Rupganj Jalshiri Abashon Connecting Road Development Project.

Serial District Name District Code/ID Upazila Name Upazila Code/ID Project ID Package No Scheme Name Road ID Length of Scheme(Km) - Road Length of Scheme(m) - Bridge/Culverts Building Quantity Estimated Amount(LAC) Contractor Name Contract Amount(LAC) Date of Contract (DD/MM/YYYY) Date of commencement (DD/MM/YYYY) Date of Completion (DD/MM/YYYY) Physical Progress(%) Financial Progress (Amount) (LAC) Financial Progress(%) Date of Progress Update (DD/MM/YYYY) Remarks
1 Narayanganj 20 rupganj 160 871 NA-JAL-10 Widening of road Yousufganj-Parshi Bazar to Jal Shiri Abashan Road by Earth Work & HBB at Ch. 00m-1710m under Upazila: Rupganj, District: Narayanganj. 367684074 1.71 187.66 Md. Eunus Al Mamun & Nusrat Trade International (JV) 222.36 13/04/2021 13/04/2021 13/01/2023 100 222.24 03/09/2023
2 Narayanganj 20 rupganj 160 871 NA-JAL-05 Construction of 75m RCC T-Girder Arch Bridge at (Yusofganj-Parshi Bazar to Jalshiri Abashan Road-1). 75.00 2994.01 M/S Abul Kalam Azad 3505.08 25/11/2019 25/11/2019 94 3265.76 03/09/2023
3 Narayanganj 20 rupganj 160 871 NA-JAL-11 Widening of road Rupganj Parshi Road Rajuk Sector-2 to Jal Shiri Abashan Road by Earth Work & HBB at Ch. 00m-1400m under Upazila: Rupganj, District: Narayanganj. 367684075 1.40 129.15 RE IE ASMT JV 156.76 18/01/2021 18/01/2021 20/03/2022 100 155.87 100 21/05/2023
4 Narayanganj 20 rupganj 160 871 NA-JAL-04 Improvement of road from Rupgang -Parshi road Rajuk sectors 02-Jalshiri abasan road by HBB at ch 00-1350m 367684075 1.35 112.98 Aristocratic Construction firms 112.95 23/05/2018 22/11/2018 100 112.95 100 08/09/2022  
5 Narayanganj 20 rupganj 160 871 NA-JAL-03 Improvement of Yuosofgang-Parshibazar-Jalshiri abasan road by HBB at ch 00-2000m 367684074 2.00 167.32 Aristocratic Construction firms 175.69 25/05/2018 22/11/2018 100 130.04 100 08/09/2022
6 Narayanganj 20 rupganj 160 871 NA-JAL-02 Improvement of road from Rupgang Parshi road Rajuk sectors 02-Jalshiri abasan road by earth filling at ch 00-1400m 367684075 1.40 399.84 M/S Nuruzzaman Khan 397.85 01/08/2017 06/02/2018 100 397.02 100 08/09/2022  
7 Narayanganj 20 rupganj 160 871 NA-JAL-01 Improvement of road from Yuosofgang-Parshibazar-Jalshiri abasan road by earth filling at ch 00-2000m 367684074 2.00 634.56 M/S Nuruzzaman Khan 633.58 01/08/2017 01/08/2017 06/02/2018 100 534.63 100 08/09/2022