Rural Infrastructure Development Project : South Sunamganj and Jagannathpur Upazila, Sunamganj District. (RIDPSJ)

Serial District Name District Code/ID Upazila Name Upazila Code/ID Project ID Package No Scheme Name Road ID Length of Scheme(Km) - Road Length of Scheme(m) - Bridge/Culverts Building Quantity Estimated Amount(LAC) Contractor Name Contract Amount(LAC) Date of Contract (DD/MM/YYYY) Date of commencement (DD/MM/YYYY) Date of Completion (DD/MM/YYYY) Physical Progress(%) Financial Progress (Amount) (LAC) Financial Progress(%) Date of Progress Update (DD/MM/YYYY) Remarks
1 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-27 Construction of 4x4.50x5.00m Box Culvert at Ch.750m on Pagla-Jagannathpur RHD Khasila Priimary School Road-Chandon Miah House. 35.95 Aminul Islam Salim 34.15 15/05/2018 15/05/2018 100 19/12/2018  
2 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-25 Construction of 39.00m Long RCC Girder Bridge on Ismail-Veri via Baudharan road at Ch.1800km. 299.92 M/S Yakub & Braders 01816-705565 312.90 24/12/2017 30/11/2018 100 19/12/2018  
3 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-24 Construction of 45.00m Long RCC Girder Bridge on Sathal-Koriain via Goalvita road at Ch.260km. 252.15 M/S Jamal Uddin Monalisa (JV) 266.02 23/10/2017 06/11/2018 100 19/12/2018  
4 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-22 Construction of 33.00m Long RCC Girder Bridge on Lama-Rasulganj-Aralia road Over Ratna Khal at Ch.1000km. 177.31 Humayun Kabir 01711-011207. 191.55 10/10/2017 31/10/2018 100 19/12/2018  
5 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-21 Construction of 33.00m Long RCC Girder Bridge on Kathakhair-Dawrai up via Joyda road at Ch.3800km. 211.22 JV of SE-LE 215.53 08/04/2018 28/02/2019 100 19/12/2018  
6 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-20 Consttruction of 4x4.50x4.50m RCC Box culvert on Syedpur UP Sanatanpur via Teghoria road ch.3400m. 32.90 MD. Atiqur Rahman 01718-283838 32.89 17/08/2017 31/03/2018 100 19/12/2018  
7 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-19 Construction of 1x4.00x3.0m Dranaige Culvert at Ch.50m on BhoberBazar -Syedpur Raod (Enayet Nagar osque)-Ludurpur Road 9.24 Talukder Enterprise 01712172756 8.58 31/03/2017 10/07/2018 100 19/12/2018  
8 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-16 Construction of 4x4.0x4.0m Dranaige Culvert at Ch.5500m on Dawrai Bazar - Sewra Raod 26.02 Anowara Enterprise 01712393624 24.97 03/04/2017 03/05/2018 100 19/12/2018  
9 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-15 Improvement of Pagla RHD Road -Syedbari Mosjid via Khashila Akhar Road.Construction of 2 nos - Drain atCh.480m & 705m onsame Rd 0.75 42.96 M/S Mamun Construction 01712-509993 45.48 21/05/2017 15/06/2018 100 19/12/2018  
10 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-14 Improvement of Kalkalia UP- Kaliteki Primary School Road 0.97 56.85 M/S Mamun Construction 01712-509993 58.38 21/05/2017 31/10/2017 100 19/12/2018  
11 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-12 Improvement of Mojidpur (Pagla-Jagannathpur R&H)- Aralia Road.Construction of 1x2.50x 2.50m Draniage Culvert at Ch. 1050m on same Road 0.95 60.01 M/S Mamun Construction 01712-509993 60.41 21/05/2017 31/10/2017 100 19/12/2018  
12 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-11 Improvement of Shibganj Bazar-Raniganj UP Road 2.12 125.41 Mahbub Enterprise 01711332076 121.29 02/04/2017 13/05/2018 100 19/12/2018  
13 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-09 Improvement of Sathal- Noyabondor Road- Pirergaon- Shaharpara via Chitolia Road 1.10 61.79 M/S Jahangir Alam 01728-035260 64.57 22/06/2017 10/05/2018 100 19/12/2018  
14 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-08 Improvement of Noyabondor High School to Shankarpur Road.Construction of U-Drain at Ch. 1390m on same Road 1.79 107.85 Hasan Enterprise 01711335076 105.22 02/04/2017 30/11/2017 100 19/12/2018  
15 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-06 Improvement of Jagannathpur- Biswanath Road-Kachan Miah House via Bourkapon Madrasa Road 1.00 57.13 Hasan Enterprise 01711335076 57.32 02/04/2017 13/05/2018 100 19/12/2018  
16 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-05 Improvement of Provakarpur- Nandirgoan Road 1.32 75.98 Hasan Enterprise 01711335076 73.17 02/04/2017 30/11/2017 100 19/12/2018  
17 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-04 Improvement of Zila Parishad- Lahori Road 0.83 47.81 Parag Enterprise 01712374292 47.76 22/03/2017 09/08/2018 100 19/12/2018  
18 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-02 Improvement of Lama Toker Bazar-Gorgori Primary School Road.Construction of 2Nos U-Drain at Ch. 755m & 1425m on same Road 1.43 84.79 M/S Chadni Enterprise 01712103185 82.39 10/04/2017 30/09/2018 100 19/12/2018  
19 Sunamganj 64 jagannathpur 469 737 RIDP/Jagan/W-01 Improvement of Kathalkhair Bazar-Dawrai UP via Joyda Road 1.37 79.72 Hasan Enterprise 01711335076 77.16 02/03/2017 13/05/2018 100 19/12/2018  
20 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-09 Imprivement of Mirzapur-Fothapur-Manikpur (Joykalas) road from at Ch. 1000-2160m. 1.16 68.61 Noor Enterprise 01716825847 74.69 07/03/2018 31/03/2019 100 19/12/2018  
21 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-08 Construction of 4x4.00x4.00m Dranage Culvert on Imprivement of Minabazar-Paglabazar RHD via Islampur Piprakandi (Minabazar-Islampur via Rosulpur Dargapasha) road at Ch. 2600m. 28.29 M/S J.H Enterprise 01716-132995 25.51 23/11/2017 20/02/2018 100 19/12/2018  
22 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-07 Construction of 60.00 Long RCC Girder Bridge on Sunamgonj-Sylhet road to Sdarpur RHD-Kamrupdolong via Parbotipur Village road at Ch. 750km Over Nanda River. 510.30 M/S Nurul Islam 01713812992 531.28 11/10/2017 31/10/2018 100 19/12/2018  
23 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-06 Construction of 51.00 Long RCC Girder Bridge on Soyhara-Banglabazar road (Dorgapasha) at Ch. 5010km. 549.43 M/S Mahabub Enterprise 01711335076 559.98 26/12/2017 06/01/2019 100 19/12/2018  
24 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-05 Improvement of Chikarkandi Bazar - Chikarkandi GPS Road via Natungram Road by BC from 00m-700m. 0.70 40.30 M/S Ray Traders 01712-288849 41.93 17/12/2017 30/04/2018 100 19/12/2018  
25 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-04 1) Improvement of Shimulbak UP Office- Joynagar GC via Muktakhai-Chanpur GPS Road by BC from 2000m-2500m. 2) By HBB From Ch 2500-4625m on Same Road .3) Construction of 2 nos 1x1.00x0.975m U-Drain at Ch 2930m & 3020m on Same Road 0.50 152.96 M/S Noor Enterprise 01716825847 164.27 14/05/2017 26/05/2018 100 19/12/2018  
26 Sunamganj 64 shantiganj 462 737 RIDP/D.Sunam/W-03 1) Impro.of RHD (Soyhara)- Banglabazar GC via Amria GPS Road by Bcfrom 4218m-4510m. By HBB From Ch 4055-4218 and 4510-5010m on Same Rd .Construction of 1x1.00x0.975m U-Drain at Ch 4255m on Same Road 0.29 75.20 Somir Chandra Das 01715278508 78.94 29/11/2017 31/10/2018 100 19/12/2018  
27 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-02 Construction of 4x 4.50x5.00m RCC Box Culvert on Mirjapur- Fatapur-Manikpur (Joykalash) Road at Ch. 1200m 33.01 Noor Enterprise 01716825847 31.11 02/04/2017 02/05/2018 100 19/12/2018  
28 Sunamganj 64 shantiganj 462 737 RIDP/D.Sun/W-01 Improvement of Santiganj-Rajaniganj Road to dungria Primary school Road via Dungria Madrasha Road by RCC from 195m-500m. 0.31 16.87 Talukder Enterprise 01712172756 15.20 31/03/2017 31/08/2018 100 19/12/2018