LGED bridge to Boat ghat.   0.00 0.00 2599.98 Dockyard & Engineering Works Limited (Address: Dockyard & Engineering Works Limited, Bangladesh Navy, Sonakanda, Bandar, Narayanganj-1413, Bangladesh) 0.00 17/05/2026 08/11/2027 0 0.00 0 17/06/2026 Contract Signed on 17 May 2026
2 Cox's bazar 13 cox's bazar-s 100 1032 CBP-WS-2 Installation of water distribution system in Ward 7   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 Test tube well work is completed. ULB verbally informed of the cancellation of this subproject.
3 Cox's bazar 13 cox's bazar-s 100 1032 CBP-D-1 a) Construction of RCC Drain with footpath from Gonarpara, Krishnanondodham and Boddho Ghona to Bakkhali River via Bazarghata Chauln Bazar and Bora Bazar. b) Construction of RCC Drain with footpath from Kalur Dokan to Bakkhali River via Tekpara Primary School and Janata Sarak Sluice gate at 4 No. Ward   0.00 0.00 3575.80   0.00 01/01/1900 0 0.00 0 17/06/2026 Tender opened on 23-02-2026, now under evaluation by the ministry.
4 Cox's bazar 13 cox's bazar-s 100 1032 CBP-SWM-2 Development of sanitary landfill site in SM Para.   0.00 0.00 5334.48   0.00 01/01/1900 0 0.00 0 17/06/2026 The LA branch is preparing the joint investigation report. With CBP, Under the Tendering Process.
5 Cox's bazar 13 cox's bazar-s 100 1032 CBP-SWM-1 Improvement open dump site to Sanitary Land Fill at Pana Market   0.00 0.00 880.25 M/S Sampan Construction 836.63 27/03/2025 10/04/2025 25/09/2026 12 64.11 0 17/06/2026 Waste shaping & Reservoir work is going on. One local person claims about 40% land in this SP as his own. ULB knows the issue. Pourashava Assistant Engineer advised the contractor to continue the work. If there is any problem, pourashava will solve it. Pourashava wants to solve the problem mutually.
6 Cox's bazar 13 cox's bazar-s 100 1032 CBP-RB-4 Construction of Coastal Road from Hotel Sayman to Marine Drive road.   1.23 0.00 0.00 19557.62   0.00 01/01/1900 0 0.00 0 17/06/2026 Drawing, Design, and Cost Estimate submitted to PMU on 25 Sep 2025. Detailed design and drawing signed by CBP and sent to LGED HQ. A letter issued by CBP for partial NoC to the relevant authorities, NoC from RHD has been received already. A revised cost estimate is underway. The design report was submitted to RHD on 9 Feb 2026. Now waiting for their approval. NOCs received from the relevant authorities.
7 Cox's bazar 13 cox's bazar-s 100 1032 CBP-RB-3 Improvement of Central Bus Terminal   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 Detailed design and drawing completed in January 2026. The Cost Estimate is ongoing.
8 Cox's bazar 13 cox's bazar-s 100 1032 CBP-RB-2 Construction of Coastal Road from Shugondha Point to Hotel Sayman.   1.28 0.00 0.00 6517.24 National Development Engineers Ltd. 0.00 27/04/2026 10/05/2026 27/05/2028 0 0.00 0 17/06/2026 Contract Agreement was signed on 27 April 2026
9 Cox's bazar 13 cox's bazar-s 100 1032 CBP-OI-1 Update of existing street light to smart light system.   0.00 0.00 2988.62 HTMS Limited 2888.98 27/11/2024 05/12/2025 25/05/2026 44 778.94 0 17/06/2026 Road restoration work and underground pipe laying work are going on. Revise estimate is approved on 16 March 2026.
10 Cox's bazar 13 cox's bazar-s 100 1032 CBP-WS-1 Installation of water distribution system in Ward 6, Ward 8   0.00 0.00 3278.98 FSL-SJC (JV) 2663.97 09/06/2024 13/06/2024 01/12/2025 54 646.70 0 17/06/2026 HDPE pipe laying is ongoing. Extended time upto 13 May 2026. For work progress, the cost estimate needs to be revised for approval.
11 Cumilla 10 cumilla-s 95 1032 CuCC-RB-1 New Construction of Bus Terminal at Alekharchar   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 After submission of the acquisition proposal on 06-02-2025. Ministry Team inspected the site on 02-04-2025, and final approval from the LGRD Ministry was received on 21-09-2025. PMU issued a letter to PE to expedite the process on 09-11-2025. Now, Land Acquisition Proposal (LAP) is being prepared by CuCC and will be submitted to DC office shortly. On the other hand, the Topo & Geo survey has been done.
12 Cumilla 10 cumilla-s 95 1032 CuCC-D-4 Re-habilitation of Racecourse and Gungaijuri Drainage System   0.00 0.00 3460.91   0.00 01/01/1900 0 0.00 0 17/06/2026 Tender opened on 12-01-2026, and evaluation has been carried out & received by PMU. Then, PMU sent to the Ministry for approval in May 2026.
13 Cumilla 10 cumilla-s 95 1032 CuCC-OI-2 Improvement of Dharmosagor City Park   0.00 0.00 4854.28   0.00 01/01/1900 0 0.00 0 17/06/2026 Tender opened on 16-04-2026 and evaluation is in progress
14 Cumilla 10 cumilla-s 95 1032 CuCC-D-5 RCC drains in northern part of Sawpara area and East side of railway   0.00 0.00 4415.11   0.00 01/01/1900 0 0.00 0 17/06/2026 Tender opened on 29-12-2025, and evaluation has been carried out & received by PMU. Then, PMU sent to the Ministry for approval in May 2026.
15 Cumilla 10 cumilla-s 95 1032 CuCC-SWM-1 Improvement of collection, transportation system and Improvement of landfill site at Jhakunipara.   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 Design, Drawing, Cnd ost Estimate submitted to PMU on 9 June 2026. Land Acquisition revised proposal for 15 acres sent to the Ministry on 06-02-2025 for administrative approval for the UDCGP Subproject. PE is asking for an approval letter from PMU for 15 acres of land acquisition. After submission of the acquisition proposal on 06-02-2025. Ministry Team inspected the site on 02-04-2025, and final approval from the LGRD Ministry was received on 21-09-2025. PMU issued a letter to PE to expedite the process on 09-11-2025. Land Acquisition Proposal (LAP) submitted to the DC office on 01-12-2025. Now, the DC Office is in the process of verifying the LAP.
16 Cumilla 10 cumilla-s 95 1032 CuCC-RB-2 Expansion of Cumilla Bus Terminal at Ashrafpur (Jangalia bus stand)   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 After submission of the acquisition proposal on 06-02-2025. Ministry Team inspected the site on 02-04-2025, and final approval from the LGRD Ministry was received on 21-09-2025. PMU issued a letter to PE to expedite the process on 09-11-2025. Lastly, the Ministry of LGRD formed a committee on 22-10-2025 for the submission of reports after visiting the disputed location/spots. Again, the LGRD Ministry reformed the previous committee on 24-03-2026. But the committee has not yet commenced their works. In DED, the master plan preparation is ongoing.
17 Cumilla 10 cumilla-s 95 1032 CuCC-D-3 RCC drains besides Cumilla Chittagong Bypass Roads and Medical College Hospital Road. i) Dhaneswar Road from Ch.0+000 to 0+180 km & from Ch. 0+000km to 0+300km. ii) Nagar Health Center Road from Ch. 0+000Km to 400Km. iii) Ballavpur Road from Ch. 0+000Km to 580Km. iv) Cumilla Chittagong Bypass Road from Ch. 0+000Km to Ch. 1+480Km. v) Goal Mathon Road from Ch. 0+000Km to Ch.0+680Km.   0.00 0.00 1772.37 Affan Builders Ltd. 1771.29 06/01/2025 07/05/2025 06/07/2026 81 1156.71 0 17/06/2026 The work started on 07-05-2025. The drain base, Vertical wall, and Top Slab 3245 m completed.
18 Cumilla 10 cumilla-s 95 1032 CuCC-OI-1 Supplying and installation of LED street light   0.00 0.00 1749.44 M/S RP Construction-Affan Builders Limited-Bothi Enterprise JV 1382.32 21/04/2025 15/06/2025 13/10/2026 42 289.41 0 17/06/2026 1186 no. poles have been installed out of total 2437. Installation of Wire Rack, Insulator & Cables are done for 986 no. poles.
19 Cumilla 10 cumilla-s 95 1032 CuCC-D-2 RCC drain from Cumilla Chittagong Bypass Road to west side along the main road   0.00 0.00 824.03 MCS.MHE (JV) 823.97 08/02/2024 21/02/2024 07/02/2025 21 0.00 0 17/06/2026 Work has been cancelled. Bill prepared as per joint measurement and Contractor signed a few days ago. Now preparation for sending PD office is in progress. Estimate of remaining works has been also sent to PD office/PMU.
20 Cumilla 10 cumilla-s 95 1032 CuCC-D-1 Construction of RCC drain in Chowara area. Part : A i) Ch.1+390 km to Ch.0+170 km (Ulurchar Road) ii) Ch.0+700 km to Ch. 0+460 km (Pathankoat Road) iii) Ch.0+000 km to Ch. 0+277 km (Ulurchar Link Road) iv) Ch.0+387 km to 0+010 km (Milestone College Road & Old Dhaka Chattagram Road). Part: B i) Ch.0+787 km to Ch.1+600 km (Old Dhaka Chattagram Road) ii) Ch.0+000 km to Ch.0+077km (Chowara Kitchen Market Road) iii) Ch.0+000 km to Ch.0+160 km (Chowara Kitchen Market Road) iv) Ch.1+020 km to Ch.1+140 km (Chowara Bazar Road). Part: C i) Ch.0+972 km to 0+570 km (Chowara Bazar Road) ii) Ch.570 km to Ch. 0+(-20) km (Raipur Road) iii) Ch.0+067 km to Ch.0+000 km (Councillor Bari Raipur Road )   0.00 0.00 2251.70 Mostufa Zaman Traders(Pvt) Ltd. 2251.48 06/01/2025 05/05/2025 06/07/2026 78 1357.83 0 17/06/2026 The work started on 05-05-2025. The drain base, wall and Top Slab 3675m completed.
21 Gazipur 21 gazipur-s 174 1032 GCC-WS-1 Installation of Production Tube well and water distribution system in Zone 3.   0.00 0.00 772.70   0.00 01/01/1900 0 0.00 0 17/06/2026 Tender Evaluation validity period expired. There is a probability of being retendered.
22 Gazipur 21 gazipur-s 174 1032 GCC-SWM-2 Improvement of collection, transportation and disposal site at Gazipur area of Gazipur City Corporation (GCC)   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 Drawing, Design, and Cost Estimate submitted to PMU on 23 May 2026
23 Gazipur 21 gazipur-s 174 1032 GCC-D-4 RCC drains from Dhaka-Mymensingh road Chandana Chowrasta to Turag River   0.00 0.00 2153.90   0.00 01/01/1900 0 0.00 0 17/06/2026 Tender in Live!
24 Gazipur 21 gazipur-s 174 1032 GCC-WS-2 Installation of Production Tube well and water distribution system in Zone 7, Zone 8   0.00 0.00 3388.46 FSL-SJC-JV 2716.52 21/05/2025 07/07/2025 11/11/2026 14 0.00 0 17/06/2026 Test boring was ongoing. Previously, a case was filed. Later on 25/01/2026, it was dismissed from the High Court Division. Now, as soon as possible, the work will restart.
25 Gazipur 21 gazipur-s 174 1032 GCC-SWM-1 Improvement of collection, transportation and disposal site at Tongi area of Gazipur City Corporation (GCC).   0.00 0.00 220.27   0.00 01/01/1900 0 0.00 0 17/06/2026 Under Tendering process.
26 Gazipur 21 gazipur-s 174 1032 GCC-RB-3 Construction of Kashimpur - Naojor Road   0.91 0.00 0.00 2284.53   0.00 01/01/1900 0 0.00 0 17/06/2026 DED Ongoing, Drawing and cost estimate are anticipated to be submitted to PMU in 1st week of June 2026.
27 Gazipur 21 gazipur-s 174 1032 GCC-RB-2 Construction of Kashimpur - Naojor Connecting Bridge over Turag River   860.00 0.00 10980.55   0.00 01/01/1900 0 0.00 0 17/06/2026 Regarding Land Acquisition, the ULB obtained NOCs from the Gazipur Development Authority, the DOE, and the Department of Urban Development. Already sent the letter. Tender Evaluation ongoing.
28 Gazipur 21 gazipur-s 174 1032 GCC-RB-1 Construction of Overpass near Joydebpur Railway Station   977.00 0.00 23699.28   0.00 01/01/1900 0 0.00 0 17/06/2026 Drawing, Design, and Cost estimate submitted to PMU on 30 Sep 2025. JICA review is completed, and A revised cost estimate is also completed. There was a technical meeting on non-scheduled items on 12 May, 2026. Land Acquisition Status (The land acquisition file is now in the DC office, awaiting a joint visit. NOC from the Roads & Highway Department, BRRI, and Bangladesh Railway is due.
29 Gazipur 21 gazipur-s 174 1032 GCC-D-3 Construction of RCC Drains 1) Inner Bari Road & Jhajhor Road to Bottola Road & Basura Road (North); i)Basura by-pass (Inner bari mor) to Pucca bridge of Inner Bari Road. (Ch.0+000 to 0+768 m). ii)Jhajhor by-pass (Jhajhor mor) to Pucca Bridge of Jhajhor Road. (Ch. 0+000 to 1+200 m). 2) From Jhajhor Bypass to Jhajhor Bypass (South); i)Morian by-pass to Morian Purbapara bridge (Ch.0+000 to 0+398 m) ii)Morian mor to Morian bridge (0+000 to 0+690 m).   0.00 0.00 1612.12 Al-ME JV 1524.84 25/07/2024 12/09/2024 15/01/2026 83 972.66 0 17/06/2026 PCC Casting=2950m, Base Casting =2950m, wall casting=2950m, Top slab casting=2925m sub base=1500m
30 Gazipur 21 gazipur-s 174 1032 GCC-D-2 RCC drains from Mirrer Bazar to Nondibari Road (Across a railway) i) Construction of Drain of Shikder Bari Road From Ch.0+000 km ~ 0+440 km ii) Construction of Drain of Kosaybari Road From Ch 0+000 km~ 0+320 km iii) Construction of Drain of Connecting road between Kosaybari road to Mirrer Bazar-Nondibari Road From Ch. 0+000 km ~ Ch. 0+380 km iv)Construction of Drain of Mirrer Bazar to Nondibari Road from Ch.0+340 km~ Ch.1+780 km   0.00 0.00 1551.09 M.N Enterprise 1469.34 01/09/2024 05/12/2024 22/02/2026 81 792.73 0 17/06/2026 PCC Casting=2200m, Base Casting =2180m, wall casting=2150m, Top slab casting=2150m
31 Gazipur 21 gazipur-s 174 1032 GCC-D-1 Construction of RCC drain from Dhaka Mymensingh Highway to Turag River i) Squibe road start from Dhaka Mymensingh Highway to Turag river from Ch.0+100 km to 1+882 km. ii)Link Connecting Safiuddin Road and College Road-College Road from Ch.0+000 km to 0+340 km. iii) Sultana Razia road start from Dhaka Mymensingh Highway to College Road Ch. 0+000 km to 0+316 km. iv) Link connecting Moktarbari road and Safiuddin Road-Safiuddin Road-Link connecting Safiuddin Road College Road-Link connecting College Road to Surtaranga road from Ch.0+000 km to 0+734 km. v) Surtaranga Road-Link connecting Surtaranga Road and Squibe road from Ch.0+000 km to 0+502 km.   0.00 0.00 4025.66 SEPL-SBL JV 3662.24 18/08/2025 24/11/2025 09/02/2027 14 195.16 0 17/06/2026 PCC Casting=200m, Base Casting =150m, wall casting=150m, Top slab casting=140m
32 Narayanganj 20 narayanganj-s 198 1032 NCC-OI-3 Construction of Community Center and Playground of Paikpara near Rishipara in Ward 18   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 Detailed Design is ongoing. A new site for the community center is selected. New place location: Dhono Kunda Water Pump attached land at ward no-8. (Siddirgonj Zone)
33 Narayanganj 20 narayanganj-s 198 1032 NCC-OI-2 Construction of Nabiganj Community Center and Restoration of Nabiganj water body in Ward 24.   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 Detailed Design is ongoing. A new site for the community center is selected. New place location Pakpanjaton mosque front road attached opposite land at ward no.23 (Kadam Rasul Zone)
34 Narayanganj 20 narayanganj-s 198 1032 NCC-WS-3 Regeneration and Rehabilitation of Existing 12 Production Tube Well (PTW) at Ward- 10, 11, 12, 14, 17, 18, 20 & 22 in NCC   0.00 0.00 0.00   0.00 01/01/1900 0 0.00 0 17/06/2026 The final list of 12 PTWs was sent by NCC to PMU. Site visit completed. Survey work is in progress. DED Ongoing.
35 Narayanganj 20 narayanganj-s 198 1032 NCC-WS-2 Installation of production tube well (PTW) at Ward-4 (Part), Ward-11, Ward-15, Ward-18, Ward-22 & Ward-23 in different zones under NCC   0.00 0.00 2138.13 Prime Engineering (Address: Ta 39/1, Gulshan Link Road, Middle Badda, Dhaka 1212) 1949.70 02/03/2026 01/04/2026 30/09/2027 6 0.00 0 17/06/2026 Test boring 4 nos completed & soil Samples collected, 2 Nos Test boring running
36 Narayanganj 20 narayanganj-s 198 1032 NCC-WS-1 Installation of production Tube Well (PTW) at Ward-4 (Part), Ward-9, Ward-10, Ward-17, Ward 18, Ward-20, Ward-21, Ward-22 & Ward-25 in different Zones Under NCC   0.00 0.00 1532.26   0.00 01/01/1900 0 0.00 0 17/06/2026 Tender Opened on 13 April, 2026. Now under evaluation by NCC. Single tender dropping. Prime Engineering, Quoted Amount:165064036.086 Provisional sum=7398387.00,Total amount =172462423.086 12.553% above Salek solar power ltd. (Writ petition no. 2140 0f 2026 attached herewith)
37 Narayanganj 20 narayanganj-s 198 1032 NCC-SWM-2 Improvement landfill site in Alamin-Nagar   0.00 0.00 942.43 Turn (Address: Holding 6/1/A, 29 Ring Road, Shyamoli, Dhaka-1207) 863.32 02/03/2026 01/04/2026 30/09/2027 6 0.00 0 17/06/2026 NoA Issued on 8th January, 2026, and the contract agreement was signed on 2nd March 2026. Labour shed completed. Mobilization on going.
38 Narayanganj 20 narayanganj-s 198 1032 NCC-SWM-1 Development of new landfill site in Jalkuri   0.00 0.00 5295.03   0.00 01/01/1900 0 0.00 0 17/06/2026 Sent to the Ministry of Land for land acquisition. PMU sent the Design, Drawing, and Cost Estimate to NCC for review and approval.
39 Narayanganj 20 narayanganj-s 198 1032 NCC-OI-1 Construction of Ali Ahmed Chunka Public Place and Playground   0.00 0.00 1761.24 FSL-SJC JV 1637.94 15/01/2025 22/01/2025 09/07/2026 40 336.11 0 17/06/2026 1.78 nos pile (North side), 49 nos pile (South side), Total 127 nos pile casting completedfor Retaining wall. 2. Boundary wall ( North side) casting Upto grade beam completed =102m 3. Drain= 65.5m (E-W) 4. Drain 38.5m (N-S Direction) 5. Wash block, Top slab & Floor Casting completed 6. Water reserve & Septic tank completed 7. Pile integrity test. done. pile cap 17 nos completed 8. Padestrian bridge pile 18nos casting completed 9. Retaining wall pile cap 17 nos casting completed
40 Narayanganj 20 narayanganj-s 198 1032 NCC-D-2 Construction of RCC drain in West side of Bangabandhu road with footpath   0.00 0.00 2191.87 M/S Ali Enterprise & Al Amin Traders (JV) 2070.98 11/06/2024 18/06/2024 24/06/2025 77 1289.01 0 17/06/2026 Curve stone & Soucer drain setting on going RCC Box culvert by the railway (Deposit work money deposit) 1. Challan no- 2526-004571211511,date:2.4.2026,amount:1,18,41,875.44 2..Challan no- 2526-00486297731, date:19.4.2026,amount:54,02855.00 letter issued date: 22.4.2026
41 Narayanganj 20 narayanganj-s 198 1032 NCC-D-1 Construction of RCC drain in East side of Bangabandhu road with footpath Part A - i) Bangabandhu Road D-1 (Ch.0+000 to Ch.0+320 km) ii) Pressclub Road D-1 (Ch.0+920 km to Ch.1+045 km ) iii)Bangabandhu Road D-1 (Ch.0+320 to 0+345 km) iv) Amlapara Road D-1 (Ch.0+010 to 0+500 km ): Part B - i) Bangabandhu Road D-1 (Ch.0+345 to Ch.0+595 km) ii) Shayastakhan Road D-1 (Ch.0+016 to 0+400 km) iii) Bangabandhu Road D-1 (Ch.0+595 to Ch. 0+950 km) iv) Bangabandhu Road D-1 (Ch.1+010 to Ch.2+010 km)   0.00 0.00 1978.75 M/S Ripa Construction & Binoy Traders (JV) 1914.96 11/08/2024 18/08/2024 10/02/2026 79 1249.26 0 17/06/2026 Curve stone & Soucer drain setting is ongoing